Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Delhi District Court

Arbt No.79/18 & 80/18 M/S. Abb India Ltd. vs . Bhel & Anr. Page 1 Of 11 on 9 May, 2018

   IN THE COURT OF SH. MUNISH MARKAN, ADDITIONAL
   DISTRICT JUDGE­01 (SOUTH), SAKET DISTRICT COURT,
                       NEW DELHI

ARBT no.79/18  &  80/18

M/s. ABB India Ltd. 
ABB India Limited
(erstwhile known as ABB Ltd.)

Regd Office:
21st Floor, World Trade Centre,
Brigade Gateway, 26/1,
Dr. Rajkumar Road, Malleshwaram West,
Bengaluru­560055

Also At:
14, Mathura Road,
Faridabad­121003

Versus

1. Bharat Heavy Electricals Ltd.
BHEL House, Siri Fort,
New Delhi­110049

Also at:
Power Sector, Northern Region,
Plot no.25, Sector­16­A,
P.B. No.55, Noida­201301

2. ICICI Bank Ltd.
A­9, Phelps Building, 
First Floor, Cannaught Place,
New Delhi­110001


ARBT no.79/18  &  80/18      M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 1 of 11
 Also At:
Raosi Court,
20, R.N. Mukherjee Road,
Kolkata­700001

Also at:
ICICI Bank Ltd. 
Commercial Branch,
1st floor, West Wing no.1,
Commissariat Road, Banglore­560025
                                                                         ........... Respondents

PETITION UNDER SECTION 9 OF THE ARBITRATION & CONCILIATION ACT, 1996 O R D E R 09.05.2018

1. Vide   this   common   order,   I   propose   to   dispose   off   the   two petitions filed under Section 9 of The Arbitration & Conciliation Act 1996 (hereinafter called 'The Act') filed by the petitioner against the two respondents   as   the   petitioner   feels   aggrieved   by   attempt   of   the respondent no.1 in invoking of the two performance bank guarantees for a   sum   of   Rs.41,80,242/­   dated   25.08.2009   and   Rs.4,64,315/­   dated 01.09.2009 (one in each case) given by the petitioner to respondent no.1 for due performance of one contract (Bawana contract) and are sought to be encashed by respondent no.1 to settle the claims in respect of another   contract   (Anapara­D   contract)   wherein   no   performance guarantee has been given and the arbitration proceedings are under way.

2. The case of the petitioner is that petitioner was awarded a ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 2 of 11 contract   for   supply,   erection,   testing   and   commissioning   of   Air Conditioning system for 2x750 MW Pragti III CCPP Bawana vide PO no.PSNR/SCP/BOP­BAWANA/AC/1926  &  1927   both   dated 26.08.2009 (hereinafter called the 'Bawana Project'). For this project, two performance bank guarantees bearing no.0002BG00060609 for a sum   of   Rs.41,80,242/­   dated   25.08.2009   and   the   performance   bank guarantee   bearing   no.0002BG00063509   for   a   sum   of   Rs.4,64,315/­ dated 01.09.2009 (one in each petition) both issued by respondent no.2 ICICI   Bank   were   furnished   by   the   petitioner.   The   petitioner successfully completed/commissioned the Bawana project and even the defect   liability   period   for   the   said   project   has   come   to   an   end   on 09.05.2017. The final bills of the Bawana project have been processed and   the   petitioner   has   an   outstanding   amount   of   Rs.47,45,023/­   due from the respondent no.1 to the petitioner. 

3. Petitioner further stated that petitioner company was also awarded   another   contract   vide   purchase   order   no.PSNR/SCP/ Anapara/AC (MAIN)­SUP/2125 and another purchase order no.PSNR/ SCP/BOP­BAWANA/AC   (Mand)/SUP2126   and   PSNR/SCP/Anapara/ AC­E & C/2127 dated 31.03.2010 (hereinafter called the 'Anapara D Project'). The disputes arose between the parties in Anapara­D project wherein no performance bank guarantee was given by the petitioner and the said dispute is pending arbitration before the Arbitral Tribunal.

4. The petitioner further stated that the Bawana contract dated 26.08.2009   was   duly   completed/commissioned,   inspite   of   that,   the ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 3 of 11 respondent   no.1   vide   letter   dated   09.02.2018   withheld   the   securities furnished under the Bawana project and adjusted the same towards the dues   of   Anapara   D   project   on   the   basis   of   clause   9.0   of   General Commercial   Terms   and   Conditions   (GCC)   and   vide   letter   dated 05.02.2018 written by the respondent no.1 to respondent no.2 ICICI Bank, presented the aforementioned two bank guarantees for invocation citing   failure   in   performance   by   the   petitioner   and   stating   that   the respondent no.1 has suffered loss, damage, costs, charges and expenses in consequence thereof. Clause 9 of the GCC is produced under:

"9.0 Recovery of Outstanding Amount In the event of any amount of  money being outstanding  at any point in time against the seller/contractor, due to excess payment or any other reason whatsoever, in the present order/contract or an other order/contract, the  outstanding amount  shall be recovered from the payments due to the seller/contractor or any other appropriate time and   manner/mode   as   deemed   fit   by   the   Purchaser   at   its   sole discretion."

5. Ld.   Counsel   for   petitioner   had   argued   that   once   the respondent   no.1   vide   letters   dated   20.02.2017   and   09.02.2018   has admitted   that   the   Bawana   project   has   been   successfully completed/commissioned   and   even  the   defect   liability   period   for   the said project has come to an end on 09.05.2017, there was no occasion for respondent no.1 to state that it has suffered any loss or damage on account of the non­performance of any of the terms of the contract by ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 4 of 11 the petitioner. He argued that invocation of the bank guarantee given in one project for settling the disputed claims of some other project where no performance guarantee has been given, is not legally permissible and doing so is a fraud of the egregious nature. He further argued that the two   bank   guarantees   has   been   kept   alive   till   such   time   the   Bawana project was completed and there was no occasion for the respondent no.1 to even ask the petitioner to keep the bank guarantees alive under the garb of the Anapara D project which is pending adjudication before the arbitrator on account of disputes. He argued that it is a clear case of fraud and the said invocation is bad in law and in support, he has relied upon judgment of  Gangotri Enterprises Ltd. Vs. Union of India & Ors. (2016) 11 SCC 720  and stated that under the identical facts, the Hon'ble Supreme Court had granted the injunction in the said judgment. Perused the said judgment.

6. Ld. Counsel for petitioner further argued that the reliance of the respondent no.1 on clause 9 of the GCC is misplaced as there are no "outstanding amounts" even in respect of Anapara D project as the matter is pending adjudication before the arbitration. He argued that amount due or outstanding amount is ascertained only if it is admitted or it is adjudicated by a competent forum which is not the case here.  Respondents' case:

7. On the other hand, the respondent no.1 filed its reply and has   strongly   opposed   the   application   primarily   on   the   ground   that present petition seeking injunction from invoking the bank guarantees is ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 5 of 11 not maintainable in the eyes of law as the subject bank guarantees are unconditional and irrevocable and the respondent no.2 is bound to make the payment of the amount claimed thereunder merely on the demand of the   beneficiary   i.e.   respondent   no.1   without   any   demur.   Respondent no.1 justified its letter of invocation dated 05.02.2018 and stated that the bank guarantees are separate and independent contracts between the bank and the beneficiary which is distinct from the underlying contract and   the   terms   thereunder   and   it   has   no   connection   with   any correspondence exchanged in relation to the underlying contract and it is only terms of the bank guarantee which have to be considered by the court while deciding the present application.

8. It is argued by the Ld. Counsel for respondent no.1 that the law contemplates only two exceptions to prevent the encashment of a bank   guarantee.   First   is   fraud   of   an   egregious   nature   and   second   is irretrievable harm or injustice to one of the parties but the petitioner has not laid any foundation in the petition to establish fraud at the hands of the respondent no.1 and has also failed to point out any irretrievable injury to it.  He further argued that there no special equities in favour of the petitioner so as to fall within the second exception and petitioner always   has   alternate  remedy   available   in   law   to  effect   recovery.  He further argued that the respondent no.1 is the best judge as to when to invoke the bank guarantee and cannot be asked to disclose the reason for   such   invocation.   He   stated   that   the   bank   guarantees   have   been invoked in terms of clause 9 of GCC.  In support of his contentions, Ld. Counsel for respondent  no.1 has relied upon a number of judgment, ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 6 of 11 however, only the latest one on these point are mentioned i.e. Vinitec Electronics Pvt. Ltd. Vs. HCL Infosystems Ltd. (2008) 1 SCC 544, Meghmala & Ors. VS. G. Narasimha Reddy & Ors. (2010) 8 SCC 383,   Abir   Infrastructure   Pvt.   Ltd.   Vs.   Teestavalley   Power Transmission   reported   in   2014   214   DLT  and  Wig   Brothers Construction   Pvt.   Ltd.   Vs.   Indiabulls   Construction   Pvt.   Ltd. Reported in 2­17 240 DLT 747. Perused the said judgments.

9. Petitioner   filed   the   rejoinder   and   reiterated   its   stand   as taken out in the petition.

10. I have carefully gone through the record and heard the Ld. Counsels for the parties. 

11. Perusal of the documents filed by the petitioner particularly the letters dated 20.02.2017 sent by the respondent no.1  shows that the respondent   no.1   acknowledged   that   package   ACs   system   was commissioned on 09.05.2016 and the guarantee shall be over after one year as per clause no.15.2 of Vol.1 Part­D of GCC of Contract. Further the letter  dated 09.02.2018 sent by respondent no.1 to the petitioner reflects that the final bill amount of Rs.47,45,023/­ is there under the contract of Bawana. Further, the petitioner has also placed on record copy of the letter dated 29.12.2017 issued by the principal employer i.e. Pragati   Power   Corporation   Ltd.   addressed   to   Assistant   Labour Commissioner   (North),   Delhi   giving   the   notice   of   completion   of contract work i.e. of Bawana contract clearly stating that the work has been completed on 30.08.2016. It being the case, it is clear that as far as ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 7 of 11 the Bawana project is concerned, it is complete in all its respects at the end of the petitioner including the defect liability period.

12. It is also not disputed that the two bank guarantees were furnished by the petitioner for the execution of the Bawana project. In this regard, perusal of the bank guarantee bonds dated 25.08.2009 and 01.09.2009 categorically reflect that the same pertain to the 'agreement' i.e. for supply of air conditioning system for Pragati CCPP­2x750 MW. This   being   the   case,   it   is   clear   that   the   two   bank   guarantees   were furnished   for   proper   execution   of   the   Bawana   Contract.   The   bank guarantees also stipulate an undertaking to pay to the company against any loss or damage caused or suffered or would be caused/suffered by the company by the reasons of any breach by the said contractor of any of   the   terms   and   conditions   contained   in   the   said   "agreement". Therefore, it is clear that the bank guarantees were given as the security deposit for the proper execution of the Bawana agreement. 

13. This being the case, now the respondent no.1 has sought to invoke the bank guarantees by relying upon clause 9.0 of the GCC. In this   regard,   since   the   dispute   regarding   the   Anapara   D   project   is pending adjudication before the Arbitrator, therefore it cannot be said that as on date, there is any sum due or outstanding amount which is to be paid by the petitioner to respondent no.1. Law in this regard is well settled and has been reiterated by the Hon'ble Supreme Court in the judgment of  Gangotri Enterprises (supra)  wherein, inter alia, it has been held that a claim for damages for breach of contract is not a claim ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 8 of 11 for   a   sum   presently   due   and   payable   and   purchaser/employer   is   not entitled   in   exercise   of   the   right   conferred   upon   it   under   such   a recovery/forfeiture   clause   to   recover   the   amount   of   such   claim   by appropriating other sums due to the contractor. It is also held that it is not true that a person who commits a breach of the contract incurs any pecuniary   liability   nor   would   the   other   party   to   the   contract   who complains of the breach has any amount due to him from the other party and no pecuniary liability arises till the court has determined that the party complaining of the breach is entitled to damages. 

14. In   the   present   case   also,   since   the   disputes   under   the Anapara   D   project   are   pending   adjudication   before   the   Arbitral Tribunal, it cannot be said that there are any outstanding dues qua the said project to be paid by the petitioner to the respondent no.1. Not only that,   the   respondent   no.1   under   the   shield   of   clause   9,   cannot appropriate   the   bank   guarantees   furnished   by   the   petitioner   for   the Bawana Project, to satisfy the disputed claims of the Anapara D project. Perusal of the judgment of Gangotri Enterprises (supra) reflects that in that case also, the bank guarantee furnish in respect of Anand Vihar contract dated 14.07.2006 was sought to be invoked by relying upon clause 62 of GCC for disputed claims in respect of another contract i.e. Agra­Etawaha   contract   dated   22.08.2005   wherein   no   performance guarantee was given and arbitration was pending. The Hon'ble supreme court had granted the injunction therein. 

15. As far as the stand of the respondent is concerned, there is ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 9 of 11 no dispute to the fact that the bank guarantee is an independent and separate contract between the bank and the beneficiary and the courts have to be slow in granting injunction for restraining the invocation of the bank guarantee. It is equally true that ordinarily, the existence of any   dispute   between   the   parties   to   the   contract   is   not   a   ground   for issuance of an order of injunction to restrain the enforcement of bank guarantees   and   this   admits   only   two   exceptions   i.e.   a   fraud   of   an egregious   nature,   and   the   irretrievable   harm   or   injustice   to   one   the parties as laid down by the Hon'ble Supreme Court in the judgment of Himadri   Chemicals   Industries   Ltd.   Vs.   Coal   Tar   Refining Company (2007) 8 SCC 1110.

16. However, it is worthwhile to note that as far as the Bawana project wherein the bank guarantees were given, is concerned there is no claim by the respondent no.1 against the petitioner. On the contrary, it   is   the   petitioner   who   claims   that   certain   amounts   are   due   and petitioner   shall   take   appropriate   recourse   for   the   same   as   per   law. Further, the bank guarantees specifically referred to the agreement of Bawana  and in  view  of   the law  laid down  by the  Hon'ble  Supreme Court in Gangotri Enterprises (supra), in my considered opinion, this is a fit case where the petitioner is entitled to the injunction as prayed for. It is also worthwhile to note that Hon'ble Supreme Court in the judgment of  Gangotri Enterprises (supra)  has taken due note of the General Principles relating to bank guarantee as reflected in para 40 of the said judgment and thereafter held that every case has to be decided ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 10 of 11 with reference to the facts of the case involved therein. In the present petition, the petitioner has not only made out a prima facie case but the given facts and circumstances also reflects balance of convenience in favour of the petitioner and if the injunction is not granted the petitioner shall suffer the irreparable loss as invocation of the bank guarantees will mar   the   image/brand   of   the   petitioner.   The   petitioner   has   therefore passed the triple test for grant of interim injunction and is entitled for the same in view of the law laid down by the Hon'ble Supreme Court in Gangotri Enterprises (supra). 

17. Therefore, both the injunction applications are allowed and both the respondents are restrained from invoking the two performance bank   guarantees   bearing   no.0002BG00060609   and no.0002BG00063509   (renewed   from   time   to   time)   submitted   by   the petitioner   in   the   Bawana   project   pending   invocation,   duration   and passing of the final award in arbitration. Both the files be consigned to Record Room.

Announced in the open court  on 09.05.2018.

(Munish Markan) Additional District Judge­01          District Courts, Saket, New Delhi ARBT no.79/18  &  80/18    M/s. ABB India Ltd. Vs. BHEL & Anr.                           Page 11 of 11