State of Rajasthan - Section

Section 22 in General Specification and Conditions of Contract

22. Measurements.

- All measurement connected with the work shall be taken geometrically or nett. The measurement of earthwork of bund shall be measured for bank section. The measurements given in Schedule 'G' or in the supplementary Schedule 'H' attached to the tender shall be held to mean the finished sizes of the respective item of the work after any dressing or cutting required has been executed.