Delhi High Court
Bharat Sanchar Nigam Ltd vs M/S Vindhya Telelinks Pvt Ltd on 26 October, 2021
Author: Vibhu Bakhru
Bench: Vibhu Bakhru
IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 26.10.2021
+ O.M.P. (COMM) 503/2019
BHARAT SANCHAR NIGAM LTD ..... Petitioner
versus
M/S VINDHYA TELELINKS PVT. LTD. ..... Respondent
Advocates who appeared in this case:
For the Petitioner :Ms Ruchi Gour Narula, Advocate with Ms
Sangeeta Sondhi and Mr Gorang Goyal,
Advocates.
For the Respondent : Mr Narendra M. Sharma, Mr Abhishek
Sharma, Mr Siddhartha Jain, Advocates.
CORAM
HON'BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J Introduction
1. Bharat Sanchar Nigam Ltd. (hereinafter 'BSNL') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the 'A&C Act') impugning an Arbitral Award dated 13.06.2019 (hereafter the 'impugned award') delivered by an Arbitral Tribunal comprising of Justice (Retired) Vijender Jain, former Chief Justice of Punjab and Haryana High Court as the Sole Arbitrator (hereafter the 'Arbitral Tribunal').
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 1 of 19 By:DUSHYANT RAWAL2. The impugned award was rendered in the context of disputes that had arisen between the parties in respect of the contract for supply and purchase of Polyethylene Insulated Jelly Filled Cables (PIJF Cables). In terms of the contract between the parties, M/s Vindhya Telelinks Pvt. Ltd. (hereinafter 'VTPL') had agreed to supply PIJF Cables to BSNL. Since the element of copper constitutes the main raw material for manufacture of the PIJF Cables, the parties had agreed that the prices of the PIJF Cables to be supplied, would be suitably adjusted to accommodate the increase or decrease in the price of copper wire rod. BSNL had agreed to issue monthly circulars regarding the price of copper for the purpose of calculation of the price variation. It had issued provisional circulars and, provisional payments were made accordingly. Subsequently, after the supplies were completed, BSNL issued a final circular setting out the monthly base prices of copper for the period April 2005 to August 2006. VTPL had contested the calculation of the price of copper as fixed by BSNL and the said dispute is central to the controversy. It claimed that the price of copper as fixed was not comparable with the base price of copper as it was reduced by the element of customs duty, which was included in the base price of copper. VTPL, raised claims for the differential payments, which were allowed by the Arbitral Tribunal.
Factual Context
3. BSNL is a Public Sector Undertaking. It is engaged in providing telecom services in India except in Delhi and Mumbai. BSNL had issued a Notice Inviting Tender (NIT) dated 12.01.2005 inviting Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 2 of 19 By:DUSHYANT RAWAL inquiries for the procurement of "120 LCKM PIJF Cables" [120 Lakh Conductor Kilometers of Polyethylene Insulated Jelly Filled Cables].
4. The Instructions to Bidders required the bidders to quote composite prices inclusive of all the levies and taxes but excluding octroi/entry tax, on the basis of the copper wire prices. Clause 9.8 of the Instructions to Bidders expressly provided that the prices would be quoted considering the price of copper wire as ₹1,83,366/-. The said clause is set out below:
"9.8 The prices will be quoted at copper wire prices of Rs.1,83,366/- (Rupees One Lac Eighty three thousand three hundred sixty six only) per MT excluding Excise Duty as on January 2005. Price variation will be applicable on copper as per standard Price variation table given in Section XI of the Bold Document."
5. Section XI of the Instructions to Bidders included a table setting out the corresponding increase and decrease in price for every increase/decrease of price of raw materials by ₹100 per metric ton for PIJF cables of different sizes/specifications. Note (1) to the said table is relevant and is set out below:
" Note:(1) The price variation will be calculated on the Basic Price element of the approved rate and the same shall be used to arrive at the composite price to be offered to all the vendors. The composite price of each size of cable shall be worked out accordingly or monthly basis based upon the Copper Price Circular issued by BSNL.Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 3 of 19 By:DUSHYANT RAWAL
This price variation shall be applicable within original delivery schedule."
6. The petitioner as well as various other bidders submitted their bid on the basis of the base price of copper as indicated. It is VTPL's case that the same also included customs duty at the rate of 15%, which was applicable at the material time.
7. VTPL was declared as one of the successful bidders, however, the price quoted by it was not accepted. VTPL claims that it entered into price negotiations with BSNL and thereafter, BSNL had made a counter offer in the form of an Advance Purchase Order dated 10.06.2005. The said Advance Purchase Order was not accepted and subsequently, a revised Advance Purchase Order dated 30.07.2005 (hereafter 'the APO') was placed on VTPL. The APO also included a price variation clause. Clause 3(i) of the APO is relevant and set out below:
"3. PRICE VARIATION:
(i) The price variation will be calculated on the basic price element of copper base price indicated in the bid document and the same shall be used to arrive at the composite price. The composite price of each size of cable shall be worked out accordingly on monthly basis, based upon the monthly Copper Price Circular issued by BSNL. However, a ready reckoner is enclosed as per annexure-III."
8. It is relevant to state that Annexure III included a table for calculation of the price variation for every month for deriving the revised composite price. Note (1) to the said table stated that the price Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 4 of 19 By:DUSHYANT RAWAL variation on base price (referred to as A1 to A16 in the Table) "are the values of PV on copper for different sizes of cables to be computed every month as per the BSNL (HQ), Monthly Price Circular and PV Table (as per Section XI of the bid document)."
9. BSNL issued monthly circulars indicating the provisional price of copper wire rod and specifying that the same would be subject to finalization. Based on the provisional prices of copper wire rod, VTPL effected supplies and raised its invoices. BSNL made payments on the basis of the provisional price of copper fixed by it. VTPL claims that BSNL had represented that it would pay or adjust the differential amount on the prices being finalized.
10. BSNL issued a circular dated 21.08.2006 finalizing the copper rod price for each month commencing April 2005 to August 2006.
The Controversy
11. VTPL claimed that the price as fixed by BSNL was not on a comparable basis as the base price of copper indicated in the bid documents had been reduced by discounting it on account of customs duty. It claimed that the base price as indicated by it for the purposes of the APO included customs duty at the rate of 15%. However, the prices of copper as declared in the circular dated 21.08.2006 - on the basis of which variation in the composite price of PIJF Cables was to be determined - did not include any element of customs duty.
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 5 of 19 By:DUSHYANT RAWAL12. VTPL requested BSNL to correct the circular to enable it to furnish invoices for the differential amount, which it quantified at ₹4,50,48,097/-.
13. Thereafter, on 20.04.2007, VTPL issued a notice calling upon BSNL to pay the differential amount of ₹4,50,48,097/- together with interest at the rate of 18% per annum, failing which to appoint an arbitrator in terms of the arbitration agreement (Clause 20 of Section III of the bid documents).
14. BSNL did not accede to the said request for the appointment of an arbitrator. VTPL claims that thereafter the parties exchanged correspondence for settlement of its claims but the same remained unresolved. VTPL claims that BSNL assured that VTPL's claims would be addressed if it withdrew its request for reference of disputes to arbitration.
15. VTPL states that since BSNL declined to appoint an arbitrator, it filed a petition under Section 11 of the A&C Act before this Court. And, by an order dated 12.02.2009, this Court appointed the learned Sole Arbitrator for adjudication of the disputes between the parties.
16. VTPL claims that even according to BSNL, a sum of ₹59,97,504/- was payable based on the final circular dated 21.08.2006. However, the said amount was also withheld by BSNL.
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 6 of 19 By:DUSHYANT RAWAL17. Before the Arbitral Tribunal, VTPL filed a Statement of Claims. Paragraph 19 of the Statement of Claims sets out the claims made by VTPL and is reproduced below:
"19. The claimant in all the aforesaid facts and circumstances is entitled for the following amounts:
S.No. Particulars Amount (Rs.)
1. The differential amount 4,50,48,097.00
on account of revision of
copper wire rod price (As
per Annexure-C11)
2. Interest on 2,17,71,190.00
Rs.4,50,48,097/- w.e.f.
21.08.2006 till 27.4.2009
@ 18% p.a.
Total (Rupees Six 6,68,19,287.00
Crores Sixty Eight Lacs
Nineteen Thousand
Two Hundred Eight
Seven only)
The claimant is further entitled for pendentelite and future interest @ 18% p.a. besides cost of Arbitration. It is submitted that if the respondent pursuant to the petition filed by the claimant under Section 9makes payment of the admitted amount the claim of the claimant to that extent shall be revised accordingly."
18. BSNL contested VTPL's claim. It stated that BSNL (erstwhile DOT) had been adopting the rate of copper as declared by M/s Hindustan Copper Ltd., Kolkata (hereafter HCL), which is also a Government of India Enterprise. It claimed that BSNL would issue monthly circulars based on the price of "CC Rod 8mm Dia (Standard)"
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 7 of 19 By:DUSHYANT RAWALdeclared by HCL for the previous month. BSNL stated that in the past, HCL had declared a base price and used a multiplication factor of 1.22 for arriving at the price of the said commodity - CC Rod. It claimed that on examination of the price circular received from HCL for the month of March, 2005, it was observed that HCL had adopted a multiplication factor of 1.17 for the price of CC Rod instead of 1.22 as used earlier. BSNL asserted that the multiplication factor had been derived by accounting for reduced customs duty at the rate of 10%.
19. BSNL requested HCL to issue a specific price circular for the telecom sector as customs duty for the telecom sector had been reduced to 'zero' in the Union Budget for the year 2005-06. HCL did not do so but advised BSNL to declare its own price. Accordingly, BSNL issued the final circular after reducing the impact of customs duty by applying a multiplication factor derived on the basis of the multiplication factors used by HCL and adjusting the same for reduction in customs duty to nil.
20. The principal dispute between the parties relates to the computation of the final monthly price of copper as declared by BSNL for the months of April, 2005 to August, 2006 in terms of its circular dated 21.08.2006. According to VTPL, no adjustment in customs duty was warranted as the base price declared by BSNL - on the basis of which bidders, including VTL, had bid a composite price - included an element of customs duty. Alternatively, it was contended by VTPL that the base price should also be adjusted to reduce the element of customs duty thus, providing for a comparable price for determination of the Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 8 of 19 By:DUSHYANT RAWAL price variations in the composite price commensurate with the price of copper.
Impugned Award
21. The Arbitral Tribunal considered the aforesaid claims and found in favour of VTPL. During the course of the arbitral proceedings, BSNL paid a sum of ₹36,32,734/- out of an amount of ₹59,97,504/-, which according to VTPL were admittedly due and payable by BSNL. BSNL also assured that the balance sum of ₹24,64,780/- would be processed. VTPL had stated that in the event it was done within the stipulated period, it would not claim any interest. Accordingly, the Arbitral Tribunal had directed that in the event BSNL paid an amount of ₹24,64,780/- within a period of four weeks from 14.04.2010, VTPL would not claim any interest on the delayed payment insofar as that amount is concerned. However, the said payments were not made within the stipulated period.
22. The Arbitral Tribunal considered the rival contentions and accepted VTPL's claim that the base price of copper as indicated in the bid documents and the APO were not comparable with the final prices as set out by BSNL in the circular dated 21.08.2006.
23. The customs duty of copper wire rod for the telecom sector had been reduced to zero pursuant to the Finance Bill tabled in the Parliament along with the Union Budget for the year 2005-06. Prior to that, the rate of customs duty of copper wire was 15%. The APO had Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 9 of 19 By:DUSHYANT RAWAL been placed on VTPL after the customs duty had been reduced for manufacturing for the telecom sector, but the base price of copper as mentioned included the element of customs duty. Since the prices of copper as fixed by BSNL in its circular dated 21.08.2006 did not include an element of customs duty, therefore, they were not comparable.
24. Accordingly, the Arbitral Tribunal allowed VTPL's claim and awarded a sum of ₹4,14,15,363/- [₹4,50,48,097/- as claimed in the Statement of Claims less ₹36,32,734/- paid by BSNL during the course of arbitral proceedings]. The same included a sum of ₹24,64,780/-, which was admittedly due to VTPL. During the course of the arbitration proceedings, BSNL had assured that the said payment would be processed. The Arbitral Tribunal awarded interest at the rate of 12% per annum on the said amount of ₹24,64,780/- from 21.08.2006 till the date of realization.
25. In respect of the principal claim, the Arbitral Tribunal did not accept VTPL's claim for interest at the rate of 18% per annum but awarded interest at the rate of 10% per annum for the period of 21.08.2006 to 27.04.2009. The Arbitral Tribunal also awarded pendente lite and future interest at the rate of 10% p.a. till realization of the amount awarded.
Submissions
26. Ms. Narula, learned counsel appearing for BSNL contended that the impugned award was vitiated by patent illegality as the Arbitral Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 10 of 19 By:DUSHYANT RAWAL Tribunal had proceeded on the basis of the Advanced Purchase Order dated 10.06.2005, which was not accepted. Thus, the impugned award is based on a non-existent contract.
27. Next, she submitted that the Arbitral Tribunal had grossly erred in holding that BSNL had breached the terms of the Agreement by not issuing monthly circulars declaring the price of copper wire. She submitted that the Arbitral Tribunal has held that BSNL had violated the terms of the Agreement and thus, VTPL was entitled to higher amounts as claimed by it. She submitted that BSNL had issued provisional circulars as due to the peculiar circumstances, it could not issue the final price circulars at the material time. However, that did not constitute a breach of its obligations under the Contract.
28. She submitted that the Arbitral Tribunal had erred in proceeding on the basis that since BSNL had issued price circulars in line with the price circulars issued by HCL in the past, VTPL would be entitled to receive the composite price calculated at a higher price of copper, which included the component of customs duty.
29. Next, she contended that the Arbitral Tribunal failed to appreciate that VTPL had given its unequivocal and unconditional acceptance to the APO [revised APO dated 10.07.2005] by its letter dated 11.08.2005 despite being aware that BSNL was already issuing provisional circulars since April, 2005, which did not include the component of customs duty. She contended that if VTPL had viewed the provisional circulars as a breach of the Agreement, it ought not to have accepted the Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 11 of 19 By:DUSHYANT RAWAL APO. She submitted that even if BSNL had issued monthly circulars declaring the final price, the same would nevertheless be computed on the same basis as the provisional circulars, which did not include the component of customs duty.
30. Lastly, Ms Narula relied on the arbitral award rendered by another arbitral tribunal in a similar matter - award dated 07.05.2018 in Sterlite Technologies Ltd. v. Bharat Sanchar Nigam Ltd. - whereby the arbitral tribunal (constituted in that case) had accepted BSNL's contentions and rejected similar claims made by the claimant.
31. In the written note of submissions filed by Ms. Narula, learned counsel appearing for BSNL, the same also referred to the decisions of the Supreme Court in Bharat Coking Coal Ltd. v. Annapurna Construction: AIR 2003 SC 660; Union of India v. Jain Associates:
(1994) 4 SCC 665; Food Corporation of India v. A.M. Ahmed & Co.:
AIR 2007 SC 829 and; PSA Sical Terminals Pvt. Ltd. v. The Board of Trustees of V O Chidambranar Port Trust, Tuticorin & Ors.: Civil Appeal no. 3699 and 3700/2018, decided on 28.07.2021.
32. Mr. Sharma, learned counsel appearing for VTPL countered the aforesaid submissions advanced by Ms. Narula. He submitted that none of the contentions advanced on behalf of BSNL fall within the grounds as set out in Section 34(2) or Section 34(2A) of the A&C Act. He also submitted that none of the contentions as advanced were pleaded. Thus, no interference with the Arbitral Award was warranted.
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 12 of 19 By:DUSHYANT RAWAL33. He pointed out that BSNL had not challenged the quantification of the claim and the decision of the Arbitral Tribunal on the construction of the contract by the Arbitral Tribunal requires no interference. He also contested the contention that the Arbitral Tribunal had not considered the revised APO dated 30.07.2005 as urged on behalf of BSNL.
Reasons and Conclusion
34. It is apparent from the tender documents (Instructions to Bidders) that the bidders were required to quote a consolidated composite price for the PIJF Cables. As noted above, since the element of copper constitutes a substantial value of the said product, the agreement also provided a mechanism for adjusting the composite price commensurate with the variation (increase and decrease) in the price of copper. The tender documents specified a base price of ₹1,83,366/-. The Instructions to Bidders as well as the APO set out a tabular statement indicating the base price of copper wire for various sizes/ specifications. The price of copper as indicated was also a consolidated price and did not separately indicate the elements that constituted that price. The base price did not indicate whether it was inclusive of customs or other duties. However, it is conceded that the base price included an element of customs duty and was based on the prices as declared by HCL. The price circulars issued by HCL also did not specify the value of customs duty [in absolute terms] as included in the price. The said circulars used a multiplication factor and according to BSNL, the said multiplication factor was in direct proportion to the element of customs duty.
Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 13 of 19 By:DUSHYANT RAWAL35. Although, the base price indicated an element of customs duty, the final monthly prices, which were declared by BSNL by its circular dated 21.08.2006, were based on the price declared by HCL and derived by BSNL by reducing the element of customs duty. BSNL did this by suitably altering the multiplication factor on the declared price.
36. It is also not in dispute that the APO had been issued much after the customs duty on copper for the telecom sector had been reduced to 'Nil'. This was by way of a special concession as the customs duty on copper for other sectors had not been reduced to Nil. Notwithstanding that the customs duty for telecom sector had been reduced to Nil, the base price included the same. In the given circumstances, VTPL's contention that base prices of copper were merely required to provide a scale for adjusting the composite price of PGIF Cables and therefore, the elements that constitute the base price were also required to be included in the monthly prices declared thereafter, cannot be stated to be unreasonable. VTPL's contention that there was no scope to reduce the element of customs duty as there was no change in the customs duty after the issuance of the APO is also not insubstantial.
37. The Arbitral Tribunal had accepted the said claim. Plainly, the view of the Arbitral Tribunal is a plausible view and warrants no interference by this Court in this proceeding. The said view does not fall foul of any fundamental policy of Indian Law.
38. The arbitral award rendered by another arbitral tribunal [arbitral award dated 07.05.2018 rendered in the case of Sterlite Technologies Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 14 of 19 By:DUSHYANT RAWAL Ltd. v. Bharat Sanchar Nigam Ltd. (supra)] is of little assistance to BSNL. Merely because another arbitral tribunal had accepted BSNL's contentions cannot be construed to mean that the view expressed by the Arbitral Tribunal in this case is patently illegal or in conflict with the Public Policy of India.
39. It is now far too well settled that this Court does not sit in appeal over the decision of an Arbitral Tribunal; it cannot re-evaluate and re- appreciate the evidence and supplant its opinion over that of the Arbitral Tribunal [See: Venture Global Engineering LLC v. Tech Mahindra Ltd and Anr: (2018) 1 SCC 656; M/s Dyna Technologies Pvt Ltd v M/s Crompton Greaves Ltd: (2019) 20 SCC 1; Associate Builders v Delhi Development Authority: (2015) 3 SCC 49]. Thus, this Court is not called upon to determine whether the view of the arbitral tribunal in Sterlite Technologies Ltd. v. Bharat Sanchar Nigam Ltd. (supra) or the decision of the Arbitral Tribunal in this case is erroneous. An arbitral award cannot be set aside on the ground that it is erroneous. In order to interfere with an arbitral award, this Court must conclude that the award is vitiated by patent illegality apparent on the face of the award.
40. In Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd.: 2021 SCC OnLine SC 695, the Supreme Court had explained the import of the expression 'patent illegality' as used in Section 34(2A) of the A&C Act in the following words:
"25. Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 15 of 19 By:DUSHYANT RAWAL the expression 'patent illegality'. Likewise, erroneous application of law cannot be categorised as patent illegality. In addition, contravention of law not linked to public policy or public interest is beyond the scope of the expression 'patent illegality'. What is prohibited is for courts to re-appreciate evidence to conclude that the award suffers from patent illegality appearing on the face of the award, as courts do not sit in appeal against the arbitral award. The permissible grounds for interference with a domestic award under Section 34(2-A) on the ground of patent illegality is when the arbitrator takes a view which is not even a possible one, or interprets a clause in the contract in such a manner which no fair- minded or reasonable person would, or if the arbitrator commits an error of jurisdiction by wandering outside the contract and dealing with matters not allotted to them. An arbitral award stating no reasons for its findings would make itself susceptible to challenge on this account. The conclusions of the arbitrator which are based on no evidence or have been arrived at by ignoring vital evidence are perverse and can be set aside on the ground of patent illegality. Also, consideration of documents which are not supplied to the other party is a facet of perversity falling within the expression 'patent illegality'."
41. It is also contended on behalf of BSNL that the Arbitral Award would result in unjust enrichment of VTPL at the cost of public money and therefore, the Arbitral Award is in conflict with the Public Policy of India. This contention is without any merit. The Agreement between BSNL and VTPL is a commercial contract and the disputes before the Arbitral Tribunal were limited to examining VTPL's claims in terms of their contract. The Arbitral Tribunal has allowed VTPL's claim and merely because the price as claimed by VTPL is higher than Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 16 of 19 By:DUSHYANT RAWAL what according to BSNL is payable, does not render the impugned award contrary to Public Policy of India. As noticed above, VTPL's claim that since the composite price of the PGIF Cables was to be adjusted on a scale of copper price, the integrity of that scale was required to be maintained is not without merit. BSNL had indicated a base price including the element of customs duty even though the APO had been issued after the customs duty for telecom sector had been reduced to 'zero'. Clearly BSNL cannot now fault the impugned award by contending that inclusion of customs duty in the price of copper is contrary to the Public Policy of Indian Law.
42. In the opening arguments, Ms. Narula, learned counsel appearing for BSNL, had contended that the Arbitral Tribunal had grossly erred in proceeding on the basis of the Advance Purchase Order dated 10.06.2005 and by completely ignoring that the Advance Purchase Order dated 10.06.2005 was not accepted and a revised Advance Purchase Order dated 30.07.2005 was issued. The said contention is erroneous as the arbitral record indicates that this issue was clarified by the Arbitral Tribunal by an order dated 15.01.2018. The impugned award also indicates that the Arbitral Tribunal had decided the disputes in reference to the APO (the revised APO dated 30.07.2005). In the note of written submissions filed by Ms. Narula, learned counsel appearing for BSNL, the said contention does not find any mention.
43. Ms. Narula had further contended that VTPL had accepted the APO despite being fully aware that BSNL had been issuing provisional circulars since April, 2005 that did not include the component of Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 17 of 19 By:DUSHYANT RAWAL customs duty and if VTPL had any grievance in this regard, it ought not to have accepted the APO. The said contention is unpersuasive. Even if the said contention is accepted, it would not warrant any interference with the impugned award as the same does not fall within the scope of the grounds available under Section 34 of the A&C Act.
44. Having stated that, it is also necessary to observe that the contention is based on a patently erroneous premise that the provisional circulars issued by BSNL since April, 2005 did not include an element of customs duty. The said contention appears to be contrary to BSNL's own case set up in its Counter Statement filed before the Arbitral Tribunal. In its Counter Statement, BSNL had expressly stated that it used to issue circulars based on the price circular issued by HCL. In the month of March, 2005, it was observed by BSNL that HCL had adopted a multiplication factor of 1.17 for pricing of CC Rod, which was less than the multiplication factor of 1.22 applied earlier. BSNL noticed that the multiplication factor of 1.17 was derived by taking 10% customs duty into account instead of zero percent and had thereafter, taken up the matter with HCL. The tabular statement set out in paragraph 3 of the Counter Statement of Facts indicates the prices finally determined by BSNL. These indicates that the provisional prices as conveyed to supplier were based entirely on the prices conveyed by HCL, which admittedly included the element of customs duty.
45. The Arbitral Tribunal had also considered the aforesaid aspect and noted that BSNL's witness (RW1) had in his cross-examination accepted that the provisional price of copper was inclusive of the Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 18 of 19 By:DUSHYANT RAWAL customs duty. Question no. 20 put to the said witness and his response to the same are unambiguous. The same are reproduced below:
"Q.20 - Whether the finalized copper price as finalized vide BSNL Circular dated 21.08.2006 Exh CW ¼ was inclusive of customs duty or exclusive of custom duty ?
Ans. It was inclusive of custom duty. However, the custom duty applicable for telecom sector was 0%."
46. In view of the above, the present petition is unmerited and, accordingly, dismissed.
VIBHU BAKHRU, J OCTOBER 26, 2021 RK/gsr Signature Not Verified Digitally Signed O.M.P. (COMM) 503/2019 Page 19 of 19 By:DUSHYANT RAWAL