Union of India - Act
Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh (Grant of Connectivity and Open Access in Intra-State Transmission & Distribution and related matters) Regulations, 2024
UNION OF INDIA
India
India
Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh (Grant of Connectivity and Open Access in Intra-State Transmission & Distribution and related matters) Regulations, 2024
Regulation JERC-JKL-REG-2024-4 of 2024
- Published on 12 February 2024
- Not commenced
- [This is the version of this document from 12 February 2024.]
- [Note: The original publication document is not available and this content could not be verified.]
Preliminary
1. Short Title, Commencement and Extent.
2. Definitions.
3. Words and expressions occurring in these Regulations and not defined herein but defined in the Act or Grid Code or State Grid Code shall bear the same meanings as respectively assigned to them in the Act or Grid Code or State Grid Code and the words and expressions used herein but not specifically defined herein or in the Act or Grid Code or State Grid Code shall have the meanings generally assigned to them in the electricity industry.
4. In the interpretation of these Regulations, unless the context otherwise requires:
Chapter 1 Connectivity
1.1 Connectivity.
1.2 Application Process for Connectivity to Intra-State Transmission System.
| Sl.No. | Quantum of power to be injected /off take into /from Intra State Transmission | Application Fee Rupees ( ) |
|---|---|---|
| 1. | Up to 10 MW | 100,000 |
| 2. | More than 10 MW and up to 50 MW | 200,000 |
| 3. | More than 50 MW and up to 100 MW | 300,000 |
| 4. | More than 50 MW and up to 100 MW | 400,000 |
1.3 Application Process for Connectivity to Distribution System by a Generating Station.
Chapter 2 General Conditions for Open Access
2.1 Phasing of Open Access.
2.2 Eligibility for Open Access and Conditions to be Satisfied.
2.3 Provisions for Existing Distribution Licensees.
2.4 Provisions for Existing Consumers and Generating Company Availing Open Access.
2.5 Settlement of Dues.
2.6 Criteria for Granting Open Access.
Chapter 3 Application Procedure and Approval
3.1 Categories of Open Access Consumers.
3.2 Nodal Agency and fee for Open Access.
| S.No. | Inter-se location of injection &drawal point | Nodal Agency | Application Fee ( ) | Time for disposal of the application (Days from the receipt of application) | Documents required with the application |
| Applicant is connected to the distribution network | |||||
| 1 | Both within the same Distribution Licensee | SLDC | 2,000 | As provided in Clause 3.7 | Proof of payment of Application fee• PPA or Sale?purchase agreement of power• Proof of installation of SEM |
| 2 | Both within the same State but in areas of different Distribution Licensees | SLDC | 5,000 | Same as above | Same as above. Additionally, consent from all Distribution Licensees |
| 3 | Injection point in the Intra- State Transmission System within the State | SLDC | 5,000 | Same as above | Same as above |
| 4 | Consumer opting to avail power supply from Power Exchange | NLDC | As per Central Commission's Regulations | ||
| 5 | In different States | RLDC | As per Central Commission's Regulations | ||
| Applicant is connected to the Intra-State transmission network | |||||
| 1 | Both within the same State (in Intra-State Transmission Network) | SLDC | 5,000 | As provided in Clause 3.7 | • Proof of payment of Application fee• PPA or Sale?purchase agreement of power• Proof of installation of SEM |
| 2 | Injection Point in the Distribution Network within State | SLDC | 5,000 | Same as above | Same as above. |
| 3 | Consumer opting to avail power supply from Power Exchange | NLDC | As per Central Commission's Regulations | ||
| 4 | In different States | RLDC | As per Central Commission's Regulations | ||
| S.No. | Inter-se location of injection &drawal point | Nodal Agency | Application Fee ( ) | Time for disposal of the application (Days from the receipt of application) | Documents required with the application |
| Applicant is connected to the distribution network | |||||
| 1 | Both within the same Distribution Licensee | SLDC | 25000 | 20 | • Proof of payment of Application fee• Bank Guarantee• PPA or Sale-purchase |
| 2 | Both within the same State but in areas of different Distribution Licensees | SLDC | 50000 | 30 | Same as above. Additionally, consent from all Distribution Licensees |
| 3 | Injection point in the Intra- State Transmission System within the State | SLDC | 50000 | 30 | Same as above |
| 4 | In different States | CTU | As per Central Commission's Regulations | ||
| Applicant is connected to the Intra-State transmission network | |||||
| 1 | Both within the same State (in Intra-State Transmission Network) | SLDC | 50,000 | 30 | • Proof of payment of Application fee• Bank Guarantee• PPA or Sale-purchase agreement of power• PPA or Sale-purchase agreement of power• In case of Generating Station or Consumer not already connected to the grid, documentary evidence for completion of the Connectivity showing that the same shall be completed before the intended date of Open Access.• Proof of installation of SEM |
| 2 | Injection Point in the Distribution Network within State | SLDC | 50,000 | 30 | Same as above |
| 3 | In different States | CTU | As per Central Commission's Regulations | ||
| S.No. | Inter-se location of injection &drawal point | Nodal Agency | Application Fee ( ) | Time for disposal of the application (Days from the receipt of application) | Documents required with the application |
| Applicant is connected to the distribution network | |||||
| 1 | Both within the same Distribution Licensee | SLDC | 1,00,000 | 30 | • Proof of payment of Application fee• Bank Guarantee• PPA or Sale-purchase agreement of power• In case of Generating station or Consumer not already connected to the grid, documentary evidence for completion of the Connectivity showing that the same shall be completed before the intended date of Open Access.• Proof of installation of SEM |
| 2 | Both within the same State but in areas of different Distribution Licensees | SLDC | 2,00,000 | • 120 Days where augmentation of Transmission / Distribution System is not required• 150 Days, otherwise | Same as above. Additionally, consent from all Distribution Licensees |
| 3 | Injection point in the Intra- State Transmission System within the State | STU | 2,00,000 | Same as above | Same as above |
| 4 | In different States | CTU | As per Central Commission's Regulations | ||
| Applicant is connected to the Intra-State transmission network | |||||
| 1 | Both within the same State (in Intra-State Transmission Network) | STU | 2,00,000 | • 120 Days where augmentation of Transmission / Distribution System is not required• 150 Days, otherwise | • Proof of payment of Application fee• Bank Guarantee• PPA or Sale-purchase agreement of power• In case of Generating Station or Consumer not already connected to the grid, documentary evidence for completion of the Connectivity showing that the same shall be completed before the intended date of Open Access.• Proof of installation of SEM |
| 2 | Injection Point in the Distribution Network within State | SLDC | 50,000 | 30 | Same as above |
| 3 | In different States | CTU | As per Central Commission's Regulations | ||
3.3 Procedure for Grant of Open Access Involving Inter-State Transmission System.
3.4 Creation of Coordination Committee and Detailed Procedure for Grant of Open Access.
3.5 Procedure for Grant of Long-term Open Access Involving Intra-State Transmission and/or Distribution System.
3.6 Procedure for Grant of Medium-term Open Access Involving Intra-State Transmission and Distribution System.
3.7 Procedure for Grant of Short-term Open Access involving Intra-State Transmission and Distribution System.
3.8 Consent by STU, SLDC or Distribution Licensee.
3.9 Allotment Priority.
| Order of priority for grant of Open Access | Allotment |
| Priority 1 | Distribution Licensee (irrespective of whether Open Access sought is for Long-term, Medium-term or Short- term) |
| Priority 2 | Other Long-term Open Access Applicants Other Medium-term |
| Priority 3 | Open Access Applicants Other Short-term Open Access |
| Priority 4 | Applicants |
3.10 Applications from Defaulters.
Chapter 4 Open Access Charges
4.1 Transmission Charges.
4.2 Wheeling Charges.
4.3 Scheduling and System Operation Charges.
4.4 Cross Subsidy Surcharge.
4.5 Additional Surcharge
4.6 Standby Power and Standby Charges for Drawal of Power by Open Access Consumer from Distribution Licensee.
4.7 Reactive Energy Charges
4.8 Other Charges.
4.9 Applicability of Open Access charges.
| S.No. | Inter-se location of injection & drawal point | Applicable charges Applicable | Applicable losses |
| Applicant is connected to the distribution network | |||
| 1 | Both within the same Distribution Licensee | Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system operation charges• Imbalance charges, if any | Distribution loss in kind at relevant voltage level |
| 2 | Both within the same State but in areas of different Distribution Licensees | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges, as applicable• Intra-State Transmission Charges, if applicable• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level in respect of both the Distribution Licensee• Intra-State Transmission Loss in kind, if applicable |
| 3 | Consumer opting to avail power supply from Power Exchange | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Power Exchange Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss• Inter-State Transmission Loss in kind |
| 4 | In different States | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss• Inter-State Transmission Loss in kind |
| Applicant is connected to the Intra-State transmission network | |||
| 1 | Both within the same State (in Intra-State Transmission Network) | Intra-State Transmission Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable• Imbalance charges, if any | Intra-State Transmission Loss in kind |
| 2 | Injection Point in the distribution network within State | • Intra-State Transmission Charges• Wheeling Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss in kind |
| 3 | Consumer opting to avail power supply from Power Exchange | • Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Power Exchange Charges• Imbalance charges, if any | • Intra-State Transmission Loss in kind• Inter-State Transmission Loss in kind |
| 4 | In different States | • Intra-State Transmission Charges• Inter-State Transmission Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Imbalance charges, if any | • Intra-State Transmission Loss in kind• Inter-State Transmission Loss in kind |
| S.No. | Inter-se location of injection & drawal point | Applicable charges Applicable | Applicable losses |
| Applicant is connected to the distribution network | |||
| 1 | Both within the same Distribution Licensee | Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system operation charges• Imbalance charges, if any | Distribution loss in kind at relevant voltage level |
| 2 | Both within the same State but in areas of different Distribution Licensees | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges, as applicable• Intra-State Transmission Charges, if applicable• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level in respect of both the Distribution Licensee• Intra-State Transmission Loss in kind, if applicable |
| 3 | Injection point in the Intra-State Transmission System within the State | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Power Exchange Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss• Inter-State Transmission Loss in kind |
| 4 | In different States | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss in kind• Inter-State Transmission Loss in kind |
| Applicant is connected to the Intra-State transmission network | |||
| 1 | Both within the same State (in Intra-State Transmission Network) | Intra-State Transmission Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable• Imbalance charges, if any | Intra-State Transmission Loss in kind |
| 2 | Injection Point in the distribution network within State | • Intra-State Transmission Charges• Wheeling Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss in kind |
| 3 | In different States | • Intra-State Transmission Charges• Inter-State Transmission Charges• Cross Subsidy surcharge• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Imbalance charges, if any | • Intra-State Transmission Loss in kind• Inter-State Transmission Loss in kind |
| S.No. | Inter-se location of injection & drawal point | Applicable charges Applicable | Applicable losses |
| Applicant is connected to the distribution network | |||
| 1 | Both within the same Distribution Licensee | Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system operation charges• Imbalance charges, if any | Distribution loss in kind at relevant voltage level |
| 2 | Both within the same State but in areas of different Distribution Licensees | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges, as applicable• Intra-State Transmission Charges, if applicable• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level in respect of both the Distribution Licensee• Intra-State Transmission Loss in kind, if applicable |
| 3 | Injection point in the Intra- State Transmission System within the State | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as• applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Power Exchange Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss |
| 4 | In different States | • Wheeling Charge• Cross Subsidy surcharge• Additional surcharge, if any• Stand-by charges, if any• Reactive Energy Charges, as applicable• Scheduling and system Operating Charges as applicable (Inter-State and Intra-State)• Intra-State Transmission Charges• Inter-State Transmission Charges• Imbalance charges, if any | • Distribution loss in kind at relevant voltage level• Intra-State Transmission Loss• Inter-State Transmission Loss in kind |