Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 4, Cited by 0]

National Green Tribunal

Dr Bharat Jhunjhunwala vs Ministry Of Environment Forests ... on 16 August, 2022

Author: Adarsh Kumar Goel

Bench: Adarsh Kumar Goel

Item No. 01                                                          (Court No. 1)

               BEFORE THE NATIONAL GREEN TRIBUNAL
                   PRINCIPAL BENCH, NEW DELHI

                            (By Video Conferencing)

                              Appeal No. 21/2021


Dr. Bharat Jhunjhunwala & Anr.                                        Appellant(s)

                                      Versus


Union of India & Ors.                                              Respondent(s)



Date of hearing:    16.08.2022


CORAM:        HON'BLE MR. JUSTICE ADARSH KUMAR GOEL, CHAIRPERSON
              HON'BLE MR. JUSTICE SUDHIR AGARWAL, JUDICIAL MEMBER
              HON'BLE PROF. A. SENTHIL VEL, EXPERT MEMBER


Appellant:    Mr. Ankur Sood, Advocate

Respondent:   Mr. Kumar Rajesh Singh, Advocate for MoEF & CC (R - 1)
              Mr. Dhruv Dewan, Advocate for M/s THDC India Limited (R - 3)




                                     ORDER

The issue raised - validity of EC for Vishnugad-Pipalkoti Hydro- Electric Project in Uttrakhand

1. This is an Appeal under section 16 (h) of the NGT Act against Environment Clearance (EC) dated 26.08.2021 granted by MoEF&CC to the Vishnugad-Pipalkoti Hydro-Electric Project of 444 MW in an area of 141.568 ha by M/s THDC India Limited located at Village Haat, Tehsil Joshimath, District Chamoli, Uttarakhand.

2. The appellants have stated that Initially EC for the project was granted on 22.08.2007 for ten years, which was extended for three years and has been now extended upto 21.08.2021. However, the project has not 1 been operationalized and is still under construction. The project is funded by the World Bank. Out of total cost of about Rs. 3800 Crores, more than 50% of the cost has already been incurred.

3. According to the appellant, Cost Benefit Analysis (CBA) is in favour of abandoning the project. Dispensing with of public hearing is not called for nor valid as the project is not completed to the extent of 50 %, as required for such exemption. EAC has not undertaken proper evaluation of the mitigation measures. It has gone by rapid EIA, ignoring the deficiencies, particularly impacts of soil erosion, blasting, decline in water quality, loss of aesthetic values and loss of aquatic biodiversity. These impacts have not been duly evaluated nor included in the CBA. The scope of the project has changed as noted in the EAC Minutes, in comparison to the 2006 DPR, as per information shown by the following table:-

"   Item            2006 DPR          2021 EAC              Change
                                      Minutes
                    (Annexure A-
                                      (Annexure A-12)
                    13)

    DIVERSION TUNNEL



    Length          490               559 m (494 m        +69 m
                                      tunnel and 65 m cut
                                      & cover)

    Diameter        10                10.5 m, Circular      +0.5m

    Gates           10m*10m           4 m * 10.5m,          +58 sqm
                                      vertical lift fixed
                                      wheel

    Ibvert level    1228              1224m                 -4m
    at entry

    Height          15 m              24 m                  +9 m

    Length          46 m              40 m                  -6 m


                                                                               2
 Height        6m                7.5 m                    +1.5 m

Top EL        1228              EL 1222.5 m              -5.5

DIVERSION DAM

Length        89.3              98.85 m (NOF             +9.55 m
                                31.85 m, OF 67 m)

SPILLING ARRANGEMENT

A. Sluices:

Nos.          4                 5                        +1

Design        8004              10840 m3/sec             +2836 m
Flood

Size of       6.6*15            7.8m (W) * 16 m (H)      +25.8
sluice

B.            10                Diameter 10.5 (),       +0.5 m
Diversion                       Circular
Cum
Spillway
Tunnel

Length        490               100 m                    -390 m

Design        1074              1578 m3/sec              +504
Discharge

Gate          2+1, 4.1 m * 10   2+1 no., 4 m* 10.5       + 1 sqm
              m                 (Vertical lift fixed
                                                         (4.1x10>4x10.5)
                                wheel gate)

DESILTING
CHAMBER

Size          350*16m*20.6      390m (L) * 16 m (W)      + 17240
              m                 * 21.25 m (H)

Gates         2.5*2.85          3 Nos. 1.8 m*2.12        -3.309
                                m (Vertical lift slide
                                gate)

HEAD
RACE
TUNNEL

Diameter      8.8 horse shoe    8.8 m Circular           Shape change

Velocity      3.56              3.76 m/sec               +0.2




                                                                           3
 Bed slope       1.208         1:121 (upstream of      -8.087
(average)                     Maina River 1:321)
                              Downstream of
                              Maina River)

UPSTREAM
SURGESHA
FT

Height (from    130           154 m                   +24 m
HRT invert)

Top EL          1305          1309 m                  +4 m

Orifice level   1185          1165 m                  -20m

Tunnel          1175          EL 1155 m               -20m
invert

Maximum         1304          1307.42m                +3.42m
surge level

PRESSURE
SHAFT

Length of       351/36.7      466.4 m/51m             -0.41893466
each PS

POWER
HOUSE

Size of P/H     127*20.3*50   146m*20.3m*48m          +13357.4
cavern

Size of         112*16*24.5   140.3m*15m*25.5         +9760.75
transformer                   m
cavern

Service bay     1041          EL 1036m                -5
level

D/S SURGE
TANK

Size            120*12*27     150m (L)*13m (W) *      +13770
                              27 m (H)

Minimum         1026.5        1022.37 m               -4.13
surge level

TAIL RACE
TUNNEL

a) Size         8.8           9.1 m (), (Circular)   +0.3



                                                                    4
          d) Min.           1027.2          1028.2 m (with 10% +1
         TWL                               load)

         e) TRT            1025            EL 1020.6 (at            -4.4
         invert level                      Outlet) crest level of
                                           weir at outlet is
                                           1027 m.

         SWITCHYA
         RD

         e) No. of         8               7 bays                   -1
         bays in the
         switchyard

         d) Size of        40*60m          40m*84m                  +960               "
         Potyard



4. The appellants have further submitted that the Project has also undergone design review as per THDC progress report of July 2021. The appellant has also presented following tables to show that only 10% of the total constructions have been done and not 50% as claimed: Table No. 1

" S. Work Present status of Analysis Percent No. the project as per completed CEA July 2021 report (Annexure A-16)
1. De-silting 3 De-silting - 40.0 chambers Chambers benching 40% completed
2. HRT-TBM Heading excavation Length of Head 5.5 commissioned of HRT by DBM has Race Tunnel is but no been completed 739 13.4 km. of this progress out of 960m. TBM (1) 739 m DBM;
                               has            been   and nil HRT has
                               commissioned.         been completed
                               During operation of   as     TBM      is
                               TBM in the RBM        hampered. Thus
                               zone, big boulders    739/13400+
                               have           been   5.5% is complete
                               encountered, which
                               has been hampered
                               TBM operation. To

                                                                                       5
                       overcome        this
                      problem         two
                      approach adits are
                      being constructed to
                      reach   the   cutter
                      head.

    3.   Tail Race    In TRT, heading Although this is 14.4
         Tunnel       excavation 443 m only excavation,
                      out    of   3070m yet giving benefit
                      completed         of doubt we may
                                        consider
                                        443/3070=14.4%
                                        complete.

    4.   Barrage      -                      As     per     our 0.0
                                             information zero
                                             work is done.
                                             Silence in CEA
                                             Progress    report
                                             confirms this.

    5.   Electro-     Supply works of Rs. The       cost     of
mechanical 167.60 Crore has Electro-
         works        been completed.       mechanical
                                            works         was
                      Total project cost is
                                            473.64 Crores out
                      4397 Crore.
                                            of project cost of
                                            2031.64 Crore as
                                            per           TEC
                                            (Annexure A-17)
                                            Pro-rata the cost
                                            of         Electro-
                                            mechanical
                                            works will be
                                            1024 crore at
                                            project cost of
                                            4397 Crore of this
                                            167.60 Crore of
                                            16.3%            is
                                            completed.

    6.   Average                                                  15.2       "



                                 Table No. 2

" EAC minutes 29th July THDC progress report CEA Report July 2020 July 2021 2021 6 Annexure A-6) (Annexure A-14 (Annexure A-16) Physical progress of major Total expenditure is Vishnugad Pipalkoti works including Financial 2271.35 Cr.
progress as on 30th June,
2020 is as under:                                      THDC       21.08.2008
                                                       4x111-444 MW Broad
 25% of Civil & Hydro
  Mechanical works                                     features Dam - 65m
  completed.                                           High 89.3 m long,
 28% of Electro                                       concrete gravity HRT
  Mechanical works                                     13.4 Km, 8.8 dia Horse
  completed.                                           shoe shape P. House
Overall investment is Rs.                              Underground 124m X
1971.95 Cr.                                            20.3m x 50m Turbine
                                                       Francis    SWYD      -
                                                       13.8/420 KV Cost :
                                                       Original       2491.58 "
                                                       Latest: 4397.8



  Procedural History

5. The matter was first considered on 08.10.2021. Considering the contentions of the appellants, the Tribunal issued notice to MoEF&CC and the Project Proponent (PP) who filed their respective response. The appellants have filed rejoinder and also additional affidavit annexing their suggestions for further mitigation measures. In the light of rival stands, we proceed to determine the issue of validity of EC. Stand of MoEF&CC
6. The stand of MoEF&CC is that the proposal was considered by the EAC as a fresh proposal with fresh data about environmental parameters, project profile etc. mentioned in the REIA alongwith the data in the original EIA/EMP report and the salient features of the project. EAC examined all aspects including compliance of environmental safeguards, conditions of the earlier EC, change in scope of the project, need of repeat public hearing, existing environmental conditions and all possible environmental concerns in a holistic manner. Suitable safeguards and measures were suggested 7 while recommending the project for grant of de-novo Environmental Clearance. Fresh evaluation was conducted by EAC in its 15th meeting held on 27.07.2021. ToR's covered the salient features of the project. Data relating to environmental aspects has been noted along with the mitigation measures and the Environmental Management Plan to be implemented by Forest Department, PP and the Contractor. There are also provisions for Fish Management Plan, e-flow and other specific and general conditions. Standard EC conditions for River Valley and Hydroelectric projects have also been incorporated. Further, there is a note of discussion in the meeting of EAC held on 28.10.2021 and 25.11.2021 to consider the observation of the Tribunal dated 08.10.2021. Fresh EMP involves Capital Cost of Rs. 1291.03 lakhs.
Stand of the PP
7. The PP has submitted that delay in completion of the project is not attributable to it. Reasons for delay include proceedings for Forest Clearance and seeking EC de-novo. Fresh EC has been granted on 26.08.2021 on the recommendations of the EAC. The PP submitted Draft REIA report prepared by M/s WAPCOS. In the said report, Cost Benefit Ratio has been presented. There is no requirement of fresh EIA or public consultation as scope of the project has not undergone any major change. Only certain components were optimized in the light of site requirement without changing basic design and main parameters. There is no change in
(i) the purpose and installed capacity of the project;
(ii) Height and Top elevation of the Dam;
(iii) Storage capacities and submergence area of the project;
      (iv)    Hydrology of the project;



                                                                         8
       (v)     Peak Maximum Flood (PMF);

      (vi)    Design discharge of the project area is same as stipulated in

              the DPR.

(vii) The project has been implemented to the extent of 53.05% justifying exemption for public hearing as per applicable norms.

8. MoEF&CC accorded ToR on 02.03.2021 for preparation of EIA/ EMP based on one-season fresh data. Additional conditions have been imposed in light of changed circumstances to take care of potential adverse impact such as sedimentation, fugitive emissions, blasting operations, pollution due to increased vehicular movement etc. The PP has explained that there are no shortcomings in the REIA which considers the impact of soil erosion, blasting, aquatic bio-diversity, water quality, loss of aesthetic values, presence of RET Species.

9. The PP has undertaken measures which include installation of watch towers, providing logistic assistance to Forest Department for monitoring of Nanda Devi Bio-sphere Reserve (NDBR), Joshimath and Compensatory Afforestation and other works. There is no potential for flooding on account of the project. The riverbed level near the project has not risen. The deposited muck around coffer dam has also been cleared. Mitigation measures also cover slope stabilization measures such as construction of a diversion tunnel, trail race tunnel area etc. Additional affidavit and rejoinder of the Appellants

10. The appellants have filed an additional affidavit on 30.03.2022 along with a copy of representation dated 10.11.2021 made to the EAC suggesting further measures for reduction of environmental and social 9 impact of the project. The appellant has also filed rejoinder to the reply of MoEF&CC and the PP reiterating the stand that the project has not been completed to the extent of 50% and thus, public hearing could not be exempted. It is further reiterated that the project should have been appraised as a fresh proposal. Entire process of scoping, public consultation and appraisal should have been undertaken afresh.

11. We have heard learned Counsel for the parties and considered the rival submissions.

Consideration of rival contentions and finding

12. On due consideration, we find that EC dated 26.08.2021 by the MoEF&CC for the project is not liable to be interfered except for laying down additional safeguards and conditions in execution of the project.

13. As already noted, the initial EC was granted on 22.08.2007. Validity of the EC was for 10 years which was further extended for three years. The project is crucial for generation of electricity in remote areas. More than 50% project has been executed. More than Rs.2000 crores of public money spent. Delay in completing the project has been explained. Thus, there is no illegality in exempting public consultation. Fresh appraisal has been conducted with the help of Rapid EIA and presentations of the PP. Significant environmental issues of soil erosions, blasting, water quality, aesthetic values and loss of aquatic biodiversity have been addressed. Fresh EC has been granted after assessment of adverse impacts due to change in the scope of work, mitigation measures proposed by the PP in the EMP laying down appropriate conditions for the EC. There are provisions in the EMP for Disaster Management Measures, strengthening of impediments and other forcible impacts on fragile Himalayan 10 Geomorphology. Concern of obstructing the movement of fisheries which may adversely affect the local communities has also been taken into account. Impact on habitations upstream and downstream areas by flooding, landslides etc. has also been considered. After order of this Tribunal, there have been further deliberations by the EAC in light of observations of this Tribunal, on consideration of concerns raised by the appellants. EAC found that environmental impacts of the Project have been minimized by the conditions laid down in the EC and enhancement of capital cost of the EMP to Rs. 1291.03 lakhs. It may thus be difficult to hold that grant of EC is without considering the impact on environment.

14. As noted earlier and shown by the response of the MoEF&CC and PP, there has been a fresh appraisal by the EAC based on REIA, exempting public consultation in view of the fact that more than 50 % of the cost of the project had already been initiated. More than Rs. 2000 crores have been invested in the project which has been executed beyond 50%. The EAC has addressed the issues of environmental impacts including soil erosion, declining water quality, loss of aesthetic value, loss of aquatic biodiversity and impact of blasting and made detailed provisions to offset the adverse impact. It is not necessary to reproduce all the measures envisaged in executing the project which are provided in detail in the REIA. There is no procedural illegality in EC dated 26.08.2021, subject to conditions laid down therein. The project is funded by the World Bank.

15. However, strenuous monitoring mechanism is required to be provided especially for areas prone to landslides and to prevent damage to the dam and other infrastructure.

11

16. There is also need to maintain e-flow in accordance with the norms notified by Central Government1 and directions of the Tribunal dated 25.9.2019 read with further orders dated 3.12.2019 and 07.09.2020 in O.A. No. 425/2019, Vijay Kumar vs. State of Himachal Pradesh. Relevant extracts from the said orders are as follows:-

Order dated 3.12.2019 "4. The recommendations mentioned in the above report (para 5 quoted above) may be duly complied.
5. As already observed in the order dated 25.09.2019, maintaining minimum flow is necessary for the riverine ecology and such requirement cannot be dispensed with.

The SPCB may ensure compliance of such mandate not only for all the units set up after 09.09.2005 when such regime was introduced prospectively, but also to pre- existing units, for future. The order of this Tribunal does not debar such a course. It merely records statement of Counsel for the applicant that the regime is prospective. Once it is held that such flow is necessary for maintaining riverine ecology, there cannot be exemption to any hydroelectric project irrespective the date of setting up for all times to come. All that can be done for the units already set up is not taking any action for the past and putting them to due notice for compliance from a future date. Since it is stated that an appeal i.e. Civil Appeal No. 1657/2018, Bharat Jhunjhunwala vs Pushp Saini & Ors. is pending before the Hon'ble Supreme Court, the present order will be subject to any further order which may be passed in the said appeal.

6. We are also of the view that similar course of action needs to be adopted with regard to hydroelectric projects in other States, including Uttarakhand, Sikkim, Arunachal Pradesh, West Bengal (North Region), Assam and Jammu & Kashmir."

Recommendations referred to above have been quoted in earlier para as follows:

"It is submitted that though now Board has issued directions for release of 15 % water to aforementioned 5 non- complying old projects (i.e. BBMB-Pandoh, Shanan Power House, Chamera-I NUIPC, Chamba, Chamera-H-NHPC, Chamba, Baira Siul Chamba) however these old projects have claimed that they are exempted by the State Govt. decision that 1 Notification dated 09.10.2018 issued by Ministry of Water Resources, River Development and Ganga Rejuvenation (NMCG) 12 notification dated 9-9-2005 has prospective effect and such decision was further upheld by this Hon'ble Tribunal vide order dated 20-11-2014. Moreover, they have also intimated that issue of 15% release of water by all HEPs is sub judice in a Civil Appeal No. 1657/2018 titled Bharat Jhunjhunwala vs Pushp Saini & Ors. before the Hon'ble Supreme Court of India. Therefore, it is humbly prayed that the afore-cited order dated 20-11-2014 may be relooked into or modified keeping in view the situation mentioned above, so that release of 15% water from old projects could also be ensured.
6. It is submitted that the State Board has issued directions to 21 non-complying HEPs less than 25 MW to adopt the mechanism recommended by Joint Committee for release of 15% water from the 1 IP. so that it could be monitored by the State Pollution Control Board. In this regard some of the projects represented that though they are releasing 15% water from HEN however, they require three months time for installation of necessary devices for measurement of 15% flow. Hence it is humbly prayed that three months time may kindly be granted to ensure implementation of recommendations of the Committee for installation of necessary devices for monitoring/measurement of 15% flow of water from HEPs."

17. Further, we find it necessary to lay down additional conditions for grant of EC. Capital cost of EMP will stand increased to 10% of the total project cost. There will be six-member Monitoring Cell to oversee execution of mitigation measures to prevent damage to the dam, the infrastructure and the habitation upstream and downstream the dam. It will be headed by the Chief Secretary, Uttarakhand, other Members being nominees of State Disaster Management Authority, MoEF&CC having expertise in dealing with of River Valley Projects, preferably belonging to Uttarakhand, NMCG, G.B. Pant National Institute of Himalayan Environment, Almora, State PCB and Director of Coldwater Fisheries Research, ICAR, Bhimtal, District Nainital, Uttarakhand. The Committee can coopt any other expert/organisation as may be found necessary. It can conduct proceedings on line or otherwise. It may initially meet within one month to take stock of the situation and plan further action and thereafter, it may meet at such intervals as may be decided but not beyond three months. 13 The Monitoring Committee may consider any suggestions from any stake holder, including the appellants and consider fresh measures to ensure compliance of EC conditions and additional conditions laid down by this order and also such other conditions found necessary for mitigation of adverse measures in the course of the project. Its minutes may be placed on the website of the PP.

The appeal is disposed of accordingly.

A copy of this order be forwarded to the Chief Secretary, Uttarakhand, State Disaster Management Authority, MoEF&CC, NMCG, G.B. Pant National Institute of Himalayan Environment, Almora, State PCB and Director, Cold Water Fisheries, ICAR by e-mail for compliance.

Adarsh Kumar Goel, CP Sudhir Agarwal, JM Prof. A. Senthil Vel, EM August 16, 2022 Appeal No. 21/2021 SN 14