Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 21]

National Consumer Disputes Redressal

Choudhary Ashok Yadav vs Rewari Central Co-Op. Bank & Anr. on 8 February, 2013

  
 
 
 
 
 

 
 
 





 

 



 NATIONAL CONSUMER
DISPUTES REDRESSAL COMMISSION

 

NEW DELHI 

   

 REVISION PETITION NO. 4894 OF 2012

 (From order dated 19.1.2012 in First Appeal
No.1283/08 of the 

 State
Consumer Disputes Redressal
Commission, Haryana, Panchkula) 

 

  

 

Chaudhary Ashok Yadav  

 

S/o Shri Manohar Lal 

 

R/o Vill. Bhaandore, P.O Punsika 

 

Tehsil & District Rewari 

 

Haryana   Petitioner 

 Versus

 

  

 

1.
The Rewari Central Co-operative Bank    

 

Through its Managing Director, Rewari 

 

Tehsil & District Rewari, Haryana  

 

  

 

2. National Horticulture Board 

 

85,Industrial Area, Sector-18 

 

Gurgaon, Haryana   Respondents 

   

 

 BEFORE: 

 HONBLE MR.JUSTICE J. M. MALIK , PRESIDING MEMBER 

 

 HONBLE
MR. VINAY KUMAR, MEMBER 

 

  

 

For the Petitioner : Mr. Siddharth Mittal, Advocate  

 

   

    

  Pronounced on_08.02.2013
  

 

  

 

  O
R D E R  

 

 JUSTICE J.M. MALIK 

 

1. Chaudhary Ashok Yadav, the complainant, mortgaged 10 acres of land for the project
establishing fruit garden, under the
Scheme of National Horticulture Board Respondent 2/OP1 with the Rewari Central
Co-operative Bank, Rewari, Respondent No.1/OP2 and in order to avail financial assistance to
the tune of Rs.25 lakh, the project was submitted with the Respondent No.1. The
complainant contacted Sh.D.P.Singh of National Horticulture Board, Gurgaon,
OP1. OP2 informed the complainant that
the amount would be sanctioned and after sanctioning of the said amount, the
project profit report should be submitted to the OP1/Respondent No.2 for the
grant of subsidy to the tune of 20% of the financial assistance. The project was sent to NABARD and the NABARD sanctioned
14.19 lakh for implementation of the project.
After disbursement of the loan by the Bank, Respondent No.1/OP2, the
project profit was sent to Respondent No.2/OP1
for consideration of subsidy on 26.07.2005. However, OP1 refused the subsidy to the
complainant on his loan. The complainant
approached the National Horticulture Board, Respondent No.2, for grant of
subsidy but the Board did not consider his case. The complainant/ petitioner filed a case
before the District Forum that there was deficiency in service.  

 

  

 

2. Respondent No.2/OP1 did not appear before the District Forum
and as such, it was proceeded against ex-parte. Respondent No.1/OP2 contested
this case. The District Forum allowed
the complaint and directed the OPs to pay the subsidy to the complainant along
with interest @ 9% p.a. from the date of filing of the complaint till final
realization. Litigation expenses in the
sum of Rs.2,000/- were also granted in favour of the complainant.  3. Aggrieved by that
order, Respondent No.1/OP2 approached the State Commission. The State Commission vide its order dated
19.10.2012 accepted the appeal and dismissed the complaint.  

 

4. In the revision petition, we have heard the counsel for the
petitioner/complainant. He vehemently
argued that his main contention was that he could not get the subsidy because
of delay. He contended that this is a
matter of contract and the petitioner/complainant is, therefore, a consumer. There was delay of 10 months on the part of
OP2. He has invited our attention to the
judgment of the District Forum. Relevant extract from Para 7 of the said
judgment, runs as follows:-  

 

7
Whereas letter Ex.OP5 placed on record by Opposite party No.2, reveals that
loan amount of Rs.14.19 lakh has been sanctioned and a sum of Rs.6.70 lakh was
already disbursed. NHB has been requested to supervise the work carried on the
complainant either by way of survey or otherwise so that subsidy be provided as
per rules in time. This letter is dated
13.09.2004. The letters placed on record by the opposite parties as well as the
complainant are sufficient enough to convince us that subsidy was to be provided
by opposite party No.1 if the project file of the complainant is sent to the
opposite party No.1 in time but the same was not on 26.07.2005 after a period
of near about 11 months after half of the loan amount was disbursed.  

 

5. The learned counsel for the petitioner
vehemently argued that he is not asking for subsidy, but the main ground is
that of delay. 6. We do not agree with the learned counsel for the
petitioner. The complaint itself in Para
Nos. 8, 9, 11, mentions about the subsidy. The District Forum also came to the conclusion
that subsidy was not given due to delay.
The principal question is that of grant of subsidy. The order passed by
the learned State Commission is supported by authorities, which clearly go to
show that the subsidy offered to be paid is not service as defined in
Consumer Protection Act, 1986.
Consequently, the
petitioner/complainant is not a consumer.
The State Commission has referred to the order of this Commission
reported in Himachal Weavers Pvt. Ltd. Vs.
Himachal Pradesh Financial Corporation & Ors., III (1993) CPJ 267 (NC). He has also referred to two authorities of
the orders passed by the State Commission.
Consequently, the revision petition filed by the petitioner/complainant
is lame of strength, therefore, the same is hereby dismissed. Nothing will debar the petitioner/complainant from seeking relief from another forum or the
civil court, as per law. The
petitioner/complainant can seek support from the celebrated authority in Laxmi
Engineering Works Vs. P.S.G. Industrial  Institute  (1995) 3 SCC 583. 

 

  .. 

(J. M. MALIK,J.) PRESIDING MEMBER   ...

(VINAY KUMAR) MEMBER dd/11