Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Section 12(1)] [Section 12] [Entire Act]

State of Odisha - Subsection

Section 12(1)(iii) in Orissa Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulation, 2005

(iii)The application shall be accompanied by a non-refundable application fee of rupees one lakh [per MW] [Inserted vide Orissa Gazette Extraordinary No. 1010, dated 18.7.2006.] for transmission access and rupees fifty thousand [per 500 KW] [Inserted vide Orissa Gazette Extraordinary No. 1010, dated 18.7.2006.] for distribution access payable in the name and in the manner to be decided by the nodal agency;