Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 13, Cited by 1]

Delhi High Court

National Highway Authority Of India vs M/S Gmr Pochanpalli Expressways Ltd on 6 April, 2022

Author: C. Hari Shankar

Bench: C. Hari Shankar

                            $~
                            *     IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                                Reserved on: 16th November, 2021
                                                                       Decided on: 6th April, 2022


                            +     O.M.P. (COMM) 433/2020, IA 4775/2020 and IA 8408/2021

                                  M/S GMR POCHANPALLI
                                  EXPRESSWAYS LTD                          ..... Petitioner
                                               Through     Mr. Atul Sharma, Ms. Milanka
                                               Chaudhury, Mr. Abhinav Agnihotri and Ms.
                                               Harshita Agarwal, Advs.

                                                      versus

                                  NATIONAL HIGHWAY
                                  AUTHORITY OF INDIA                       ..... Respondent
                                               Through    Mr. Dayan Krishnan, Sr.
                                               Advocate with Mr. Ankur Mittal, Mr. Abhay
                                               Gupta and Ms. Sukrit, Advs.

                            +     O.M.P. (COMM) 449/2020, I.A. 6682/2020 and I.A. 6683/2020

                                  NATIONAL HIGHWAY
                                  AUTHORITY OF INDIA                       ..... Petitioner
                                               Through    Mr. Dayan Krishnan, Sr.
                                               Advocate with Mr. Ankur Mittal, Mr. Abhay
                                               Gupta and Ms.Sukrit, Advs.

                                                      versus

                                  M/S GMR POCHANPALLI
                                  EXPRESSWAYS LTD                        ..... Respondent
                                               Through     Mr. Atul Sharma, Ms. Milanka
                                               Chaudhury, Mr. Abhinav Agnihotri and Ms.
                                               Harshita Agarwal, Advs.


Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 1 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             CORAM:
                            HON'BLE MR. JUSTICE C. HARI SHANKAR

                            %                  JUDGMENT
                                                 06.04.2022

                            1.    Both these petitions, under Section 34 of the Arbitration and
                            Conciliation Act, 1996, ("the 1996 Act") assail an award dated 14th
                            January, 2020, passed by a learned three member Arbitral Tribunal.
                            The award was passed by a majority of two learned members to one.
                            GMR Pochanpalli Expressways Ltd ("GMR") was the claimant before
                            the learned Arbitral Tribunal and National Highway Authority of India
                            ("NHAI") was the respondent. GMR preferred five claims, whereas
                            NHAI preferred a single counter-claim for the costs of the arbitration.
                            Of the five claims preferred by GMR, the learned Arbitral Tribunal,
                            per majority, rejected Claims 1, 3 and 4 and allowed Claims 2 and 5.
                            As Claim 5 of GMR pertains to awarding of costs as per actuals,
                            allowing of the said claim also resulted in the rejection of the counter-
                            claim of NHAI. The minority award rejected all five claims of GMR.


                            2.    GMR and NHAI have both assailed the impugned award, to the
                            extent that the award has rejected their respective claims/counter-
                            claims and allowed the claim of the opposite party.


                            A Prefatory Note


                            3.    During the course of arguments, in this case, Mr. Atul Sharma,
                            learned counsel for GMR, drew the attention of the Court to the fact
                            that, in an earlier award dated 21st August 2019 between NHAI and
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 2 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Nirmal BOT Ltd, another contractor, in similar circumstances and
                            involving an identically worded contract, the very issues which
                            constituted subject matter of Claim 1 of GMR in the present case had
                            arisen for consideration before another three member Arbitral
                            Tribunal. The award in that case, which was rendered prior in point of
                            time to the impugned award, has been placed on record. Paras 8.2.9 to
                            8.2.20 of the said award indicate that the learned Arbitral Tribunal,
                            which was in seisin of the dispute in that case has interpreted the very
                            clauses with which the learned Arbitral Tribunal in the present case
                            was concerned and that the interpretations of the relevant clauses in
                            the two awards are diametrically opposed to each other.


                            4.         This does not appear to be an isolated phenomenon. The
                            Supreme Court, in NHAI v. Progressive-MVR (JV)1, observed, in
                            para 15 of the report, thus:
                                       "15. Thus, the main reason because of which the NHAI lost
                                       in those proceedings was that two possible interpretations
                                       could be given to the Clause in question and, therefore, the
                                       recourse taken by the Arbitral Tribunal by adopting one
                                       particular interpretation was not required to be interfered
                                       with. SLP against that was dismissed. In a situation like this,
                                       this Court would not have undertaken further exercise in the
                                       matter. However, another Arbitral Tribunal in the case of
                                       M/s. Ssangyong Engineering and Construction Co. Ltd. has
                                       accepted the other view, which goes in favour of the NHAI. It
                                       leads to an anomalous situation. The NHAI has entered into
                                       multiple contracts with different parties containing the same
                                       clauses of price variation. Once we find that Arbitral
                                       Tribunals are taking different views, and the view taken in
                                       favour of the NHAI is also one of the possible interpretations,
                                       the effect thereof would be to uphold both kinds of awards
                                       even when they are conflicting in nature in respect of the

                            1   (2018) 14 SSC 688
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                             Page 3 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   same contractual provision. It may not be appropriate to
                                  countenance such a situation which needs to be remedied.
                                  Therefore, under this peculiar situation, we deem it proper to
                                  go into the exercise of interpreting the said Clause so that
                                  there is a uniformity in the approach of the Arbitral Tribunals
                                  dealing with this particular dispute and a sense of certainty is
                                  attached in the outcomes."


                            5.    NHAI is possibly the only Public Sector Enterprise involved in
                            the largest number of arbitrations, nearly all of which involved
                            substantial claims and counter-claims. The possibility of diverse views
                            being taken by different Arbitral Tribunals in respect of identical
                            contractual clauses, as happened in NHAI v. Progressive-MVR (JV)1
                            and as has happened in the present case, always looms large. In such
                            circumstances, it would be the duty of the NHAI to inform a later
                            Arbitral Tribunal, before which the same issue as has already been
                            considered and decided by an earlier Arbitral Tribunal in identical
                            circumstances, arises, of the earlier award, so that the later Arbitral
                            Tribunal is aware of the view of the earlier Arbitral Tribunal. This
                            fosters uniformity of views, as also public faith in the administration
                            of arbitral justice. Of course, arbitral awards are not binding
                            precedents, and it is always open to the later Arbitral Tribunal to take
                            a different view. At the same time, the import of para 15 of NHAI v.
                            Progressive-MVR (JV)1, which advocates uniformity in arbitral
                            awards involving identical issues cannot be ignored. If, therefore, the
                            later Arbitral Tribunal is to depart from the view of the earlier Arbitral
                            Tribunal, one would expect that it would be for good and cogent
                            reasons, and that, if the later Arbitral Tribunal is of the view that the
                            earlier Arbitral Tribunal has wrongly decided the issue, the reasons for

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                         Page 4 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             that view would be forthcoming in the arbitral award.


                            6.    NHAI having failed to inform the learned Arbitral Tribunal in
                            the present case of the award passed in the case of Nirmal BOT, two
                            contradictory arbitral awards, both by three-member Arbitral
                            Tribunals, having come to be passed. Applying the principle in NHAI
                            v. Progressive-MVR (JV)1, the Court is bound to enunciate what, in its
                            opinion, is the correct legal position. To that extent, I am in agreement
                            with the submissions of Mr. Atul Sharma, learned counsel for NHAI,
                            that the situation envisaged in para 15 of NHAI v. Progressive-MVR
                            (JV)1 constitutes an exception to the general principle of rectitude and
                            reticence, which is required to inform the Section 34 Court.

                            7.           Though Mr. Dayan Krishnan, learned Senior Counsel for
                            GMR sought to contend that NHAI v. Progressive-MVR (JV)1 was
                            rendered under Article 142 of the Constitution and could not constitute
                            a binding precedent, I cannot agree. The judgment in NHAI v.
                            Progressive-MVR (JV)1 does not indicate and it was rendered under
                            Article 142 of the Constitution. It is well settled that courts lower in
                            the judicial hierarchy should not desist from following decisions of the
                            Supreme Court by regarding them as having been rendered in the
                            context of Article 142, unless the precedent in question unmistakably
                            so indicates. Madras Bar Association v. U.O.I.2, in fact, goes to the
                            extent of holding that "the directions issued under Article 142 of the
                            Constitution, are binding on every Court in terms of Article 141 of the
                            Constitution". NHAI v. Progressive-MVR (JV)1 does not purport to
                            have been rendered under Article 142. The contention of Mr. Dayan

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 5 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Krishnan that NHAI v. Progressive-MVR (JV)1 should be treated as
                            having been rendered under Article 142 of the Constitution and is not,
                            therefore, binding, is, accordingly, rejected.

                            Facts

                            8.      With the above prefatory note, one may proceed to the facts in
                            which the present dispute arises.


                            9.      The present dispute involves a contract for "Design,
                            Construction, Development, Finance, Operation and Maintenance of
                            k.m. 367.000 (Adloor Yellareddy) to k.m. 447.000 (Kalkallu) covering
                            85.745 kilometres, and Improvement, Operation and Maintenance of
                            k.m. 447.000 (Kalkallu) - 464.000 (Gundla Pochanpali) covering
                            17.000 kilometres on National Highway No.7 (NH·7) in the State of
                            Andhra Pradesh" ("the Project", hereinafter).

                            10.     A notice, inviting proposals from contractors interested in
                            undertaking the Project was issued by NHAI on 27th May, 2005.
                            Letter of Acceptance was issued to a consortium of GMR Energy Ltd
                            and GMR Infrastructure Ltd on 30th December, 2005. GMR
                            Pochanpalli Expressways Ltd was incorporated as a Special Purpose
                            Vehicle (SPV) to undertake the project.

                            11.     Consequent thereupon, a Concession Agreement (CA), dated
                            31st March, 2006 was executed between GMR and NHAI. The
                            following clauses of the Concession Agreement are relevant to the
                            present dispute:

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 6 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   "1.2 In this Agreement, unless the context otherwise
                                  requires:
                                                        *****

                                         (k)    the Schedules to this Agreement form an
                                         integral part of this Agreement and will be in full force
                                         and effect as though they were expressly set out in the
                                         body of this Agreement;

                                                              *****

                                  2.1 The Project shall be executed on the Site; which is
                                  described in Schedule 'A' of this Agreement. The scope of the
                                  Project shall include performance and execution by the
                                  Concessionaire of all design, engineering, financing,
                                  procurement, construction, completion, operation and
                                  maintenance of the Project-Hjghway as described in Schedule
                                  'B' and Schedule 'C' of this Agreement. It shall Include (brief
                                  description of the project) in accordance with the
                                  Specifications and Standards set forth in Schedule 'D' and
                                  operation and maintenance thereof in accordance with
                                  Schedule L. It shall also include the performance and
                                  fulfillment of other obligations by the Concessionaire under
                                  this Agreement.

                                  The Concessionaire shall undertake its obligations at its own
                                  cost and risk.

                                                              *****

                                  6.4    Payment Mechanism

                                         (a)    Submission of Invoice

                                         The Concessionaire shall at least month prior to the
                                         relevant Annuity Payment Date submit to the
                                         Independent Consultant, its invoice (addressed to
                                         NHAI) for payment of Annuity duly adjusted for Non-
                                         availability, if any, in accordance with the preceding
                                         Article 6.3. The independent Consultant shall after
                                         verification and certification of the amount claimed in

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 7 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                          the invoice forward the invoice to NHAI with
                                         necessary recommendation for payment thereof so as
                                         to reach NHAI at least one week prior to the relevant
                                         Annuity Payment Date.

                                         (b)   Payment of Annuity

                                         Upon receipt of the invoice together with
                                         recommendation for payment forwarded by the
                                         Independent Consultant, 'NHAI shall take all necessary
                                         steps and ensure payment of Annuity on the relevant
                                         Annuity Payment Date. The mode of payment of
                                         Annuity shall be as provided in Article 23.

                                         For avoidance of doubt, the Parties agree that
                                         notwithstanding arty dispute which either of them may
                                         have as to the amount of invoice/Annuity certified and
                                         recommended for payment by the Independent
                                         Consultant; the Annuity payable on the relevant
                                         Annuity Payment Date shall be that certified by the
                                         Independent Consultant. Provided such payment shall
                                         be without prejudice to a final adjustment according to
                                         the terms on which such dispute is resolved whether
                                         amicably or through arbitration in accordance with the
                                         provisions of Article 39.

                                                             *****

                                  18.2 The Concessionaire shall in consultation with the
                                  Independent Consultant prepare not later than 180 (one
                                  hundred and eighty) days before the Scheduled Project
                                  Completion Date, the repair and maintenance manual (the
                                  "Maintenance Manual") for the regular and periodic
                                  maintenance, and shall ensure and procure that at all times
                                  during the Operations Period, the Project Highway is
                                  maintained in a manner that it complies with the
                                  Specifications and Standards and the minimum maintenance
                                  requirements set forth in Schedule L. The Concessionaire
                                  shall supply, at least two months before the COD, 10 (ten)
                                  copies of the Maintenance Manual to NHAI and 3 (three)
                                  copies each to Government of Andhra Pradesh and
                                  Independent Consultant. Copies of the Maintenance Manual
                                  shall also be made available by the Concessionaire for public
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 8 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   inspection during office hours at a conspicuous place on the
                                  Project Highway.

                                                               *****

                                  18.12 In the event the Concessionaire does not maintain
                                  and/or repair the Project Highway or a part thereof upto and
                                  in accordance with the Specifications and Standards and/or in
                                  accordance with the Maintenance Programme or the
                                  Maintenance Manual, and shall have failed to commence
                                  remedial works within 30 (thirty) days of receipt of notice in
                                  this behalf from NHAI or the Independent Consultant, or the
                                  O&M Inspection Report, as the case may be, NHAI shall,
                                  without prejudice to its rights under. this Agreement,
                                  including Termination thereof, be entitled to undertake the
                                  repair and maintenance Of the Project Highway at the risk
                                  and cost of the Concessionaire and to recover the same from
                                  the Concessionaire. In addition to recovery of the aforesaid
                                  cost of repair and maintenance by NHAI, a sum equal to 25%
                                  (twenty five per cent) of such cost shall also be recovered by
                                  NHAI from the Concessionaire as Damages. NHAI· shall
                                  have the right and the Concessionaire hereby expressly grants
                                  to NHAI the right to recover the same directly from the
                                  Escrow Account and for that purpose the Concessionaire
                                  hereby expressly authorises NHAI and hereby gives
                                  irrevocable instructions to the Escrow 'Bank to make payment
                                  from the Escrow Account in accordance with the instructions
                                  of NHAJ under this Clause.

                                  18.13 In the event NHAI does not exercise its option to
                                  undertake the required repair and maintenance after expiry of
                                  the 30 (thirty) days period stipulated in Clause 18.12 it shall
                                  recover Damages from the Concessionaire for default in
                                  operating and maintaining the Project Highway in conformity
                                  with this Agreement. Such Damages shall be payable after the
                                  aforesaid period 30 (thirty) days and until the default is cured.
                                  The amount of Damages shall be calculated for each day of
                                  default at the higher of the following, namely (a) Rs.10,000
                                  (Rs. Ten thousand), and (b) 0.1% (zero point one per cent) of
                                  the cost of such repair as estimated by the Independent
                                  Consultant. Recovery of such Damages shall be without
                                  prejudice to the rights of NHAI under this Agreement,
                                  including Termination thereof.
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                         Page 9 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   18.14 If the Concessionaire commences any works for curing
                                  any defects or deficiencies in the Project Highway, it shall
                                  complete such works expeditiously in accordance with Good
                                  Industry Practice. If such works are carried out in a manner
                                  that results in a delay of more than 30 (thirty) days as
                                  compared to the time required in accordance with Good
                                  Industry Practice, NHAI shall recover Damages from the
                                  Concessionaire as if a default had occurred under Clause
                                  18.13.

                                                              *****


                                  XIX MONITORING AND SUPERVISION DURING
                                  OPERATION

                                  19.1 The Concessionaire shall undertake periodic (at least
                                  once every calendar month but once every week during
                                  monsoons) inspection of the Project Highway to determine
                                  the condition of the Project Highway including its compliance
                                  or otherwise with the Maintenance Manual; the Maintenance
                                  Programme Specifications and Standards and the
                                  maintenance required and shall submit reports of such
                                  inspection ("Maintenance Reports") to NHAI and the
                                  Independent Consultant.

                                  19.2 The Independent Consultant shall review the
                                  Maintenance Reports and inspect the Project Highway at least
                                  once a month during the Operations Period and make out an
                                  Inspection Report of such inspection (the "O&M Inspection
                                  Report"). The Independent Consultant shall send a copy of its
                                  O&M Inspection Report to NHAI and the Concessionaire,
                                  The Concessionaire shall within 30 (thirty) days of the receipt
                                  of the O&M Inspection Report remedy the defects and
                                  deficiencies, if any, set forth in such O&M Inspection Report
                                  and submit its report in respect thereof to the Independent
                                  Consultant and NHAI within the said 30 (thirty) days period.
                                  Where the remedying of such defects or deficiencies is likely
                                  to take more than 30 (thirty) days in accordance with Good
                                  Industry Practice, the Concessionaire shall undertake the
                                  works in accordance with such practice and submit progress
                                  reports of such works every fortnight. The O&M Inspection
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 10 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   Report may also require the Concessionaire to undertake such
                                  tests as may be specified by the Independent Consultant for
                                  the purpose of determining that the Project Highway is at all
                                  times in conformity with the Specifications and Standards.
                                  The Concessionaire shall undertake such Tests without any
                                  delay and furnish a copy of the results thereof to the
                                  Independent Consultant and NHAI along with a written
                                  statement specifying in reasonable detail the measures, if any,
                                  that it proposes to undertake for curing the defaults or
                                  deficiencies indicated in such results. Such inspection or
                                  submission of O&M Inspection Report by the Independent
                                  Consultant or submission of O&M Inspection Compliance
                                  Report by the Concessionaire shall not relieve or absolve the
                                  Concessionaire of its obligations and liabilities hereunder in
                                  any manner whatsoever.

                                                              *****

                                  XX. INDEPENDENT CONSULTANT

                                  20.1 NHAI shall appoint a consulting engineering firm or
                                  body corporate in accordance with the selection process' set
                                  forth in Schedule 'N' to be the Independent Consultant to
                                  undertake and perform the duties, work, services and
                                  activities set forth in Schedule 'O'. In addition NHAI, at any
                                  time during the Concession Period at its own cost, may
                                  appoint a Technical Auditor in the nature of a Proof
                                  Consultant to review the work carried out by the Independent-
                                  Consultant.

                                                              *****
                                                                             SCHEDULE 'B'

                                                SCOPE OF THE PROJECT

                                  1.     GENERAL

                                  The following sections of this Schedule briefly highlight the
                                  scope of the work of the Project Highway pertaining to
                                  construction package from km 367.00 to 447.00 for the
                                  information of the Concessionaire. The descriptions of the
                                  requirements for the various elements of the Project Highway
                                  given herein under arc the bare minimum requirements that
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 11 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   the Concessionaire needs        to   undertake/provide     for
                                  improvement of the same.

                                  The Concessionaire shall also do the value addition for
                                  improving safety by providing safety items and also provide
                                  road furniture for this BOT package, after handing over to
                                  him to bring it to specified standard· of Project Highway as
                                  per specifications and standards mentioned in Schedule D and
                                  Schedule L.

                                  The designs for different Project facilities shall follow the
                                  locations and indicative designs given in Schedule C and shall
                                  comply with design, specifications and standards outlined in
                                  Schedule D. The maintenance of the different elements of
                                  Project Highway and facilities thereon shall follow the
                                  minimum maintenance requirements as described in Schedule
                                  L. All the designs and drawings shall be reviewed by the
                                  Independent Consultant prior to execution.

                                                             *****

                                                                            SCHEDULE 'D'

                                  SPECIFICATIONS AND STANDARDS

                                  1. INTRODUCTION

                                                             *****

                                  1.6    All works related to the Project Highway shall
                                  conform to the Guidelines and Special Publications as
                                  applicable 10 National Highways and Ministry of Shipping,
                                  Road Transport and Highway earlier Ministry of Road
                                  Transport and Highway (MORT&H) Specifications and
                                  Indian Roads Congress (IRC) standards, Codes, with all
                                  updates till 30 days before the date of bid submission by the
                                  Concessionaire. In the absence of any definite provisions on
                                  any particular issue related to the Specifications and/or
                                  standards, reference may be made to the latest codes and
                                  Specifications of Bureau of Indian Standards, British
                                  Standards, AASHTO, ASTM or any other International
                                  standard in that order. But, where even these are silent, the
                                  construction and completion of the works shall conform to
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 12 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   sound engineering practice with the approval of the
                                  Independent Consultant/NHAI.

                                  1.7    Amendments and/or modifications carried out by the
                                  Ministry of Road Transport and Highway in the MORT&H
                                  Specifications and IRC standards, and codes and available to
                                  public 30 days before the date of receipt of bids shall be
                                  applicable.

                                  1.8    Whenever any specific provision for any building
                                  works is given in the MORT&H Specifications, IRC
                                  standards and codes, those shall apply. All building works
                                  shall conform to Central Public Works Department (CPWD)
                                  Specifications for class 1 building works or standards given in
                                  the National Building Code (NBC) as amended and/or
                                  modified from time to time. For the purpose of this clause,
                                  building works shall be deemed to include road furniture,
                                  landscape elements and/or any other works incidental to the
                                  building works.

                                                              *****
                                                                               SCHEDULE L

                                  OPERATION AND MAINTENANCE REQUIREMENTS

                                  2. Operation and Maintenance (O&M) Requirements

                                                              *****

                                  2.6    Operation and Maintenance Stage

                                  2.6.1 This is applicable for the entire Operations Period for
                                  the Project Highway during the entire Concession Period.
                                  Various important activities to be carried out during this stage
                                  are:

                                        a)      Regular periodic maintenance activities:

                                             i) Renewal of the wearing surface of the road
                                             pavement once every 5 years;

                                             ii) Strengthening course to be provided on 'as
                                             required' basis.
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                         Page 13 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                         b) Maintenance activities arising out of the specific
                                        need(s) on account of the site Conditions are:

                                            i. Strengthening course required on account at the
                                            Benkelman Beam Deflection (B.B.D) values in
                                            excess of the prescribed criteria obtained during
                                            regular testing as per the Concession Agreement
                                            requirement:

                                            ii. Wearing course required on account of the IRI
                                            values higher than the prescribed criteria obtained
                                            during regular testing as per· the Concession
                                            Agreement) requirement;

                                            iii. Localized repairs in short lengths less than 500
                                            m on account of pot holes, racking, subsidence in
                                            isolated spots or in scattered areas.

                                                              *****
                                  4.     MAINTENANCE

                                                              *****

                                  4.2 Maintenance Section of Maintenance Manual

                                                              *****

                                  4.2.1. Regular Maintenance

                                  It consists of the routine maintenance and periodic
                                  maintenance throughout the Concession Period and extension
                                  thereof, if any, for all elements of the Project Highway.

                                                              *****

                                  4.3    Periodic Maintenance of Pavement

                                  The framework of activities relating to pavement maintenance
                                  and rehabilitation in respect of flexible and rigid pavement
                                  are given in the flow charts in Appendix 3.1 and Appendix
                                  3.2 respectively. The Concessionaire shall set forth in the
                                  Operations and Maintenance Manual the detailed procedures
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 14 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   to be followed under each of these activities and also choose
                                  the operational and performance criteria from the
                                  performance standards set forth in this Schedule.

                                                             *****

                                  4.3.1 Pavement Riding Quality

                                  The riding quality of the pavement shall be ensured by
                                  satisfying the minimum requirements given herein under.

                                         i)    Surface roughness of the Project Highway on
                                         completion of construction shall be 2000 mm/km as
                                         measured by vehicle mounted Bump Integrator.

                                         ii)     Surface roughness shall not exceed 3000
                                         mm/km during the service life of pavement at any
                                         time. A renewal coat of bituminous concrete shall be
                                         laid every 5 years after initial construction or where
                                         the roughness value reaches 3000 mm/km whichever is
                                         earlier to bring it to the initial value of2000 mm/km.

                                  4.3.2. Structural Condition of the Pavement

                                         I)     The structural condition of the flexible
                                         pavement of the Project Highway shall be assessed
                                         every year by taking Benkelman Beam Deflections and
                                         working out characteristic deflections of homogeneous
                                         sections of the Project Highway as per IRC-81-1997.
                                         Wherever the characteristic deflection exceeds 1.2 mm
                                         a bituminous overlay shall be provided appropriately
                                         designed according to IRC-81-1997 or its latest
                                         versions or amendments to it.

                                         II)    Recycling of existing crust using milling as an
                                         option can be explored by the Concessionaire in
                                         consultation with the IC to maintain the FRL at the
                                         same level throughout the concession period.
                                         However, while adopting such measures, the residual
                                         strength of existing pavement shall be estimated and
                                         equivalent thickness of new material added before
                                         laying the designed overlay. The design of profile
                                         with altered pavement treatments shall be finalised in
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 15 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                          consultation with IC.

                                         III) In the case of cement concrete pavement, joints
                                         shall be thoroughly inspected every year and the loss
                                         of sealing compounds made good.
                                                        *****
                                  4.4.   Minimum Requirements of Maintenance Activities
                                  4.4.1. Major Breaches in the Roadway
                                  Major breaches in the roadway of any type endanger safety of
                                  traffic and cause obstruction in movement of vehicles. These
                                  breaches shall be repaired urgently. Steps as mentioned in
                                  O&M manual shall be followed by the Concessionaire tor
                                  repairing the breaches.

                                  The Concessionaire shall ensure speedy restoration of traffic
                                  and take immediate action to repair the damages as permanent
                                  measures for the Project Highway. The restoration of traffic
                                  shall be made within 24 hours of its occurrence. The
                                  permanent measures shall be completed within a period of
                                  one week.
                                                                 *****




                                                                 *****
                                  Schedule L                                    Appendix 3

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 16 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   Schedule L                                      Appendix 3.1


                                                 Equivalent Rating Conditions

                                      Category                  Status               Rating
                                  Very Good           On completion as per             9
                                  Condition           specification and
                                                      standards
                                  Good Condition      no repairs needed                8
                                  Generally good      Potential exists for             7
                                  condition           minor maintenance
                                  Fair Condition      Potential exists for             6
                                                      major maintenance
                                  Generally fair      Potential exists for             5
                                  condition           minor maintenance
                                   Marginal condition Potential exists for             4
                                                      major maintenance
                                  Poor Condition      Repair or rehabilitation         3
                                                      required immediately
                                  Critical condition  need for repair or               2
                                                      rehabilitation is urgent.
                                                      Facility should be
                                                      closed until the
                                                      indicated repair is
                                                      complete
                                  Very Critical       Facility is closed. Study        1
                                  condition           should determine the
                                                      feasibility for repair
                                  Unserviceable       Facility is closed and is        0
                                                      beyond repair

                                  Sufficiency Rating System

                                  1.     Load Performance
                                  2.     Safety Performance
                                  3.     Remaining Life"



                            12.   The contract was performed in time by GMR, as it is not in
                            dispute that the Appointed Date for the Project was 25th September,

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 17 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             2006, and GMR had achieved the Provisional Commercial Operation
                            Date (PCOD) and obtained the Final Completion Certificate on 25th
                            July, 2009. The dispute pertains to the operations stage of the contract,
                            after obtaining of the Final Completion Certificate and, primarily, to
                            the interpretation of Clauses 4.3.1 and 4.3.2 read with Appendix 3.1,
                            vis-à-vis Clause 2.6.1, of Schedule L to the CA.


                            13.   On 22nd October, 2012, GMR wrote to MSV International, the
                            Highway Maintenance Engineer/Independent Contractor ("the IC",
                            hereinafter), with a copy marked to NHAI, drawing attention to the
                            requirement of testing of the pavement riding quality, as contained in
                            Clause 4.3.1 of Schedule L to the CA and enclosing, with the letter,
                            the test reports for the year 2012-13 with respect to the project
                            highway. The test reports indicated that the average Roughness Index
                            was, at all points in the highway, found to be less than 2000 mm/km.

                            14.   A similar letter, dated 2nd November, 2013, was addressed by
                            GMR to the IC, enclosing the pavement riding quality/Roughness
                            Index test reports for the year 2013, in respect of the Project Highway.
                            As in the case of the test reports for the year 2012, the Roughness
                            Index was found, at all stretches of the highway, to be less than 2000
                            mm/km.


                            15.   The average Roughness Index for the years 2012 and 2013 were
                            1749 mm/km and 1788 mm/km, respectively.

                            16.   These facts are not in dispute.

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 18 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             17.   Vide letters dated 24th August, 2013 and 23rd September, 2013,
                            the IC wrote to the Project Director, NHAI, drawing attention to
                            Clause 4.3.1 of the CA and pointing out that, both during 2012 and
                            2013, the Roughness Index of the project highway was less than 2000
                            mm/km. The relevant recitals, in the letter dated 23rd September, 2013,
                            may be reproduced thus:


                                  "Roughness Index of the Road:

                                          As per Schedule L of Operations And Maintenance
                                  Requirements, Clause 4.3.1 Pavement Riding Quality, surface
                                  roughness shall not exceed 3000 mm/km during the service
                                  life of pavement at any time. A renewal coat of bituminous
                                  concrete shall be laid every 5 years after initial construction or
                                  where the roughness value reaches 3000 mm/km whichever is
                                  earlier to bring it to the initial value of 2000 mm/km.

                                        In compliance of above concession agreement clause
                                  the Roughness Index of the road has been tested by the
                                  Concessionaire on 09.08.2010 and 22.10.2012.

                                         As per the report the maximum Roughness Index on
                                  09.08.2010 is 1745 mm/km and on 22.10.2012 is 1889
                                  mm/km. In general the Roughness Index of the Project Road
                                  is within the permissible limits of 3000 mm/km as per Cl
                                  4.3.1 of Schedule L of Operation And Maintenance
                                  Requirements of the Concession Agreement."


                            18.   On 31st October, 2013, the Project Director, NHAI, wrote to the
                            IC with the copy marked to GMR, essentially seeking to state that
                            Clause 4.3.1 of Schedule L to the CA mandatorily required fixing of
                            an application of renewal coat of bituminous concrete (alternatively
                            referred to as "overlay") every five years after initial construction.

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                          Page 19 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             The Project Director opined that the requirement of five yearly overlay
                            was independent of the Roughness Index of the highway. Appendix
                            3.1 of Schedule L to the CA was, it was observed in the said letter,
                            required to be read in conjunction with Clause 4.3.1(ii), which
                            required five yearly mandatory laying of a renewal coat. Thus viewed,
                            the communication observed that the first renewal coat was required to
                            be laid on 25th March, 2014.


                            19.   On 14th November, 2013, GMR wrote to the IC, with a copy
                            marked to the Project Director, NHAI, pointing out that the tests
                            conducted in October, 2013 indicated that the Roughness Index, at all
                            places on the project highway, was less than 2000 mm/km and that,
                            therefore, Appendix 3.1 of Schedule L to the CA required GMR to "do
                            nothing". The relevant paragraphs from the said communication may
                            be reproduced thus:
                                  "With reference to the above we wish to bring the following
                                  to your kind notice regarding the periodic maintenance:

                                         The periodic maintenance is mentioned under clause
                                  4.3 of Schedule "L" of Concession Agreement. Clause 4.3
                                  says, "The framework of activities relating to pavement
                                  maintenance and rehabilitation in respect of flexible and rigid
                                  pavement are given in the flow charts in Appendix 3.1 and
                                  Appendix 3.2 respectively." Hence as per 4.3, the first step
                                  shall be as per the framework mentioned in appendix 3.1 and
                                  3.2

                                         As per appendix 3.1, the first step to be carried out
                                  under periodic maintenance is the periodic inspection. The
                                  periodic inspection should be carried out through Roughness
                                  survey and Benkelman bream deflection measurement. Such
                                  test measurements should be compared with the
                                  operation/performance criteria. If the test measurements are
                                  within the operation/performance criteria, appendix 3.1 says
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 20 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   "Do nothing".     If the test measurements are beyond
                                  operation/performance   criteria, appendix  3.1   says
                                  "Renewal/Overlay".

                                          Thus Clause 4.3.1 and the Appendix 3.1 are the same
                                  criteria for deciding the periodic maintenance requirement.
                                  Clause 4.3.1 and 4.3.2 only specify the performance criteria
                                  for comparison purpose under Appendix 3.1.               The
                                  performance criteria for surface roughness are specified as
                                  3000 mm/km under maintenance period and up to 2000
                                  mm/km construction as well as after periodic maintenance.
                                  Thus, if existing surface is already below 2000 mm/km, the
                                  same is classified under "Do nothing" as per Appendix 3.1

                                         The surface roughness as measured during Oct 13 is
                                  below 2000 mm/km at all places. Hence there is no need to
                                  carryout periodic maintenance as there is no need to improve
                                  the surface roughness. Since the test is carried out regularly,
                                  we confirm that we shall carry out the periodic maintenance
                                  of the stretches as and when surface roughness reaches
                                  3000mm/km under these criteria."


                            20.   Apparently influenced by the view expressed by the Project
                            Director, NHAI, in his letter dated 31st October, 2013 supra, the IC,
                            on 18th November, 2013, wrote to GMR, echoing the view of the
                            Project Director to the effect that GMR was required to do
                            renewals/overlay of the highway every five years after construction,
                            irrespective of the Roughness Index of the highway. GMR was,
                            therefore, advised to take up the exercise of renewal/overlay of the
                            highway as per schedule w.e.f. 25th March, 2014.


                            21.   The Project Director, NHAI also wrote to GMR on 5th
                            December, 2013, requiring GMR to submit its programme for laying
                            of the renewal coat on the Project stretch of about 103 km without
                            delay and threatening, in the alternative, to withhold the annuity
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 21 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             payable to GMR for March, 2014.

                            22.   GMR avers that thus pressurized and under duress, a
                            programme for laying of renewal coat was communicated by GMR to
                            NHAI vide letter dated 14th December, 2013, even while objecting to
                            the interpretation of Clause 4.3.1 of schedule L to the CA as advanced
                            by NHAI and reiterating that the said clause required laying of a
                            renewal coat only if the Roughness Index fell below 2000 mm/km.

                            23.   This was followed by a further communication dated 18 th
                            February, 2014 from GMR to the IC, in which GMR informed that it
                            had already submitted the periodic maintenance programme for
                            milling and replacement vide its letter dt. 14.12.2013 (supra). Further
                            details, as requisitioned by the IC, were also provided. It was further
                            informed, in the said communication, that GMR would be disposing of
                            milled bituminous material away from the site of the project at
                            identified locations. Consent for commencement of periodic
                            maintenance activity, as per the programme intimated by GMR was,
                            therefore, sought.

                            24.   The    petition   avers     that,   without   responding    to   the
                            communications dated 14th December, 2013, 12th February, 2014 and
                            18th February, 2014, the IC, on 28th February, 2014, objected to GMR
                            having carried out the renewal work using a milling schedule without
                            prior consultation with the IC. It was also noted, in the said letter, that
                            no programme for milling had been submitted to the IC for approval.
                            Renewal of the bituminous coat via milling having been conducted by
                            GMR     purportedly     without    the    knowledge   of   the   IC,   the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 22 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             communication stated that the activity was undertaken at the risk and
                            cost of GMR.

                            25.   Though the IC and the Project Director recommended release of
                            annuity to GMR, it is alleged that the Chief General Manager, NHAI,
                            in violation of Clause 6.4 (b) of the CA, stopped payment of annuity
                            to GMR.


                            26.   On 27th March, 2014, NHAI wrote to GMR, objecting to the
                            delay, on the part of GMR, in undertaking renewal work for the entire
                            stretch of the project highway, which according to NHAI, would
                            constitute a material breach of the CA. GMR, was, therefore, granted
                            an opportunity to demonstrate that it was making diligent efforts in
                            making all arrangements to take up the renewal work in the entire
                            stretch of 103 km comprising the project highway, without further
                            delay. On the same date, GMR responded to NHAI pointing out that
                            renewal work on the project highway had commenced on 26 th March,
                            2014 and had already been completed for part of the stretch of the
                            Project highway. GMR, nonetheless, sought an opportunity of being
                            heard on the proper interpretation to be accorded to Clause 4.3.1 of the
                            CA, regarding the requirement of renewal/overlay work on the
                            highway, even where the Roughness Index was found to be less than
                            2000 mm/km.


                            27.   Subsequent to the said communication from GMR to NHAI, the
                            annuity was released on 30th March, 2014.


Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 23 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             28.   As a result of the above communications, GMR submits that it
                            was constrained to undertake overlay work without milling, despite
                            Clause 4.3.2 (ii) of Schedule L which granted the concessionaire an
                            option of milling and recycling for carrying out the renewal work.

                            29.   On 6th May, 2014, GMR again wrote to the IC proposing a
                            methodology for recycling of the bituminous pavement by milling, for
                            the review and approval of the IC, assuring that, in the interregnum,
                            GMR would continue periodic maintenance as per the earlier
                            approved   methodology.     It   was      further stated, in     the   said
                            communication, that the date of commencement of recycling of the
                            bituminous pavement would be intimated to the IC.


                            30.   By a letter dated 12th October, 2014, the IC wrote to GMR,
                            stating that it had never approved the proposal for recycling and
                            directing GMR "to continue the renewal of the wearing course of the
                            road pavement pursuant to Clause 2.6.1, 2.6.2 and Cl 4.3.1 under
                            Schedule L of the Concession Agreement of the subject project".


                            31.   The renewal/overlay work was completed by the petitioner on
                            30th December, 2014, after a delay of 250 days.

                            32.   On 8th June, 2016, the IC wrote to NHAI, recommending raising
                            of a demand, on GMR, of ₹ 10,31,50,520/- as delay damages for delay
                            in executing periodical renewal coat on the project highway. A copy
                            of the letter was also addressed to GMR.

                            33.   GMR, in turn, wrote, on 19th July, 2016, to NHAI, opposing the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 24 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             proposal to charge delay damages from it. GMR, in turn, claimed an
                            amount of ₹ 104,47,80,462/- from NHAI, which include idling cost of
                            milling and recycling machinery owing to delay in grant of approval
                            by the IC for conducting the renewal by milling. This amount, it was
                            stated, principally included the expenses incurred by GMR towards
                            the periodic maintenance carried out, by it under duress, though,
                            according to GMR, Clause 4.3.1 of Schedule L to the CA did not
                            require it to do so.


                            34.    Reference was made, in the said communication, to letters dated
                            25th August, 2014 and 10th October, 2014 from GMR to the IC,
                            informing the IC that it was undertaking recycling work, to which the
                            IC responded only on 12th October, 2014, rejecting the recycling
                            proposal.

                            35.    Vide communication dated 23rd August, 2016, NHAI rejected
                            the claims of GMR as contained in its letter dated 19th July, 2016.


                            36.    GMR, in the circumstances, wrote to NHAI on 9th September,
                            2016, raising a dispute and seeking reference of the dispute to the
                            Chairman, NHAI and the Chairman of the Board of Directors of GMR
                            for an amicable resolution in terms of Clause 39.1(b) of the CA.


                            37.    On 15th March, 2018, K & J Projects Pvt. Ltd. (who had
                            replaced MSV International as the IC) wrote to the Project Director,
                            NHAI, conveying its opinion that Clause 18.1.3 of the CA empowered
                            NHAI to recover damages from the Concessionaire for default in

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 25 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             operating and maintaining the project highway in conformity with the
                            CA. Following this, vide letter dated 27th March, 2018, addressed to
                            GMR, NHAI conveyed its decision to deduct, from the annuity
                            payable to GMR, ₹ 10.78 crores as damages.


                            38.    GMR, in the circumstances, invoked Clause 39.2 of the CA,
                            which provided for resolution of disputes by arbitration, and appointed
                            its nominee arbitrator, while requesting the Indian Council of
                            Arbitration (ICA) to constitute the Arbitral Tribunal.


                            39.    While matters stood thus, GMR petitioned this Court under
                            Section 9 of the 1996 Act by way of OMP (I) (Comm) 421/2018,
                            which came to be disposed of, by a Coordinate Bench, vide order
                            dated 2nd November, 2018. This Court noted, at the outset, the
                            contention of GMR "that the only dispute between the parties is
                            whether in the terms of Clause 4.3 of Schedule L to the Concession
                            Agreement dated 31.03.2006 executed between the parties, the
                            petitioner is under an application to relay the surface and bituminous
                            concrete only because the five years period has expired though the
                            surface roughness is of the prescribed measure". Having so noted, this
                            Court disposed of the petition with a direction to the ICA to constitute
                            an Arbitral Tribunal within one week, and with a direction to the
                            Arbitral Tribunal, so constituted, to adjudicate OMP (I) (Comm)
                            421/2018 treating it as an application under Section 17 of the 1996
                            Act.

                            40.    Needless to say, as the learned Arbitral Tribunal has passed a

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 26 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             final Award, which is under challenge, the subject matter of OMP (I)
                            (Comm) 421/2018 is no longer of significance.


                            The Award

                            41.   Before the learned Arbitral Tribunal, GMR advanced the
                            following five claims:


                                  "Claim No.1: Claim for a sum of ₹ 104,47,80,462 on account
                                  of (i) reimbursement of costs incurred for relaying the pavement
                                  at the end of the fifth year, and (ii) extra costs incurred due to
                                  the decision not to allow recycling of milled material.


                                  Claim No.2: Claim for a sum of ₹ 10,78,61,864/- in respect of
                                  deductions made by the Respondent on account of damages.


                                  Claim No.3: Claim for a direction to the Respondent not to
                                  insist upon relaying of the surface in the 10th year or thereafter
                                  if the roughness criterion as set out in the contract is met.


                                  Claim No.4: Claim for interest @ 5% over SBI PLR on the
                                  above claims from the due date of payment till the actual date of
                                  payment.


                                  Claim No.5: Claim for costs [as per actual]"


                            42.   NHAI, per contra, advanced only one counter claim, for costs

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 27 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             incurred in the arbitral process.


                            Contentions of GMR before the learned Arbitral Tribunal


                            43.   GMR contended, before the learned Arbitral Tribunal, that the
                            clauses of the CA could not be read in isolation or dissociated from
                            one another and that, read in conjunction, GMR was required to do the
                            overlay work only if the Roughness Index of the highway, at any
                            point, exceeded the stipulated minimum level of 2000 mm/km.
                            Commercial contracts, it was submitted, were required to be
                            commercially construed. Clause 4.3 of Schedule L to the CA read with
                            Appendix 3.1 of Schedule L to the CA, submitted GMR, clearly
                            indicated that the stringent pre-conditions stipulated for carrying out
                            of overlay work had to be strictly adhered to. Where the Roughness
                            Index was below 2000 mm/km, there was no requirement for carrying
                            out overlay work every five years. As a result of such unnecessary
                            overlay work that GMR had, under duress, to carry out, it had suffered
                            huge losses which NHAI was duty bound to recompense.


                            44.   GMR also questioned the relevance of Clause 2.6.1 of Schedule
                            L to the CA to the issue in controversy. It was submitted that Clause
                            2.6.1 merely set out the various activities to be performed by the
                            Concessionaire, and could not override Clause 4.3 of Schedule L to
                            the CA. Reliance was also placed by GMR on Clause 2.6.1 (b) (ii) of
                            Schedule L to the CA which provided, among the maintenance
                            activities to be carried out by GMR, "wearing course required on
                            account of the RI values higher than the prescribed criteria obtained
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 28 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             during regular testing as per the Concession Agreement requirement".
                            Reliance was also placed on the flow chart scheme contained in
                            Appendix 3.1 in Schedule L to the CA, which envisaged that, while
                            carrying out periodic maintenance and inspection of the highway, a
                            roughness survey was to be conducted and, if the Roughness Index
                            favourably compared with the stipulated operations/performance
                            criteria, GMR was to "do nothing".

                            45.    GMR further disputed the legitimacy of the objection, belatedly
                            raised by NHAI to the carrying out of the overlay/renewal work, by
                            the petitioner, using the milling process. For the entire expense that
                            GMR had to suffer, on the above account, GMR claimed ₹
                            104,47,80,462/-.


                            46.    Additionally, GMR contested the recovery, by NHAI, of
                            damages of ₹ 10,78,61,864/-. Damages, under Clauses 18.12, 18.13
                            and 18.14 of the CA, it was submitted, could only follow on breach,
                            by GMR, of its obligations thereunder, and on failure, by GMR, to
                            rectify the breach within the period allowed by NHAI. GMR having
                            completed the project work within the stipulated period, it was
                            submitted that NHAI had no justifiable reason to levy damages. The
                            deducted damages of ₹ 10,78,61,864/- were, therefore, refundable to
                            GMR.

                            47.    GMR, additionally, also claimed interest and costs.


                            NHAI's submissions before the learned Arbitral Tribunal

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 29 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             48.   NHAI contested the interpretation placed by GMR on Clause
                            4.3.1 of Schedule L to the CA. It was submitted that the said clause
                            did not envisage any condition precedent for carrying out renewal
                            work and did not contain the expression "exceeds 2000 mm/km".
                            Apropos Appendix 3.1 in Schedule L to the CA, NHAI submitted that
                            Clauses 2.6.1 and 4.3.1 of Schedule L to the CA, being substantive
                            provisions, could not cede place to Appendix 3.1 in Schedule L to the
                            CA. Besides, it was pointed out, Appendix 3.1 in Schedule L to the
                            CA did not stipulate any prescribed Roughness Index value, as the
                            basis for deciding whether renewal/overlay work was required to be
                            done or not. Specifically drawing attention to Clause 2.6.1 of Schedule
                            L to the CA, NHAI submitted that the said Clause unequivocally
                            required GMR to undertake maintenance using a bituminous coat for
                            renewal of the road pavement once every five years. Clause 2.6.1 of
                            Schedule L to the CA, it was submitted, was unambiguous and not
                            admitting of any two interpretations. It was not conditional upon the
                            Roughness Index of the highway. The lower the Roughness Index, the
                            better, it was submitted, would be the riding quality of the pavement.


                            49.   The words "to bring it to the initial value of 2000 mm/km" in
                            Clause 4.3.1 of Schedule L to the CA, it was submitted, were to be
                            read with the immediately preceding stipulation of the Roughness
                            Index exceeding 3000 mm/km. Where the Roughness Index exceeded
                            3000 mm/km, therefore, according to NHAI, the overlay work was
                            required to bring the Roughness Index below 2000 mm/km. This did
                            not derogate from the responsibility of GMR to, in any event, carry
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 30 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             out overlay work every five years. NHAI also relied on GMR's letter
                            dated 21st March, 2014 supra to contend that the recitals in the said
                            letter amounted to a concession, by GMR, to the interpretation of
                            Clause 4.3.1 of Schedule L to the CA, as advanced by NHAI.


                            50.   Emphasis was laid, by GMR, on the words "whichever is
                            earlier" in Clause 4.3.1(ii) of Schedule L to the CA to contend that
                            overlay work, in any event, was to be done at the end of every 5 years.
                            This stipulation, as it figures in the said sub-Clause was a contractual
                            obligation, without any condition precedent. If, for example, the
                            Roughness Index was 2999 mm/km, accepting the contention of
                            NHAI would exempt GMR from the requirement of doing any overlay
                            work even under routine maintenance, which would result in the
                            riding quality of the road being merely 'average' whereas, periodic
                            renewal work carried out even when the Roughness Index was below
                            2000 mm/km, the roughness would be further reduced, thereby
                            improving riding quality.


                            51.   Reliance was placed, by NHAI, on the 'Cash Flow Projection'
                            chart filed by GMR at the time of the financial bid. It was pointed out
                            that, under the heading 'projected periodic maintenance', the cost of
                            periodic maintenance had been included for June 2013, June 2018 and
                            June 2022, without the cost of periodic maintenance being mentioned
                            against any other year. As such, in the chart, the cost of carrying out
                            overlay work had been provided for. No occasion, it was submitted,
                            arose for GMR to do so, if carrying out of overlay work was subject to
                            the condition of Roughness Index of the highway.
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 31 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             52.   In fact, contended NHAI, GMR had raised the demand for
                            compensation only in July 2016, when damages were imposed by
                            NHAI. This demand, therefore, it was submitted, was essentially in the
                            nature of a counterblast to the imposition of damages on GMR.


                            53.   NHAI further contended that the initial opinion of the IC could
                            not be regarded as sacrosanct and was subject to scrutiny. Even if,
                            based on the test results of 2012, the IC had not advised periodic
                            renewal, that, submitted NHAI, did not exonerate GMR of the
                            obligation to periodically carry out overlay work.


                            54.   These submissions, contended NHAI, also discredited Claim 3
                            of GMR.


                            55.   Apropos the right, of GMR, to recycle the existing crust of the
                            road using milling as an option, NHAI submitted that Clause 4.3.2(ii)
                            of Schedule L to the CA permitted GMR to do so only in consultation
                            with the IC, to maintain FRL. GMR could not do so unilaterally. It
                            had, however, proceeded to do so, as was clear from GMR's letter
                            dated 19th July, 2016, which draws reference to GMR's letter dated
                            12th February, 2014 wherein the IC was informed about the scheduled
                            commencement of the milling of the existing pavement from 15 th
                            February, 2014. The unilateral communication from GMR on 6th May,
                            2014, it was submitted, did not confer any right on GMR to start
                            recycling of the milled material. The absence of any response from the
                            IC did not indicate that the methodology adopted by GMR had been
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 32 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             approved. Rather, vide letter dated 28th February, 2014, the IC had
                            categorically stated that as option of milling is exercised by the
                            Concessionaire without the consent of the IC, resulting in damage to
                            the project, the cost of damages to the project shall be borne by the
                            Concessionaire. Reference was also made, in this context, to the
                            communication dated 7th March, 2014, from the IC to GMR, wherein
                            the IC had clearly communicated to GMR that no milling operation
                            was to be done without its approval and GMR's response dated 20th
                            March 2014 thereto, wherein GMR had admitted that milling was not
                            agreed by the IC or NHAI. NHAI was, therefore, it was submitted,
                            entitled, under Clause 30.1 of the CA, to suspend or any of the
                            contractual rights of GMR, including payment of annuity.


                            The Impugned Award


                            56.   The findings of the learned Arbitral Tribunal, qua the issues that
                            arose for determination, may be distilled, claim-wise, thus.


                            Re. Claim 1 - for ₹ 104,47,80,462/- towards (i) reimbursement of
                            costs incurred for relaying the pavement at the end of the fifth year
                            and (ii) extra costs incurred on account of NHAI refusing permission
                            to allow recycling of milled material.


                            57.   The learned Arbitral Tribunal commences its discussion, in
                            Claim 1 of GMR, by referring to the basic principles regarding
                            interpretation of contracts and citing, in that context, various decisions
                            of the Supreme Court and authoritative texts. Therefrom, the learned
                            Arbitral Tribunal, after observing that, if there is any ambiguity in the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 33 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             terms of a commercial contract, an interpretation which accords with
                            business common sense is to be preferred, holds, with respect to
                            Clause 4.3.1 of Schedule L to the CA, that the words "to bring it to the
                            initial value of 2000 mm/km" did not qualify the requirement of
                            laying new renewal coat after every 5 years, but were, instead, used
                            only in respect of the phrase "where the roughness value reaches 3000
                            mm/km". In other words, according to the learned Arbitral Tribunal,
                            "if the renewal coat is required to be laid down because the roughness
                            value has reached 3000 mm/km, the same is laid down to bring the
                            surface roughness value to 2000 mm/km". The words "to bring it to
                            the initial value of 2000 mm/km", it was observed, were not used with
                            respect to the words "every 5 years after initial construction". Overlay
                            work was in the nature of regular periodic maintenance activity, to be
                            done every 5 years, and was not dependent on the surface Roughness
                            Index.


                            58.      To support its interpretation, the learned Arbitral Tribunal also
                            places reliance on Clause 2.6.1 of Schedule L to the CA which,
                            according to the learned Arbitral Tribunal, unequivocally envisages
                            periodic renewal every 5 years with no condition precedent. The
                            contention, of GMR, that Clause 2.6.1 of Schedule L to the CA related
                            only to traffic management and land closure was rejected by relying
                            on Clause1.2 (d) of the CA, whereunder it was stipulated that the
                            Headings of the contractual clauses would not cover their contents.
                            Clause 1.4.2(i) of the CA, which stipulated that, in the event of
                            ambiguity between clauses in the CA, the specific clause would
                            prevail over other clauses, it was felt, would also not apply, as Clause
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 34 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             2.6.1 of Schedule L to the CA could not be regarded as a specific
                            clause, so as to be accorded primacy. The word "after", in Clause
                            4.3.1(ii) of Schedule L to the CA, it was noted, was placed before
                            "initial construction" and not "every 5 years", thereby indicating that
                            the work was required to be done once every 5 years after initial
                            construction. The use of the word "laid", it was held, meant that the
                            renewal work was required to be completed once every 5 years.


                            59.   The learned Arbitral Tribunal also held Clauses 6.1 and 6.2 of
                            IRC:82, on which GMR relied, not to be applicable. Reliance was,
                            instead,   placed   by   the   learned    Arbitral   Tribunal   on   the
                            communications from the Project Director, NHAI to GMR, requiring
                            GMR to take steps and furnish the program for immediate periodic
                            maintenance/renewal, "irrespective of whether the roughness reaches
                            3000 mm/km or not, as per Clause 2.6.1 and Clause 4.3.1 of Schedule
                            L of Concession Agreement". 5 yearly renewal work being part of the
                            contractual stipulations, the learned Arbitral Tribunal held that GMR
                            was not entitled to claim any extra payment therefor. The claim of ₹
                            100,67,80,462/- was, therefore, held to be "absolutely unsustainable".


                            60.   The learned Arbitral Tribunal, thereafter, proceeded to deal with
                            GMR's claim for extra costs incurred owing to NHAI's refusal to
                            allow recycling of milled material. Clause 4.3.2 (ii) of Schedule L to
                            the CA was cited, to hold that recycling of the existing crust using
                            milling was permissible only in consultation with the IC, to maintain
                            the same level of FRL throughout the concession period. It was
                            observed that there was no material on record to indicate that any
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 35 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             attempt at deliberation or discussion with the IC, regarding the milling
                            of the existing crust, had been undertaken by GMR. GMR had
                            commenced milling on its own. The assertion that the IC had, initially,
                            supervised the milling operation, it was found, was also not supported
                            by any material. The letter, dated 12th February, 2014, from GMR to
                            the IC, stating that GMR was planning to start milling work on 15th
                            February, 2014, did not refer to any requirement of consultation with
                            the IC. Further communications from GMR to the IC, too,
                            acknowledged the requirement of consultation. The IC, vide letter
                            dated 28th February, 2014, informed GMR that, while proposing
                            milling operations before the start of maintenance activities, GMR had
                            not specified the reasons therefor; also, no program for milling was
                            submitted to the IC. As such, the IC stated that GMR had undertaken
                            milling without the knowledge of the IC, contrary to the stipulations in
                            the CA. The learned Arbitral Tribunal held that GMR could not
                            unilaterally decide to carry out milling operations. In view thereof, it
                            was held that GMR could not claim, from NHAI, the costs incurred on
                            account of want of approval, by GMR, for recycling of the milled
                            material, or for idling of machinery on that count.


                            Re. Claim 2 - for ₹ 10,78,61,864/- towards deductions made by
                            NHAI against damages


                            61.   The learned Arbitral Tribunal noted that Clause 18.12 of the CA
                            entitled NHAI to recover damages in the event of GMR failing to
                            maintain and/or repair the Project Highway, or any part thereof, in
                            accordance with the Maintenance Program or the Maintenance Manual

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 36 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             and having failed to commence remedial works within 30 days of
                            receipt of notice in that behalf from NHAI. The learned Arbitral
                            Tribunal noted that no notice, as required by Clause 18.12 of the CA,
                            for failure to commence the work, had been served by NHAI on GMR.
                            The contention of NHAI that a notice to undertake periodic
                            maintenance activities was inbuilt in the clauses of the CA such as
                            Clause 2.6.1 and 4.3.1 of Schedule L to the CA was rejected by the
                            learned Arbitral Tribunal on the ground that a written notice was a
                            condition precedent for imposition of damages under Clauses 18.12,
                            18.13 and 18.14 of the CA. This position, it was noted, was also
                            acknowledged by the IC in his letter dated 15 th March, 2018, which
                            deducted, from the total number of days of delay to calculate
                            liquidated damages, the 30 day notice period. The communications
                            from NHAI to GMR, calling upon GMR to submit the work program
                            and threatening not to process annuity, too, it was observed, did not
                            envisage recovery of damages. These communications, specifically
                            the letters dated 21st August, 2013, 18th November, 2013 and 5th
                            December, 2013, it was held, could not be regarded as notices as
                            stipulated by Clause 18.12 of the CA. In fact, GMR had continued the
                            periodic maintenance work and completed the work by December
                            2014. The delay, if any, on the part of GMR, it was observed, did not
                            elicit any protest from NHAI. In these circumstances, the learned
                            Arbitral Tribunal held the imposition of damages, by NHAI on GMR,
                            to be unwarranted.


                            62.   The learned Arbitral Tribunal held, additionally, that damages
                            could not be levied in terms of Illustration (iii) in para 4.4 of the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                  Page 37 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Policy Circular dated 5th February, 2018 of NHAI, as it would amount
                            to a unilateral amendment, by NHAI, of the terms of the CA, which
                            was impermissible in law.


                            63.   For all these reasons, the learned Arbitral Tribunal allowed
                            GMR's claim for ₹ 107,861,864/-, being the amount recovered by
                            NHAI by way of damages, from the annuity payable to GMR.


                            Re. Claim 3 - For directing NHAI not to insist upon relaying of the
                            surface in the 10th year or thereafter, if the Roughness Index was 2000
                            mm/km or less


                            64.   In view of its preceding findings, especially with respect to
                            Claim 1, the learned Arbitral Tribunal directed that the second and
                            third cycles of overlay work be completed by the 11 th and 16th years of
                            the contract. The renewal work for the second cycle was directed to
                            commence on or before 1st April, 2020 and be completed by the end of
                            2020 and, for the third cycle, to be completed by 1st April, 2025.


                            Re. Claim 4 - For interest


                            65.   Noting the fact that, on different occasions, Courts had granted
                            different rates of interest, the learned Arbitral Tribunal held that, in the
                            facts and circumstances of the case, it would be appropriate to award,
                            to GMR, interest @ 12% p.a. on the awarded amount of ₹
                            107,861,864/-, from the date of deduction of the said amount, by
                            NHAI, as damages, i.e. from 27th March 2018, till the date of payment.

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 38 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Re. Counter-claim by NHAI


                            66.   NHAI's counterclaim, which was limited to costs, was rejected
                            by the learned Arbitral Tribunal.


                            Rival Submissions and Analysis


                            67.   I have heard Mr. Atul Sharma on behalf of GMR and Mr.
                            Dayan Krishnan, learned Senior Counsel, along with Mr. Ankur
                            Mittal, on behalf of NHAI, at length.


                            Re: Claims 1 and 3


                            68.   Mr. Sharma contends that the interpretation, placed by the
                            learned Arbitral Tribunal on the covenants of the CA, is, ex facie,
                            perverse and, not one which any person, conversant with the law,
                            would arrive at. On a plain reading, according to Mr. Sharma, Clause
                            4.3.1 (ii) of Schedule L to the CA required laying of a renewal coat of
                            bituminous concrete only where the Roughness Index was above 2000
                            mm/km.


                            69.   This, he submits, was the purpose of laying the renewal coat.
                            He relies, for this purpose, on Clauses 1.2 (i) and (k) of the CA, 4.9.2
                            and 2.1 of the CA, Clause (1) "scope of the project" in Schedule B to
                            the CA and Clauses 2.6.1, 4.2 and 4.3 of Schedule L to the CA, read
                            with Appendices 3.1 and 3.4 thereto. Read conjointly, Mr. Sharma
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 39 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             submits that these clauses left no manner of doubt that, unless and
                            until the Roughness Index fell below 2000 mm/km, GMR was to "do
                            nothing". The interpretation placed by the learned Arbitral Tribunal
                            on Clause 4.3.1 of Schedule L to the CA, he submits, would militate
                            against all other clauses in the CA and could not, therefore, be said to
                            be reasonably acceptable. He also submits that Clause 2.6.1(a) of
                            Schedule L to the CA has to be read along with Clause 4.3.1 of
                            Schedule L to the CA, and clearly sets out the activities which were
                            required to be done, the specifications in respect whereof were to be
                            found in Clause 4.3.1 of Schedule L to the CA.


                            70.   Appendix 3.1 of Schedule L to the CA, Mr. Sharma submits,
                            requires yearly estimation of Roughness Index to be undertaken. If, on
                            comparison, the Roughness Index throughout the highway was in
                            accordance with the operation/performance criterion stipulated in
                            Appendix 3.4 read with Clause 4.3.1(i) and (ii) of Schedule L to the
                            CA, the concessionaire was to "do nothing". Periodic maintenance
                            was required, if at all, only where the Roughness Index exceeded 2000
                            mm/km.


                            71.   Admittedly, the Roughness Index throughout the highway was,
                            at all times, below 2000 mm/km. The trigger point for carrying out
                            periodic maintenance was, therefore, never reached. "No repairs"
                            were, therefore, "required", as per Appendix 3.1 of Schedule L to the
                            CA, and GMR was required to "do nothing". The fact that the
                            Roughness Index was below 2000 mm/km at all points in the project
                            highway also stands acknowledged in the impugned award of the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 40 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             learned Arbitral Tribunal. It was, for this reason that the IC, vide letter
                            dated 23rd September, 2013, communicated to NHAI that renewal coat
                            was not necessary.


                            72.   Clause 4.3 of Schedule L to the CA, points out Mr. Sharma,
                            required   activities   relating   to     pavement    maintenance      and
                            rehabilitation, in respect of flexible and rigid pavement to be
                            undertaken as per the flow charts in Appendix 3.1 and 3.2 to Schedule
                            L to the CA. This provision, being anterior to Clause 4.3.1 of Schedule
                            L to the CA, would prevail over Clause 4.3.1 of Schedule L to the CA,
                            assuming there was any ambiguity in the latter provision. Any other
                            interpretation, submits Mr. Sharma, would render Appendices 3.1 and
                            3.4 of Schedule L to the CA nugatory and redundant.


                            73.   Mr. Sharma also faulted the learned Arbitral Tribunal for
                            having brushed aside the reliance, by GMR, on the IRC specifications,
                            which were binding on the parties under the CA.


                            74.   Mr. Sharma points out that, in its award in Nirmal BOT, the
                            learned Arbitral Tribunal which was in seisin of that dispute had
                            interpreted the various clauses of the CA in accordance with the
                            submissions advanced by him in the present case.


                            75.   As against this, Mr. Dayan Krishnan, learned Senior Counsel
                            for NHAI, submits that Clause 2.6.1(b) of the Schedule L to the CA
                            relates to regular maintenance activities, which have nothing to do
                            with periodic activities. He points out that Clause 2.6.1(a)(i) of the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 41 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Schedule L to the CA, which requires five yearly renewal coat to be
                            laid does not condition the said requirement by any caveat. Clause
                            4.3.1 of Schedule L to the CA, according to Mr. Dayan Krishnan, only
                            stipulates a minimum criterion.


                            76.   Mr. Dayan Krishnan submits that, in the absence of any
                            "operation/performance criteria", Appendix 3.1 of Schedule L to the
                            CA would have no application. He also disputes the applicability of
                            Appendix 3.4 of Schedule L to the CA, as he submits that laying of the
                            renewal coat did not amount to "repairs". The Roughness Index, he
                            submits, only tested the riding quality. Bituminous concrete overlay
                            served two functions. It improved the riding quality of the pavement
                            and also provided a protective layer protecting the underlying Dense
                            Bituminous Macaderm. As such, he submits that GMR is not justified
                            in its contention that, if the Roughness Index was above 2000 mm/km,
                            no overlay was required.


                            77.   Mr. Dayan Krishnan submits that the mandate of Clause
                            2.6.1(a)(i) of Schedule L to the CA was clear and unequivocal, in
                            requiring renewal of the wearing surface of the road pavement to
                            mandatorily be undertaken "once every five years". Clause 2.6.1 of
                            Schedule L to the CA, he submits, governs Clause 4.3.1 of Schedule L
                            to the CA and would apply as it applied throughout the contract
                            period. Clause 4.3 of Schedule L to the CA only referred to periodic
                            inspection for the purpose of maintenance. Without prejudice, Mr.
                            Dayan Krishnan submits that word "or" between the two parts of the
                            sentence, "a renewal coat of bituminous concrete shall be laid every
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 42 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             five years after initial construction" and "where the Roughness value
                            reached 3000 mm/km, whichever is earlier, to bring to the initial value
                            of 2000 mm/km", clearly indicated that the two parts of the clause
                            were to be read disjunctively and that, irrespective of whether the
                            second part of the sentence applied, or did not apply, a renewal coat of
                            bituminous concrete was mandatorily required to be laid every five
                            years after initial construction. Any other interpretation, he submits,
                            would be unrealistic and would amount to ignoring normal wear and
                            tear that the highway surface would suffer. The findings of the learned
                            Arbitral Tribunal, submits Mr. Dayan Krishnan, were entirely in order,
                            and did not call for any interference by this Court.


                            78.         In such circumstances, Mr. Dayan Krishnan submits that no
                            occasion arises for this Court to interfere with the impugned award.
                            He relies, for this purpose, on the judgment of the Supreme Court in
                            Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail
                            Corporation Ltd2. Mr. Dayan Krishnan has, in this context,
                            specifically invited my attention to Section 34(2A)3 of the 1996 Act
                            which permits, interference by a Court, with the arbitral award, only in
                            the case of "patent illegality".


                            79.         The interpretation postulated by him, submits Mr. Dayan
                            Krishnan, was in line with the view expressed by a coordinate Bench

                            2   (2022) 1 SCC 131
                            3   34.     Application for setting aside arbitral awards. -
                                                                                    *****
                                        (2A)       An arbitral award arising out of arbitrations other than international commercial
                                        arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent
                                        illegality appearing on the face of the award: Provided that an award shall not be set aside merely
                                        on the ground of an erroneous application of the law or by reappreciation of evidence.
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                                                          Page 43 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             of this Court in NHAI v. Patel KNR Infrastructure Ltd.4 (Mr.
                            Sharma, on the other hand, seeks to distinguish the decision in Patel
                            KNR Infrastructure Ltd.4 on facts). He points out that, in para 28 of
                            the report, the coordinate Bench has clearly observed that the intent of
                            the parties was to ensure that the riding quality of the pavement does
                            not fall below the specified minimum standard. Besides, para 20 of
                            the report in that case indicated that the de minimis Roughness Index
                            was 3000 mm/km and not 2000 mm/km.


                            Analysis


                            80.        Ordinarily, a Section 34 Court would not interfere with the
                            interpretation adopted by an Arbitral Tribunal with respect to a
                            contractual covenant. This proscription is, however, not absolute.
                            Where it appears to the Court that the interpretation placed by the
                            Arbitral Tribunal on the contractual clauses is not one which can be
                            adopted by any reasonable person, the Court can interfere. In deciding
                            whether the interpretation, placed by the learned Arbitral Tribunal on
                            the contractual covenants is, or is not, reasonable, the Court would be
                            required to examine all relevant covenants in the contract. An
                            interpretation of a particular clause, which stands alone and is
                            unconditioned by any other clause in the contract would be less
                            vulnerable to interference by a Court, apropos the interpretation that
                            an Arbitral Tribunal may choose to place on it. Where, however, a
                            contractual covenant is interlinked to other covenants in the contract,
                            or where there are more than one covenants in a contract dealing with

                            4   2021 SCC Online Del 4152
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 44 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             a particular exigency, then, if the Arbitral Tribunal interprets one of
                            the covenants in such a manner as would frustrate the intent of the
                            other covenants, or in a manner in which is not in sync with the other
                            covenants, a Court would be bound to interfere.


                            81.        Equally, if an Arbitral Tribunal does not consider a particular
                            relevant covenant, despite its attention having been invited thereto, the
                            Court would be justified in interfering. In this context one may refer to
                            para 61 of the report in Ssangyong Engg. & Construction Co. Ltd. v.
                            NHAI5 in which the Supreme Court addressed the question of the
                            amenability to interference of an arbitral award, on the ground that a
                            contention raised by a party was not considered. The Supreme Court
                            approved the following passage from the decision of the Singapore
                            Court of Appeal in CRW Joint Operation v. PT Perusahaan Gas
                            Negara (Persero) TBK6 which, in turn, relied on the following
                            enunciation of the law in "Redfern and Hunter on International
                            Arbitration" (Oxford University Press, 5th Edn., 2009):


                                       "The significance of the issues that were not dealt with has to
                                       be considered in relation to the award as a whole. For example,
                                       it is not difficult to envisage a situation in which the issues that
                                       were overlooked were of such importance that, if they had been
                                       dealt with, the whole balance of the award would have been
                                       altered and its effect would have been different."


                            The Court, faced with a submission by an aggrieved litigant that the
                            Arbitral Tribunal had failed to consider a contention advanced before

                            5   (2019) 15 SCC 131
                            6   2011 SGCA 33

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                                Page 45 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             it is, therefore, required to examine whether, if the Arbitral Tribunal
                            would have considered the contention, the outcome may have been
                            different. If the answer to this query is in the negative, no cause for
                            interference exists, merely because the Arbitral Tribunal has not
                            considered the contention. If, however, the Court comes to the
                            conclusion that, were the contention to be considered, the outcome of
                            the proceedings might have been different, the failure, on the part of
                            the Arbitral Tribunal, in considering the contention, would imperil the
                            award.


                            82.        An important decision, in this context, is the pronouncement of
                            the Supreme Court, through Ramana J (as the Hon'ble Chief Justice
                            then was) in South East Asia Marine Engineering & Constructions
                            Ltd. v. Oil India Ltd.7 The issue before the Supreme Court was with
                            respect to the interpretation, by the Arbitral Tribunal, with a "change
                            in law" clause in the contract, in which event Oil India Ltd (OIL), the
                            respondent before the Supreme Court, became liable to re-imburse
                            South East Maritime Constructions Ltd. (SEAMEC), the appellant
                            before the Supreme Court. SEAMEC claimed that the increase in price
                            of High Speed Diesel (HSD), an item essential to carry out the
                            contract, constituted "change in law" and, thereby, entitled SEAMEC
                            to re-imbursement. The learned Arbitral Tribunal, per majority,
                            allowed the claim, albeit by holding that the increase in price of HSD
                            was not a "change in law" stricto senso. Nonetheless, the learned
                            Arbitral Tribunal held that it had the "force of law" and was also,


                            7   2020 5 SCC 164
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                       Page 46 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             therefore, covered by the "change in law" clause.


                            83.        The High Court, however, reversed the decision of the learned
                            Arbitral Tribunal, holding that the manner in which the learned
                            Arbitral Tribunal had interpreted the clauses of the contract was
                            contrary to public policy and amounted to patent illegality.


                            84.        The Supreme Court, in appeal, first noted the position, in law,
                            as enunciated in Dyna Technologies Pvt. Ltd v. Crompton Greaves
                            Ltd.8, that the mere possibility of an alternative interpretation of the
                            contractual covenants would not justify interference with arbitral
                            award under Section 34 of the 1996 Act. The need for deference and
                            caution, by Courts seized with Section 34 challenges, was also
                            underscored in the said decision.


                            85.        Having so noticed, the Supreme Court in South East Asia
                            Marine Engineering & Constructions7, in para 14 of the report,
                            framed the issue arising before it for consideration as "whether the
                            interpretation provided to the contract in the award of the tribunal was
                            reasonable and fair, so that the same passes the muster under Section
                            34 of the Arbitration Act".


                            86.        Having thus framed the issue that arose for consideration, the
                            Supreme Court disapproved the interpretation of the contract, both by
                            the learned Arbitral Tribunal as well as by the High Court. In so far as


                            8   (2019) 20 SCC 1

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 47 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             the reasoning of the learned Arbitral Tribunal was concerned, the
                            Supreme Court held, significantly, that "although the Arbitral
                            Tribunal correctly held that a contract needs to be interpreted taking
                            into consideration all the clauses of the contract, it failed to apply the
                            same standard while interpreting Clause 23 of the contract".


                            87.   Having thus set out the legal position, the Supreme Court held
                            that, while interpreting the "change in law" clause in the contract, the
                            Arbitral Tribunal was required to take into account other contractual
                            terms such as Item 1 of List II which indicated that fuel would be
                            supplied by the contractor at his expense. If other contractual terms
                            were taken into account, the Supreme Court held that the
                            interpretation, accorded to the "change in law" clause in the contract
                            by the Arbitral Tribunal, could not sustain.


                            88.   While examining the vulnerability of the decision of the learned
                            Arbitral Tribunal, on Claim 1 of GMR, to interference under Section
                            34 of the 1996 Act, this Court would, applying the law enunciated in
                            South East Asia Marine Engineering & Constructions 7, have to
                            examine whether the interpretation of the covenants of the CA, by the
                            learned Arbitral Tribunal, is reasonable and fair. In doing so, no doubt,
                            the Court is required to bear in mind the constraints that operate on it,
                            as a Court exercising jurisdiction under Section 34 of the 1996 Act, in
                            the matter of interference with the manner in which the Arbitral
                            Tribunal has chosen to interpret the contract. If, however, the Court
                            finds that the learned Arbitral Tribunal has not taken into account all
                            relevant clauses, or that the manner in which the learned Arbitral
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 48 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Tribunal has interpreted the contract is disharmonious with other
                            clauses, the Court would have necessarily to interfere.


                            89.   This is apart from the fact that applying the law in NHAI v.
                            Progressive-MVR (JV)1, the same clauses having been subjected to
                            mutual conflicting interpretations by two Arbitral Tribunals, this Court
                            would, in any case, be duty bound to set out what, in its estimation, is
                            the correct interpretation.


                            90.   A bare reading of the impugned award reveals that it proceeds
                            on two basic premises. The first is that the requirement of renewal of
                            the wearing surface of the road pavement every five years was, as per
                            Clause 2.6.1(a)(i) of Schedule L to the CA, mandatory and non-
                            negotiable, irrespective of the Roughness Index of the Project
                            Highway.


                            91.   The second is that the words, "to bring it to the initial value of
                            2000 mm/km", in Clause 4.3.1(ii) of Schedule L to the CA would
                            have to be read with the latter part of the second sentence in the said
                            clause, i.e., with the immediately preceding stipulation which reads,
                            "where the roughness value reaches 3000 mm/km". According to the
                            learned Arbitral Tribunal, the stipulation, "to bring it to the initial
                            value of 2000 mm/km", in Clause 4.3.1 (ii) of Schedule L of the CA
                            would not apply to the initial part of the sentence which reads, "shall
                            be laid every five years after initial construction".


                            92.   In my opinion, the manner in which the learned Arbitral
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 49 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Tribunal has interpreted Clause 4.3.1(ii) of Schedule L to the CA
                            appears to be contrary to the wording of the clause itself. The clause
                            states that "a renewal coat of bituminous concrete shall be laid every 5
                            years after initial construction or where the roughness value reaches
                            3000 mm/km whichever is earlier to bring it to the initial value of
                            2000 mm/km".


                            93.   The question is as to how this clause would apply in a case such
                            as the present when the roughness value/Roughness Index never
                            exceeded 2000 mm/km. Laying of a renewal coat of bituminous
                            concrete, in such a situation, would result in the Roughness Index
                            falling even below the level at which it already stood. In the facts of
                            the present case, for example, the Roughness Index was found, on two
                            tests, to be 1749 mm/km and 1788 mm/km. At all times, therefore, the
                            Roughness Index was in any event below 2000 mm/km. Laying of a
                            renewal coat could never, therefore, bring the roughness value to 2000
                            mm/km. In fact, laying of a renewal coat would reduce the roughness
                            value even further away from the standard of 2000 mm/km stipulated
                            in Clause 4.3.1(ii) of Schedule L to the CA. Requiring GMR to
                            undertake overlay work in such circumstances, therefore, ex-facie,
                            violates Clause 4.3.1(ii) of Schedule L to the CA which envisages
                            bringing of the roughness value, as a consequence of such overlay
                            work, "to the initial value of 2000 mm/km".


                            94.   The learned Arbitral Tribunal has, however, chosen to interpret
                            Clause 4.3.1(ii) of Schedule L to the CA by reading the initial part of
                            the second sentence of the said clause, which reads "a renewal of
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 50 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             bituminous concrete shall be laid every 5 years after initial
                            construction" as a stand-alone stipulation, completely unrelated to the
                            latter part of the same sentence and, particularly, unrelated to the
                            stipulation that the roughness value is to be brought to the initial value
                            of 2000 mm/km.


                            95.   There is, prima facie, substance in the contention of Mr. Sharma
                            that, at the very least, according to such an interpretation would result
                            in reducing, to a superfluous redundancy, the words "to bring it to the
                            initial value of 2000 mm/km".


                            96.   Even if one were to read the stipulations, in Clause 4.3.1(ii) of
                            Schedule L to the CA of the requirement of laying the renewal coat
                            "every 5 years after initial construction" and "where the roughness
                            value reaches 3000 mm/km" distinctively - as the word "or" between
                            these two clauses would seem to indicate - the concluding stipulation
                            that the laying of the renewal coat is to bring the roughness value to
                            the initial value of 2000 mm/km would nonetheless apply to both
                            stipulations. The emphasis, by Mr Dayan Krishnan, on the use of the
                            word "or" in Clause 4.3.1 (ii) of Schedule L to the CA, between "shall
                            be laid every 5 years after initial construction" and "where the
                            roughness value reaches 3000 mm/km" does not, therefore, advance
                            the interpretation of the clause that he seeks to advocate. In either
                            case, the renewal coat is to be laid to ensure that the Roughness
                            Index/roughness value is brought to the initial value of 2000 mm/km.
                            Bringing of the Roughness Index to 2000 mm/km is the purpose of
                            laying the renewal coat. This stipulation would, therefore, apply to the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                      Page 51 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             entirety of Clause 4.3.1(ii) of Schedule L to the CA, and not merely to
                            the latter part of the second sentence therein.


                            97.   I have deliberated on whether, in so holding, this Court would
                            be interfering, without due justification, with the interpretation placed
                            by the learned Arbitral Tribunal on Clause 4.3.1(ii) of the Schedule L
                            to the CA or the other contractual covenants, or would, thereby, be
                            breaching the boundaries of Section 34 of the 1996 Act. On a holistic
                            appreciation of the issue, I am inclined to feel that I would not. 2000
                            mm/km is the optimum Roughness Index, for maintaining good
                            pavement riding quality. An increase in Roughness Index,
                            undisputedly, reduces pavement riding quality. Overlay/renewal work
                            reduces Roughness Index. On these, there is no dispute; indeed, the
                            submissions of Mr Dayan Krishnan were predicated on these
                            premises. It is for this purpose that Clause 4.3.1(ii) of Schedule L to
                            the CA envisages laying of a renewal coat, so that the Roughness
                            Index remains at 2000 mm/km or below, and pavement riding quality
                            is optimum. Overlay work for bringing the Roughness Index to 2000
                            mm/km is, therefore, envisaged, by Clause 4.3.1(ii) of Schedule L to
                            the CA in two situations; either every five years or whenever the
                            Roughness Index exceeds 3000 mm/km. In either case, the objective is
                            to ensure that the Roughness Index of the Project Highway does not
                            exceed 2000 mm/km.


                            98.   Per sequitur, where the Roughness Index is already below 2000
                            mm/km, on a plain interpretation of Clause 4.3.1(ii) of Schedule L to
                            the CA, no overlay/renewal work by the Concessionaire would be
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 52 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             warranted. The manner in which the learned Arbitral Tribunal has
                            chosen to interpret the clause appears, with deepest respect to the
                            eminent members of the learned Arbitral Tribunal, opposed to
                            commercial common sense. Commercial contracts have, it is trite, to
                            be commercially construed, as the learned Arbitral Tribunal has itself
                            observed in the impugned Award. In Mumbai Metropolitan Region
                            Development Authority v. Unity Infraproject Ltd.9, Dr Chandrachud,
                            J. (as he then was) tellingly exposited this principle thus:
                                       "In interpreting a contract, the Court cannot place emphasis on
                                       an isolated provision divorced from the context and unrelated
                                       to the other provisions which govern contractual obligations.
                                       Contracts represent business understandings between the
                                       parties. Commercial dealings between persons who are well
                                       versed in the transaction of business are regulated by contracts
                                       which parties opt to govern themselves. The law regulates
                                       those contracts and provides an ordered framework in which
                                       business dealings can be implemented. The duty of the Court
                                       when called upon to assess where the balance lies in a
                                       contractual dispute, is to read the contract as a whole in order
                                       to understand the business meaning which the parties
                                       attributed to their obligations. Interpretation in law must
                                       ensure in commercial matters that the view which the Court
                                       takes records the sense, which the parties to an arms length
                                       transaction attribute to the terms which they incorporate. The
                                       law is not divorced from business realities nor can the vision of
                                       the Judge who interprets the law be disjointed from the modem
                                       necessities to make business sense to business dealings."

                                                                                   (Emphasis supplied)


                            99.        The emphasis laid by the learned Arbitral Tribunal on Clause
                            2.6.1(a)(i) of Schedule L to the CA cannot, either, be said to be
                            justified. A bare reading of Clause 2.6.1 of Schedule L to the CA
                            indicates that the various clauses that follow merely set out the

                            9   2008 (4) Arb LR 313 (Bom)
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                             Page 53 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             activities which are required to be carried out by GMR. Amongst the
                            activities envisages in the CA is, undoubtedly, renewal of the wearing
                            surfaces of road pavements once every 5 years. It is obviously for that
                            purpose that the said activity finds mention in Clause 2.6.1(a)(i) of
                            Schedule L to the CA.


                            100. The specifications and stipulations relating to the manner in
                            which, and the circumstances in which, such activity would have to be
                            undertaken, however, specifically finds place in Clause 4.3.1 of
                            Schedule L of the CA. Clause 2.6.1 of Schedule L of the CA would,
                            therefore, have to be read subject to Clause 4.3.1 of Schedule L to the
                            CA and not vice-versa. More specifically, the circumstances in which
                            renewal coat would be required to be laid have necessarily to be
                            gleaned from Clause 4.3.1 of Schedule L to the CA, and not from
                            Clause 2.6.1(a) of Schedule L to the CA.


                            101. Clause 1.4.2(i) of the CA specifically provides that, in the event
                            of ambiguity between clauses, the specific clause would prevail over
                            other clauses. This is the contractual avatar of the generalia
                            specialibus non derogant principle of statutory interpretation.


                            102. The learned Arbitral Tribunal has dismissed the reliance, by
                            GMR, on Clause 1.4.2 (i) by a simple finding that Clause 4.3.1 of
                            Schedule L to the CA could not be regarded as specific in nature. No
                            reason for this finding is forthcoming in the impugned award. On a
                            bare reading of Clause 2.6.1 and Clause 4.3.1 of Schedule L to the
                            CA, it is apparent, ex facie, that the latter is specific and the former
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 54 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             general, clause and that, therefore, in the event of any ambiguity
                            between the two, Clause 4.3.1 of Schedule L to the CA would prevail.


                            103. Had these been the only issues, perhaps, it might have been
                            possible to argue - though I sincerely doubt whether the argument
                            would be sustainable - that the matter related to the realm of arbitral
                            interpretation of contractual covenants and may not, therefore, be
                            amenable to Section 34 interference.


                            104. The matter, however, does not rest there. The manner in which
                            the learned Arbitral Tribunal has chosen to interpret Clause 4.3.1 (ii)
                            of Schedule L to the CA is directly contrary to other relevant clauses
                            of the CA, the most important among them being Appendix 3.1 read
                            with Clause 4.3 of Schedule L to the CA. Clause 4.3 of Schedule L to
                            the CA clearly states that the framework of activities relating to
                            pavement, maintenance and rehabilitation in respect of flexible and
                            rigid pavement are given in the flow charts in Appendix 3.1 and
                            Appendix 3.2 of Schedule L to the CA respectively.


                            105. The flow chart in Appendix 3.1 of Schedule L to the CA ordains
                            that, in the matter of periodic maintenance of the highway surface,
                            apropos Roughness Survey, the Concessionaire is required to compare
                            the Roughness Index with the operation/performance criteria and
                            either "do nothing" or renew the surface. It is obvious that, if the
                            Roughness Index of the highway surface was in accordance with the
                            operation/performance criteria, GMR was to do nothing.


Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 55 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             106. Mr Dayan Krishnan has sought to contend that there were no
                            stipulated "operational/performance criteria" for the Roughness Index,
                            to enable a comparison, as envisaged by Appendix 3.1 to Schedule L
                            of the CA, to be made. I am unable to agree. The stipulated Roughness
                            Index, as per Clause 4.3.1(i) of Schedule to the CA, was 2000 mm/km.
                            The NHAI itself contends, during arguments, that the lower the
                            Roughness Index, the higher would be the riding quality of the
                            pavement. Where, therefore, the Roughness Index was already below
                            2000 mm/km, and the stipulated operation/performance criterion was
                            2000 mm/km, Appendix 3.1 to Schedule L to the CA is categorical in
                            envisaging that the Concessionaire would "do nothing". Appendix 3.1
                            of Schedule L to the CA was binding on GMR in view of Clause 4.3
                            of Schedule L to the CA. Clause 4.3.1 of Schedule L to the CA, being
                            a sub-clause of Clause 4.3, would necessarily have to be read in
                            accordance with Clause 4.3, and not contrary thereto. Thus read, the
                            Roughness Index of the highway having been always below 2000
                            mm/km, there could be no question of the CA having required GMR
                            to carry out further overlay work on the highway surface.


                            107. This is also supported by Appendix 3.4 to Schedule L of the
                            CA, reproduced supra. The said appendix clearly states that, if the
                            condition of the road is "good", no repairs were needed. Mr. Dayan
                            Krishnan has sought to contend that overlay work/laying of the
                            renewal coat on the surface, would not constitute "repair work". There
                            is, however, nothing to support this submission.


                            108. The CA does not define "repair work". In Sir Shadi Lal and
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 56 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Sons v. IT Commissioner10, the Supreme Court has held that
                            "restoration of stability or safety of subordinate or subsidiary part of a
                            portion of a building is repair but not the reconstruction of the entirety
                            of the building". In Hansraj Tiratharam Hans v. Jammu
                            Municipality11, the High Court of Jammu & Kashmir had refined
                            "repair" thus:


                                    "The expression 'repair' signifies restoration to the original
                                    condition. Anything which substantially improves or materially
                                    alters a thing from its original condition cannot be said to be
                                    merely a repair of that thing."


                            "Restoration of the stability or safety of a subordinate or subsidiary
                            part of a building" has also been held to be repair by the High Court of
                            Mysore in Ullal Dinkar Rao v. M. Ratna Bai12.


                            109. Clause 4.3.1(ii) of Schedule L to the CA envisages laying of a
                            renewal coat of bituminous concrete to bring the Roughness Index to
                            the original value of 2000 mm/km. Clearly, therefore, the activity
                            constitutes "repair".


                            110. Where the condition of the road is "good", therefore, such
                            overlay work would not be required as per Appendix 3.4 of Schedule
                            L of the CA.


                            111. The Roughness Index of the project highway, as per roughness


                            10
                               AIR 1988 SC 424
                            11 AIR 1963 J&K 18
                            12
                               AIR 1958 Mys. 77
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 57 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             survey carried out during the period 22 nd to 27th January, 2020, using
                            bump integrator, available on record, specifically certifies that, at all
                            points on the highway, "as per the obtained values at site, the road
                            condition is good". That being so, even applying Appendix 3.4 to
                            Schedule L to the CA, there was no requirement for any overlay work
                            to be done on the project highway by GMR.


                            112. The dismissal of the learned Arbitral Tribunal, in para 90 of the
                            impugned award, of the prescribed IRC standards as having "no
                            relevance to the determination of the controversy at hand" is also, in
                            my opinion, not sustainable in law. No reason is forthcoming on
                            record as to why the IRC standards have no relevance to determining
                            the controversy at hand. Clause 4.2.1.1 of the Schedule L to the CA,
                            on the other hand, makes the IRC standards binding on the
                            Concessionaire.


                            113. Clause 6 of IRC: 82 (reproduced in para 88 of the impugned
                            award) specifically deals with periodic renewals of pavements and
                            maintenance of pavement quality and read thus:

                                  "6.    Periodic Renewals

                                  6.1    Need and importance of Periodic renewals

                                         Periodic renewals consist of the provisions of a
                                  surfacing layer over the pavement at regular intervals of time,
                                  so as to preserve the required characteristics of the pavement
                                  and the offset the wear and tear caused by traffic, weathering,
                                  etc. In effect, periodic renewals represent preventive
                                  maintenance which is needed to prevent deterioration of the
                                  pavement of characteristics and to ensure that initial qualities

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 58 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   are kept up for the future requirement of traffic during the
                                  design life of the pavement. Early detection and repair of
                                  noticeable defects can prevent a major break-down of the
                                  surface. For example, if symptoms like hungry surface,
                                  ravelling etc. are noticed at an early stage and suitable
                                  preventive action by way of renewal of surface is taken to
                                  arrest further deterioration, the life of pavement can be
                                  prolonged.

                                  6.2    Planning and Programming of Renewals

                                         The general practice in this country is to finalise
                                  renewal program on an annual basis. In order that necessary
                                  steps leading to the laying of renewal layer on the road could
                                  be taken in proper time, the renewal programme for each
                                  section of a road should be decided well in advance. Once the
                                  programme is finalised, steps could be taken to secure the
                                  required allocations and start the preliminary filed action such
                                  as collection of material etc.

                                         While the nomenclature "Periodic Renewal" would
                                  imply that the renewal treatment be carried out a fixed and
                                  pre-determined frequency, it would neither be practicable nor
                                  desirable to follow implicitly any specified frequency
                                  irrespective of the condition of the road surface proposed to
                                  be renewed. The most effective way to plan a renewal
                                  programme is to carry out inspections of the road surface at
                                  suitable intervals. Visual inspection of the road as detailed in
                                  Section 3 of this Code should be carried out. In addition,
                                  special inspections also are necessary before and after the
                                  rains as to assess the need for patching and other remedial
                                  measures required to be carried out either in advance or
                                  together with the renewal treatment"
                                                                              (Emphasis supplied)
                            Clearly, therefore, IRC: 82 envisages periodic renewals, to prevent
                            deterioration of the pavement and to ensure maintenance of initial
                            qualities for future traffic requirements during the design life of the
                            pavements. The IRC is binding as per Clause 4.2.1.1 of Schedule L to
                            the CA. The relevance of the IRC cannot, therefore, be gainsaid.

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 59 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Clause 5, 5.1 and 5.2 of IRC:SP:16:2004 read thus:


                                  "5.    Recommended Standard for roughness values

                                  5.1    The maximum permissible values of surface roughness
                                  measured with a bump integrator for different surfaces are
                                  given in Table 3.

                                  5.2    Newly constructed surfaces are expected to given
                                  roughness values corresponding to 'Good' category while the
                                  values under 'Average' and 'Poor' category indicate level-of-
                                  service and intervention level for maintenance. Surfaces with
                                  very low roughness value skid resistance and are not desirable
                                  from safety considerations. Such surfacing should receive
                                  prompt attention for restoring frictional resistance."

                                                                           (Emphasis supplied)


                            114. Clause     5.2    of    IRC:SP:16:2004,      therefore,     envisages
                            intervention, for maintenance, where the roughness values of newly
                            constructed surfaces was "average" or "poor" and specifically
                            discountenances the need for such intervention where the surface
                            quality was "good". This harmonises, in its entirety, with Appendix
                            3.4 of Schedule L to the CA. The learned Arbitral Tribunal has,
                            without returning any finding on the said standards, merely held them
                            not to be relevant to determination of the controversy before it. This,
                            in my considered opinion, cannot sustain.


                            115. As has already been noted hereinabove, where submissions
                            advanced by the parties before it are either not considered or
                            considered and rejected without any reasons, the Section 34 court
                            would be justified in interfering where consideration of the said

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 60 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             submissions would result in materially altering the outcome of arbitral
                            process. The learned Arbitral Tribunal, in the impugned award,
                            confined its consideration to its interpretation of Clause 4.3.1(ii) of
                            Schedule L to the CA, in support of which it has relied on Clause
                            2.6(1)(a)(i) of Schedule L to the CA. The interpretation accorded, by
                            the learned Arbitral Tribunal, to Clause 4.3.1(ii) of Schedule L to the
                            CA, is, even on a reading of the said clause, not reasonable or an
                            interpretation which is in accordance with the wording of the clause.
                            Moreover, such an interpretation would also be contrary to Clause
                            4.3.1 (i) of Schedule L to the CA.


                            116. The interpretation accorded by the learned Arbitral Tribunal to
                            Clause 4.3.1(ii) of Schedule L to the CA would also be out of sync
                            with Clause 4.3 of Schedule L to the CA read with Appendix 3.1
                            thereto, Appendix 3.4 and Clause 5.2 of IRC:SP:16:2004 read with
                            Clauses 6.1 and 6.2 of IRC:82 which, as per Clause 4.2.1.1 of the
                            Schedule L to the CA, had necessarily to govern the execution of
                            operations by the concessionaire i.e., GMR.


                            117. I cannot, therefore, concur with the finding, of the learned
                            Arbitral Tribunal, that, though the Roughness Index, at all points of
                            time, below 2000 mm/km, GMR was, nonetheless, required to carry
                            out renewal/overlay work.


                            118. The manner in which the learned Arbitral Tribunal has come to
                            the said conclusion is, in my respectful opinion, contrary to several
                            binding clauses of the CA and is also not sustainable on a plain
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 61 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             reading of Clause 4.3.1 (ii) of Schedule L to the CA itself. It is,
                            therefore, "patently illegal" within the meaning of Section 34(2A) 4 of
                            the 1996 Act.


                            119. GMR was constrained to carry out overlay work on the
                            insistence of NHAI which, from time to time, threatened to withhold
                            its annuity payment in the event the work was not carried out. Even
                            otherwise, once the work was carried out at the insistence of NHAI,
                            despite GMR protesting, in writing, in that regard, if the work was not
                            within the work contemplated by the contract, GMR is entitled, in law,
                            to additional payment.


                            120. Claim 1 also covered a claim for extra costs incurred by GMR,
                            on account of NHAI refusing permission to allow recycling of milled
                            material. The learned Arbitral Tribunal, in this context, held that
                            milling, as an option, was available, under Clause 4.3.2 (ii) of
                            Schedule L to the CA, only in consultation with the IC.             It is
                            specifically held that there was no material on record to indicate that
                            any attempt or deliberation or discussion with the IC, regarding
                            milling of the existing crust, had been undertaken by GMR, which had
                            proceeded to commence milling on its own. The letter dated 12 th
                            February, 2014, from GMR to the IC, stating that GMR was intending
                            to carry out milling activity, did not seek any consultation with the IC,
                            as per the impugned award. GMR having undertaken the milling
                            exercise without consultation with the IC, learned Arbitral Tribunal
                            has found GMR not to be entitled to the expense involved in recycling
                            of the milled crust.
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 62 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             121. The finding, of the learned Arbitral Tribunal, that the milling
                            exercise have been undertaken without due consultation with the IC
                            and that, therefore, GMR would not be entitled to any expense
                            incurred on account of recycling of the milled crust has to be
                            examined in the light of the actual situation on ground and the
                            communications exchanged between the parties.


                            122. In its letter dated 5th December, 2013, addressed by NHAI to
                            GMR, NHAI specifically stated thus:


                                  "4.   Since the 5 years period is getting completed by
                                  25/03/2014 after construction, the first surface overlay is to
                                  be provided immediately, irrespective of whether the
                                  Roughness reaches 3000 mm/km or not, as per CL. 2.6.1 &
                                  CL 4.3.1 of Schedule 'L' of Concession Agreement.

                                  5.     As the project stretch is about 103 km and carrying out
                                  renewal coat on 4 lanes takes significant time, it is requested
                                  to furnish the programme as sought by PD, NHAI & IC, to
                                  take up the renewal coat with BC and complete by
                                  25/03/2014, within 10 days positively, otherwise your next
                                  annuity (10th) which is due in March 2014 will not be
                                  processed."

                            123. In view of the urgency expressed by NHAI, GMR with its
                            response dated 14th December, 2013, submitted the schedule for taking
                            up periodic maintenance by carrying out overlay work, as required by
                            NHAI. Clause 4.3.2 (ii) of Schedule L to the CA clearly permits, the
                            exploring, by the Concessionaire, of recycling of the existing crust
                            using milling as an option, only requiring that the Concessionaire has
                            to consult with the IC before doing so. The entitlement, of the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                        Page 63 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             Concessionaire to, recycle the crust used by milling cannot, therefore,
                            be gainsaid and is an entitlement of the Concessionaire under the CA.


                            124. The learned Arbitral Tribunal has, nonetheless, held GMR not
                            to be entitled to the extra costs incurred for recycling of the milled
                            material on the ground that, before carrying out renewal work by
                            milling, there was no "consultation" with the IC. The communications
                            from GMR to the IC, according to the learned Arbitral Tribunal, did
                            not propose any "consultation".


                            125. How sustainable is this finding?


                            126. As has already been noticed, consequent to the Project Director
                            of NHAI writing, to GMR, on 5th December, 2015, requiring GMR to
                            immediately undertake overlay work and threatening GMR with the
                            possibility of withholding of annuity payable to it in the alternative,
                            GMR submitted its work programme to the IC vide its communication
                            14th December, 2013. The programme annexed to the communication
                            clearly shows that renewal would involve "milling of BC surface" for
                            a period of 61 days, from 1st February, 2014 to 2nd April, 2014.


                            127. Following this, on 12th February, 2014, GMR again wrote to
                            IC, informing IC that it was commencing milling work on 15th
                            February, 2014 and enclosing, with the letter, the plan for diversion of
                            traffic, which would be occasioned as a result of the work. Following
                            this, on 18th February, 2014, GMR again wrote to IC, seeking its
                            approval for milling activity undertaken by it and seeking, further,
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 64 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             approval for disposal of milled bituminous material. A copy of the
                            said letter was also forwarded to NHAI.


                            128. NHAI remained silent throughout, not condescending to
                            respond to any of these communications. It was only on 28th February,
                            2014, that the IC wrote to NHAI, with a copy to GMR, objecting to
                            GMR having carried out renewal work by milling without prior
                            consultation with it. Immediately on this communication being
                            received by GMR, it discontinued milling, as the method for overlay
                            work.


                            129. In the backdrop of these communications, the finding, of the
                            learned Arbitral Tribunal, that GMR would not be entitled to the
                            expenses incurred for recycling of the mild material, I am constrained
                            to observe, is patently unreasonable. The communication dated 5th
                            December, 2013 compelled GMR, under threat of withholding annuity
                            payable to it, to immediately commence overlay work. In order to
                            comply with the requirement of consultation with the IC, GMR
                            addressed as many as three communications to the IC on 14th
                            December, 2013, 12th February, 2014 and 18th February, 2014,
                            informing the IC of carrying out of the renewal work using milling as
                            an option. The IC, at no point, disapproved this course of action.
                            Having compelled GMR to carry out renewal work immediately and
                            GMR having communicated, to NHAI, its intent to carry out the work
                            by milling, NHAI cannot, either in law or in equity, be permitted to
                            take advantage of its silence and refusal to respond to the
                            communications of GMR as a ground to fault GMR for having carried
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 65 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             out milling without proper consultation. This would amount to NHAI
                            being permitted to take advantage of its own wrong which, it is well
                            settled in law, is not permissible. The learned Arbitral Tribunal has, in
                            my view, erred in failing to take stock of the fact that, given the
                            urgency expressed by NHAI in its communication dated 5th December,
                            2013 and the threat held out therein, GMR could not have waited for
                            approval of the IC before carrying out the renewal work using milling,
                            which was an option contractually available to GMR vide under
                            Clause 4.3.2 (ii) of Schedule L to the CA. Significantly, GMR ceased
                            renewal work using milling immediately on being informed by the IC
                            that it was not permissible.


                            130. In these circumstances, the finding, of the learned Arbitral
                            Tribunal, that GMR would not be entitled to the costs incurred on
                            account of the recycling of the mild material is also, in my view,
                            "patently illegal" within the meaning of Section 34(2A) 4 of the 1996
                            Act.


                            131. The offshoot of the above discussion is that GMR would be
                            entitled to be recompensed for carrying out the overlay work by
                            renewal of the highway coat using bituminous concrete, as, under the
                            CA, this was not required to be done. It qualifies, therefore, as "extra
                            work", for which GMR is entitled to extra payment. GMR is also
                            entitled to the costs of recycling of the mild material.


                            132. In view thereof, the finding of learned Arbitral Tribunal, qua
                            the claim of GMR for ₹ 104,47,80,462/-, that it was not entitled to the
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 66 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             said claim, as the overlay work carried out by it, under the instructions
                            of NHAI, was within the work contemplated by the CA, cannot
                            sustain and has necessarily to be set aside.


                            133. Having said that, it is not open to this Court to, straightway,
                            allow Claim 1 of GMR on this ground alone, as the quantification of
                            the said claim by GMR has not been examined by the learned Arbitral
                            Tribunal, which proceeded on the basis that the claim itself was not
                            allowable.


                            134. As this Court has held the claim to be allowable, the
                            quantification of the claim would necessarily have to be assessed
                            afresh, for which purpose this Court intends to appoint a suitable
                            arbitrator.


                            Re. Claim 3


                            135. As I have held that GMR was not contractually required to carry
                            out renewal/overlay work of the project highway, as the roughness
                            index was, at all points, on the highway, below 2000 mm/km, Claim 3
                            of the contractor, which sought an injunction against NHAI from
                            insisting of relaying of the surface every five years, if the roughness
                            index was 2000 mm/km or less, would have to be allowed. The award
                            of the learned Arbitral Tribunal qua the said claim is also, therefore,
                            set aside.


                            Re: Claim 2
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 67 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             136. The learned Arbitral Tribunal has allowed Claim 2 of GMR, for
                            ₹ 10,78,61,864/-, recovered by NHAI towards damages. The damages
                            were recovered, by NHAI, under Clause 18.12 of the CA. GMR, vide
                            Claim 2 before the learned Arbitral Tribunal, sought reimbursement of
                            the damages. A reading of letter dated 8th June, 2016 from the IC to
                            the Project Director of NHAI, which proposes recovery of damages
                            from GMR, makes it clear that the recovery was on account of GMR's
                            perceived default in carrying out overlay work by renewal of the
                            bituminous coat on the highway surface. The learned Arbitral Tribunal
                            has held that NHAI was entitled to recover damages, but has allowed
                            GMR's claim on the ground that, prior to recovering damages, NHAI
                            had not issued, to GMR, the requisite notice under Clauses 18.12 and
                            18.13 of the CA.


                            137. That issue, however, pales into insignificance, in view of the
                            finding, hereinabove, that GMR was not, in fact, required, under the
                            CA, to carry out the overlay/renewal work as desired by NHAI. The
                            delay in carrying out the said work was, as is apparent from the
                            communications between GMR and NHAI, only because of the
                            repeated attempts of GMR to convince NHAI that, as the roughness
                            index of the highway was, at all points, less than 2000 mm/km,
                            overlay/renewal work was not required to be done, and NHAI's stoic
                            refusal to accede to this position. As the work that NHAI called upon
                            GMR to do was itself outside the CA, and the delay in performing the
                            work was only because of NHAI's refusal to accept this plain
                            contractual position, it is obvious that NHAI could not claim any
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                  Page 68 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             damages from GMR for the said delay.


                            138. As such, the question of issuance of notice under Clauses 18.12
                            and 18.13 of the CA does not arise for consideration, NHAI not
                            having been entitled in law, at all, to recover damages from GMR.
                            The decision of the learned Arbitral Tribunal to allow Claim 2 of
                            GMR has, therefore, to be upheld, albeit on different grounds.


                            Re: Claim 4 - Award of interest to GMR


                            139. The only ground on which NHAI has, in OMP(Comm)
                            449/2020, challenged the award of interest to GMR by the learned
                            Arbitral Tribunal is that, as GMR had delayed completion of overlay
                            work by almost nine months and had, therefore, breached its
                            obligations under the CA, no interest could have been awarded to it.


                            140. In view of the finding, hereinabove, that there was, in fact, no
                            breach of contract by GMR, carrying out of overlay/renewal work not
                            being a contractual obligation under the CA, the submission of NHAI,
                            in response of the award of interest to GMR, cannot sustain.


                            141. The award of the learned Arbitral Tribunal with respect to
                            Claim 4 of GMR is, therefore, upheld.


                            Re: Claim 5 of GMR and Counter-claim 1 of NHAI


                            142. GMR and NHAI, by their respective Claim 5 and Counter-claim
Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                   Page 69 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                             1, claimed the costs of the arbitration. The learned Arbitral Tribunal
                            awarded costs to GMR. NHAI's contention, against the said decision
                            is that, having rejected GMR's principal Claim 1 for ₹ 104,47,80,462/-
                            , the costs of the arbitration should not have been awarded to GMR.


                            143. As the decision to reject GMR's Claim 1 for ₹ 104,47,80,462/-
                            has been reversed by me hereinabove, no occasion arises for this Court
                            to interfere with the impugned award of the learned Arbitral Tribunal
                            insofar as it deals with Claim 5 of GMR and Counter-claim 1 of
                            NHAI.


                            Conclusion

                            144. In view of the aforesaid, these petitions are disposed of in the
                            following terms:


                                  (i)     OMP(Comm) 449/2020 is dismissed.

                                  (ii)    The award of the learned Arbitral Tribunal, qua Claims 2,
                                  4 and 5 of GMR, is upheld.


                                  (iii)   The award of the learned Arbitral Tribunal qua Claims 4
                                  and 5 is set aside, holding that GMR was entitled to extra
                                  payment for having carried out overlay work over the project
                                  highway by renewal of the bituminous surface, as the said work
                                  was not required, contractually, to be carried out under the CA,
                                  the roughness index of the project highway, at all points, and at

Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                    Page 70 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   all times, having been below 2000 mm/km. The decision of the
                                  learned Arbitral Tribunal, with respect to Claims 1 and 3 of
                                  GMR, holding GMR was not entitled to extra payment for
                                  carrying out the said overlay/renewal work is, therefore, set
                                  aside, as suffering from patent illegality.


                                  (iv)   This Court requests Hon'ble Mr Justice D.K. Jain, an
                                  eminent former judge of the Supreme Court of India, to arbitrate
                                  on the sustainability of the claim of GMR to the extent of ₹
                                  1,04,47,80,462/-, claimed by it, as there has been no prior
                                  arbitral adjudication of the quantum of the said claim or
                                  entitlement of GMR thereto, to the extent claimed. It shall be
                                  open to NHAI, in the said arbitral proceedings, to contest the
                                  quantification of the claim by GMR, though GMR's entitlement
                                  to extra payment would not be open for debate, having been
                                  concluded by this judgement.


                                  (v)    The learned arbitrator is requested to furnish the requisite
                                  disclosure under Section 12(2) of the 1996 Act within a week of
                                  entering on reference.


                                  (vii) The learned sole arbitrator would be entitled to the fees
                                  which were being paid to the learned presiding arbitrator in the
                                  proceedings which culminated in the rendition of the impugned
                                  award, or as otherwise finalized by the learned Arbitrator in
                                  consultation with the parties.


Signature Not Verified      O.M.P. (COMM) 433/2020 & contd. matters                     Page 71 of 72
Digitally Signed By:SUNIL
SINGH NEGI
Signing Date:07.04.2022
21:28:14
                                   (viii) OMP(Comm) 433/2020 stands allowed in the aforesaid
                                  terms.


                            145. There will be no order as to costs. Miscellaneous applications
                            also stand disposed of.


                                                                      C. HARI SHANKAR, J.

APRIL 6th, 2022 r.bararia/kr/SS/dsn Signature Not Verified O.M.P. (COMM) 433/2020 & contd. matters Page 72 of 72 Digitally Signed By:SUNIL SINGH NEGI Signing Date:07.04.2022 21:28:14