Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 26, Cited by 0]

Orissa High Court

M/S.Jindal India Thermal Power vs M/S. Quartz Infra & Engineering ... ... on 12 January, 2024

Author: D.Dash

Bench: D.Dash

      IN THE HIGH COURT OF ORISSA AT CUTTACK

              CRLREV No.226 of 2023           :      (A)
                          AND
              CRLREV No.320 of 2023           :      (B)

     In the matter of Revisions under section 397 read with
section 401 of the Code of Criminal Procedure, 1973 and from an
order dated 05.04.2023 passed by the learned Sub-Divisional
Judicial Magistrate, Talcher in 1CC Case No.33 of 2017.

CRLREV No.226 of 2023 (A)

    M/s.Jindal India Thermal Power        ...           Petitioners
    Limited & Others

                               -versus-

    M/s. Quartz Infra & Engineering       ...       Opposite Parties
    Private Limited & Others

CRLREV No.320 of 2023 (B)

    M/s. Sinhotia Metals & Minerals        ... Petitioners
    Pvt. Ltd., West Bengal & Others.

                               -versus-

    M/s. Quartz Infra & Engineering        ...            Opposite
    Private Limited                                       Party

         Appeared in this case by Hybrid Arrangement
                   (Virtual/Physical Mode):

     For Petitioners           -     Mr.S.P. Misra, Sr. Advocate
                                     Mr. P.K. Rath, Sr. Advocate,
                                     A.K. Dash & A. Mishra, Advocates
                                     (In CRLREV No.226 of 2023)


                                                             Page 1 of 27

CRLREV Nos.226 & 320 of 2023
                                        -2-




                                   -   Mr. Rajeet Roy, S.K. Mishra,
                                       S. Sourav, T.P. Tripathy & A.
                                       Mohanty, Advocates
                                       (In CRLREV No.320 of 2023)

         For Opposite Party        -   Mr.Vegesna Subha Raju,
                                       (M.D. of O.P.-Company in person)

    CORAM:
    MR. JUSTICE D.DASH
    Date of Hearing : 05.12.2023 :::   Date of Judgment :12.01.2024

D.Dash,J. Since in both these Criminal Revisions as at (A) and (B)

    filed under section 397 read with section 401 of the Code of

    Criminal Procedure, 1973 (for short, hereinafter called as 'the

    Code'), the Petitioners have called in question the legality and

    propriety of an order dated 05.04.2023 passed by the learned

    S.D.J.M., Talcher in 1CC Case No.33 of 2017; those were heard

    together for their disposal by this common judgment.

    2.   The Petitioner No.1 of the Revision as at (A) is the

    Company, namely, M/s. Jindal India Thermal Power Ltd. (shortly

    stated as M/s.JITPL) arraigned as accused No.1 in the complaint

    filed by the Opposite Party-Company, namely, M/s.Quartz Infra

    & Engineering Pvt. Ltd. (in short, M/s. QIEL), whereas the other

    Petitioners are the Liason Officer & Ex-Director, the Liason

    Officer, who too have been arraigned as accused persons in the

    said complaint numbered as ICC No.33 of 2018.



                                                             Page 2 of 27
    CRLREV Nos.226 & 320 of 2023
                                     -3-




        The Revision as at (B) has been filed by the Company,

M/s.Sinhotia Metals & Minerals Private Limited (in short, 'M/s.

SMMPL') and its two Directors, who too have been arraigned as

accused persons in the said complaint numbered as ICC No.33 of

2018.

3.      For the sake of convenience, in order to avoid confusion

and bring in clarity, the parties hereinafter have been referred to

as their position has been assigned in the complaint petition filed

by the Opposite Parties (Complainant), i.e., M/s. QIEL.

4.      Facts necessary for the purpose

        The Complainant-Company, M/s.QIEL carries on the

activities of civil engineering and providing construction services.

The Complainant-Company had undertaken a back to back sub-

contract work from one M/s. GSR Ventures Private Limited to

execute the construction of a boundary wall as well as area

grading and leveling work sometime in the month of March, 2010

at the newly constructed 2 X 600 MW Thermal Power Plant of the

Company, M/s.JITPL, the accused No.4 situated at Derang known

as Derang Power Plant. The Complainant-Company, M/s.QIEL

entered into six Civil Engineering Work contracts with the

accused-Company-M/s.JITPL sometime between the month of

April, 2011 to February, 2012 for construction of peripheral roads

and drains, internal roads and drains, security sheds, boundary
                                                          Page 3 of 27
CRLREV Nos.226 & 320 of 2023
                                    -4-




wall, raw water reservoir extension and execution of balance

work left in the Ash Dyke by M/s. GSR Ventures Private Limited

for the said Derang Power Plant.

     For the purpose, the Complainant-Company, M/s.QIEL had

furnished three bank guarantees for a total sum of Rs.2.72 Crores

towards security/ earnest money as per the terms of the contract.

In December, 2012 the work relating to the construction of the

boundary wall was completed and the work of the construction

of the security shed was closed whereas the work pertaining to

the remaining four contracts, such as, construction of peripheral

roads and drains, internal roads and drains, raw water reservoir

extension and execution of the balance work left in the Ash Dyke

by M/s. VSR Ventures Private Limited were underway.

     It is stated that the accused-Company M/s. JITPL

unilaterally terminated the contract on 31.01.2013 and the bank

guarantees furnished by the Complainant-Company, M/s.QIEL to

the tune of Rs.2.72 Crores were encashed on 29.01.2013 without

prior notice or intimation. The Complainant-Company, M/s.QIEL

was then asked to draw up the final bill after measurement of the

work done till 31.01.2013 and vacate the premises of Derang

Power Plant.

     It is further stated that before terminating the contract, the

accused-Company, M/s.JITPL maliciously entered into an

                                                         Page 4 of 27
CRLREV Nos.226 & 320 of 2023
                                    -5-




understanding with the Company, M/s.SMMPL, the accused

No.1 sometime in the month of December, 2012 to usurp the

work contract from the Complainant-Company, M/s.QIEL at that

Derang Power Plant at a much higher rate, compared to one

awarded to the Complainant-Company, M/s.QIEL.

5.   The     Complainant-Company,        M/s.QIEL     vehemently

objected to the manner of termination of the contract, which is

stated to be illegal. It is next said that this accused-company

M/s.SMMPL, having entered into the worksite, had illegally

kicked out the Complainant-Company, M/s.QIEL beyond the

arena, the Complainant-Company, M/s.QIEL was forced to accept

the words of the Officer of accused-Company-M/s.JITPL, who

assured that upon the assessment of the entire work done at the

site and measurement, the final bill would be processed within

nine (09) days of the meeting held on 06.02.2013 wherein it was so

resolved.

6.   As a follow-up measure, a joint verification of the of work

done till 31.01.2013 as well as the measurement of the materials of

the Complainant-Company, M/s.QIEL lying in the store at

Derang Power Plant was conducted by the Officers of the

accused-Company-M/s. JITPL, Officers of another company

M/s.Quari and Brown as well as the Officer of the Complainant-

Company, M/s.QIEL. Upon measurement, the details were
                                                          Page 5 of 27
CRLREV Nos.226 & 320 of 2023
                                    -6-




recorded in the Ground Level Books and all the above Officers

attested the same by putting their signatures. Accordingly, the

final bill of Rs.1.53 Crores was submitted which was duly

endorsed by the concerned Officers of accused-Company

M/s.JITPL. Subsequently, the Complainant-Company, M/s.QIEL

vacated the premises of Derang Power Plant. The accused-

Company, M/s.JITPL, thereafter made payment of Rs.92.25 lacs to

the Complainant-Company, M/s.QIEL but did not make further

payment of the rest amount of Rs.60.80 lacs as claimed by the

Complainant-Company, M/s.QIEL.

      It is stated that despite repeated request for release and

payment of the said amount, the accused-Company M/s.JITPL

did not pay any heed to the same. So, the Complainant-

Company, M/s.QIEL had to invoke the Arbitration Clause as per

the contract.

7.    During    the   Arbitral   Proceeding,   the   Complainant-

Company, M/s.QIEL raised the issue of non-payment of the

residue amount as above said and further disputed the

termination of the contract as well as the encashment of the bank

guarantees as illegal. The Complainant-Company, M/s.QIEL on

going through the reply of the accused-Company-M/s.JITPL then

to his utter surprise learnt that the accused-Company M/s.JITPL

has forged and fabricated the documents and in the process

                                                         Page 6 of 27
CRLREV Nos.226 & 320 of 2023
                                      -7-




altered the final bill and the ancillary twenty-nine Level Books

containing the measurement of the work in order to show that the

final bill stands around Rs.94.88 lacs. It is stated that the accused-

Company-M/s.JITPL had submitted the documents wherein they

themselves have contradicted the modified amount arrived at by

them and stated that the final bill was to the extent of further

reduced amount of Rs.92.25 lacs which has been fully paid.

      It is alleged that the bill as well as ancillary documents were

forged, manipulated and fabricated and those were relied upon

by the accused-Company-M/s.JITPL to deprive the Complainant-

Company, M/s.QIEL of its lawful dues.

8.    The learned Arbitral Tribunal, without delving upon the

allegations of forgery, manipulation and fabrication in its award

dated 21.02.2017 rejected all such objections and contentions

raised by the accused-Company-M/s. JITPL and awarded a sum

of Rs.9.71 Crores, which included the entire sum of Rs.1.53 crores

of the final bill, to the Complainant-Company, M/s.QIEL by the

accused-Company (M/s.JITPL)

9.    Thereafter   on   22.03.2017     the   Complainant-Company,

M/s.QIEL filed four complaints arraigning several persons as

accused therein and we are here considered with the complaint

petition numbered as 1CC No.33 of 2017 wherein the accused

persons are the present Petitioners.
                                                            Page 7 of 27
CRLREV Nos.226 & 320 of 2023
                                      -8-




10.   Learned S.D.J.M., Talcher, embarking upon an inquiry

under section 202 of the Code, took cognizance of the offences

under sections 379/406/420/120-B/34 of the IPC and issued process

against these accused persons.

      The accused persons thereafter carried an application under

section 482 of the Cr.P.C. to this Court seeking quashment of the

proceeding.

      The said prayer was rejected by judgment dated 13.05.2022.

The Petitioners having carried the matter further to the Hon'ble

Apex Court have been unsuccessful.

11.   The learned S.D.J.M. then sitting over the complaint has

recorded the pre-charge evidence tendered from the side of the

Complainant-Company,           M/s.QIEL.   On   behalf    of    the

Complainant-Company, its Managing Director gave his evidence

and he too has been cross-examined at that stage by the accused

persons in exercise of their rights as per law. Thereafter an

application filed by these accused persons, for their discharge

under section 245(1) of the Code, having been rejected by the

impugned order, these Revisions have come to be filed.

12.   In so far as the complaint petition numbered as 1CC Case

No.33 of 2017 is concerned, to be more specific the allegations are

that the accused-Companies M/s.JITPL and M/s. SMMPL have

misappropriated the properties of the Complainant-Company,

                                                          Page 8 of 27
CRLREV Nos.226 & 320 of 2023
                                    -9-




M/s.QIEL, which were lying in the worksite of Derang Power

Plant for their benefits and thereby have made unlawful gain. It is

stated that for the purpose, the accused-Companies had colluded

and acted in connivance with each other in a concerted manner

hatching a criminal conspiracy to oust the Complainant-

Company, M/s.QIEL from the worksite. The accused-Companies

have forcibly entered the worksite of Derang Power Plant and

took over of the work of the Complainant-Company, M/s.QIEL in

a malfide manner behind its back. The accused-Company,

M/s.JITPL has also forced the Complainant-Company, M/s.QIEL

to sale its materials lying on the worksite to the accused-

Company M/s. SMMPL at a much lower rate than the acceptable

and payment towards the same was not made despite demands

on several occasions. It is thus stated that the accused persons

have    dishonestly   misappropriated    the     moveables    of   the

Complainant-Company,        M/s.QIEL     and     have    cheated   the

Complainant-Company,        M/s.QIEL     while    also    committing

criminal breach of trust;   they have colluded with each other to

cheat the Complainant-Company, M/s.QIEL so as to cause loss of

the property and have, therefore, committed the breach of

agreement.

13.    Heard Mr. S.P. Mishra and Mr. P.K. Rath, learned Senior

Counsels for the Petitioners (accused-Company-M/s. JITPL and


                                                             Page 9 of 27
CRLREV Nos.226 & 320 of 2023
                                    - 10 -




Others) of the Revision as at (A) and Mr. Rajeet Roy, learned

counsel for the accused-Company-M/s. SMMPL at length.

      Mr. V.S. Raju, the Managing Director of the Complainant-

Company, M/s.QIEL, who appeared in person, was also heard.

      I have perused the case records and the notes placed.

14.   At the outset, at the risk of repetition, it be stated that the

impugned order relates to the rejection of the prayer advanced by

these accused persons for their discharge under sub-section 1 of

section 245 of the Code.

15.   The present case has been instituted by the Complainant-

Company and the offences of which cognizance have been taken

are triable by following the procedures for trial of the warrant

cases. The procedures prescribed for trial of such cases are

contained in section 244 to 250 of the Code. In such warrant, case

arising upon a complaint instituted otherwise than in a police

report when the accused appears or is brought before the

Magistrate under section 244 (1) of the Code, the Magistrate is

called upon to hear the prosecution and take all such evidence as

may be produced in support of the prosecution. In that exercise,

the Magistrate may also issue summons to the witnesses also

under section 244(2) of the Code on an application by the

prosecution. All such evidence would stand as evidence before

charge. After such recording of the evidence is over, the

Magistrate as ordained under section 245(1) of the Code to
                                                          Page 10 of 27
CRLREV Nos.226 & 320 of 2023
                                    - 11 -




consider as to whether any case against the accused is made out,

which if unrebutted would warrant his conviction. If the

Magistrate comes to the conclusion that there is no such case

made out against the accused, the Magistrate would discharge

the accused. On the other hand, if the Magistrate is satisfied that a

prima facie case is made out against the accused, the Magistrate

would frame charge under section 246(1) of the Code when the

Complainant would get the second opportunity to lead further

evidence in support of the charge and so also the accused would

then besides leading evidence would get further opportunity to

cross-examine the witnesses already examined at the pre-charge

stage with further opportunity to cross-examine the witnesses

examined during the pre-charge stage.

      Therefore, under section 245(1) of the Code, the Magistrate

has the advantage of the evidence led by the prosecution before

him under section 244 of the Code. He has to consider whether if

the evidence remains goes unrebutted, the conviction of the

accused would be warranted. If there is no discernible

incriminating materials in the evidence, then the Magistrate

would be within its domain to discharge the accused under

section 245(1) of the Code.

16.   The Magistrate under sub-section 2 of section 245 of the

Code has also the power to discharge the accused at any previous

stage of the case, i.e., before such any such evidence is lead.
                                                          Page 11 of 27
CRLREV Nos.226 & 320 of 2023
                                    - 12 -




However, for discharging an accused under section 245(2) of the

Code, the Magistrate has to come to a finding that the charge is

groundless. In that exercise no question arises for consideration

of the evidence at that stage as no such evidence had by then

being taken. The Magistrate can take this decision before the

accused appears or is brought before this Court or the evidence is

lead under section 244 of the Code and that is what is clearly

borne out from the words "at any previous stage of the case"

which appear in section 245(2) of the Code which would be

obviously before the evidence of the prosecution under section

244(1) of the Code is completed or at any stage prior thereto.

      The accused persons when had earlier carried an

application under section 482 of the Code before this Court for

quashment of the complaint, which was after the order by which

the learned S.D.J.M. had taken cognizance of the offences as

afore-stated; the stage was not the present as in our hand. The

consideration before the Magistrate at that earlier stage while

taking cognizance was as to whether there is sufficient ground for

proceeding by issuing process against the accused persons when

here the consideration stands as to if as per the evidence let in by

the Complainant-Company, a case is made            out against the

accused persons and that remaining unrebutted, would warrant

their conviction.


                                                         Page 12 of 27
CRLREV Nos.226 & 320 of 2023
                                      - 13 -




17.   In case of Ajoy Kumar Ghose Vrs. State of Jharkhand & Another,

(2009) 14 SCC 115, the Hon'ble Apex Court has held:-

              "41. Before we approach this question, we must
      note that while Section 245(2) Cr.P.C. speaks about the
      discharge of the accused on the ground that the charge is
      groundless, Section 246(1) operates in entirely different
      sphere. An order under Section 245(2) Cr.P.C. results in
      discharge of the accused, whereas, an order under Section
      246 Cr.P.C. creates a situation for the accused to face a
      full-fledged trial. Therefore, the two Sections would have
      to be interpreted in slightly different manner, keeping in
      mind the different spheres, in which they operate. The
      words "or at any previous stage of the case" appearing in
      Section 246 Cr.P.C. would include Section 245 also,
      where the accused has not been discharged under Section
      245 Cr.P.C., while the similar term in Section 246(2) can
      include the stage even before any evidence is recorded. It
      cannot, therefore, be held that the words "at any previous
      stage of the case" as appearing in Section 245 Cr.P.C.,
      would have to be given the same meaning when those
      words appear in Section 246 Cr.P.C.
              The Bombay High Court, in a decision in Sambhaji
      Nagu Vs. State of Maharashtra reported in 1979
      Criminal Law Journal 390, has considered the matter.
      While interpreting the words "at any previous stage"
      under Section 246(1) Cr.P.C., the Learned Single Judge
      in that case, came to the conclusion that the phraseology
      only suggested that the Magistrate can frame charge,
      even before "all" the evidence is completed under Section
      244 Cr.P.C. Section 244 Cr.P.C. specifically mandates
      that as soon as the accused appears or is brought before
      the Court, the Magistrate shall proceed to hear the
      prosecution and take all such evidence as may be
      produced in support of the prosecution.

                                                             Page 13 of 27
CRLREV Nos.226 & 320 of 2023
                                      - 14 -




            Further, Section 245 Cr.P.C. also mandates that
            "245. When the accused shall be discharged- (1) if,
     upon taking all the evidence referred to in Section 244
     Cr.P.C., the Magistrate considers, for reasons to be
     recorded, that no case against the accused has been made
     out which, if unrebutted, would warrant his conviction,
     the Magistrate shall discharge him."
            In Section 246 Cr.P.C. also, the phraseology is "if,
     when such evidence has been taken", meaning thereby, a
     clear reference is made to Section 244 Cr.P.C. The
     Bombay High Court came to the conclusion that the
     phraseology would, at the most, mean that the Magistrate
     may prefer to frame a charge, even before all the evidence
     is completed. The Bombay High Court, after considering
     the phraseology, came to the conclusion that the typical
     clause did not permit the Magistrate to frame a charge,
     unless there was some evidence on record. For this, the
     Learned Single Judge in that matter relied on the ruling
     in Abdul Nabi Vs. Gulam Murthuza reported in 1968
     Criminal Law Journal 303.
            The similar view seems to have been taken in T.K.
     Appu Nair Vs. Earnest reported in AIR 1967 Madras
     262 and in re. M. Srihari Rao reported in AIR 1964
     Andhra Pradesh 226. The similar view has been expressed
     in P. Ugender Rao & Ors. Vs. J. Sampoorna & Ors.
     reported in 1990 Criminal Law Journal 762, where it has
     been expressed that previous stage is a stage, after
     recording some evidence. It is neither a stage before
     recording any evidence at all nor a stage after recording
     the entire evidence, but is in between. The interpretation,
     thus, placed on words "at any previous stage of the case",
     occurring in Section 246(1) Cr.P.C. also appears to be
     more in consonance with the order of the Sections
     numbered in the Code and also with the heading given to
     Section 246 Cr.P.C., viz., "Procedure where accused is

                                                             Page 14 of 27
CRLREV Nos.226 & 320 of 2023
                                      - 15 -




     not discharged". The very heading of the Section even
     indicates that it would come into play only after the
     matter is examined in the light of Section 245 Cr.P.C.
     and the accused is not discharged thereunder. Therefore,
     it is incumbent upon the Magistrate to examine the
     matter for purposes of considering the question whether
     the accused could be discharged under Section 245
     Cr.P.C. and it is only when he finds it otherwise, he could
     have resort to Section 246 Cr.P.C.
             The Learned Single Judge in this ruling has also
     noted another ruling by the same High Court in Abdul
     Nabi Vs. Gulam Murthuza reported in 1968 Criminal
     Law Journal 303 (cited supra). We, therefore, find that
     consistently, the view taken by the High Court is that
     there would have to be some evidence before the charge is
     framed. In the last mentioned case of P. Ugender Rao &
     Ors. Vs. J. Sampoorna & Ors. reported in 1990 Criminal
     Law Journal 762, there is one incorrect observation in
     respect of a decision of this Court in Cricket Association
     of Bengal & Ors. Vs. State of West Bengal & Ors.
     reported in 1971 (3) SCC 239 (cited supra) to the effect
     that the Magistrate cannot discharge the accused before
     recording any evidence, whatsoever, under Section 244
     Cr.P.C. We have not been able to find out such an
     expression in the aforementioned case of Cricket
     Association of Bengal & Ors. Vs. State of West Bengal &
     Ors. (cited supra). That was a case under old Section
     253(2), which is pari materia to the present Section
     245(1). On the other hand, the Court has very specifically
     stated therein that Section 253(2) gives ample
     jurisdiction to the Magistrate to discharge the accused in
     the circumstances mentioned therein and the order of
     discharge can be passed at any previous stage of the case.
     It is further stated in Para 13 that sub-Section (1) under
     those circumstances will not operate as a bar to the

                                                             Page 15 of 27
CRLREV Nos.226 & 320 of 2023
                                     - 16 -




     exercise of jurisdiction by the Magistrate under sub-
     Section (2). Since we have found error in the above
     mentioned judgment, we have mentioned so.
             However, the ruling in Cricket Association of
     Bengal & Ors. Vs. State of West Bengal & Ors. (cited
     supra) also supports our earlier finding that the
     Magistrate has the power to discharge the accused, even
     before any evidence is recorded and thus, an application
     for discharge at that stage is perfectly justifiable.
     However, insofar as Section 246(1) Cr.P.C. is concerned,
     we are of the clear opinion that some evidence would have
     to be there for framing the charge.
            There is only one judgment of the Andhra Pradesh
     High Court in Verendra Vs. Aashraya Makers reported in
     1999 Criminal Law Journal 4206, which has taken the
     view that the Magistrate can frame the charge even
     without any evidence having been taken under Section
     244 Cr.P.C. We do not think that is a correct expression
     of law, as the right of the accused to cross-examine the
     witnesses at the stage of Section 244(1) Cr.P.C. would be
     completely lost, if the view is taken that even without
     Ajoy Kumar Ghose vs State of Jharkhand &
     Anr. on 18 March, 2009 Indian Kanoon -
     http://indiankanoon.org/doc/1735221/ 11 the evidence, a
     charge can be framed under Section 246(1) Cr.P.C.
            The right of cross-examination is a very salutary
     right and the accused would have to be given an
     opportunity to cross-examine the witnesses, who have
     been offered at the stage of Section 244(1) Cr.P.C. The
     accused can show, by way of the cross-examination, that
     there is no justifiable ground against him for facing the
     trial and for that purpose, the prosecution would have to
     offer some evidence. While interpreting this Section, the
     prejudice likely to be caused to the accused in his losing
     an opportunity to show to the Court that he is not liable

                                                            Page 16 of 27
CRLREV Nos.226 & 320 of 2023
                                      - 17 -




      to face the trial on account of there being no evidence
      against him, cannot be ignored.
             Unfortunately, the earlier cases of the same Court,
      which we have referred to above, were brought to the
      notice of the Learned Judge. Again, the Learned Judge has
      not considered the true impact of the clause "at any
      previous stage of the case", which could only mean that
      even with a single witness, the Magistrate could proceed
      to frame the charge.

18.   The provision is intended only to filter private complaints

and protect the accused from harassment. The test then of 'prima

facie' case has to be applied which means a case established by

prima facie evidence which in turn means evidence sufficient in

law to raise a presumption of fact in question unless rebutted.

The Magistrate is required to consider the evidence with a view to

framing prima facie case for conviction.

      Keeping in mind, the allegations arising from out of the

contracts entered into between the parties in case of execution of

the works, it has to be borne in mind that simply because the

Complainant relates to commercial transaction or breach of

contract for which the civil remedy is available and being so

available has been availed of; that itself is no ground to discharge

the accused. The test is whether the evidence recorded at the pre-

charge stage discloses a prima facie case to presume that the

accused persons are guilty of commission of the offences and the

question of conviction would finally be decided on threadbare

                                                             Page 17 of 27
CRLREV Nos.226 & 320 of 2023
                                   - 18 -




examination of the evidence as would stand recorded in the full-

fledged trial applying the tests of reliability and acceptability.

Under section 245(1), the Magistrate has the advantage of the

evidence led by the prosecution before him under section 244 of

the Code and he has to consider whether if the evidence remains

unrebutted the conviction of the accused would be warranted. If

there is no incriminating material in evidence, then the Magistrate

proceeds to discharge the accused under section 245(1) of the

Code.

19.   In the case of Union of India Vrs. Prafulla Kumar Samal &

Another; (1979) 3 SCC 4; the Hon'ble Apex Court has held that the

words used in the context 'not sufficient ground for proceeding

against the accused show that the Judge cannot be assumed to be

a Post Office to frame the charges at the instruction of the

prosecution, and application of judicial mind to the facts of the

case is necessary to determine whether a case has been made out

by the prosecution for trial. In determining this fact, it is not

mandatory to drive into the pros and cons of the matter by the

Court.

      There is a major distinction as regards discharge of an

accused from a warrant case instituted upon a police report and a

warrant case instituted upon a private complaint filed under

section 200 of the Code.


                                                        Page 18 of 27
CRLREV Nos.226 & 320 of 2023
                                     - 19 -




20.   In order to address on the question of the legality and

propriety of the impugned order, it is found that in the

touchstone of the above settled legal base, the learned S.D.J.M.

has refused to discharge the accused persons under section 245(1)

of the Code.

21.   The narration of the facts constituting the commission of

offences are the followings:-

            On 29.01.2013 when four numbers of contracts
         awarded in favour of complainant company
         were      illegally  terminated,     Three  Bank
         Guarantees worth of Rs.2.72 crores were en-
         cashed without notice to the complainant's
         company and on 07.02.2013, when the properties
         of the complainant worth of Rs.9.8 crores were
         taken away and controlled and there was
         restraint upon the Company for their entry into
         the campus and prior to 30th January, 2013,
         illegal award of the said two numbers of
         contracts works out of four numbers of contract
         works to accused M/s.SMMPL who were
         allowed their free entry into the JITPL campus as
         well as complement sites in that campus before
         officially intimating the termination of contract
         to the Complainant-Company.

22.   First of all, it is stated that firstly the offence was committed

on 29.01.2013 when the contracts were terminated and the Bank

guarantees worth of Rs.2.72 crores were encashed; on 07.02.2013

the accused-Company, M/s.JITPL seized the properties of the

Complainant-Company, M/s.QIEL whose entry to the campus was

                                                           Page 19 of 27
CRLREV Nos.226 & 320 of 2023
                                        - 20 -




restrained and on 30.01.2013 when the accused-Company M/s.

JITPL awarded two contract works out of the four to the accused-

Company M/s.SMMPL.

     Further    narrations     stand      that   the   accused-Company

M/s.JITPL being hand in gloves with two of its Liaison Officers and

one of whom was an Ex-Director unilaterally terminated the four

contracts and suddenly encashed the Bank Guarantees. It is next

stated that accused-Company-M/s.JITPL in collusion with those

above two accused persons illegally misappropriated the bank

guarantees worth Rs.2.72 crores for no justifiable reason breaching

the trust of the Complainant-Company, M/s.QIEL which it had

reposed on the accused-Company-M/s.JITPl. It is also stated that

the dominance of the accused-Company M/s.JITPL was misused by

willful coercive action in rejecting the contract encashing and

misappropriating the amount covered under the Bank Guarantees

and allowing the accused-Company-M/s.SMMPL and its two

Directors to do the work at the site where the Complainant-

Company, M/s.QIEL was executing the work without waiting for

the resolution of the dispute in terms of the Arbitration clause in

place in the contract executed between the Complaint-Company

and the accused-Company-M/s.JITPL.

     Facts further narrated are practically the follow up actions to

the above that the accused-Company-M/s.JITPL inducted the accused-Company-M/s.SMMPL and its authorized agents, the two Page 20 of 27 CRLREV Nos.226 & 320 of 2023

- 21 -

Directors into the worksite and allowed them to do the jobs remaining incomplete which is stated to be in order to cheat and defraud the Complainant-Company, M/s.QIEL.

The other allegations remain with regard to illegal utilization of the materials worth of Rs.91.80 lacs belonging to the Complainant-Company, M/s.QIEL.

But then interestingly it is stated that the Complainant- Company, M/s.QIEL was forced to agree to sale the materials worth of Rs.91.80 lacs to the accused-Company-M/s.JITPL and thereafter part payment towards the same being made, rest amount of Rs.38.80 lacs was not paid despite several approaches.

23. It would be profitable at this stage to indicate that the Arbitral Proceeding stood concluded by passing of the award on 21.02.2017. The learned Arbitral Tribunal awarded a sum of Rs.9,71,06,938/- to be paid by the accused-Company-M/s. JITPL to the Complainant-Company with interest @18% per annum from the date of the award till actual payment. As per the order finally passed on 27.09.2023 by the Hon'ble Apex Court in SLP(C) No.19380 of 2023; the awarded amount has been paid and the full and final satisfaction to that effect has been recorded by the Executing Court on 19.10.2023 in the Execution Proceeding No.158 of 2017. Thus, the accusd-Company, M/s.JITPL has paid all the dues of the Complainant-Company of more than Rs.17.00 crores as Page 21 of 27 CRLREV Nos.226 & 320 of 2023

- 22 -

per the determination in the Arbitration Proceeding and subsequent final order of the Hon'ble Apex Court.

24. Admittedly, the Complainant-Company, M/s.QIEL during the recording of the evidence at the pre-charge stage has not tendered any documentary evidence in admitting any of those into evidence. In the Arbitral Proceeding no finding as regards the termination of the contract or encashment of the bank guarantees as tainted with mala fides or for the purpose of misappropriation has been given.

25. At paragraph 763 of the award, the learned Tribunal has stated the following:-

"The meeting dated 06.02.2013 took place after the termination of Contract. It was a Tripartite Agreement. The Respondent at best was working as a facilitator. It has not undertaken any vicarious liability to pay to the contractor any amount in the event the new agency namely M/s. Sinhotia failed and/or neglect to pay any amount towards the price of the Precast Tiles. The Tribunal is unable to agree with the submissions of the Claimant that the Respondent has made itself liable to pay the said amount in terms of the contract as new agency was introduced by the Respondent to the Claimant and the sale of materials took place only to benefit in advance their own works. The Claimant has not brought on record any material to show that the Respondent had undertaken any such responsibility. The rights and liabilities of the parties in the opinion of the Tribunal are contained in the minutes of meeting dated 06.02.2013 only."
Page 22 of 27

CRLREV Nos.226 & 320 of 2023

- 23 -

26. The learned Tribunal at paragraphs 758 to 764 of its award has expressed its disagreement with the aforementioned contention of the Claimant therein, i.e., M/s.QIEL that by reason thereof accused-Company, M/s. JITPL had undertaken any liability/responsibility to monitor all the payments.

The contention of the Claimant, i.e., the Complainant- Company, M/s.QIEL was that the accused-Company-M/s.JITPL had taken the responsibility to monitor all payment transaction and that had undertaken the contractual obligation to see that the new entity (accused-Company-M/s.SMMPL) pay the entire bill amount to it.

27. In the minutes of the meeting dated 06.02.2023, it finds mention that the Complainant-Company, M/s.QIEL expressed their unwillingness to complete the work in other area as work in raw water reservoir and Ash Dyke had been uploaded.

28. The Managing Director of the Complainant-Company, M/s.QIEL in his evidence at the pre-charge stage has admitted that there was a clause for termination of his contract, i.e., Clause No.12.4 and that as per the said contract, the date of completion of aforesaid contract was scheduled to be on or before 28.02.2012 and that the said contract works were not completed by that date. He has again admitted that on 02.02.2013 he had issued one letter whose contents he admits to one Mr.Ashok Kumar Jain, Vice President (Head Civil), accused-Company-M/s.JITPL and therein Page 23 of 27 CRLREV Nos.226 & 320 of 2023

- 24 -

he has not mentioned the name of any of the Officers of the accused-Company-M/s.JITPL to have restrained him in any manner.

It has also been admitted by him that on 14.02.2013 he had issued one letter to accused Sunil Kumar Agrawal, the Liaison Officer and Ex-Director of the Accused-Company-M/s.JITPL wherein he had not indicated the role of the accused persons in selling the materials of the Complainant-Company, M/s.QIEL. Rather he admits to have written that he was asked to sale those materials. As per his evidence, he had handed over the Bank Guarantees to the accused-Company-M/s.JITPL for performance of the contract. He also admits to have filed no such document in any way hinting at the conspiracy as alleged to have been hatched by the accused persons.

29. It would also be pertinent to state here that the evidence of the said Managing Director of the Complainant-Company, M/s.QIEL is to the effect that when the work was in full swing, the accused-Company-M/s.JITPL in collusion with the accused- Company-M/s.SMMPL terminated the contract, encashed the bank guarantees and obstructed the Complainant-Company, M/s.QIEL to enter the worksite and by then the accused-Company M/s. JITPL had already inducted the accused-Company-M/s.SMMPL to start construction utilizing the materials of the Complainant- Company.

Page 24 of 27

CRLREV Nos.226 & 320 of 2023

- 25 -

It is, however, next stated that meeting had been convened by the accused-Company, M/s.JITPL inside the premises of JITPL for settlement of the dispute. In the said meeting, accused- Company, M/s.JITPL along with with other accused persons agreed to pay for entire stock of sand and pre cast tiles as per the rate already mentioned amounting to Rs. 91.80 lacs. However, they have only paid Rs.53,00,000/- and remaining Rs.38.8 lacs was not paid despite several demand and they also denied to pay the said amount. He has accordingly stated that they misappropriated the said amount for their own purpose and illegal gain. His evidence is that the learned Arbitration Tribunal being approached; in its award the claim with respect to sand and pre cast tiles has been declined citing that the contract is a tripartite agreement. So it is said that the complaint petition was filed.

30. Having led the evidence as above at the pre-charge stage, the Complainant-Company, M/s.QIEL has expressed not to lead any further evidence at that stage and thus with such evidence has urged before the Court to proceed further by framing charge against the accused persons.

31. The learned S.D.J.M. having narrated the allegations and going through the Arbitral Award has expressed its agreement with the view of the learned Tribunal with such termination of contract by the accused-Company-M/s.JITPL at that stage appears Page 25 of 27 CRLREV Nos.226 & 320 of 2023

- 26 -

to be illegal. So, it is not on the basis of any evidence taken on record at the pre-charge stage.

32. It is next stated that, therefore, the accused persons need to prove their stand with regard to such termination of the contract and encashment of bank guarantees by adducing evidence which is not the relevant consideration to weigh in mind for the purpose. It has further stated that the amount in full has not been paid to the Complainant-Company. The views taken above are not deriving any support from the evidence recorded at the pre-charge stage. The evidence laid by the Complainant-Company, M/s.QIEL under section 244 of the Code as above even upon their acceptance in entirety do not make out a prima facie case against the accused persons in the direction of commission of offences so as to stand charged. All these do not appear to impute criminality upon the accused persons for their said actions giving rise to a dispute which having been raised in arbitration proceeding has been final followed by award of the amount which has been satisfied in entirety as per the final order of the Hon'ble Apex Court. This Court thus taking the evidence as available which have been referred to and touched upon on their face value and accepting all those as such records that no prima facie case against the accused persons for any of those offences is made out so as to frame charge for the noted offences in placing the accused persons to full- fledged trial.

Page 26 of 27

CRLREV Nos.226 & 320 of 2023

- 27 -

33. In the wake of all the aforesaid, it is held that the order impugned in these Revisions is liable to be set aside. Accordingly, impugned order dated 05.04.2023 passed in 1CC Case No.33 of 2017 by the learned S.D.J.M., Talcher is set aside and the accused persons are discharged under section 245 (1) of the Code.

34. Resultantly, both the Revisions stand allowed. No order as to cost.

S/d-

(D. Dash) Judge True Copy P.A. Signature Not Verified Digitally Signed Signed by: HIMANSU SEKHAR DASH Reason: Authentication Location: OHC Date: 30-Jan-2024 15:48:35 Page 27 of 27 CRLREV Nos.226 & 320 of 2023