Section 105(c) in Chhattisgarh Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Rules, 2008
(c)where the floor to ceiling height of a concreting work exceeds nine metres or where the formwork deck used in such concreting work is supported by shores constructed in two or more tiers, or where the dead, live and impact loads on the formworks used in such concreting work exceed seven hundred kilogram per square metre, the structure of such formwork is designed by a professional engineer in the relevant field and the specifications and drawing of such formwork are kept at such construction site and produced on demand before the Inspector having jurisdiction;