Delhi High Court

National Highways Authority Of India vs Irb Goa Tollwayprivate Ltd. on 21 February, 2022

Author: C. Hari Shankar

Bench: C. Hari Shankar

                          $~
                          *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                              Reserved on: 14th February, 2022
                                                            Pronounced on: 21st February, 2022

                          +      O.M.P. (COMM) 349/2016 & I.A. 9043/2016, I.A. 11952/2020,
                                 I.A. 11953/2020

                                 NATIONAL HIGHWAYS AUTHORITY OF INDIA
                                                                        ..... Petitioner
                                              Through: Mr. S. Nandakumar and Ms.
                                              Deepika Nandakumar, Advs.

                                                   versus

                                 IRB GOA TOLLWAY PRIVATE LTD.          ..... Respondent
                                              Through: Mr. Saurabh Kirpal, Sr. Adv.
                                              with Mr.Sanjay Agarwal, Mr.Parthiv
                                              Goswami, Mr.H.P Chaturvedi, Mr.M.V
                                              Ravindran,     Mr.Apoorva        Agrawal,
                                              Mr.Sarthak Sachdev and Ms. Terresa R.
                                              Daulat, Advs.

                          CORAM:
                          HON'BLE MR. JUSTICE C. HARI SHANKAR

                          %                    JUDGMENT
                                                 21.02.2022

                          1.     This petition, at the instance of the National Highways
                          Authority of India (NHAI), has been preferred under Section 34 of the
                          Arbitration and Conciliation Act, 1996 ("the 1996 Act"), assailing an
                          Award, dated 26th February, 2016, passed by an Arbitral Tribunal by a
                          majority of two learned Arbitrators to one.


                          2.     The respondent was the claimant before the learned Arbitral
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                      Page 1 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Tribunal and the petitioner-NHAI was the respondent.


                          3.     The respondent raised two claims. The learned Arbitral Tribunal
                          awarded, to the respondent,
                                 (i)    against Claim No. 1, ₹ 196,38,00,000/- along with
                                 interest of ₹ 100,15,38,000/- and
                                 (ii)   against Claim No. 2, ₹ 4,71,00,000/- along with interest
                                 of ₹ 2,73,18,000/-.

                          4.     As a result, a total amount of ₹ 303,98,01,213/- stands awarded
                          against NHAI and in favour of the respondent along with further
                          interest @ 12 % on the said amount from the date of Award till the
                          date of payment, in the event of failure, on the part of NHAI, to pay
                          the amount to the respondent within 30 days of the award.


                          5.     It merits mention, at the outset, that the present petition does not
                          assail, directly or indirectly, the award of interest by the learned
                          Arbitral Tribunal. Nor were arguments on the aspect of interest
                          advanced before the court, by Mr. Nandakumar, learned Counsel for
                          the NHAI. The award of interest by the learned Arbitral Tribunal, as
                          an independent cause of action has, therefore, gone unassailed.


                          6.     As such, the court is concerned only with the correctness of the
                          grant, by the impugned Award, of the amount of ₹ 196.38 crores
                          against Claim No. 1 and ₹ 4.71 crores against Claim No. 2, in favour
                          of the respondent and against the NHAI. Needless to say, however,
                          should the court find the said award to be deserving of interference,

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                           Page 2 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           interest as granted by the learned Arbitral Tribunal would also perish
                          with the principal. If, however, the court finds the award of the
                          principal amount not to be justifying of interference, the principal
                          amount would become payable along with interest as awarded by the
                          learned Arbitral Tribunal, as the award of interest has not been
                          independently contested.

                          7.      It also merits mention that the petition does not include any
                          challenge to the computation, by the learned Arbitral Tribunal, of the
                          amount awarded to the respondent.       All that is contested is the
                          entitlement of the respondent to the awarded amount.                 Mr
                          Nandakumar did, however, make certain limited submissions on the
                          aspect of computation, with which I would presently deal.


                          Facts


                          Events till execution of Concession Agreement


                          8.      In response to a Notice Inviting Tenders (NIT) floated by the
                          NHAI in March, 2008, for operation and maintenance of a stretch of
                          NH-4A in the State of Goa, a consortium of IRB Infrastructure
                          Developers Ltd. (IIDL) and Modern Road Makers Ltd. (MRM) ("the
                          IIDL-MRM consortium") submitted their bid and were successful.


                          9.      IIDL wrote to NHAI on 20th July, 2009, requesting to issue a
                          Letter of Acceptance (LoA) in favour of the IIDL-MRM Consortium,
                          as it had emerged as the lowest bidder against the NIT issued by

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 3 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           NHAI. Para 2 of the letter also indemnified NHAI, in the following
                          terms:
                                   "We are aware of the recent changes brought in with regard to
                                   land acquisition related pre-compliances. In this regard, we
                                   hereby indemnify NHAI for any delay caused with respect to
                                   signing of Concession Agreement due to delay arising out of
                                   completion of 3D process for 80% land acquisition."


                          10.      LoA was issued by NHAI in favour of IRB-MRM Consortium
                          on 5th January, 2010. The LoA required the Consortium to form a
                          Special Purpose Vehicle (SPV), execute a Concession Agreement
                          (hereinafter referred to as "CA") and submit performance security by
                          way of an irrevocable and unconditional Bank Guarantee of ₹ 23.55
                          crores within the period expiring on the 180th day from the date of
                          signing of the Concession Agreement.


                          11.      In compliance, the IRB-MRM Consortium wrote to NHAI on
                          8th February, 2010, informing NHAI that the Consortium had
                          constituted the respondent IRB Goa Tollways Pvt. Ltd. as an SPV, to
                          undertake the project.


                          12.      Following the constitution of the respondent as an SPV by the
                          Consortium, the CA was executed between the NHAI and the
                          respondent on 19th February, 2010. The CA, significantly, did not
                          contain any indemnity clause, as was contained in the letter dated 20 th
                          July, 2009 (supra) from IIDL to NHAI.


                          13.      The following clauses of the CA are relevant:
                                   "4.1.2       The Concessionaire may, upon providing the
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 4 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  Performance Security to the Authority in accordance with
                                 Article 9, at any time after 90 (ninety) days from the date of
                                 this Agreement or on an earlier day acceptable to the
                                 Authority, by notice require the Authority to satisfy any or all
                                 of the Conditions Precedent set forth in this Clause 4.1.2
                                 within a period of 30 (thirty) days of the notice, or such longer
                                 period not exceeding 60 (sixty) days as may be specified
                                 therein, and the conditions precedent required to be satisfied
                                 by the Authority prior to the Appointed Date shall be deemed
                                 to have been fulfilled when the Authority shall have:

                                        (a)   provided to the Concessionaire the Right of
                                        Way to the site in accordance with the provisions of
                                        Clause 10.3.1; provided that the conditions set forth in
                                        Clause 10.3.2 shall also be satisfied on or prior to the
                                        Appointed Date;

                                        (b)    Deleted

                                        (c)    procured approval of the Railway authorities in
                                        the form of a general arrangement drawing that would
                                        enable the Concessionaire to construct road
                                        overbridges/ underbridges at level crossings on the
                                        Project Highway in accordance with the Specifications
                                        and Standards and subject to the terms and conditions
                                        specified in such approval; and

                                        (d)   procured all Applicable Permits relating to
                                        environmental protection and conservation of the Site:

                                        (e)   execute and procure execution of the State
                                        Support Agreement.

                                        Provided that the Authority may from time to time by
                                        notice extend, for up to 6 (six) months, the period for
                                        procuring the approval set forth in Subclause (c) and/or
                                        Sub-clause (d) above and in that event the land to be
                                        covered by overbridges or the affected sections of the
                                        Project Highway, as the case may be, shall be included
                                        in the Appendix referred to in Clause 10.3 and dealt
                                        with in accordance with the provisions thereof; and
                                        provided further that upon procurement of such
                                        approval, the Concessionaire shall be entitled to a
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                               Page 5 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                         period of 12 (twelve) months therefrom for completion
                                        of the overbridges.

                                 4.2    Damages for delay by the Authority

                                 In the event that (i) the Authority does not procure fulfilment
                                 of any or all of the Conditions Precedent set forth in Clause
                                 4.1.2 within the period specified in respect thereof, and (ii) the
                                 delay has not occurred as a result of breach of this Agreement
                                 by the Concessionaire or due to Force Majeure, the Authority
                                 shall pay to the Concessionaire Damages in an amount
                                 calculated at the rate of 0.1% (zero point one percent) of the
                                 Performance Security for each day's delay until the fulfilment
                                 of such Conditions Precedent, subject to a maximum of 20%
                                 (twenty percent)of the Performance Security.

                                 7.2    Representations and Warranties of the Authority
                                 The Authority represents and warrants to the Concessionaire
                                 that:
                                        (a)    it has full power and authority to execute,
                                        deliver and perform its obligations under this
                                        Agreement and to carry out the transactions
                                        contemplated herein and that it has taken all actions
                                        necessary to execute this Agreement, exercise its rights
                                        and perform its obligations, under this Agreement;
                                        (b)   it has taken all necessary actions under the
                                        Applicable Laws to authorize the execution, delivery
                                        and performance of this Agreement;
                                        (c)   it has the financial standing and capacity to
                                        perform its obligations under the Agreement;
                                        (d)    this Agreement constitutes a legal, valid and
                                        binding obligation enforceable against it in accordance
                                        with the terms hereof;
                                        (e)    there are no actions, suits or proceedings
                                        pending or, to its knowledge, threatened against it at
                                        law or in equity before any court or before any other
                                        judicial, quasi-judicial Or other authority, the outcome
                                        of which may result in the default or breach of this
                                        Agreement or which individually or in the aggregate
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                               Page 6 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                         may result in any material impairment of its ability to
                                        perform its obligations under this Agreement;
                                        (f)    it has no knowledge of any violation or default
                                        with respect to any order, writ, injunction or any decree
                                        of any court or any legally binding order of any
                                        Government Instrumentality which may result in any
                                        material adverse effect on the Authority's ability to
                                        perform its obligations under this Agreement;
                                        (g)    it has complied with Applicable Laws in all
                                        material respects;
                                        (h)    all information provided by it in the Tender
                                        Notice and invitation to bid in connection with the
                                        Project is, to the best of its knowledge and belief, true
                                        and accurate in all material respects;
                                        (i)   it has the right, power and authority to manage
                                        and operate the Project Highway up to the Appointed
                                        Date;
                                        (j)    it has good and valid right to the Site, and has
                                        power and authority to grant a licence in respect
                                        thereto to the Concessionaire; and
                                        (k)    upon the Concessionaire paying the Concession
                                        Fee and performing the covenants herein, it shall not at
                                        any time during the term hereof, interfere with peaceful
                                        exercise of the rights and discharge of the obligations
                                        by the Concessionaire, in accordance with this
                                        Agreement


                                 10.3.2 Without prejudice to the provisions of Clause 10.3.1,
                                 the Parties hereto agree that on or prior to the Appointed Date,
                                 the Authority shall have granted vacant access and Right of
                                 Way such that the Appendix shall not include more than 50%
                                 (fifty per cent) of the total area of the Site required and
                                 necessary for the Four-Lane Project Highway, and in the
                                 event Financial Close is delayed solely on account of delay in
                                 grant of such vacant access and Right of Way, the Authority
                                 shall be liable to payment of Damages under and in
                                 accordance with the provisions of Clause 4.2.


Signature Not Verified
                          O.M.P. (COMM) 349/2016                                              Page 7 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  24.1 Financial Close

                                 24.1.1 The Concessionaire hereby agrees and undertakes that
                                 it shall achieve Financial Close within 180 (one hundred and
                                 eighty) days from the date of this Agreement and in the event
                                 of delay, it shall be entitled to a further period not exceeding
                                 120 (one hundred and twenty) days, subject to payment of
                                 Damages to the Authority in a sum calculated at the rate of
                                 0.1% (zero point one per cent) of the Performance Security
                                 for each day of delay; provided that the Damages specified
                                 herein shall be payable every week in advance and the period
                                 beyond the said 180 (one hundred and eighty) days shall be
                                 granted only to the extent of Damages so paid; provided
                                 further that no Damages shall be payable if such delay in
                                 Financial Close has occurred solely as a result of any default
                                 or delay by the Authority in procuring satisfaction of the
                                 Conditions Precedent specified in Clause 4.1.2 or due to Force
                                 Majeure.

                                 24.2 Termination due to failure to achieve Financial Close

                                 24.2.2 Upon Termination under Clause 24.2.1, the Authority
                                 shall be entitled to encash the Bid Security and appropriate
                                 the proceeds thereof as Damages provided, however, if
                                 Financial Close has not occurred solely as a result of the
                                 Authority being in default of any of its obligations under
                                 Clause 4.1.2. it shall upon Termination, return the Bid
                                 security forthwith along with Damages, equal to 25% (twenty-
                                 five per cent) thereof. For the avoidance of doubt, it is
                                 expressly agreed that if the Bid Security shall have been
                                 substituted by Performance Security, the Authority shall have
                                 been substituted by Performance Security, the Authority shall
                                 be entitled to encash therefrom an amount equal to Bid
                                 Security.

                                 33.3 Certification of claims by Statutory Auditors

                                 Any claim or document provided by the Concessionaire to the
                                 Authority in connection with or relating to receipts, income,
                                 payments, costs, expenses, accounts or audit, and any matter
                                 incidental thereto shall be valid and effective only if certified
                                 by its Statutory Auditors. For the avoidance of doubt, such
                                 certification shall not be required for exchange of information
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                              Page 8 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  in the normal course of business including the submission of
                                 Monthly Fee Statements under Clause 19.5.

                                 34.1   Force Majeure

                                 As used in this Agreement the expression "Force Majeure" or
                                 "Force Majeure Event" shall mean occurrence in India of any
                                 or all of Non-Political Event, Indirect Political Event and
                                 Political Event, as defined in Clauses 34.2,34.3 and 34.4
                                 respectively, if it affects the performance by the Party
                                 claiming the benefit of Force Majeure (the "Affected Party")
                                 of its obligations under this Agreement and which act or event
                                 (i) is beyond the reasonable control of the Affected Party, and
                                 (ii) the Affected Party could not have prevented or overcome
                                 by exercise of due diligence and following Good Industry
                                 Practice, and (iii) has Material Adverse Effect on the Affected
                                 Party.

                                 34.4   Political Event

                                 A Political Event shall mean one or more of the following acts
                                 or events by or on account of any Government
                                 Instrumentality:

                                        (a)    Change in Law, only if consequences thereof
                                        cannot be dealt with under and in accordance with the
                                        provisions of Article 41 and its effect, in financial
                                        terms, exceeds the sum specified in Clause 41.1;

                                        (b)   compulsory acquisition in national interest or
                                        expropriation of any Project Assets or rights of the
                                        Concessionaire or of the Contractors;

                                        (c)    unlawful or unauthorised or without jurisdiction
                                        revocation of, or refusal to renew or grant without
                                        valid cause, any clearance, licence, permit,
                                        authorisation, no objection certificate, consent,
                                        approval or exemption required by the Concessionaire
                                        or any of the contractors to perform their respective
                                        obligations under this Agreement and the Project
                                        Agreements; provided that such delay, modification,
                                        denial, refusal or revocation did not result from the
                                        Concessionaire's or any Contractor's inability or failure
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                              Page 9 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                         to comply with any condition relating to grant,
                                        maintenance or renewal of such clearance, licence,
                                        authorisation, no objection certificate, exemption,
                                        consent, approval or permit;

                                        (d)    any failure or delay of a Contractor but only to
                                        the extent caused by and/or Political Event and which
                                        does not result in any offsetting compensation being
                                        payable to the Concessionaire or on behalf of such
                                        Contractor; or

                                        (e)    any event or circumstance of a nature analogous
                                        to any of the foregoing.

                                 34.5 Duty to report Force Majeure Event

                                 34.5.1 Upon occurrence of a Force Majeure Event, the
                                 Affected Party shall by notice report such occurrence to the
                                 other Party forthwith. Any notice pursuant hereto shall
                                 include full particulars of:

                                        (a)    the nature and extent of each Force Majeure
                                        Event which is the subject of any claim for relief under
                                        this Article 34 with evidence in support thereof;

                                        (b)    the estimated duration and the effect or probable
                                        effect which such Force Majeure Event is having or
                                        will have on the Affected Party's performance of its
                                        obligations under this Agreement;

                                        (c)   the measures which the Affected Party is taking
                                        or proposes to take for alleviating the impact of such
                                        Force Majeure Event; and

                                        (d) any other information relevant to the Affected
                                        Party's claim.

                                 34.5.2 The Affected Party shall not be entitled to any relief
                                 for or in respect of a Force Majeure Event unless it shall have
                                 notified the other Party of the occurrence of the Force
                                 Majeure Event as soon as reasonably practicable, and in any
                                 event not later than 7 (seven) days after the Affected Party
                                 knew, or ought reasonably to have known, of its occurrence,
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                            Page 10 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  and shall have given particulars of the probable material effect
                                 that the Force Majeure Event is likely to have on the
                                 performance of its obligations under this Agreement.

                                 34.5.3 For so long as the Affected Party continues to claim to
                                 be materially affected by such Force Majeure Event, it shall
                                 provide the other Party with regular (and not less than
                                 weekly) reports containing information as required by Clause
                                 34.5.1, and such other information as the other Party may
                                 reasonably request the Affected Party to provide.

                                 34.7 Allocation of costs arising out of Force Majeure

                                 34.7.1 Upon occurrence of any Force Majeure Event prior to
                                 the Appointed Date, the Parties shall bear their respective
                                 costs and no Party shall be required to pay to the other Party
                                 any costs thereof.

                                 34.7.2 Upon occurrence of a Force Majeure Event after the
                                 Appointed Date, the costs incurred and attributable to such
                                 event and directly relating to the Project (the "Force Majeure
                                 Costs") shall be allocated and paid as follows:

                                        (a)    upon occurrence of a Non-Political Event, the
                                        Parties shall bear their respective Force Majeure Costs
                                        and neither Party shall be required to pay to the other
                                        Party any costs thereof;

                                        (b)    upon occurrence of an Indirect Political Event,
                                        all Force Majeure Costs attributable to such Indirect
                                        Political Event, and not exceeding the Insurance Cover
                                        for such Indirect Political Event, shall be borne by the
                                        Concessionaire, and to the extent Force Majeure Costs
                                        exceed such Insurance Cover, one half of such excess
                                        amount shall be reimbursed by the Authority to the
                                        Concessionaire; and

                                        (c)    upon occurrence of a Political Event, all Force
                                        Majeure Costs attributable to such Political Event shall
                                        be reimbursed by the Authority to the Concessionaire.

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 11 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  For the avoidance of doubt, Force Majeure Costs may include
                                 interest payments on debt, O&M Expenses, any increase in
                                 the cost of Construction Works on account of inflation and all
                                 other costs directly attributable to the Force Majeure Event,
                                 but shall not include loss of Fee revenue or debt repayment
                                 obligations, and for determining such costs, information
                                 contained in the Financial Package may be relied upon to the
                                 extent that such information is relevant.

                                 34.9 Termination Payment for Force Majeure Event

                                 34.9.3 If Termination is on account of a Political Event, the
                                 Authority shall make a Termination Payment to the
                                 Concessionaire in an amount that would be payable under
                                 Clause 37.3.2 as if it were an Authority Default.

                                 37.3.2 Upon Termination on account of an Authority Default,
                                 the Authority shall pay to the Concessionaire, by way of
                                 Termination Payment, an amount equal to

                                        (a)    Debt Due; and

                                        (b) 150% (one hundred and fifty per cent) of the
                                        Adjusted Equity.

                                 37.3.3 Termination Payment shall become due and payable to
                                 the Concessionaire within 15 (fifteen days of a demand being
                                 made by the Concessionaire to the Authority with the
                                 necessary particulars and in the event of any delay the
                                 Authority shall pay interest at a rate equal to 3% (three per
                                 cent) above the Bank Rate on the amount of Termination
                                 Payment remaining unpaid; provided that such delay shall not
                                 exceed 90 (ninety) days. For the avoidance of doubt, it is
                                 expressly agreed that Termination Payment shall constitute
                                 full discharge by the Authority of its payment obligations in
                                 respect thereof hereunder

                                 37.4. Other rights and obligations of the Authority

                                 Upon Termination for any reason whatsoever, the Authority
                                 shall:

                                    (a) be deemed to have taken possession and control of the
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                           Page 12 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                     Project Highway forthwith;

                                    (b) take possession and control of all materials, stores,
                                    implements, construction plants and equipment on or
                                    about the Site;

                                    (c) be entitled to restrain the Concessionaire and any
                                    person claiming through or under the Concessionaire from
                                    entering upon the Site or any part of the Project;

                                    (d) require the Concessionaire to comply with the
                                    Divestment Requirements set forth in Clause 38.1; and

                                    (e) succeed upon election by the Authority, without the
                                    necessity of any further action by the Concessionaire, to
                                    the interests of the Concessionaire under such of the
                                    Project Agreements as the Authority may in its discretion
                                    deem appropriate, and shall upon such election be liable to
                                    the Contractors only for compensation accruing and
                                    becoming due and payable to them under the terms of their
                                    respective Project Agreements from and after the date the
                                    Authority elects to succeed to the interests of the
                                    Concessionaire. For the avoidance of doubt, it is hereby
                                    agreed, and the Concessionaire hereby acknowledges, that
                                    all sums claimed by such Contractors as being due and
                                    owing for works and services performed or accruing on
                                    account of any act, omission or event prior to such date
                                    shall constitute debt between the Concessionaire and such
                                    Contractors, and the Authority shall not in any manner be
                                    liable for such sums. It is further agreed that in the event
                                    the Authority elects to cure any outstanding defaults under
                                    such Project Agreements, the amount expended by the
                                    Authority for this purpose shall be deducted from the
                                    Termination Payment."

                                 44.3 Arbitration

                                 44.3.1 Any dispute which is not resolved by conciliation, as
                                 provided in Clause 44.2, shall be finally decided by reference
                                 to arbitration by a Board of Arbitrators appointed in
                                 accordance with Clause 44.3.2. Such arbitration shall be held
                                 in accordance      with the Rules of Arbitration of the
                                 International Centre for Alternative Dispute Resolution, New
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                            Page 13 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  Delhi (the "Rules"), or such other rules as may be mutually
                                 agreed by the Parties, and shall be subject to the provisions of
                                 the Arbitration Act. The venue of such arbitration shall be
                                 Delhi, and the language of the arbitration proceedings shall be
                                 English.

                                 48.1 Definitions

                                 "Appointed Date" means the date on which Financial Close is
                                 achieved or an earlier date that the Parties may by mutual
                                 consent determine, and shall be deemed to be the date of
                                 commencement of the Concession Period;

                                 "Adjusted Equity" means the Equity funded in Indian Rupees
                                 and adjusted on the first day of the current month (the
                                 "Reference Date"), in the manner set forth below, to reflect
                                 the change in its value on account of depredation and
                                 variations in WPI, and for any Reference Date occurring:

                                        (a)    on or before COD, the Adjusted Equity shall be
                                        a sum equal to the Equity funded in Indian Rupees and
                                        expended on the Project, revised to the extent of one
                                        half of the variation in WPI occurring between the first
                                        day of the month of Appointed Date and the Reference
                                        Date;

                                        (b)    from COD and until the 4th (fourth) anniversary
                                        thereof, an amount equal to the Adjusted Equity as on
                                        COD shall be deemed to be the base (the "Base
                                        Adjusted Equity") and the Adjusted Equity hereunder
                                        shall be a sum equal to the Base Adjusted Equity,
                                        revised at the commencement of each month following
                                        COD to the extent of variation in WPI occurring
                                        between COD and the Reference Date;

                                        (c)    after the 4th (fourth) anniversary of COD, the
                                        Adjusted Equity hereunder shall be a sum equal to the
                                        Base Adjusted Equity reduced by 0.28% (zero point
                                        two eight per cent) thereof at the commencement of
                                        each month following the 4th (fourth) anniversary of
                                        COD and the amount so arrived at shall be revised to
                                        the extent of variation in WPI occurring between COD
                                        and the Reference Date;
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 14 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  For the avoidance of doubt, the adjusted Equity shall, in the
                                 event of Termination be computed as on Reference Date
                                 immediately preceding the Transfer Date; provided that no
                                 reduction in the Adjusted Equity shall be made for a period
                                 equal to the duration, if any, for which the Concession Period
                                 is extended, but the revision on account of WPl shall continue
                                 to be made;"


                          Achieving Financial Close


                          14.    On 31st March, 2010, the respondent wrote to NHAI stating that
                          it had achieved "financial close", within the meaning of Clause 24.1.2
                          of the CA. Thereafter, certain amendments in the financing agreement
                          were sought by NHAI, which were also effected by the respondent on
                          3rd September, 2010. Vide letter dated 20th October, 2010, addressed
                          to the respondent, NHAI acknowledged that the respondent had
                          achieved financial close on 3rd September, 2010, albeit as against the
                          Scheduled Date of Financial Close i.e. 18th August, 2010. This fact is
                          also acknowledged by NHAI in its written statement filed before the
                          learned Arbitral Tribunal, as has been noticed in the impugned Award.
                          The learned Arbitral Tribunal has, therefore, justifiably held that the
                          achievement of financial close, by the respondent, on 3 rd September,
                          2010 could not be disputed.

                          Sub-contract with IIDL and communications from IIDL


                          15.    In the interregnum, the respondent, in turn, sub-contracted the
                          work to IIDL as the EPC contractor on 17th March, 2010, and
                          forwarded a copy of the EPC contract to NHAI on 31 st March, 2010.
                          IIDL, thereafter, addressed several communications to the respondent,
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                           Page 15 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           inter alia on 20th April, 2010, 19th May, 2010, 11th June, 2010, 25th
                          August, 2010, 4th November, 2010, 8th December, 2010, 31st January,
                          2011, 4th April, 2011, 27th May, 2011, 13th July, 2011, 9th September,
                          2011, 18th November, 2011 and 1st December, 2011, stating that huge
                          expenses were being incurred as, owing to non-commencement of
                          work on the project, the resources that had been mobilised were lying
                          idle.


                          Demand for damages and the "Appointed Date"


                          16.     Performance security, as required by Clause 4.1.3 (a) read with
                          Clause 9.1 of the CA was furnished, by the respondent, on 2nd August,
                          2010, within the time stipulated in that regard. On 20th October, 2010,
                          NHAI wrote to the respondent thus:

                                  "NHAI/BOT/11012/46/2005/14734             20th October, 2010

                                  To,

                                  M/s IRB Goa Tollways Private Limited
                                  IRB Complex
                                  Chandivali Farm, Chandivali Village
                                  Andheri (East), Mumbai - 400072
                                  Fax 022-66751024

                                  Sub; Four Laning of Goa/Karnataka Border to Panaji-Goa
                                  stretch of NH-4A from Km 844+000 to Km 153+070 in the
                                  State of Goa on BOT (Build, Operate and Transfer) Toll basis
                                  on DBPO Pattern under NHDP Phase-III Appointed
                                  Date/Financial Close-Reg.

                                  Sir,
                                         Please refer to various correspondences in connection
                                  with Financial Close of subject project. In this contexts, it is
                                  intimated that you have achieved the Financial Close as on
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                              Page 16 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  03.09.2010 as against the Scheduled Date of Financial Close
                                 i.e.18.08.2010 (180 days from the date of Concession
                                 Agreement).

                                        As per Clause 24.1.1 of the CA, the Concessionaire is
                                 requested to deposit the applicable damages at the rate of
                                 0.1% of the performance security for each day of delay.

                                        In pursuant to above provision, you are requested to
                                 deposit the requisite amount on priority at the rate of 0.1% of
                                 the performance security for each day of delay w.e.f.
                                 18.08.2010 till the date of the financial close i.e. 03.09.2010,
                                 so that further action on fixation of Appointed Date can be
                                 taken.

                                                                          Yours faithfully,
                                                                                Sd/-
                                                                          (A.K. Sharma)
                                                                    General Manager (Tech.)"


                          17.    The respondent replied on 27th October, 2010, objecting to the
                          demand of NHAI to the respondent to pay damages under Clause
                          24.1.1, contending that the delay, if any, was owing to reasons not
                          attributable to the respondent.      As such, the respondent requested
                          NHAI to waive the demand for damages, comply with the obligations/
                          Conditions Precedent cast on NHAI under Clause 4.1.2 of the CA and
                          declare the Appointed Date for the project.


                          18.    Communications were also addressed by the respondent and by
                          IIDL to NHAI, stating that NHAI had not provided Right of Way, as
                          required by Clause 10.3.1 and 10.3.2 of the CA. This was reiterated
                          by IIDL vide letter dated 28th April, 2011, in which NHAI was again
                          put on notice that it had failed to grant Right of Way to the
                          respondent, as required by Clause 4.1.2 read with Clauses 10.3.1 and

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 17 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           10.3.2 of the CA, as well as to provide applicable permits relating to
                          environmental protection and conservation of the site. As a result, it
                          was stated that NHAI had been unable to declare the Appointed Date
                          for the project. NHAI was, therefore, requested to expedite fulfilment
                          of the conditions precedent as they apply to it.


                          Appointment of Statutory Auditor


                          19.    In the interregnum, vide letter dated 26th October, 2010, NHAI
                          concurred to the appointment of Dass Maulik Mahindra K. Aggarwal
                          & Co. as the statutory auditor for the project, in terms of Clause 33.2.1
                          of the CA. The statutory auditor, vide letter dated 12th April, 2011,
                          certified the aggregate project cost incurred till 31st March, 2011 to be
                          ₹ 142.09 crores, of which ₹ 34.6 crores was sourced through equity
                          capital and ₹ 92.94 crores through unsecured loans.


                          Termination of CA


                          20.    On 23rd November, 2011, the following communication was
                          addressed by NHAI to the respondent, terminating the CA:


                                 "NHAI/BOT/11019/46/2008/1373           November 23, 2011

                                                                        By Speed Post/Fax
                                 M/s IRB Goa Tollway Private Limited
                                 IRB Complex, Chandivali Farm,
                                 Chandivali Village, Andheri (East),
                                 Mumbai - 400072
                                 Tel: 022-66404220
                                 Fax 022-66751024

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                        Page 18 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  Kind Attn: Mr. D.K. Joshi, Director

                                 Sub: Four Laning of Goa/Karnataka Border - Panaji Goa
                                      Stretch of NHAI- 4A From Km 84.000 to km 153.070
                                      in the State of Goa on BOT (Toll) Basis under NHDP
                                      Phase III - Termination of Concession Agreement of
                                      the Project

                                 Ref:   Your Letter No.       IRBGTPL/CTO/OUT/1936/2011
                                        dated 24/08/2011

                                 Sir,
                                        Please refer to the Concession Agreement signed on
                                 19/02/2010 for the above subject project and to state that the
                                 issues of Land Acquisition, Clearance of forest &
                                 Environmental and disputes on Toll Rates is pending with the
                                 Government of Goa for a long time and after persistent
                                 persuasion with the Government of Goa, the matter is, stand
                                 still.

                                        Further, without resolving the above issues, there can
                                 not be any progress on construction of said project.

                                 2).    In light of the above peculiar situation and best efforts
                                 by NHAI, the Competent Authority had no other option but
                                 constrained to terminate the said Concession Agreement as
                                 per provisions provided in Article 37 of the Concession
                                 Agreement and cancellation of the entire project. Thus the
                                 Agreement is, hereby, terminated.

                                 3)    Accordingly;    the     'Bank      Guarantee      No.
                                 2915IGPER036910 dated 30/07/2010 for Rs. 23,55,00,000(.-
                                 (Rupees Twenty Three Crores Fifty Five Lacs Only) issued by
                                 Bank of Baroda, Mumbai in favour of NHAI, towards
                                 Performance Security for the subject work is released
                                 herewith.

                                 4)     You would appreciate that despite best efforts of NHAI
                                 the project can not be started and your participation in the
                                 bidding has been highly appreciated and any inconvenience is
                                 regretted.

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 19 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                                                        Yours sincerely,
                                                                             Sd/-
                                                                   Anil Kumar Sharma
                                                                General Manager (Tech)
                                                             (Maharashtra & Goa Division)"


                          This letter does not admit of two interpretations. NHAI has, clearly
                          and umabiguously and without any equivocation whatsoever, admitted
                          the failure to commence the project to be attributable to its inability in
                          obtaining Governmental clearance, despite its best efforts. Somewhat
                          inexplicably, NHAI sought to contend, before the learned Arbitral
                          Tribunal as well as before me, that the termination was owing to
                          default of both NHAI and the respondent.           The learned Arbitral
                          Tribunal, per majority, has rightly rejected this submission.


                          21.    Following the aforesaid termination of the CA, the respondent
                          wrote to IIDL on 25th November, 2011, requesting it to de-mobilise its
                          resources, at the site.


                          Claim of respondent and invocation of arbitration


                          22.    On 6th February, 2012, the respondent wrote to NHAI,
                          submitting its claim for ₹ 267.1245 crores and ₹ 4.71 crores under
                          Clause 37.3.2 and 4.2 of the CA. The details of the cost incurred as
                          certified by the statutory auditors were also enclosed therewith.


                          23.    On NHAI failing to honour the aforesaid claim of the
                          respondent, the respondent issued a notice under Section 21 of the
                          1996 Act, invoking arbitration, on 25th November, 2013. Consequent
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                          Page 20 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           thereto, by consent of parties, the disputes were referred to a three
                          member Arbitral Tribunal which has come to render the impugned
                          Award by a majority of two learned Arbitrators to one.

                          24.    Reference to the "award", hereinafter, would denote the
                          majority award, as that is the ultimately enforceable award, and
                          subject matter of challenge.

                          The Award


                          25.    It would be appropriate to summarise the impugned Award,
                          before proceeding to examine the challenge thereto.


                          Rival contentions of parties before the learned Arbitral Tribunal


                          26.    At the outset, the learned Arbitral Tribunal set out the rival
                          stands of the parties before it. The respondent, as the claimant before
                          the learned Arbitral Tribunal, contended that it had fulfilled the
                          Conditions Precedent in Clauses 9, 24 and 47 of the CA, as (i)
                          Performance Security was given within the stipulated time, (ii)
                          financial close was achieved by it on 31st March, 2010, though it was
                          not contesting the stand of NHAI, in its letter dated 22nd October,
                          2010, as well as in the written statement filed before the learned
                          Arbitral Tribunal that financial close had been achieved by the
                          respondent on 3rd September, 2010 and (iii) by operation of Clause
                          48.1 of the CA, therefore, the Appointed Date was also 3rd September,
                          2010. The respondent contended, before the learned Arbitral Tribunal,
                          that NHAI had defaulted in providing the Right of Way as was
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 21 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           required by Article 4.1.2 of the CA, till April 2011, which was more
                          than a year from the execution of the CA, during which period the
                          respondent's investment and resources remained idle. The respondent
                          also submitted that Clause 7.2 of the CA misrepresented, to the
                          respondent, that NHAI had good and valid right to the site, whereas, in
                          actual fact, NHAI had no Right of Way, as it had to approach the
                          Government of Goa in that regard. The respondent pointed out that
                          Clause 10.3.2 of the CA required NHAI, at or before the Appointed
                          Date, to grant vacant access and Right of Way to the site, which was
                          not done.


                          27.    The respondent also assailed the termination of the CA, by
                          NHAI on 23rd November, 2011, as illegal. As such, before the learned
                          Arbitral Tribunal, the respondent contended that it was entitled to
                          damages under Clause 37.3.2 of the CA read with Section 73 of the
                          Indian Contract Act, 1872 ("the Contract Act").


                          28.    Thus did the respondent lay, before the learned Arbitral
                          Tribunal, two claims, the first predicated on Clause 37.3.2 for 150% of
                          the Adjusted Equity, amounting to ₹ 267.21245 crores and the second
                          for damages towards delay in fulfilment of the Conditions Precedent
                          by NHAI.


                          29.    NHAI contended, per contra, that financial close had never
                          taken place, as the respondent had failed to pay penalty/damages at the
                          rate of 0.1% of Performance Security for each day of delay in
                          achieving the financial close, as required by Clause 24.1.1 of the CA.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 22 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           It also disclaimed any liability to pay damages to the respondent,
                          citing force majeure. NHAI relied on Clause 4.1 of the CA to contend
                          that the rights and obligations of the parties under the CA was subject
                          to satisfaction of the Conditions Precedent, stipulated in the said
                          Clause.


                          30.    It was further contended, by NHAI, that the CA was terminated
                          on account of non-fulfilment of Conditions Precedent by both parties
                          and that the termination was valid. As both parties had failed to
                          perform their Conditions Precedent, NHAI submitted that no
                          Appointed Date had been determined. NHAI's contention was that
                          merely achieving financial close did not amount to fixation of the
                          Appointed Date even on the date of achievement of financial close as
                          endorsed by NHAI. The respondent had failed, contended NHAI, to
                          fulfil the Conditions Precedent, cast on it by the CA, prior to the
                          Appointed Date and these Conditions Precedent had not been waived
                          by NHAI. As such, the contention of NHAI was that the Appointed
                          date had not reached till the termination of the CA by NHAI on 23 rd
                          November, 2011.          As the Appointed Date had yet to reach, the
                          Concession Period had also yet to commence. NHAI also placed
                          reliance on Clause 34 of the CA to contend force majeure and
                          submitted that the CA had been terminated by NHAI on account of
                          failure, by both parties, to fulfil the Conditions Precedent, owing to
                          force majeure.




Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 23 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Consideration by the learned Arbitral Tribunal


                          31.    Having thus set out the rival stands of the parties before it, the
                          learned Arbitral Tribunal proceeded to examine the issues arising,
                          seriatim.


                          Financial Close


                          32.    The learned Arbitral Tribunal first addressed the issue of
                          attainment of financial close. Clause 24.1.1 of the CA, it was noted,
                          recorded the undertaking of the respondent to achieve financial close
                          within 180 days from the execution of the CA, with an additional
                          permissible period of 120 days, subject to payment of damages to
                          NHAI @ 0.1% of the Performance Security per day. Clause 24.1.1
                          also exempted the requirement of payment of damages if delay in
                          achieving financial close was solely due to delay/default by NHAI in
                          satisfying the Conditions Precedent stipulated in Clause 4.1.2 of the
                          CA, or owing to force majeure.


                          33.    NHAI had, it was noted, admitted, both in its letter dated 22 nd
                          October, 2010, as well as in the written statement filed before the
                          learned Arbitral Tribunal, that financial close had been achieved by
                          the respondent on 3rd September, 2010. On the ground that this was
                          beyond the period of 180 days from the execution of the CA, which
                          expired on 18th August, 2010, NHAI, vide its letter dated 20th October,
                          2010, called upon the respondent to deposit damages under Clause
                          24.1.1 @ 0.1% of the Performance Security per day of delay, so that
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                        Page 24 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           further action for fixation of the Appointed Date could be taken. The
                          learned Arbitral Tribunal noted, however, in this regard, that (i) NHAI
                          did not deduct, from the Performance Security, any damages under
                          Clause 24.1.1, (ii) the quantum of damages was not stipulated in the
                          letter dated 20th October, 2010, (iii) no counter claim was preferred by
                          NHAI, seeking damages and (iv) Clause 24.2.2 exempted the
                          requirement of payment of damages where the delay in achieving
                          financial close had occurred solely on account of force majeure.
                          Inasmuch as NHAI was itself pleading force majeure, the learned
                          Arbitral Tribunal opined that it could not, very well, call upon the
                          respondent to pay damages.


                          34.    In any event, these circumstances did not alter the fact that the
                          respondent had achieved financial close, admittedly at least on 3rd
                          September, 2010.


                          Appointed Date


                          35.    The learned Arbitral Tribunal noted that Clause 48 of the CA,
                          plainly and simply read, stipulated, as the only precondition for
                          determining the Appointed Date, achievement of financial close, and
                          that no other condition or stipulation was contained in this regard.
                          The only circumstance in which Clause 48 envisaged any other
                          Appointed Date, was where the parties, by mutual consent, fixed an
                          earlier date as the Appointed Date. That had not taken place in the
                          present case.


Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 25 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           36.    As financial close, even as per NHAI, had been achieved by the
                          respondent on 3rd September, 2010, the learned Arbitral Tribunal held
                          that, by operation of Clause 48 of the CA, the Appointed Date was
                          also 3rd September, 2010.


                          37.    The communications exchanged between NHAI and the
                          respondent, the learned Arbitral Tribunal noted, indicated that both
                          parties were harbouring a misunderstanding regarding the Appointed
                          Date, presuming that the Appointed Date had yet to be fixed. This
                          misunderstanding, however, it was observed, could not alter the effect
                          of the contractual covenants contained in Clause 48. Clause 48 did not
                          provide for any determination of the Appointed Date by NHAI. The
                          Appointed Date automatically came into existence on achievement of
                          financial close. Having, therefore, admitted, both in its letter dated
                          22nd October, 2010, as well as in its written statement filed before the
                          learned Arbitral Tribunal, that financial close had been achieved by
                          the respondent on 3rd September, 2010, it was held that NHAI could
                          not contend that the Appointed Date had yet to reach, as damages
                          were not paid by the respondent under Clause 24.1.1.


                          Frustration due to force majeure


                          38.    NHAI contended, before the learned Arbitral Tribunal, that as,
                          prior to the Appointed Date, force majeure had occurred (in the form
                          of the Government of Goa not granting approval as sought by NHAI)
                          and was known to the respondent earlier in point of time, it was not
                          entitled to any claim from NHAI, by virtue of Clause 34.7.1.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 26 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           39.    The learned Arbitral Tribunal noted that force majeure was
                          defined in Clause 34. The CA envisaged force majeure on account of
                          occurrence of a political event, non-political event or an indirect
                          political event. In the circumstances of the present case, no non-
                          political event or indirect political event had occurred and the
                          stipulations to that effect in the CA were not, therefore, relevant.


                          40.    Of the various sub-clauses in Clause 34.4, therefore, the learned
                          Arbitral Tribunal held that the only relevant sub-clause would be
                          Clause 34.4(c), if at all. This sub-clause applied only where clearance,
                          as required by the Concessionaire, i.e. the respondent, was not
                          granted. It was not applicable where NHAI had applied for
                          authorisation or clearance. The invocation of force majeure by NHAI
                          was not, therefore, it was held, valid.


                          41.    Besides, noted the learned Arbitral Tribunal, Clause 34.5 cast,
                          on the party seeking to avail the benefit of force majeure, a duty to
                          report force majeure by way of notice under Clause 34.5.1, containing
                          the necessary particulars. Admittedly, no such notice had been given
                          by NHAI to the respondent. On this ground, too, therefore, the learned
                          Arbitral Tribunal held that NHAI could not claim the benefit of force
                          majeure.


                          42.    Having thus held, the learned Arbitral Tribunal also noted that,
                          under Clause 37.3.1, NHAI was liable to reimburse force majeure
                          costs to the respondent.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                          Page 27 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Termination of the CA


                          43.    The learned Arbitral Tribunal next addressed the issue of
                          termination of the CA by NHAI.


                          44.    Before the learned Arbitral Tribunal, NHAI placed reliance on
                          the indemnity, granted while submitting its bid in response to the NIT,
                          in the letter dated 20th July, 2009, indemnifying NHAI from damages
                          on account of delay in handing over the land. It was sought to be
                          contended that the CA had been executed, based on the said
                          undertaking.


                          45.    The learned Arbitral Tribunal noted that no such undertaking
                          was contained in the CA itself. Moreover, observed the learned
                          Arbitral Tribunal, the claim of the respondent against NHAI under
                          Clause 37.3.2 arose out of termination of the CA by NHAI, and not
                          delay in handing over of land. In any event, once the CA had been
                          terminated, it was held that the undertaking lost all significance. The
                          CA had been terminated on 23rd November, 2011, after the
                          commencement of the Concession Period on 3rd September, 2010,
                          being the Appointed Day, when financial close had been achieved by
                          the respondent. The contention of NHAI that the Concession Period
                          had not yet commenced, as the Appointed Date had not been reached
                          before the termination of the CA was, therefore, found to be
                          untenable.


Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 28 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Satisfaction of Conditions Precedent


                          46.    NHAI sought to contend, before the learned Arbitral Tribunal,
                          that the respondent had not fulfilled the Conditions Precedent
                          stipulated in the CA. This, in fact, was also contended to be one of the
                          grounds on account of which the Appointed Date had not been
                          reached.


                          47.    As against this, the respondent contended that NHAI had not
                          provided the Right of Way, as required by Clause 4.1.2 read with
                          Clause 10.3.2 of the CA, till April 2011.


                          48.    NHAI, in its letter dated 13th June, 2012, addressed to the
                          Independent Engineer, stated thus:
                                 "a)    The Concession Agreement for the project has been
                                 terminated under clause 37 due to non-fulfilment of
                                 conditions precedent by both the parties i.e. Concessionaire
                                 and NHAI. Reasons for non-fulfilment of a condition
                                 precedent by both the parties may be the same and no support
                                 from State Government."


                          This communication, noted the learned Arbitral Tribunal, admitted, in
                          so many words, non-fulfilment of the Conditions Precedent by NHAI.
                          It remains, therefore, to be decided whether the respondent was also
                          remiss in this regard. Needless to say, the respondent contended in
                          the negative.


                          49.    The learned Arbitral Tribunal noted that the issue of the ground
                          on which the CA had been terminated by NHAI would essentially

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 29 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           have to be determined by reading the termination letter, dated 23 rd
                          November, 2011, as it stood.        This letter, it was found, was
                          unambiguous in acknowledging that the grounds for terminating the
                          CA was the failure, of the NHAI, to obtain land acquisition, clearance
                          of forested environment and settlement of disputes on toll rates
                          pending with the Government of Goa, despite its best efforts or on any
                          default on the part of the respondent. Nor did it seek to invoke force
                          majeure. In view thereof, the learned Arbitral Tribunal held that the
                          CA had not been terminated on account of any default on the part of
                          the respondent, and that the contention of NHAI, to this effect, was
                          misguided. In this context, the learned Arbitral Tribunal noted that
                          NHAI had not, in any of its communications to the respondent, or
                          even before the learned Arbitral Tribunal, clarified which condition
                          precedent was remaining to be fulfilled by the respondent.         The
                          learned Arbitral Tribunal also sought support, for these conclusions,
                          from the fact that no amount was deducted, by NHAI, from the Bank
                          Guarantee for ₹ 23.55 crores, furnished by the respondent, at the time
                          of releasing the said Bank Guarantee.


                          Respondent's claim for damages


                          50.    The learned Arbitral Tribunal held that, having terminated the
                          CA on account of its own default, NHAI was bound by the
                          consequences of the said act. It was noted that the respondent had,
                          vide its letters dated 23rd December, 2011 and 5th December, 2011, put
                          NHAI on notice that it would be claiming damages.


Signature Not Verified
                          O.M.P. (COMM) 349/2016                                      Page 30 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Analysis of Claims


                          51.      Having thus set out the rival contentions of the parties before it,
                          and expressed its views thereon, the learned Arbitral Tribunal
                          proceeded to deal with the two individual claims of the respondent.


                          Re. Claim 1


                          52.      Addressing Claim 1 of the respondent, the learned Arbitral
                          Tribunal noted that, in its communications dated 13 th April, 2011, 14th
                          July, 2011 and 2nd August, 2011, the respondent had noticed the
                          expenses which it had incurred as a result of non-commencement of
                          work. This, it was observed, was supported by the certificate, dated
                          31st March, 2011, of the Statutory Auditor's, to the effect that the
                          respondent had incurred a cost of ₹ 142.9 crores on the project.


                          53.      The learned Arbitral Tribunal noted that Clause 37.3.2 of the
                          CA stipulated the method for determination of damages in the event of
                          termination of the CA on account of default of NHAI. This clause
                          entitled the respondent, in such events, to be paid the debt due and
                          150% of the Adjusted Equity. The entitlement of the respondent, to
                          these amounts, also stood vouchsafed by the Section 73 of the
                          Contract Act1. Of these, the respondent was not claiming, before the


                          1 "73.    Compensation for loss or damage caused by breach of contract. - When a contract has been
                          broken, the party who suffers by such breach is entitled to receive, from the party who has broken the
                          contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual
                          course of things from such breach, which the parties knew, when they make the contract, to be likely to result
                          from the breach of it.
                                    Such compensation is not to be given for any remote an indirect loss or damage sustained by reason
                          of the breach."
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                                                        Page 31 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           learned Arbitral Tribunal, the amount payable to it by way of Debt
                          Due, but was claiming 150% of Adjusted Equity. NHAI sought to
                          contend that the equity bought could not be used, as no work had
                          commenced at their site and that, therefore, 150% thereof would be
                          nil.


                          54.        The definition of "Adjusted Equity", as contained in Clause 48
                          of the CA, to the extent it was relevant, read as under:
                                     " "Adjusted Equity" means the equity funded in Indian rupees
                                     and adjusted on the 1st day of the current month (the
                                     "Reference Date"), in the manner set forth below, to reflect
                                     the change in its value on account of depreciation and
                                     variations in WPL, and for any Reference Date occurring:

                                               (a)    On or before COD2, the adjusted Equity shall be
                                               a sum equal to the equity funded in Indian Rupees and
                                               expended on the project, revised to the extent of one
                                               half of the variation in WPI occurring between the 1st
                                               day of the month of Appointed Date and the Reference
                                               Date;

                                                                                *****

                                     For the avoidance of doubt, the Adjusted Equity shall, in the
                                     event of Termination, be computed as on the Reference Date
                                     immediately preceding the Transfer Date; provided that no
                                     reduction in the Adjusted Equity shall be made for a period
                                     equal to the duration, if any, for which the Concession Period
                                     is extended, but the revision on account of WPI shall continue
                                     to be made."

                          The learned Arbitral Tribunal noted that, as operations were yet to
                          commence, there was no "Commercial Operation Date" and that,
                          therefore, sub- clause (a) of Clause 48 of the CA3 alone was relevant.

                          2
                              Commercial Operation Date (as per Clause 48 of the CA)

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                                 Page 32 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           55.    The Statutory Auditors as appointed by the respondent with the
                          consent and approval of NHAI and had certified the cost incurred by
                          the respondent on the project to be ₹ 164.91 crores up to 9th
                          December, 2011.          This certificate, observed the learned Arbitral
                          Tribunal, was valid and effective, in view of Clause 33.3 of the CA,
                          already reproduced supra. The respondent, in fact, vide letter dated
                          24th August, 2015, which was also vouchsafed by the Statutory
                          Auditor and the Chartered Accountant of the respondent, reduced the
                          cost incurred up to 21st August, 2015 from ₹ 164.91 crores 2 ₹ 130.92
                          crore. No objection, to this computation, had been raised by NHAI.


                          56.    Thereafter, the learned Arbitral Tribunal proceeds to conclude,
                          qua Claim 1 of the respondent, thus:
                                 "131. The aforesaid amount of ₹ 130.92 crores has to be
                                 further calculated as per the definition of "Adjusted Equity".
                                 According to the said definition, the said amount of ₹ 130.92
                                 crores has to be "revised to the extent of one half of the
                                 variation in WPI occurring between the 1st day of the month
                                 of Appointed Date and the Reference Date".

                                 132. As per the calculation given by the Statutory Auditors
                                 the one half of the variation in WPI occurring between the 1st
                                 day of the month of Appointed Date and the Reference Date
                                 is 7.9882%; ₹ 13.69 crores (₹ 212.07 as claimed minus ₹
                                 198.38) (see page 38 of the Claimants revised documents).
                                 However, the Statutory Auditors have not given any method
                                 for its calculation or for arriving at the said percentage
                                 amount. He has only mentioned WPI of 1-Mar-10 - 135.20
                                 and 31-Oct-11 - 156.80 and calculated the difference between
                                 the said 2 figures. This is not sufficient. The Arbitral
                                 Tribunal requires complete details before any amount may be
                                 awarded. Hence, this cannot be taken into consideration.

                                 133.   Therefore, the Concessionaire/Claimants are entitled to
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                           Page 33 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  a sum of Adjusted Equity amounting to ₹ 130.92 crores + ₹
                                 65.46 crores (being 50% of the Adjusted Equity) = ₹ 196.38
                                 crores. The same is awarded to the Claimants."


                          Re. Claim 2


                          57.    Claim 2, as raised by the respondent, was for an amount of ₹
                          4.71 crores, towards damages sustained on account of delay by NHAI
                          in providing Right of Way as provided for under Clause 10.3.2 read
                          with Clause 4.1.2 of the CA. Clause 4.2 of the CA was invoked by the
                          respondent for the said purpose.       The respondent contended that
                          Clause 4.1.2 required NHAI to satisfy all Conditions Precedent within
                          60 days of providing of Performance Security by the respondent.
                          Performance Security had been provided by the respondent on 2nd
                          August, 2010. 60 days, therefrom, expired on 10 th October, 2010. As
                          NHAI had failed to provide Right of Way by the said date, the
                          respondent claimed damages in terms of Clause 4.2 of the CA.


                          58.    As against this, NHAI contended that the respondent had failed
                          to fulfil its contractual obligations under the CA.


                          59.    The learned Arbitral Tribunal observed that no specific
                          contractual obligation, which remained to be fulfilled by the
                          respondent, had been pointed out by NHAI. The defence of NHAI
                          was, therefore, rejected as unsustainably general and vague.


                          60.    Resultantly, the learned Arbitral Tribunal awarded, to the
                          respondent, the claim of ₹ 4.71 crores.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 34 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Interest


                          61.    Interest, held the learned Arbitral Tribunal, was payable in
                          terms of Clause 37.3.3 of the CA, read with Clause 47.4.2 thereof. As
                          the dispute pertained to the years 2010 and 2011, at which time Bank
                          rate of interest was in the region of 12% per annum, the learned
                          Arbitral Tribunal held the respondents to be entitled to interest, on the
                          amounts found payable to it, @ 12% per annum.


                          Operative portion


                          62.    The learned Arbitral Tribunal, in para-143 of the majority
                          award, summed up its conclusions thus:
                                 "(a) In respect of claim No. 1, the claim for a sum of ₹
                                 196.38 crores is allowed.

                                 (b)   Interest from the date of termination of the Concession
                                 Agreement, that is, November 23, 2011 at the rate of 12% per
                                 annum till the date of award, that is 29 February 2016 (for 4
                                 years and 3 months) amounting to ₹ 1,001,538,000/- is
                                 allowed.

                                 (c)    In respect of claim No. 1, the claim for a sum of ₹
                                 15.69 crores is rejected.

                                 (d)    In respect of claim No. 2, the claim for a sum of ₹
                                 4,71,00,000/-is allowed.

                                 (e)    Interest from the date of the demand of the Right of
                                 way, that is, April 27, 2011 at the rate of 12% per annum till
                                 the date of award, that is, 29th February, 2016 (for 4 years and
                                 10 months) amounting to ₹ 27,318,000/- is allowed.

                                 (f)    The claimants have also paid, as per their letter dated 9
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 35 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                  September 2015 arbitration venue charges and other expenses
                                 for 10 hearings amounting to ₹ 90,426. The Claimants are
                                 entitled to 50% of the said fees and expenditure amounting to
                                 ₹ 45,213. The same is allowed to the Claimants.

                                 (g)    Thus, the Respondents are liable to pay to the
                                 Claimants a total sum of ₹ 3,039,801,213. The said amount
                                 shall be paid within 30 days from the date of receipt of this
                                 Award. If the Respondents failed to pay the same, the
                                 Respondents shall be liable to pay interest at the rate of 12%
                                 on the total amount of ₹ 3,039,801,213 from the date of The
                                 award till the date of payment.

                                 (h)    All other claims and counter claims, if any, not
                                 specifically dealt with herein shall be treated as rejected.

                                 (i)   The Parties to bear their own cost of these arbitration
                                 proceedings."


                          Rival Contentions


                          63.    I have heard Mr. S. Nandakumar, learned Counsel for NHAI
                          and Mr. Saurabh Kirpal, learned Senior Counsel for the respondent, at
                          length.


                          64.    Arguing for NHAI, Mr. S. Nandakumar essentially raises the
                          same grounds which were raised by NHAI before the learned Arbitral
                          Tribunal and were rejected. He submits that having, in its letter dated
                          20th July, 2009, whereby LoA was sought, indemnified NHAI from
                          any damages on account of delay in signing of the CA or in acquiring
                          the land, the respondent (of which IIDL was, according to Mr.
                          Nandakumar, a mere alter ego) would not claim damages from NHAI.
                          Secondly, Mr. Nandakumar submits that, prior to payment of damages
                          @ 0.1% of performance security for each day of delay in achieving
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                           Page 36 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           financial close beyond 180 days from the date of signing of the CA,
                          the Appointed Date could not be said to have been reached. In this
                          context, he drew my attention to the communication dated 20 th
                          October, 2010, from NHAI to the respondent (reproduced in para 16
                          supra), which concluded with the request to the respondent to deposit
                          damages @ 0.1% of performance security for each day of delay in
                          achieving financial close beyond 180 days from the date of signing of
                          the CA, in terms of Clause 24.1.1, without delay, "so that further
                          action on fixation of Appointed Date can be taken". The respondent
                          not having complied with the request contained in the aforesaid letter
                          dated 20th October, 2010, Mr. Nandakumar submits that the Appointed
                          Date was never fixed by the NHAI. He has invited my attention, in
                          this context, to Clause 4.1.3, which set out the Conditions Precedent,
                          required to be fulfilled by the respondent. To a query from the Court,
                          as to how, in the face of the definition of "Appointed Date", as
                          contained in the CA, it could be said that, till the respondent paid
                          damages under Clause 24.1.1, the Appointed Date had not yet been
                          reached, Mr. Nandakumar invited my attention to the communications
                          between NHAI and the respondent, which indicate, prima facie, that
                          both NHAI and the respondent were of the opinion that the Appointed
                          Date was required to be fixed by NHAI.        That, Mr Nandakumar
                          emphasizes, never took place.


                          65.    Addressing, next, the issue of termination, Mr. Nandakumar,
                          referring to the notice of termination dated 23rd November, 2011,
                          issued by NHAI to the respondent, submits that the CA was
                          terminated by NHAI on account of default by NHAI as well as of the
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                      Page 37 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           respondent.

                          66.    Mr. Nandakumar also invoked force majeure, under Clause
                          34.4(c) of the CA, to contend that, by operation of the said clause,
                          NHAI was indemnified of the need to pay any damages to the
                          respondent, the failure in obtaining approvals from the Government of
                          Goa, constituting, as it were, force majeure within the meaning of
                          Clause 34.4(c) of the CA.

                          67.    Considerable emphasis was laid, by Mr. Nandakumar, on the
                          fact that the respondent had not even commenced work. He submits
                          that the impugned Award results in a windfall to the respondent, as,
                          without doing a day's work, the respondent has become richer by ₹
                          303 crores. He submits that the learned Arbitral Tribunal erred in
                          failing to notice that damages could only be relatable to the costs
                          incurred by the respondent and, without commencing work, it could
                          not be said that the respondents had incurred any costs at all.

                          68.    Mr. Nandakumar submits that, as the CA stood terminated
                          prior to the Appointed Date being reached, owing to force majeure
                          events, the claims of the respondent were misconceived. Besides, he
                          reiterates, without paying damages in accordance with Clause 24.1.1,
                          it could not be said that the Appointed Date had been reached.

                          69.    Apropos the aspect of quantification of Claim No. 1, though the
                          petition does not raise any challenge to the impugned Award on that
                          ground, NHAI has placed brief written submissions on record, which
                          were reiterated by Mr. Nandakumar. The said submissions, too, do

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                            Page 38 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           not question, in any manner, the propriety of the quantification of
                          Claim 1 by the majority Award of the learned Arbitral Tribunal.
                          Instead, the petitioner has merely sought to place reliance on the
                          following findings in the minority Award, on the aspect of entitlement
                          of damages under Clause 37.3.2. of the CA:
                                 "7.    The Respondent is seeking compensation under the
                                 following heads:

                                        EPC Contractor (Idling): 75.360 crore
                                        Fixed Overheads: 31 crore
                                        Design Supervision: 0.828 crore
                                        Preliminary and Pre-operative Expenses: 8.516 crore
                                        Interest During Construction: 15.216 crore
                                        TOTAL: 130.92 Crore

                                 That accordingly, 150% adjust equity determined with interest
                                 by the Majority Award. But the dissenting Award delivered
                                 by the Dr. B.P. Bagish has stated in their Award that,

                                        "I have examined the above figures without adjustment
                                        of equity.

                                        I have come to a conclusion that idling of EPC
                                        Contractor is not payable by the respondent as per
                                        agreement. Moreover, there is nothing on record to
                                        prove that the claimant has incurred this expenditure
                                        and paid to EPC. Under Section 73 of the contract only
                                        actual losses can be compensated.

                                        Fixed overheads will also be not payable because the
                                        claimant is under duty to mitigate losses when the right
                                        of way is not available to him. Only design charges and
                                        pre-operative expenses are payable to him if there is
                                        proof. Thus, the claim can be entertained." "


                          70.    On Claim 2, the only submission advanced by Mr. Nandakumar
                          is that this claim was effectively included in Claim 1 and that,
                          therefore, it could not be separately awarded.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                            Page 39 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           71.    No submissions were advanced with respect to awarding of
                          interest by the learned Arbitral Tribunal.


                          72.    Responding to the submissions of Mr. Nandakumar, Mr. Kirpal,
                          learned Senior Counsel for the respondent submits that, under Clause
                          34.9.3 of the CA supra, where termination was on account of a
                          political event, NHAI was required to make termination payment to
                          the concessionaire, as would be payable under Clause 37.3.2 as if it
                          were a default on the part of NHAI. As such, he submits, the entire
                          issue of force majeure was merely a red herring, as the NHAI was
                          pleading force majeure on the basis of a political event, in which case,
                          by operation of Clause 34.9.3, the respondent would in any event be
                          entitled to the benefit of Clause 37.3.2.

                          73.    On the aspect of indemnity in the letter dated 20 th July, 2009,
                          Mr. Kirpal points out that the concluding paragraph of the said letter
                          makes it clear that the indemnity remained in place only till signing of
                          the CA. It was an indemnity granted for delay in signing of the CA.
                          Once the CA stood signed on 19th February, 2010, without any
                          corresponding indemnity clause, Mr. Kirpal submits that NHAI could
                          not claim indemnity on the basis of the letter dated 20 th July, 2009.

                          74.    Insofar as the quantification of Claim 1, by the learned Arbitral
                          Tribunal, was concerned, Mr. Kirpal submits that no dispute,
                          regarding quantification, was ever raised before the learned Arbitral
                          Tribunal or has been raised in the present petition under Section 34 of
                          the 1996 Act. NHAI, therefore, he submits, is estopped from raising
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 40 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           any dispute regarding quantification at this stage.

                          75.    That apart, Mr. Kirpal submits that the learned Arbitral Tribunal
                          had proceeded on the basis of the certificate issued by the statutory
                          auditor. The statutory auditor was appointed with the consent of the
                          NHAI in terms of Clause 33.2.1 of the CA. Clause 33.2.1, as the
                          learned Arbitral Tribunal rightly held, made the certificate of the
                          statutory auditor valid and binding. Mr. Kirpal further points out that
                          the incurring of cost by the respondent of ₹ 130.92 crores also stood
                          certified by the Chartered Accountant of the respondent vide letter
                          dated 24th August, 2015. Supportive invoices, issued by IIDL have
                          also been placed on record.


                          76.    Mr. Kirpal contests the submission, of Mr. Nandakumar, that, as
                          the respondent had been unable to commence work, it could not have
                          incurred any costs. He submits that costs have been incurred, by the
                          respondent, on the efforts made by it to mobilise resources, which had
                          continued to remain idle for want of commencement of work. This, he
                          submits, stands vouchsafed by the letters on which the learned Arbitral
                          Tribunal itself relied. The contention of Mr. Nandakumar that, as
                          work on the project had not commenced, no expenses had been
                          incurred by the respondent is, therefore, according to Mr. Kirpal,
                          thoroughly misconceived.        He had invited my attention, in this
                          context, to the following passages, from the letters dated 2 nd April,
                          2011 and 24th August, 2011 issued by the respondent to NHAI:

                                 Letter dated 2nd April, 2011


Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 41 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                                      "For your information, the EPC Contractor has already been
                                     mobilized by us to take up the construction Works for the
                                     project and we wish to assure you that once these critical
                                     issues listed above are sorted out by NHA1, we will be in a
                                     position to quickly proceed with the mobilization of plant &
                                     Machinery and manpower, finalization of quarries for which,
                                     preliminary surveys have already been carried Out, and
                                     setting up of Camps. As you are aware, drawings for bridges
                                     have already been submitted to you for review, Plan & Profile
                                     drawings are also ready for the entire length of the project
                                     road and will be submitted to you very soon."

                                     Letter dated 24th August, 2011

                                     "We once again request you to expedite the negotiations with
                                     the State Government and issue us the Appointed Date for the
                                     Project since our Manpower and Machinery are ready since
                                     the last one year to start the work."

                                                                             (emphasis supplied)

                          Analysis


                          77.        The position in law, as regards the scope of interference by a
                          Court, exercising jurisdiction under Section 34 of the 1996 Act, with
                          an arbitral award is, by now, fossilised through a number of judicial
                          authorities, of which one may take due stock of the judgments in
                          Sangyong Engineering & Construction Co. Ltd v. N.H.A.I.4 and
                          Delhi Airport Metro Express Pvt Ltd v. D.M.R.C.5 These decisions
                          clearly hold that the Court, exercising jurisdiction under Section 34, is
                          to interfere only in cases of "patent illegality" or perversity in the
                          Award under challenge. Mistakes of fact or law, or the predilection of
                          the Section 34 Court to incline to a view contrary to that expressed by

                          4   (2019) 15 SCC 131
                          5   (2022) 1 SCC 131
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                                   Page 42 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           the Arbitral Tribunal, cannot constitute a basis for interference. The
                          Section 34 Court does not substitute its subjective view in place of the
                          view of the Arbitral Tribunal.


                          78.    The present case, however, is one where the Court does not
                          really have to invoke the law laid down in these decisions, as the
                          reasoning and finding of the learned Arbitral Tribunal is eminently
                          acceptable even as per the terms of the CA, and the contentions of
                          NHAI, to the contrary, as raised before the Arbitral Tribunal and as
                          reiterated before this Court, have rightly been rejected in the
                          impugned Award.

                          79.    Inasmuch as the reasoning in the impugned Award, regarding
                          the entitlement of the respondent to damages in accordance with
                          Clause 37.3.2 of the CA, completely commends itself to acceptance by
                          this Court, a brief recapitulation thereof would be more than sufficient.

                          80.    The reliance, by Mr. Nandakumar, on the letter dated 20 th July,
                          2009 from IIDL to NHAI, and the reference, in the said
                          communication, to the indemnity granted to NHAI, is completely
                          misconceived.      In the first place, the stipulations in the letter
                          exhausted themselves with the execution of the CA. Once the CA
                          stood executed, any indemnity would have to be in terms of the CA
                          and not outside it. There is, as the learned Arbitral Tribunal correctly
                          holds, no corresponding indemnity clause in the CA.

                          81.    That apart, the provision for indemnity, in the letter dated 20 th
                          July, 2009, was only "for any delay caused with respect to signing of
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                        Page 43 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Concession Agreement due to delay arising out of completion of 3D
                          process for 80% land acquisition".      The learned Arbitral Tribunal
                          correctly holds that Clause 37.3.2, under which the respondent was
                          seeking damages, was not on account of delay in signing of the CA,
                          but on account of termination of the CA on the ground of NHAI
                          default. The claim of the respondent, which was relatable to Clause
                          37.3.2 had, therefore, nothing to do with the indemnity granted by the
                          letter dated 20th July, 2009. Expressed otherwise, the letter dated 20th
                          July, 2009, does not indemnity NHAI from its liability under Clause
                          37.3.2 of the CA - which had, moreover, not even been executed at
                          that point of time.

                          82.    The reliance on the letter dated 20th July, 2009, by NHAI, is,
                          therefore, fundamentally misconceived, and has been rightly rejected
                          by the learned Arbitral Tribunal.

                          83.    The learned Arbitral Tribunal has also correctly noted that
                          NHAI and the respondent were both, apparently, harbouring a
                          misconception regarding the fixation of the "Appointed Date". The
                          definition of "Appointed Date", as contained in the CA, is clear and
                          categorical. The Appointed Date is the date on which financial close
                          is achieved or any earlier date that the parties may by mutual consent
                          determine. The definition also deems the Appointed Date to be the
                          date of commencement of the Concession Period. It is not in dispute
                          that no date, prior to achievement of financial close by the respondent,
                          was fixed by the parties by mutual consent. As such, per definition,
                          the date of achievement of financial close was the Appointed Date.

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 44 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           84.    NHAI, both in its letter dated 22nd October, 2010, as well as in
                          their written statement filed before the learned Arbitral Tribunal,
                          admitted that the financial close had been achieved by the respondent,
                          on 3rd September, 2010. The finding of the learned Arbitral Tribunal
                          that, in view of the said admission, it could not lie in the mouth of
                          NHAI to contend otherwise and that financial close had necessarily to
                          be treated as having been achieved by the respondent on 3rd
                          September, 2010 is, therefore, clearly unexceptionable. By definition,
                          therefore, 3rd September, 2010 became the Appointed Date within the
                          meaning of the CA. The finding of the learned Arbitral Tribunal, in
                          this regard, is also perfectly in order, and the reliance by Mr.
                          Nandakumar on the communications exchanged before the parties
                          which betrayed confusion regarding the fixing of the Appointed Date
                          is completely without merit.

                          85.    The grievance, repeatedly voiced by Mr Nandakumar, about the
                          respondent never having commenced work is also, in the
                          circumstances, misconceived.     The Commencement Date was, per
                          definition in the CA, the Appointed Date. Though the Appointed Date
                          stood fixed with the achievement of financial close by the respondent,
                          NHAI never disabused the respondent in that regard. Rather, NHAI,
                          perhaps bona fide, kept writing to the respondent, calling on the
                          respondent to accede to its requests, so that it could fix the Appointed
                          Date. The learned Arbitral Tribunal has correctly held that these
                          communications were without basis, as the CA does not even
                          obliquely contemplate fixation or determination of the Appointed Date
                          by NHAI. Having, thus, kept the respondent under the impression that

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                       Page 45 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           the Appointed Date had yet to be "fixed" by NHAI, and given the fact
                          that the Concession Period, per definition in the CA, commenced with
                          the Appointed Date, NHAI can hardly fault the respondent for not
                          having commenced work.         Rather, the communications from the
                          respondent to NHAI in this regard betray considerable anxiety on this
                          score, as the resources mobilized by the respondent were idling.


                          86.    Proceeding, now, to the aspect of termination of the CA, the
                          letter, dated 23rd November, 2011, whereby NHAI terminated the CA,
                          is also clear in its terms. It is obvious from a plain reading of the said
                          letter that the CA was terminated only on the ground that, despite its
                          best efforts, NHAI was not able to source the requisite approvals from
                          the Government of Goa. The submission of Mr. Nandakumar to the
                          effect that the termination was on the ground of default on the part of
                          NHAI as well as on the part of the respondent merely requires to be
                          stated to be rejected, as it is directly in the teeth of the recitals
                          contained in the letter of termination dated 23 rd November, 2011. The
                          learned Arbitral Tribunal has correctly held that termination was only
                          on the ground of default on the part of NHAI and that there is not even
                          a whisper of an averment in the letter dated 23 rd November, 2011 of
                          the termination being attributable to any default on the part of the
                          respondent.

                          87.    The sequitur, in the form of Clause 37.3.2, had inexorably to
                          follow. Clause 37.3.2 clearly holds that, were the CA to be terminated
                          on the ground of "Authority default", i.e. on the ground of default on
                          the part of NHAI, the Concessionaire, i.e. the respondent, is entitled to

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 46 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           the "Debt Due" alongwith 150% of the Adjusted Equity. This is an
                          absolute dispensation in the CA, which brooks no exception or
                          relaxation whatsoever. The termination of the CA being solely on the
                          ground of NHAI default, the respondent was, by operation of Clause
                          37.3.2 entitled, ipso facto, to the Debt Due as well as 150% of
                          Adjusted Equity. The respondent not having claimed the debt due, the
                          learned Arbitral Tribunal cannot be faulted for having held the
                          respondent entitled to 150% of the Adjusted Equity.

                          88.    In that view of the matter, the entire grievance, voiced by Mr.
                          Nandakumar, regarding the respondent having defaulted in paying
                          damages @ 0.1 % per day for delay in achieving financial close, under
                          Clause 24.1.1, completely loses significance. Clause 24.1.1 does not
                          make achievement of financial close conditional on the said payment.
                          In any event, once the NHAI had itself acknowledged that financial
                          close stood achieved by the respondent on 3rd September, 2010, the
                          achievement of financial close could not be made conditional on
                          payment of damages by NHAI.

                          89.    NHAI, arguendo, may have had a case for claiming damages by
                          way of a counter claim. The learned Arbitral Tribunal has correctly
                          held that no such counter claim was preferred by it. It is too late in the
                          date, therefore, for NHAI to now complain that the respondent did not
                          pay damages as required by Clause 24.1.1.

                          90.    Financial close having been achieved by NHAI on 3rd
                          September, 2010 which, therefore, was the Appointed Date within the
                          meaning of the CA, and the contract having been terminated after the
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 47 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Appointed Date on the ground of default on the part of NHAI, the
                          learned Arbitral Tribunal was entirely justified in awarding, to the
                          respondent, 150% of Adjusted Equity, under Clause 37.3.2 of the CA.

                          91.    Mr Nandakumar also pleads force majeure and invokes, for the
                          purpose, Clause 34.4(c) of the CA. It is apparent, at a bare glance of
                          the said provision, that it has no application whatsoever.             Clause
                          34.4(c) at the cost of repetition, reads thus:
                                 "34.4 Political Event

                                 A Political Event shall mean one or more of the following acts
                                 or events by or on account of any Government
                                 Instrumentality:

                                                             ****
                                        (c)    unlawful or unauthorised or without jurisdiction
                                        revocation of, or refusal to renew or grant without
                                        valid cause, any clearance, licence, permit,
                                        authorisation, no objection certificate, consent,
                                        approval or exemption required by the Concessionaire
                                        or any of the contractors to perform their respective
                                        obligations under this Agreement and the Project
                                        Agreements; provided that such delay, modification,
                                        denial, refusal or revocation did not result from the
                                        Concessionaire's or any Contractor's inability or failure
                                        to comply with any condition relating to grant,
                                        maintenance or renewal of such clearance, licence,
                                        authorisation, no objection certificate, exemption,
                                        consent, approval or permit;"


                          92.    On its plain reading, Clause 34.4(c) applies in the case of
                          failure, on the part of the authorities, to grant authorization, etc., as
                          required by the Concessionaire or any of the contractors to perform
                          their respective obligations. It does not, therefore, apply where the
                          default in granting approval was consequent on a request made by
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                             Page 48 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           NHAI. Had there been a default in grant of approval consequent to a
                          requirement of the respondent, Clause 34.4(c) may have applied. The
                          delay in approval by the Government of Goa being in response to a
                          request made by NHAI, Clause 34.4(c) has been rightly held by the
                          learned Arbitral Tribunal to have no application whatsoever.


                          93.    Though, in view of this contractual position, the plea of force
                          majeure does not really survive for consideration. I also find myself
                          in agreement with the learned Arbitral Tribunal that, having failed to
                          issue prior notice as required by Clause 34.5 of the CA, the NHAI
                          could, in any event, not plead force majeure.


                          94.    There is also substance in the contention of Mr. Kirpal that, by
                          operation of Clause 34.9.3, where the termination was on account of a
                          political event, NHAI would make a termination payment to the
                          Concessionaire in an amount payable under Clause 37.3.2 as if it were
                          a default on the part of the NHAI.       This, in fact, reinforces the
                          position that Clause 34.4(c) applies only where the default was in
                          granting approval as sought by the Concessionaire, i.e. by the
                          respondent. Clause 34.4(c), in conjunction with Clause 34.9.3, is
                          reflective of the contractual intent. What is intended by these clauses,
                          seen vis-à-vis and in conjunction, is that, where the Concessionaire
                          applies for grant of statutory approval from the governmental
                          authorities, and the governmental authorities fail in granting such
                          statutory approval, it would be treated as a "political event" for which
                          the Concessionaire cannot be held responsible and, in such event,
                          Clause 34.9.3 compensats the Concessionaire by making NHAI liable
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 49 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           to pay the Concessionaire as though it were an "Authority default"
                          under Clause 37.3.2.


                          95.        The invocation by NHAI, of force majeure was, therefore,
                          thoroughly misconceived.


                          96.        For all the aforesaid reasons, no infirmity whatsoever can be
                          found, in the decision of the learned Arbitral Tribunal, that the
                          respondent was entitled to 150% of Adjusted Equity in terms of
                          Clause 37.3.2 of the CA.


                          97.        Apropos the aspect of computation, Mr. Kirpal is correct that,
                          not having raised any dispute regarding computation either before the
                          learned Arbitral Tribunal or even before this Court in its Section 34
                          petition, NHAI cannot seek to argue in Court that the computation
                          was erroneous. Section 34 of the 1996 Act6 envisages setting aside of


                          6
                              "34.   Application for setting aside arbitral award. -
                                     (1)           Recourse to a Court against an arbitral award may be made only by an application for setting aside
                                     such award in accordance with sub-section (2) and sub-section (3)
                                     (2) An arbitral award may be set aside by the Court only if--
                                            (a) the party making the application 1 [establishes on the basis of the record of the arbitral tribunal that]--
                                            (i) a party was under some incapacity, or
                                            (ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing
                                            any indication thereon, under the law for the time being in force; or
                                            (iii) the party making the application was not given proper notice of the appointment of an arbitrator or of
                                            the arbitral proceedings or was otherwise unable to present his case; or
                                            (iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the
                                            submission to arbitration, or it contains decisions on matters beyond the scope of the submission to
                                            arbitration:
                                            (v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the
                                            agreement of the parties, unless such agreement was in conflict with a provision of this Part from which
                                            the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
                                            (b) the Court finds that--
                                            (i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time
                                            being in force, or
                                            (ii) the arbitral award is in conflict with the public policy of India.
                                     (2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be
                                     set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the
                                     award:
                                     Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by
                                     reappreciation of evidence.]"

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                                                                         Page 50 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           the arbitral award on grounds to be pleaded by the applicant [Section
                          34(2)(a)] or as found by the Court [Section 34(2)(b) and Section 34(2-
                          A)]. No doubt, "patent illegality", as a ground to set aside the award,
                          finds mention in Section 34(2-A). That, however, does not mean that
                          the Court can proceed to interfere with the award consequent on a suo
                          motu exercise, sans any plea to that effect by either part, of seeking to
                          ferret out errors in the award.          Such an approach would stand
                          discountenanced by Section 34(1), which permits setting aside of an
                          arbitral award only on an application by the aggrieved party. The
                          grounds for setting aside the award have, therefore, to be pleaded by
                          the party so praying before the Court, in its application under Section
                          34(1). Once such grounds are pleaded, and the Court finds them to be
                          made out, the Court would proceed to set aside the award. De hors
                          and in excess of the grounds urged in the Section 34 petition,
                          therefore, the Court would be acting in excess of its jurisdiction if it
                          were to set aside the award. Even if "patent illegality" were the
                          ground cited for setting aside the arbitral award, the basis for urging
                          "patent illegality" has to be forthcoming in the Section 34(1)
                          application.   The challenger would remain bound by the contents
                          thereof, and the pleas raised therein.


                          98.     That apart, even during arguments and in written submissions,
                          NHAI has provided no ground whatsoever to discountenance the
                          manner in which the learned Arbitral Tribunal has computed the
                          Adjusted Equity. The only reliance placed is on a paragraph from the
                          decision of the descending member, which computes the Adjusted
                          Equity without adjustment.
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                        Page 51 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           99.    "Adjusted Equity", per definition, was relatable to the costs
                          incurred by the respondent in the project. This costs incurred stood
                          certified by the statutory auditor. The statutory auditor had been
                          appointed with the concurrence of the NHAI in terms of Clause 33.2.1
                          of the CA. The certification of the claim by the statutory auditor was
                          also accorded contractual sanctity in Clause 33.3 of the CA. That
                          apart, the claim of the respondent also stood certified by the
                          respondent's own Chartered Accountant, vide Certificate dated 9th
                          December, 2011. No attempt was made by NHAI, before the learned
                          Arbitral Tribunal, to question the correctness of the certification either
                          by the statutory auditor or by the Chartered Accountant.


                          100. If, therefore, the learned Arbitral Tribunal proceeded on the
                          basis of the certificate of the Statutory Auditor and the Chartered
                          Accountant of the respondent in awarding Claim 1, no "patent
                          illegality" can be said to have been committed.

                          101. Having said that, there does appear to be some want of clarity
                          in the manner in which the learned Arbitral Tribunal has, in para 133
                          of the impugned award, proceeded to hold the respondent entitled to ₹
                          196.38 crores, after rejecting the calculation given by the statutory
                          auditor in para 132. That, however, would have been an issue for the
                          NHAI to raise either before learned Arbitral Tribunal or before this
                          Court. It has not chosen to do so. No objection to the said finding of
                          the learned Arbitral Tribunal is contained either in the Section 34
                          petition or in the written submissions filed by the NHAI before this

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 52 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           Court, or even in the oral arguments advanced at the bar by Mr.
                          Nandakumar. No occasion for the respondent to explain this aspect,
                          therefore, arose either. Even if it did, an excursive exercise into this
                          issue, by the Court, might teeter perilously on the edge of the
                          provisory precipice in Section 34(2A), which proscribes setting aside
                          of an arbitral award by reappreciating evidence.


                          102. Given the limited scope of the jurisdiction of this Court vested
                          in it by Section 34 of the 1996 Act, no occasion arises for this Court to
                          revisit the said findings of the learned Arbitral Tribunal on the basis of
                          the case set up by NHAI before this Court.


                          103. In view thereof, the challenge, by NHAI, to the award of the
                          learned Arbitral Tribunal, qua Claim 1 in the impugned award, has
                          necessarily to be rejected.


                          104. Claim 2, as raised by the respondent before the learned Arbitral
                          Tribunal, was on the ground predicated on Clause 4.2 of the
                          Concession Agreement, which envisaged payment of damages by
                          NHAI for delay in fulfillment of the conditions precedent set out in
                          Clause 4.1.2 of the CA, not attributable to force majeure.

                          105. There appears to be substance in the contentions of Mr.
                          Nandakumar that, having awarded damages to the respondent under
                          Clause 37.3.2, which was also attributable to termination on the
                          ground of default on the part of the NHAI in fulfilling its contractual
                          obligations within the stipulated time, the learned Arbitral Tribunal

Signature Not Verified
                          O.M.P. (COMM) 349/2016                                         Page 53 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           could not, all over again, award damages on the ground of default in
                          providing Right of Way within the period stipulated in the CA. This
                          finding, on the part of the learned Arbitral Tribunal, thus, prima facie,
                          amounts to a doubling of the damages awarded to the respondent. The
                          learned Arbitral Tribunal does not appear to have noticed this fact.


                          106. In view thereof, I am of the opinion that, having awarded Claim
                          1 to the respondent under Clause 37.3.2 of the CA, the learned
                          Arbitral Tribunal was in patent error in again awarding damages to the
                          respondent, albeit under Clause 4.2 of the CA, which was again
                          attributable to delay on the part of the NHAI.


                          107. The respondent cannot be permitted to be enriched twice over
                          for the same default on the part of the NHAI.


                          108. In view thereof, the award of the learned Arbitral Tribunal, qua
                          Claim 2 as raised by the respondent, cannot, in my view, sustain on
                          facts or in law. It deserves, accordingly, to be set aside.


                          Conclusion


                          109. In view of the aforesaid discussion, the impugned award is
                          upheld to the extent it awards Claim 1, both with respect to the
                          principal amount as well as the amount of interest awarded thereon,
                          but is set aside qua Claim 2. As the two claims are severable, it is
                          open to this Court in exercise of Section 34 jurisdiction to uphold the
                          award qua one claim and set it aside qua the other, in view of the law
Signature Not Verified
                          O.M.P. (COMM) 349/2016                                        Page 54 of 55
Digitally Signed
By:SUNIL SINGH NEGI
Signing Date:21.02.2022
15:25:58
                           laid down in M. P. Power Generation Co. Ltd v. Ansaldo Energia
                          SPA7.


                          110. The petition accordingly stands partly allowed to the aforesaid
                          extent with no orders as to costs.




                                                                    C. HARI SHANKAR, J.

st FEBRUARY 21 , 2022 kr/dsn/r bararia 7 (2018) 16 SCC 661 Signature Not Verified O.M.P. (COMM) 349/2016 Page 55 of 55 Digitally Signed By:SUNIL SINGH NEGI Signing Date:21.02.2022 15:25:58