Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 2]

State Consumer Disputes Redressal Commission

C.G. State Electrictiy Supply Company ... vs Suresh Prasad on 29 November, 2012

                CHHATTISGARH STATE 
    CONSUMER DISPUTES REDRESSAL COMMISSION, 
                PANDRI, RAIPUR (C.G.) 
                                                              (A/11/2743)   
                                                     Appeal No.462/2011 
                                                Instituted on : 18.08.2011  
 
1.

  G.G. State Electricity Supply Company Limited,  Through : Junior Engineer,  Rajpur (C.G.)   

2.   Executive Engineer,  C.G. State Electricity Supply Company Limited,  Ambikapur (C.G.)                     ....   Appellants. 

 

           Vs.    Suresh Prasad, S/o Late Shri Ramvriksha,  R/o : Village : Dadhkhadua, Police Station & Tehsil  

- Rajpur, District ‐  Sarguja (C.G.)              ....  Respondent.    PRESENT : 

HONʹBLE SHRI JUSTICE  S.C. VYAS, PRESIDENT  HON'BLE SHRI V.K. PATIL, MEMBER    COUNSEL FOR THE PARTIES : 
Shri R.K. Bhawnani, for appellant. 
Shri K. Anandani, for respondent. 
 
ORDER (ORAL)  DATED : 29/11/2012  PER :‐ HON'BLE SHRI JUSTICE  S.C. VYAS, PRESIDENT.    This  appeal  is  an  appeal  of  the  OPs/Electricity  Supply  Company, who has  been directed by the District Consumer Disputes  Redressal  Forum,    Sarguja  -  Ambikapur  (C.G.)  (hereinafter  called  "District Forum" for short), in Complaint Case No.92/2007 vide order  // {PAGE } // dated 21.07.2011 to restore the electricity supply from  three phase  for  the  purpose  of  irrigation  to  the  respondent/complainant  within  15  days  from  the  date  of  order.    The  respondent/complainant  was  also  directed to  produce test report of the qualified contractor within one  month  from  the  date  of  order.    It  has  further  been  directed  by  the  impugned  order  that  the  bills  issued  by  the  appellant  company  for  Rs.2,666/‐  on  20.03.2006  and  another  bill  of  Rs.6,519/‐  of  February,  2007,  stand  quashed.    The  appellant  company  has  further  been  directed  to  pay  Rs.2,000/‐  as  compensation  for  mental  agony  and  Rs.1,000/‐ as cost of litigation to the respondent/complainant. 
2.  Undisputedly,  the  respondent/complainant  is  having  agricultural  land  and  he  applied  for  providing  electricity  supply  connection for irrigation, so that his land can be  irrigated by  electric  motor pump  to be operated on three phase.  It is also not in dispute  that  the  appellant  company  completed  work  of  installation  of  electricity pole etc., but the supply was not started. 
3.  The  case  of  the  respondent/complainant  before  the  District  Forum was that the appellant company left the work incomplete and  has not started electricity supply for running the irrigation pump, but  in spite of that  it has unnecessarily  issued demand bills in the month  // {PAGE } // of December, 2005  & February,  2007, though notice was already sent  to the appellant company in this regard, but even then supply was not  started  and  demand  was  not  withdrawn,  so  the  consumer  complaint  was filed before the District Forum. 
4.  The appellant Company in reply averred that in the year 2004,  in the month of January, the work of installation of electricity supply  line    through  pole  was  completed  and  the  respondent/complainant  was  directed  to  file  test  report  of  a  qualified  contractor  within  three  months, so that supply can be started, but that report was not filed by  the  respondent/complainant  till  filing  of  the  consumer  complaint  before  the  District  Forum.    It  has  further  been  averred  that  on  24.10.2007,  competent officer  of the  appellant  company inspected the  spot  and  found  that  respondent/complainant  was  using  3  H.P.  irrigation  motor    pump  by  illegally  &  directly  connecting  from  main  supply line.  When it was observed, then a bill was issued for demand  of  charges.    It  has  further  been  averred  that  as  per  terms  of  the  contract, the respondent/complainant was  required to pay  charges at  least on minimum average basis from the date when line was installed  and the report of the contractor was not  submitted within stipulated  period, thus the appellant company has not  committed any deficiency  in service in issuing bills. 

// {PAGE } //

5.  Learned District Forum did not agree with the defences raised  by  the  appellant  company  and  allowed  the  complaint  by  the  impugned order. 

6.  Before us the appellant company has filed affidavit of Shri S.P.  Markam,  Assistant  Engineer,  C.G.  State  Electricity  Supply  Company  Ltd.,  Rajpur,  District  Balrampur  (C.G.)  along  with  statement  of  the  bills  issued  to  the  respondent/complainant  in  respect  of  use  of  electricity  from  the  line  which  was  installed  for  running  3  H.P.  irrigation  pump.    On  the  basis  of  these  documents,  it  has  been  contended  by  learned  counsel  for  the  appellants  that  on  28.01.2004  when  respondent/complainant  was  asked  to  submit  report  of  a  qualified  contractor  within  a  stipulated  time  and  when  such  report  was  not  submitted,  then  as  per    terms  of  the  contract,  the  respondent/complainant was to pay at least the minimum charges for  running the pump.  It has further been submitted by learned counsel  for  the  appellants  that  such  letter  was  issued  and  contract  was  also  signed  by  the  respondent/complainant,  which  is  in  possession  of  the  appellant company. 

7.  Learned  counsel  for  the  respondent/complainant  submitted  that  no  such  letter  dated  28.01.2004  was  ever  received  by  the  // {PAGE } // respondent/complainant.  It was never sent by the appellant company  to  the  respondent/complainant  and  no  report  of  any  qualified  contractor  was  ever  demanded.    It  was  a  cooked  up  story  of  the  appellant company. 

8.  From the aforesaid contentions of both parties and after going  through the record of  the District Forum, we find that for the purpose  of  settling  the  dispute  between  the  parties,  it  is  necessary  to  go  through  the  terms  of  the  contract  executed  between  the  parties  regarding supply of electricity.  It is also necessary for the appellants  to  show  that  letter  dated  28.01.2004    was  actually  sent  to  the  respondent/complainant and demand was made for submitting report  of  a  qualified  contractor  within  stipulated  period,  otherwise  irrespective of the fact, whether supply has been started or not, as per  terms of the contract, the respondent/complainant would be required  to pay charges and bills will be generated.  It is also necessary to see  whether  thereafter    bills  were  regularly  sent  by  the  appellants  to  the  respondent/complainant  or  not.    Respondent/complainant  is  also  required to submit report of  a qualified contractor, as per demand of  the  appellant  company.    For  doing  the  entire  aforesaid  exercise,  it  appears necessary to us to remit the case back to the District Forum so  that new evidence can be led by both the parties. 

// {PAGE } //

9.  In view of aforesaid, without expressing any further opinion on  the merits of the case, the appeal is allowed and the impugned order  is  set  aside.    The  case  is  remanded  back  to  the  District  Forum  with   direction to provide opportunity of filing documents and affidavits on  behalf  of  both  parties  and  thereafter  to  decide  the  matter  afresh  on  merits.    Affidavit  of  Shri    S.P.  Markam,  Assistant  Engineer  of  the  appellant  company  as  well  as  the  statement  regarding  bills  of  sanctioned  load  of  3  H.P.,  filed  by  the  appellants  before  us    be  also  sent to the  District Forum along with its record.   Parties are directed  to appear before District Forum on 28.12.2012.  No order as to the cost  of this appeal. 

   
        (Justice S.C.Vyas)                                                      (V.K. Patil) 
               President                                                           Member 
                    /11/2012                                                           /11/2012