Section 18(2) in The M.P. Bhumi Sudhar Yojana Adhiniyam, 1967

(2)After the whole of the work under the scheme is carried out, the Executive Officer shall prepare-
(a)the final statement specifying therein-
(i)the work carried out;
(ii)the total cost of the whole work;
(iii)the balance after deducting from the total cost the interim amount set out in the interim statement;
(iv)in relation to such balance the amount to be recovered from the owners as cost or part cost;
(v)the period within which such amount is to be recovered;
(vi)the names of persons whom such amount is recoverable;
(vii)the general rate per acre or per rupee of assessment per annum at which the amount specified under clause (iv) should be recovered;
(viii)if in the case of any survey number or subdivision of a survey number the amount recoverable from the owner thereof is to be recovered at a rate other than the general rate, such rate and a list of all such survey numbers or sub-divisions;
(ix)the work which, in his opinion, shall be maintained and repaired individually or jointly and the names of such persons;
(x)such other particulars as may be prescribed;
(b)a map showing the work carried out in the village.