Delhi High Court

Union Of India vs Rccivl-Litl (Joint Venture) on 8 July, 2024

Author: Vibhu Bakhru

Bench: Vibhu Bakhru

                          $~
                          *        IN THE HIGH COURT OF DELHI AT NEW DELHI

                          %                                        Judgement delivered on: 08.07.2024

                          +        FAO(OS) (COMM) 197/2023 and CM APPL. 7578/2024

                          UNION OF INDIA                                            ..... Appellant
                                                          versus
                          RCCIVL-LITL (JOINT VENTURE)                               ..... Respondent


                          Advocates who appeared in this case:
                          For the Appellant                : Mr Jaswinder Singh, Advocate.
                          For the Respondent              : Ms Amrita Panda, Advocate.

                          CORAM:
                          HON'BLE MR. JUSTICE VIBHU BAKHRU
                          HON'BLE MS. JUSTICE TARA VITASTA GANJU

                                                                   JUDGMENT

VIBHU BAKHRU, J.

1. The appellant - Directorate General Married Accommodation Project (hereafter also referred as DGMAP) - has filed the present intra court appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning an order dated 29.05.2023 passed by the learned Single Judge in OMP (COMM) No.200/2023 captioned Union of India v. RCCIVL-LITL (Joint Venture) (hereafter the impugned order).

2. The respondent had filed the aforesaid application [OMP (COMM) No.200/2023] under Section 34 of the A&C Act impugning an Arbitral Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 1 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 Award dated 07.11.2022 (hereafter the impugned award) rendered by an Arbitral Tribunal comprising of the Sole Arbitrator (hereafter the Arbitral Tribunal).

3. By the impugned order, the said application was dismissed and the learned Single Judge had declined to interfere with the impugned award.

4. The impugned award was rendered in the context of disputes arising in connection with the agreement dated 03.02.2014 for "Completion of Balance Work for Construction of Residential Accommodation for Army at Amritsar and Tibri" (hereafter the Agreement) entered into between the parties. The respondent had participated in the bidding process and its bid was accepted. The contract for completion of the balance work was awarded to the respondent at a contract value of ₹261,21,11,110.93.

5. The scope of works under the Agreement included completion of balance work left by the previous contractor including construction of (i) 35 Dwelling Units for Officer's Quarters; (ii) 260 Dwelling Units for JCO's Quarters; 1952 units for OR's Quarters; and 39 Garbage bins.

6. The respondent was required to execute these works at 3 different stations/locations i.e., Old Amritsar Cantt, New Amritsar Military Station, in 12 locations viz. NOC-I, NOC-II, NME Khetarpal, Kathania, Red Colony, Gulat Road, Golf Course, Military Farm, Dumping Ground, Field Regiment and, Tibri.

7. The Project was to be completed in four Phases within a period of twenty-seven months from the date of handing over of site, which was Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 2 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 stipulated as 24.02.2014. The Original Date of Commencement of the Project was 24.02.2014. There was delay in the completion of the Project and extensions of time were granted to the respondent without imposition of liquidated damages. Extensions of time to complete the project were granted for Phases I to IV, as detailed in the impugned award "33. ...The details of the extensions granted by the Respondent to the Claimant are as under:

                                   Phase        Actual Date of             Extended Date of
                                                  Completion                   Completion
                                               rd
                                      I      23 November 2014               31st March 2015
                                     II         23rd May 2015             15th December 2016
                                    III       23rd October 2015           30th November 2017
                                                   rd
                                    IV          23 May 2016              30th November 2017"


8. The work of Phase IV of the Project was completed on 30.11.2017. The respondent submitted its Final Bill on 04.10.2018 (hereafter Final Bill dated 04.10.2018) for a sum of ₹ 71,44,01,074.76.

9. The Final Bill dated 04.10.2018 was returned by DGMAP on 22.10.2018 and the respondent was called upon to submit the final bill in two parts - 'disputed' and 'undisputed'.

10. Since the payments as claimed were not made, the respondent invoked the arbitration agreement and filed Arbitration Petition No. 483/2019 under Section 11(6) of the A&C Act before this Court for reference of disputes to arbitration. The said petition was allowed by an order dated 09.08.2019 and the Arbitral Tribunal was appointed.

11. The respondent claimed that the contract did not provide for Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 3 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 submission of bills in two parts. Nonetheless, on 20.09.2019 - that is after the Arbitral Tribunal was constituted but prior to the filing of the Statement of Claim - the respondent resubmitted the final bill (hereafter the Final Bill) setting out the disputed and the undisputed amounts.

12. The respondent filed the Statement of Claim, which was based on the Final Bill setting out 'disputed' and 'undisputed' amounts. The respondent claimed a sum of ₹5,31,23,148/- as undisputed amount of Final Bill in addition to the release of the securities (Claim no.1). In addition, the respondent had also made an aggregate claim of ₹99,40,16,602/-(Claim no.2) under various heads (Claim nos. 2A to 2U), being the disputed part of the Final Bill.

13. The Arbitral Tribunal passed the procedural order dated 06.09.2019, inter alia, setting out the schedule for completion of pleadings, and the admission/denial of the documents. In terms of the said schedule, DGMAP was required to file the Statement of Defence and Counterclaim, if any, on 05.11.2019. However, DGMAP failed to do so. By an email dated 25.10.2019 addressed to the Arbitral Tribunal, DGMAP sought further time to file the Statement of Defence. By a procedural order dated 25.10.2019, the Arbitral Tribunal allowed the said prayer and granted further time to DGMAP till 26.11.2019 to file its Statement of Defence and Counterclaim, if any.

14. DGMAP filed the Statement of Defence and Counterclaim on 21.11.2019. In addition to disputing the claims, DGMAP also raised the following counterclaim: an amount of ₹25,00,000/- on account of alleged Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 4 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 defective works carried out by the respondent (counterclaim no.1); an amount of ₹27,20,000/- on account of non-submission of CPM chart by the respondent (counterclaim no.2); sum of ₹50,00,000/- on account of excess escalation paid on steel, cement and labour (counterclaim no.3); interest on the claims at the rate of 12% per annum (counterclaim no.4); and a sum of ₹25,00,000/- as cost of reference to arbitration (counterclaim no.5).

15. After significant delay, DGMAP sought to amend its Statement of Defence and Counterclaim and moved an application before the Arbitral Tribunal for permission to do so. The said application was allowed by the Arbitral Tribunal by a procedural order dated 24.03.2021. DGMAP filed its amended Statement of Defence and Counterclaim on 25.03.2021. DGMAP sought to delete its claim for recovery of excess escalation allegedly paid to the respondent and raised an additional claim for recovery of approximately ₹6.47 Crores on account of "minus amount of final bill (subject to audit check)".

16. The Statement of Defence and Counterclaim was amended and, DGMAP sought the following counterclaims: Recovery of an amount of ₹6.47 Cr (Approx.) on account of minus amount of final bill subject to Audit Check (Counterclaim no. 1); Claim of ₹25,00,000/- on account of alleged defective work carried out by the contractor (Counterclaim no. 2); Claim of a sum of ₹27,20,000/- on account of non-submission of CPM Chart by contractor (Counterclaim no. 3); Interest at the rate of 12% on the amount of counterclaim (Counterclaim no. 4); a sum of ₹25,00,000/- as cost of reference to arbitration (Counterclaim no. 5).

Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 5 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024

17. DGMAP stated that the Final Bill dated 04.10.2018 was found to be incorrect as the quantities and the amount were not matching the Measurement Books (MBs) and the bill was not made in two parts (disputed portion and undisputed portion). Thus, for the aforesaid reason, the same was returned to the respondent for submission afresh. It claimed that the respondent had resubmitted the bill on 20.09.2019, but during the scrutiny it was found that the quantities and the rates stated in the extract did not match the Measurement Books and the schedules and therefore, the same was returned.

18. DGMAP claimed that thereafter it had prepared the final bill on 01.09.2020 (hereafter also referred to as the DGMAP Final Bill) and called upon the respondent to sign the same. However, the respondent did not do so. According to the DGMAP, the final bill as prepared by it worked out to '6.47 Crores (minus) subject to audit check'.

19. The Arbitral Tribunal evaluated the evidence led by the parties in respect of the claims and counterclaims as raised by the parties. The Arbitral Tribunal found that the undisputed portion of the Final Bill as submitted by the respondent reflected an amount of ₹4,51,13,888.02 payable by DGMAP. The witness examined on behalf of the respondent (PW-1) affirmed that the said Final Bill is correct. The Arbitral Tribunal accepted the same and awarded a sum of ₹4,51,13,888.02 as against the sum of ₹5,31,23,148/- claimed by the respondent against the undisputed part of the Final Bill.

20. The Arbitral Tribunal did not accept the DGMAP Final Bill, which was filed at a belated stage, essentially, for three reasons. First, that the Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 6 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 DGMAP Final Bill was stoutly disputed by the respondent and DGMAP did not lead any evidence to establish the correctness of its version of the final bill. Second, that the DGMAP Final Bill was incomplete and was not supported by relevant material. And third, the DGMAP Final Bill had various handwritten corrections and the person carrying out the said corrections was not examined. The Arbitral Tribunal found that the DGMAP Final Bill lack credibility and thus, rejected the same.

21. In so far as the respondent's claim regarding certain disputed items is concerned (claim no.2), the Arbitral Tribunal rejected a bulk of the claims but allowed some of the claims based on the assessment and the material placed on record.

22. A tabular statement setting out the amount awarded by the Arbitral Tribunal against the claims and counter-claims, as set out in the impugned award, is reproduced below:-

"Claim Brief description Amount Awarded No. of claim Claimed (INR) amount (INR)
1. Claim towards 5,31,23,148/- 4,51,13,888/-
                                            Undisputed Part                      with interest at
                                            of Final Bill                        the rate of 8
                                                                                 percent       per
                                                                                 annum from 26th
                                                                                 August 2019 to
                                                                                 7th   November
                                                                                 2022.
                                   2A       Ser No 1 of 2,61,21,111.10/-         1,00,00,000/-
                                            "Disputed" part                      with interest at
                                            of the Final Bill:                   the rate of 8
                                            Reimbursement                        percent       per
                                            of           extra                   annum from 26th
                                            expenditure    on                    August 2019 to



Signature Not Verified
Digitally Signed            FAO (OS) (COMM) 197/2023                                           Page 7 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                           account of change                     7th   November
                                          in location of site                   2022.
                                          office, site store
                                          and labour camps
                                 2B       Ser No 2 of 1,22,85,158.22/-                NIL
                                          "Disputed" part
                                          of Final Bill: DO
                                          for provision of
                                          cut off wall in
                                          lieu of brick work
                                          in Officers, JCOs
                                          and ORs quarters
                                          at Amritsar &
                                          Tibri
                                 2C       Ser No 3 of 54,55,192.52/-            54,55,192.52/-
                                          "Disputed" part                       with interest at
                                          of Final Bill: DI                     the rate of 8
                                          for Omission of                       percent      per
                                          grit wash and                         annum from 26th
                                          provn of 15mm                         August 2019 to
                                          thick plaster                         7th   November
                                                                                2022.
                                 2D       Ser     No.4      of 11,49,921.52/-   NIL
                                          "Disputed" part
                                          of the Final Bill:
                                          DO for Omission
                                          of     flat     iron
                                          30X3mm           for
                                          bonding between
                                          Brick work and
                                          RCC columns
                                 2E       Ser     No.5      of 4,86,787.97/-    4,86,787.97/-
                                          "Disputed" part                       with interest at
                                          of the Final Bill:                    the rate of 8
                                          DO for Omission                       percent annum
                                          of kota stone                         26th     August
                                          flooring at loft                      2019    to    7th
                                          floor above lobby                     November 2022.
                                          for        Officers,
                                          JCOs and ORs
                                          qtrs.



Signature Not Verified
Digitally Signed          FAO (OS) (COMM) 197/2023                                            Page 8 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                  2F       Ser No. 6 of 16,981.63/-            16,981.63/- with
                                          Disputed" part of                   interest at the
                                          the Final Bill: DO                  rate of 8 percent
                                          for Provn of cable                  per annum from
                                          pits inside and                     26th      August
                                          outside of all the                  2019 to 7th
                                          blocks           at                 November 2022.
                                          Amritsar & Tibri
                                 2G       Ser    No.7      of 4,93,235.93/-   4,93,235.93/-
                                          "Disputed" part                     with interest at
                                          of the Final Bill:                  the rate of 8
                                          Do for Omission                     percent       per
                                          of glazed ceramic                   annum from 26th
                                          tiles in certain                    August 2019 to
                                          portions of dry                     7th   November
                                          out balcony                         2022.
                                 2H       Ser No 8 of 76,64,240.19/-          76,64,240.19/-
                                          "Disputed" part                     with interest at
                                          of Final Bill: DO                   the rate of 8
                                          for increase in                     percent       per
                                          roof projection of                  annum from 26th
                                          ORs       DUs at                    August 2019 to
                                          Amritsar & Tibri                    7th   November
                                                                              2022.
                                  2I      Ser No 9 of 44,88,921/-             NIL
                                          "Disputed" part
                                          of Final Bill:
                                          Escalation
                                          towards amount
                                          of Claim 2(A) to
                                          2(H), 2(R) and
                                          2(S)
                                  2J      Ser No 10 of 86,73,525.98/-         NIL
                                          "Disputed" part
                                          of Final Bill:
                                          Reimbursement
                                          of          extra
                                          expenditure
                                          incurred      for
                                          purchase of new
                                          machine/Plants to



Signature Not Verified
Digitally Signed          FAO (OS) (COMM) 197/2023                                          Page 9 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                            be issued vide
                                           item No 7 to 10
                                           of Schedule of
                                           credit
                                  2K       Ser No 11 of           5,77,19,935.40/-   The Claimant is
                                           "Disputed" part                           granted       8
                                           of Final Bill:                            percent interest
                                           Reimbursement                             on the delayed
                                           of compensation                           payments.
                                           on      Short/Less
                                           payment of RARs
                                  2L       Ser No 12 of           3,24,69,263.12/-   The Claimant is
                                           "Disputed" part of                        granted       8
                                           Final    Bill      :                      percent interest
                                           Reimbursement                             on the delayed
                                           of                                        payments.
                                           compensation on
                                           delayed payment
                                           of RARs
                                 2M        Ser No 13 of           6,09,03,785.22/-   NIL
                                           "Disputed" part
                                           of Final Bill:
                                           Reimbursement
                                           for
                                           idle/underutilizati
                                           on               of
                                           plant/machineries
                                  2N       Ser No 14 of           1,74,14,257.50     The Claimant is
                                           "Disputed" part                           awarded       the
                                           of Final Bill:                            actual      cost
                                           Reimbursement                             incurred by it in
                                           of            extra                       keeping       the
                                           expenditure                               Bank
                                           incurred         on                       Guarantees alive
                                           extension of BGs
                                  2O       Ser No 15 of           1,79,09,829.49     The Claimant is
                                           "Disputed" part of                        awarded interest
                                           Final          Bill:                      on the extra
                                           Reimbursement                             deduction     of
                                           of Extra recovery                         VAT effected by
                                           of VAT at source                          the Respondent


Signature Not Verified
Digitally Signed          FAO (OS) (COMM) 197/2023                                                 Page 10 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                                                                     (i.e. 6% minus
                                                                                    3.5% = 2.5%) at
                                                                                    the rate of 8
                                                                                    percent    per
                                                                                    annum instead
                                                                                    of 18 percent
                                                                                    claimed by the
                                                                                    Claimant.
                                  2P       Ser No 16 of         7,36,22,991.93      NIL
                                           "Disputed" part      (modified      to
                                           of Final Bill:       Rs.5,41,29,905.
                                           Reimbursement        23/-    in   the
                                           of Escalation due    Rejoinder      to
                                           to Claimant as per   SoC)
                                           condition       of
                                           contract including
                                           interest
                                  2Q       Ser No 17 of         32,93,32,286.49     NIL
                                           "Disputed" part
                                           of Final Bill:
                                           Compensation on
                                           account         of
                                           various breaches
                                  2R       Ser No 18 of         8,92,707.50/-       8,92,707.50/-
                                           "Disputed" part                          with interest at
                                           of Final Bill:                           the rate of 8
                                           Provn of 5mm                             percent       per
                                           thick plain PVC                          annum from 26th
                                           sheet                                    August 2019 to
                                                                                    7th   November
                                                                                    2022.
                                  2S       Ser No 19 of 21,83,119.10/-              21,83,119.10/-
                                           "Disputed" part                          with interest at
                                           of Final Bill:                           the rate of 8
                                           Provn of 20mm                            percent       per
                                           solid square bar                         annum from 26th
                                           in bulaster's of                         August 2019 to
                                           stair case in lieu                       7th   November
                                           of 20mm square                           2022.
                                           hollow tube in
                                           ORs qtrs.



Signature Not Verified
Digitally Signed          FAO (OS) (COMM) 197/2023                                                Page 11 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                   2T       Ser No 20 of         95,77,615.18/-     83,91,338/-
                                           "Disputed" part
                                           of Final Bill:
                                           Reimbursement
                                           of excess interest
                                           recovered       on
                                           Mobilization
                                           Advance
                                  2U       Ser No 21 of         9,41,16,041.75/-   NIL
                                           "Disputed" part
                                           of Final Bill:
                                           Reimbursement
                                           of        GST@12
                                           percent       with
                                           effect from 1 July
                                           2017 on total
                                           amount          of
                                           Undisputed and
                                           Disputed     Final
                                           Bill
                               Claim 3     Interest     Past,   Past:              The      claimant
                                           Pendente Lite and    14,63,49,149.83    has          been
                                           Future                                  awarded
                                                                Pendente Lite at   appropriate
                                                                18 percent per     interest    while
                                                                annum              deciding       the
                                                                                   individual
                                                                Future at 18       claims.      Any
                                                                percent   per      other claim qua
                                                                annum              interest(past and
                                                                                   pendent       lite)
                                                                                   stands rejected.
                               Claim 4     Cost            of 25,00,000/-          20,00,000/-
                                           Arbitration
                              TOTAL                             96,49,49,206.57    8,26,97,491/-
                                                                alongwith          along       with
                                                                interest           interest       as
                                                                                   granted    under
                                                                                   the    respective
                                                                                   heads.
                                                         COUNTERCLAIM


Signature Not Verified
Digitally Signed          FAO (OS) (COMM) 197/2023                                                Page 12 of 29
By:DUSHYANT
RAWAL
Signing Date:09.07.2024
                                 Countercl Recovery       on    6,47,00,000/-   NIL
                                aim No.1 account of Minus      APPROX
                                          Amount of Final
                                          Bill subject to
                                          Audit Check
                                Countercl Defective Work       25,00,000/-     NIL
                                aim No.2 carried out by the
                                          Contractor
                                Countercl Non-submission       27,20,000/-     NIL
                                aim No.3 of the CPM Chart
                                          by the Contractor.
                                Countercl Interest             12 percent on NIL
                                aim No.4                       Claim Nos.1-3
                                Countercl Cost            of   25,00,000/-   NIL
                                aim No.5 Arbitration
                                TOTAL                          7,24,20,000/-    NIL"
                                                               along       with
                                                               interest



                          IMPUGNED ORDER

23. The learned Single Judge did not accept that any interference with the impugned award was warranted. The learned Single Judge held that the Arbitral Tribunal's findings could not be considered implausible or irrational. It was also conceded on behalf of DGMAP that the impugned award in respect of Claim nos. 2(A) to 2(U) was based on appreciation of evidence and therefore, the challenge to the impugned award in respect of the said claims, was not pressed.
24. The learned Single Judge rejected the contention that DGMAP was not granted full opportunity to present its case as the Arbitral Tribunal had not allowed a competent technical officer to explain and argue the case. The learned Single Judge found that DGMAP was represented by counsel Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 13 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 throughout the arbitral proceedings and DGMAP was granted full opportunity to lead evidence. The learned Single Judge also observed that matters relating to procedure of the Arbitral Tribunal are within its domain but subject to compliance of the rules of natural justice. And, in the present case, the principles of natural justice had not been violated by not permitting DGMAP's Engineer to address final arguments. The learned Single Judge also observed that it was always open for the counsel to take his assistance.
25. In view of the above, the application filed by DGMAP under Section 34 of the A&C Act to set aside the impugned award was dismissed by the impugned order.
SUBMISSIONS
26. Mr. Jaswinder Singh, learned counsel appearing for DGMAP advanced submissions on three fronts. First, he submitted that the impugned award is liable to be set aside under Section 34(2)(a)(iii) of the A&C Act as DGMAP was not given full opportunity to present its case. He submitted that the counsel for DGMAP had requested the Arbitral Tribunal, by an email dated 03.02.2022, to permit the Director (Contracts) to further expound on the issue involved in counterclaim no.1 as the same was technical in nature. However, the Arbitral Tribunal had declined the said request. He submitted that therefore, technical matters could not be clarified to the Arbitral Tribunal as DGMAP was, in effect, unable to present its case.
27. Second, he submitted that the Arbitral Tribunal had erred in accepting the Final Bill and allowing Claim no.1 regarding undisputed amounts. He submitted that there was no amount which was undisputed as DGMAP had Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 14 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 presented its Final Bill (the DGMAP Final Bill), which reflected that a sum of ₹6.47 Crores was recoverable from the respondent. He submitted that the Arbitral Tribunal had rendered the award on an erroneous assumption that any amount was admittedly owed to the respondent.
28. Third, he submitted that the impugned award was inherently inconsistent with regard to the award of escalation. He referred to Paragraph Nos. 67 and 178 of the impugned award. He submitted that Paragraph No. 67 of the impugned award indicates that the Arbitral Tribunal had accepted that a sum of ₹10,60,00,000/- had been paid as escalation against the undisputed amount due to the respondent. However, in Paragraph no.177 of the impugned award, the Arbitral Tribunal had noted that an amount of ₹10,60,00,000/- was released to the respondent as per RAR No.69 against an escalation amount of ₹7,18,81,658.72/- as worked out by DGMAP. He submitted that therefore, the admitted amount payable against escalation was ₹7,18,81,658.72/- but an excess amount had been paid to the respondent. He contended that although the Arbitral Tribunal had noted that the escalation worked out by DGMAP was ₹7,18,81,658.72/-, an amount of ₹10,60,00,000/- was awarded as an undisputed amount.
29. Ms. Panda, learned counsel appearing for the respondent countered the aforesaid submissions. She submitted that DGMAP had not pleaded that the impugned award was liable to be set aside under Section 34(2)(a)(iii) of the A&C Act and no such plea could, thus, be orally advanced. She further contended that the request to permit a technical person to advance submissions was a ruse to lead evidence at the stage of final arguments. She submitted that counterclaim no.1 was in regard to the DGMAP Final Bill, Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 15 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 which was introduced at a much belated stage. The same was fabricated later. The Final Bill submitted by DGMAP (DGMAP Final Bill) was unsigned and there were further alterations after the bill had been signed. She contended that none of the alterations had been specifically signed, which indicate that the said alterations had been carried out after the final bill had been signed by the concerned officer.
30. Lastly, she submitted that DGMAP could not challenge the impugned award in relation to Claim Nos. 2(A) to 2(U) as the learned counsel for DGMAP had not pressed the challenge in respect of the said claims.
REASONS AND CONCLUSION
31. The first question to be addressed is whether the impugned award is liable to be set aside under Section 34(2)(a)(iii) of the A&C Act. The said Clause reads as under:
"Section 34. Application for setting aside arbitral wards. (2) ***
(a)***
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or"

32. There is no specific ground either in the application filed under Section 34 of the A&C Act or in the present appeal that specifically seeks to challenge the impugned award on the aforesaid ground. However, DGMAP has specifically pleaded that the impugned award is vitiated on account of "denial of opportunity to explain the case findings of ld Arbitrator". Notwithstanding that the impugned award is not challenged on the ground that DGMAP was unable to present its case, we are unable to accept that Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 16 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 DGMAP is precluded from raising the said ground at this stage. This is because it does not seek to introduce any new facts in the pleadings. The contention that the impugned award is vitiated under Section 34(2)(a)(iii) of the A&C Act is premised on the fact that the counsel for DGMAP had, by an email dated 03.02.2022, requested the Arbitral Tribunal to permit Mr. Sushil Kumar Jain, Director (Contracts) of DGMAP to expound on the issue involved in Counterclaim no.1 and the decision of the Arbitral Tribunal to deny the said request. The said facts are specifically pleaded. More importantly, there is no dispute that the counsel for DGMAP had made a request to permit the Director (Contracts) to address arguments on 04.02.2022 and the said request was not accepted.

33. However, we find no merit in the contention that DGMAP was unable to present its case or was denied full opportunity to do so. Concededly, both the parties had been granted ample opportunity to lead evidence including expert evidence. Undisputedly, the parties were given the opportunity to produce the documents relied upon by them and they had filed the respective affidavits of admission and denial of documents. The respondent had filed the affidavit of Sh. Luv Jain, Director of respondent (CW-1) as evidence. And, DGMAP had filed an affidavit of Sh. Rajnikant Sharma, Project Manager (MAP), Directorate General, Married Accommodation Project (RW-1) as evidence. Both the witnesses were extensively cross-examined. After its witness had submitted the evidence by way of affidavit and while its witness (RW-1) was being cross-examined, DGMAP moved an application on 04.03.2021 seeking amendment of its Statement of Defence and Counterclaim. The said application was filed on 01.03.2021. The Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 17 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 Arbitral Tribunal had allowed the said application and had also called upon the parties to indicate whether they propose to lead further evidence. DGMAP did not avail the said opportunity and had declined to lead further evidence. Thus, undeniably, both the parties had ample opportunity to lead expert evidence on technical matters and to some extent, had done so. It is also not disputed that DGMAP was represented by counsel throughout the proceedings and was given full opportunity to advance oral submissions on behalf of DGMAP. It is material to note that while arguments were being advanced by DGMAP's counsel and the matter was scheduled before the Arbitral Tribunal for further hearing on 04.02.2022, the counsel for DGMAP had requested to permit Director (Contracts) to further expound on the issue relating to Counterclaim no.1 on the ground that it is technical in nature and deals with calculations prepared by the Department on the basis of Measurement Books, actual work on site etc. It is material to note that the authority of the counsel was not withdrawn. However, DGMAP's request was that in the midst of the arguments, the Director (Contracts) to DGMAP be permitted to further add explanations. Clearly, the denial of such request did not render DGMAP unable to present its case. Its counsel, who was on record, had full opportunity to address submissions on the basis of evidence led by the parties. No further technical facts or explanations could be introduced after the evidence had been closed and the matter was at the stage of final arguments. DGMAP was also required to confine itself to pleadings and the material on record. Clearly, no submissions could have been advanced, which were not supported by pleadings. In the given facts, we are unable to accept that the impugned award is liable to be set aside on the ground that DGMAP did not have notice of proceedings or was otherwise Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 18 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 unable to present its case after DGMAP had fully participated in the proceedings. It is also important to note that even at this stage, no submissions have been made before this Court pointing out any particular pleading or seeking to explain any of the pleadings or documents which, according to DGMAP, it was unable to do before the Arbitral Tribunal. As noted above, DGMAP's contention rests solely on the basis that a particular technical officer was not allowed to make submissions in the midst of the arguments being advanced by its counsel.

34. We are unable to accept that the principles of natural justice were violated or that DGMAP had been denied any opportunity to meet the case set up by the respondent or to advance its counterclaims. We concur with the decision of the learned Single Judge that the matter was one regarding procedure, which was within the domain of the Arbitral Tribunal and its decision to decline the request for the technical person to join the oral submissions of its counsel, is not amenable to review in these proceedings.

35. The second question to be addressed is whether the impugned award is vitiated by patent illegality.

36. The impugned award may be set aside if it is vitiated by patent illegality appearing on the face of the award. It is also well settled that the ground of patent illegality is attracted only if the illegality strikes at the root of the arbitral award. A plausible view of the Arbitral Tribunal, even though may be considered as erroneous by the courts, is not liable to be interfered with in proceedings under Section 34 of the A&C Act. This is because it is impermissible for the court to re-adjudicate the disputes as an appellate court Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 19 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 and supplant its view in place of that of the Arbitral Tribunal. The Arbitral Tribunal is the sole adjudicator of the disputes between the parties and unless the said view is perverse or one that no reasonable person can possibly accept, no interference with the arbitral award is permissible.

37. It is material to note that the proviso to Section 34(2A) of the A&C Act also expressly provides that an arbitral award would not be set aside merely on the ground of erroneous application of law or by reappreciation of evidence.

38. In the present case, the Arbitral Tribunal had rejected the DGMAP Final Bill for various reasons. The Arbitral Tribunal had first noted that the DGMAP Final Bill had seen the light of the day while the proceedings were mid-way. Even though the respondent had denied the DGMAP Final Bill, DGMAP had not taken any steps to establish its correctness or prove the same. The Arbitral Tribunal noted that it had granted opportunity to DGMAP to lead further evidence by an order dated 24.03.2021, but DGMAP had not led any evidence to prove the DGMAP Final Bill.

39. Second, that the DGMAP Final Bill was incomplete as it was not accompanied by relevant documents including the Deviation Orders (DOs). DGMAP had sought to produce the DOs at a subsequent stage, however, had not led any additional evidence to prove the same. In the given circumstances, the Arbitral Tribunal held that DGMAP had failed to prove the DGMAP Final Bill and the DO(s) placed on record.

40. The aforesaid conclusion cannot be held to be perverse or vitiated by patent illegality. There is no dispute that DGMAP had not led any evidence Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 20 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 to prove the DGMAP Final Bill. The Arbitral Tribunal had noted that the DGMAP Final Bill showed handwritten/manual adjustments/alterations, which were subject matter of dispute between the parties. However, DGMAP had not examined its officer who had carried out the handwritten/ manual adjustments/alterations in the DGMAP Final Bill or proved the correctness of the said alterations/corrections.

41. DGMAP Final Bill was also not confirmed as it was subject to an audit check.

42. Admittedly, the work was completed on 30.11.2017 and the defects liability period also expired on 30.11.2019. In the given facts, after evaluating the material on record, the Arbitral Tribunal concluded that the DGMAP Final Bill lack credibility and thus, rejected the same. The decision of the Arbitral Tribunal as to the quality of the evidence is not amenable to the judicial review under Section 34 of the A&C Act. It is not permissible for a Court to reappreciate the evidence and undertake a merits review of an arbitral award under Section 34 of the A&C Act. Unless the Court finds that the Arbitral Tribunal's view is ex facie not a plausible one, the arbitral award cannot be set aside. Clearly, in the present case, there is no ground to accept that the decision of the Arbitral Tribunal to reject the DGMAP Final Bill, is perverse or patently illegal. The Arbitral Tribunal has given cogent reasons for its conclusion and it is not possible to hold that the said conclusion is not a plausible one.

43. The respondent had also submitted the Final Bill dated 04.10.2018. The said Final Bill was returned by DGMAP on 22.10.2018 inter alia on the Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 21 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 ground that it was not divided in two parts - disputed and undisputed. According to DGMAP, the Final Bill was required to be bifurcated into two parts. One in regard to the amounts that were disputed and the second in respect of amounts that were undisputed. The Arbitral Tribunal found that there was no contractual basis for this assertion. The relevant clause of the Agreement (Clause 56 of the Agreement) required "those items of the Final Bill in respect of which there is no dispute" to be paid within a period of six months from the date of receipt of the Final Bill by the Project Manager. The said Clause did not mean that the Contractor was required to submit the bill by dividing it into two parts. It merely required that the amounts in respect of which there was no dispute were to be paid within a stipulated period. However, in the present case, DGMAP had returned the Final Bill and had not processed the same.

44. The respondent had led evidence as to the correctness of the Final Bill. CW-1 had affirmed as to the correctness of the said Final Bill. He was extensively cross-examined. He testified that the Final Bill contained the details of the work done. It also contained an item wise break-up of the work executed by the respondent. He had also affirmed that the Final Bill dated 04.10.2018 was in the requisite format. However, the respondent had modified and re-submitted the same (Final Bill) as required by DGMAP.

45. The Arbitral Tribunal accepted the evidence of CW-1. Accordingly, it allowed Claim no.1 to the extent of ₹4,51,13,888/-, which was also mentioned in Appendix A to the Statement of Claim. The summary of the undisputed amounts due appearing at the said Appendix A indicated the amounts of the bills raised/gross value of the work done as Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 22 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 ₹2,67,79,20,650.09/- and escalation as ₹10,60,00,000/-. The summary of the undisputed amounts payable as mentioned in Appendix A and as noted by the Arbitral Tribunal is set out below:

"67. It is correct that the amount claimed in the SOC is different from the amount mentioned in Appendix A filed by the Claimant. The Summary appearing at page 5 of Appendix A filed by the Claimant reads as under:
                                   Ser Description              Minus         Plus
                                   No
                                   1       Amount of the Bill                 2,67,79,20,650.09
                                   2       Gross value of                     2,67,79,20,650.09
                                           work
                                   3       Escalation                         10,60,00,000.00
                                   4       Recovery         of 25,58,96,985.
                                           Mobilization         00
                                           Advance including
                                           Interest
                                   5       Schedule of Credit 3,26,59,765.0
                                                                7
                                   6       Total     Payments 2,45,02,50,01
                                           Made on Running 2.00
                                           Account Receipts
                                           from 01 RAR to
                                           69th RAR
                                   7       Net Amount of the                  4,51,13,888.02
                                           bill
                                   8       Net Amount of the                  4,51,13,888.00"
                                           bill

46. The Arbitral Tribunal also examined the respondent's claim in regard to the undisputed portion of the Final Bill. The same was largely considered in the 69th RAR, which was paid on 05.05.2018. The escalation amount of ₹10,60,00,000/- was accepted as the undisputed part of the Final Bill as it had been paid till the 69th RAR after due approvals at various stages.
Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 23 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024
47. No specific dispute has been pointed out as to the gross value of the work set out in the summary appearing at Page 5 of Appendix A. The Arbitral Tribunal noted the testimony of RW-1 to the effect that payment of escalation of a sum of ₹10,60,00,000/- was made after it was examined and approved by the concerned officials at various stages.
48. There appears to be no dispute as to the total payments made on the running account.
49. In the given circumstances, the Arbitral Tribunal accepted the undisputed part of the Final Bill and accordingly, allowed Claim no.1, albeit to the extent of ₹4,51,13,888.02/- as mentioned in Appendix A to the Statement of Claims, as against a sum of ₹5,31,23,148/- claimed by the respondent.
50. The contention that the impugned award is vitiated on the ground of patent illegality as the Arbitral Tribunal has rejected the Final Bill produced by DGMAP, is also untenable and without merit. We find no ground to set aside the Arbitral Tribunal's decision to accept the undisputed portion of the Final Bill. The Arbitral Tribunal had accepted the respondent's justification for the same and the said decision cannot, by any stretch, be held to be perverse.
51. The third question to be addressed is whether the impugned award suffers from inconsistencies and is thus liable to be set aside.
52. Mr Singh had also assailed the impugned award on the ground that it was inconsistent. The said contention rested on the conclusion as recorded in Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 24 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 Paragraph Nos. 67 and 178 of the impugned award. Paragraph No. 67 of the impugned award sets out a summary of the Final Bill filed as Appendix A to the Statement of Claim. As noted above, the same indicated the escalation on the value of work done as ₹10,60,00,000/-. The Arbitral Tribunal had reproduced the synopsis of the arguments. The respondent had justified including the said amount in the undisputed portion of the Final Bill on the ground that the said amount had been agreed and had been paid by DGMAP till the 69th RA Bill in May 2018. It was contended that in view of the above, there was no dispute as to the said escalation. However, DGMAP had reduced the amount to approximately ₹7.21 crores in the DGMAP Final Bill. The respondent claimed that this rejection was unjustified and arbitrary, particularly after the respondent had already agreed and paid the same.
53. The Arbitral Tribunal also noted the responses of RW-1 to the questions put in cross-examination. The relevant extract, as noted by the Arbitral Tribunal in the impugned order, is reproduced below:
"70. During cross-examination, RW1 has deposed as under:
Q.102 I put it to you that the payment in respect of escalation and earthwork done by the Claimant was duly paid by the Respondent after complete checking and verification by the PM MAP, Station Commander, Consultant and then by the Controller of Defence accounts in May 2018. What do you have to say?
Ans. Yes.
Q. 103 Did the Respondent ever take any action against any of these officials by alleging that they have wrongly made the payment?
Ans. I do not want to answer this question as it is a departmental matter and cannot be answered here. Per Tribunal: The witness is requested to answer the Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 25 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 question.
I do not know what action has been taken by DG MAP. Q.104 I put it to you that no action whatsoever has been taken against any of those officials till date. What do you have to say?
Ans. I do not know."

54. The Arbitral Tribunal noted that DGMAP had not led any independent evidence to dispute the aforesaid stand and thus, had accepted that escalation of ₹10,60,00,000/- was admitted. However, the Arbitral Tribunal rejected the respondent's claim for enhanced escalation, which was part of the disputed Claim no.2(P).

55. The respondent claimed that it was entitled to escalation amounting to ₹16,18,77,052.43/-. There was no dispute that it had received payment of ₹10,60,00,000/- against escalation for cement and steel. Accordingly, the respondent claimed the balance payment along with interest, which was quantified at ₹7,36,22,991.93. The said amount was included in the disputed portion of the Final Bill and claimed as Claim No. 2(P).

56. The respondent had calculated the said escalation by assuming that steel constituted 13% of the value and cement constituted 27% of the value. The said constituents were referred to as Ks and Kc in the formula as provided in the Agreement. The respondent had determined the value of steel component on the basis that it had purchased steel reinforcement of approximately ₹34 crores including material issued by DGMAP lying at site, This, according to the respondent, worked out to be 13%. The respondent had also relied on note no.7 of the special conditions of contract, which Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 26 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 provided that the value/percentage of Kc and Ks (cement and steel components respectively) would be determined on the type of construction and codal provisions but their sum would be 40%. Thus, according to the respondent, the escalation was required to be computed on the basis that the steel component (Ks) is 13% and the cement component (Kc) is 27%. According to the respondent, the same would work out to ₹16,18,77,052.43/-. The respondent contended that it was the obligation of the accepting officer to ascertain the correct value of Ks and Kc based on the details submitted by the respondent, but he had not done so.

57. The Arbitral Tribunal rejected the said claim - Claim No. 2(P) - on the ground that the respondent had failed to establish the indices on which the calculations were based. In the aforesaid context, the Arbitral Tribunal also observed, in paragraph 177 of the impugned award, that the respondent had "failed to dispute/discredit the statement of the Respondent that an amount of Rs.10,60,00,000/- was released to it as per RAR No.69 as against the escalation amount of Rs.7,18,81,658.72/- worked out by the Respondent keeping in view the constant of 15:25". This, according to Mr Singh, is contradictory to the finding of the Arbitral Tribunal as recorded in Paragraph 67 of the impugned award whereby the Arbitral Tribunal accepted that escalation of ₹10,60,00,000/- was not disputed.

58. We find no merit in the aforesaid contention. A plain reading of the Arbitral Tribunal's decision in regard to the undisputed portion of the Final Bill (Claim no.1) and the disputed portion of the escalation of cement and steel (Claim no.2(P)] indicates that there is no inconsistency in the findings read in the proper context. The Arbitral Tribunal had accepted that Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 27 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024 escalation of ₹10,60,00,000/- was not disputed by DGMAP at the appropriate time as the said escalation had been paid till the 69 th RAR after the concerned officials of DGMAP had examined and approved the same examining the calculations for the same. RW-1 had accepted that the payments were made after the calculations had been duly verified by the concerned officers including the Accounts Department and there was no material that any action had been taken against the concerned officers for accepting the calculations of escalation and payment of the said amount. However, the Arbitral Tribunal did not accept the respondent's calculation of the enhanced escalation assuming the steel component to be 13% and the cement component to be 27%. Undoubtedly, there was a dispute regarding the constants (Kc and Ks) to be applied for computing the escalation. DGMAP had subsequently computed the escalation at ₹7,18,81,658.72/-. Apparently, keeping in view the said constants at 15:25. However, this was subject matter of serious dispute. It is apparent that whilst the Arbitral Tribunal rejected the respondent's contention that the escalation was to be reduced and allowed Claim no.1, it also rejected the respondent's claim for the additional escalation as claimed by it. The observations made in Paragraph no. 177 of the impugned award cannot be read to mean that the Arbitral Tribunal had accepted that the subsequent reduction of escalation from ₹10,60,00,000/- to ₹7,18,81,658.72/-, as claimed by DGMAP, was correct.

59. Before concluding, it is also necessary to note that before the learned Single Judge, DGMAP had not pressed its challenge to amounts awarded against Claim no.2 [Claim nos.2(A) to 2(U)].

Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 28 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024

60. Mr Singh, learned counsel appearing for DGMAP, had fairly stood by the said stand and had not advanced any contention to challenge the impugned award in respect of amounts awarded in favour of the respondent against Claim no.2.

61. We find no infirmity with the impugned order or any ground to interfere with the impugned award.

62. The present appeal is unmerited and, accordingly, dismissed. All pending applications are also disposed of.

VIBHU BAKHRU, J TARA VITASTA GANJU, J JULY 08, 2024 m/RK Signature Not Verified Digitally Signed FAO (OS) (COMM) 197/2023 Page 29 of 29 By:DUSHYANT RAWAL Signing Date:09.07.2024