Court No. - 3 Case :- CONSOLIDATION No. - 120 of 2001 Petitioner :- Babu Lal Tewari Respondent :- Deputy Director Of Consolidation,Sultanpur Petitioner Counsel :- Nilish Anand,Puttu Lal Mishra,Raj Kumar Pandey Respondent Counsel :- C.S.C.,Mattool Ali,R.N. Gupta Hon'ble Shri Narayan Shukla,J.
Cause shown in the affidavit filed in support of this application is sufficient. Application is allowed.