Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 0]

Calcutta High Court (Appellete Side)

Mrt Signals Limited And Another vs Union Of India And Others on 1 October, 2024

Author: Shampa Sarkar

Bench: Shampa Sarkar

                    IN THE HIGH COURT AT CALCUTTA
                   CONSTITUTIONAL WRIT JURISDICTION
                            APPELLATE SIDE


Present:
Hon'ble Justice Shampa Sarkar

                                     WPA 13366 of 2024

                             MRT Signals Limited and another
                                           vs.
                                Union of India and others



Mr. Jayanta Kumar Mitra, Ld. Sr. Adv.
Mr. Jishnu Saha, ld. Sr. Adv.
Ms. Rajshree Kajaria,
Mr. Sarvapriya Mukherjee
Ms. Ishan Saha
                                                            ... for the petitioners
Mr. S.N. Mookherjee, Ld. Sr. Adv.
Mr. Srijib Chakraborty,
Mr. Subhasis Chakraborty,
Mr. Dhruv Chadha,
Mr. Amit Chowdhury
Ms. Susmita Kumari Singh,
Mr. Aditya Mondal
                                                     ... for the Respondent No.4
Mr. Debasish Kundu, Ld. Sr. Adv.
Mr. Pinaki Ranjan Chakraborty,
Ms. Susmita Sarkar
                                                        ... for the Union of India

Hearing concluded on : 23.08.2024
Judgment on : 01.10.2024

Shampa Sarkar J.:-

 1.   The petitioner No.1 is a company incorporated under the provisions of

 the Companies Act 1956. The petitioner No.2 is the senior executive of the

 petitioner No.1. In this writ petition, the rejection of the technical bid of the

 petitioners on the ground that the same was found to be technically

 unsuitable, is under challenge.
                                         2


2.   The respondent No.2 published a Request For Proposal (RFP), which

contained the notice inviting tender No. NCR-S&T-EPC-ABS-GMC-VGLJ

dated January 19, 2024, hereinafter referred to as the 'said tender'. The

description of the work was "Provision of EI based Automatic Signaling

with continuous track circuiting and other Associated works including

suitable indoor alterations in EI/RRI/PI stations enroute in GMC(Incl)-

VGLJ (Incl) section of Jhansi Division of North Central Railway",. The said

tender was in respect of an Engineering Procurement and Construction

(EPC) contract. The advertised value/the estimated cost of the project was

Rs.274,34,40,010.47/-.

3.   The tender was for a single stage two packets system, namely,

technical bid and financial bid. The last date for submission of bids was

February 27, 2024 at 12.00 noon. The petitioner No.1 participated and

deposited the earnest money to the tune of Rs.1,37,17,200/-. After

submission of the bids, the petitioner No.1 received a letter dated March

18, 2024, from the respondent No.2, that is, the Chief Signal and Telecom

Engineer-III, ALD/NCR/Subdarganj/Prayagraj, calling upon the petitioners

to submit an undertaking in an enclosed format. The letter stated that an

undertaking showing fulfillment of clause 2.2.2.1 (ii) of the RPF had to be

filed, inter alia, stating that the petitioner No.1 had undertaken at least one

eligible project of the railway sector as mentioned in clause 2.2.2.4/iii, of

value   not   less   than   35%    of       the   estimated   project   cost,   i.e.,

Rs.96,02,04,003/- and had received payment for not less than 75% of the

present contract value.
                                      3


4.   Mr. Jayanta Mitra, learned Senior Advocate for the petitioners

submitted that the said undertaking was called for in terms of the

Amendment No.6 dated December 29, 2023, incorporated by the railway

board in the standard terms and conditions. The terms and conditions of

the RFP did not require that an undertaking in the enclosed format would

have to be filed. The petitioners did not submit the purported undertaking,

but explained in detail why the petitioners were not covered by the

illustration. The petitioners explained that the amendment did not debar

the petitioners from participating in the tender. The technical eligibility of

the petitioners remained unaffected by the amendment. By the said

amendment, after clause 2.2.2.1 (ii), an illustration had been introduced.

The illustration applied in cases of receipt of money from prior eligible

projects of the railway sector, in which there was a scope for part-payment

to the contractor on procurement of goods and equipment on the basis of

an indemnity bond/bank guarantee. The prior eligible railway projects in

which the petitioners participated did not have a provision for part

payment on procurement of goods and equipments on the basis of

indemnity bond/guarantee. Thus, the petitioners received payments as a

whole, in the projects they had participated.

5.   According to the petitioners, clause 2.2.2.1 (ii) prescribed that the

bidders should have received payment of not less than 75 % of the contract

value from any prior eligible project. The newly introduced illustration by

the sixth amendment did not change the purport of clause 2.2.2.1 (ii), as it

stood prior to such amendment. The amendment only explained that if the

prospective bidders had received payment on the basis of indemnity
                                        4


bond/bank guarantee for procurement of goods and equipments from prior

projects, they would have to satisfy the tendering authorities that they had

received payments of not less than 75 % of the contract value for the

construction work as well. In other cases where such payment mode was

not prescribed by the terms of the contracts of such prior eligible projects,

as in the case of the petitioners, the illustration would not be applicable.

6.   Thus, it was contended by Mr. Mitra, that the railway authorities had

demanded such undertaking arbitrarily, only to oust the petitioners from

the bidding process. As the petitioners had not received part payment upon

furnishing indemnity bond/bank guarantee, for procurement and supply of

goods, the petitioners were required to satisfy the tendering authority that

payment amounting to 75% payment of the present contract value had

been received from a prior eligible project. The petitioners had submitted a

certificate dated June 14, 2023, issued by the Deputy Chief Signal &

Telecom Engineer (construction) South-Eastern Railways, Kharagpur,

certifying that the petitioner had carried out work in an eligible project and

received payment amounting to more than 75% of the present contract

value. On the basis of such certificate, the petitioners claimed to have

satisfied the condition set out in clause 2.2.2.1 (ii).

7.   Such explanation was forwarded to the respondent No.2 vide reply

dated April 9, 2024. Thereafter, the petitioners received an electronic mail

dated May 4, 2024, at about 12.07 with the information that their bid was

found to be technically unsuitable.

8.   Mr. Mitra urged that such communication was in violation of the

principles of natural justice. No reasons had been assigned as to why the
                                      5


technical bid was found to be technically unsuitable. The e-mail was

received at the registered office of the petitioners, at Kolkata. Before such

rejection, an opportunity of hearing should have been given to the

petitioners. Had the petitioners been given an opportunity to explain why

the sixth amendment would not be applicable in their case, the authority

could have understood that the undertaking would not be necessary. The

cancellation on the ground of non-furnishing of such undertaking, was

unfounded. The bid was cancelled on extraneous considerations and not in

terms of the tender conditions. Thus, the rejection was arbitrary, irrational

and unreasonable.

9.   Mr. Mitra submitted that the petitioner No.1 duly furnished all

necessary documents. The petitioners were singled out, only to favour the

respondent No.4. To demonstrate technical capacity, eligibility and

experience, the petitioner No. 1 was required to satisfy the authority that

the petitioner No.1 had undertaken at least one eligible project of the

railway sector as mentioned in clause 2.2.2.4/ iii of value of not less than

35 % of the estimated cost of the project and had received payment for

value not less than 75 % of the project. The certificate of eligibility

submitted by the petitioners was in respect of a contract, having value of

Rs.98,74,31,628.32/-. Out of the contract value, for the work already

carried out by the Petitioner No. 1, the Petitioner No. 1 had received

Rs.74,29,14,380/- which was more than 75% of the project value. 35 % of

the present contract value was Rs.96,02,04,003/-. The rejection of the

technical bid dated May 4, 2024, was done in a wrongful manner, without
                                       6


 taking into consideration the documents which were furnished by the

 petitioners.

10.   Mr. Mitra further submitted that the clause 2.2.2.1 (ii) should have

been followed verbatim and applied in the case of the petitioners, in order to

assess the technical eligibility of the petitioners. The illustration was an

explanation introduced only to demonstrate what was actually expected

from the bidder. Such illustration could only be applied in case of those

category of bidders who had not received part payment from a prior eligible

project for supply of goods and equipments on furnishing indemnity bond

and bank guarantee and part payment for construction. Such illustration

and the requirement to file an undertaking justifying eligibility on the basis

of the illustration, were beyond the scope of the terms and conditions of the

tender. The illustration could not have an overriding effect to the main

condition. A bidder who fulfilled the condition, was not required to submit

an undertaking demonstrating the break up of receipt of payment as per the

illustration. The illustration was not a term. It was an explanation of a

situation, under the term. The rejection of the technical bid also suffered

from non-application of mind. As per the tender terms, to demonstrate

Technical Capacity and experience, bidders were required to show that

during the five previous financial years and current financial year upto the

base month, they had the necessary qualifications to satisfy the criterions

under two separate and independent terms of the tender, inter alia:- a)

Clause 2.2.2.1(i), i.e. had received payments for construction of Eligible

Projects as mentioned in Clause 2.2.2.4(i) & (ii), the sum total of which was

more than 2.5 times the Estimated Project Cost; i.e.; Rs.685,86,00,026/-
                                        7


(Threshold Technical Capacity). In Support of such technical capacity the

bidder was required to furnish information as per Annexure II of Appendix

IA. b) Clause 2.2.2.1(ii), i.e., Undertaken at least one Eligible Project of

Railway Sector as mentioned in clause 2.2.2.4/iii. The value of such project

should not be less than 35% of the Estimated Project Cost, i.e.

Rs.96,02,04,003/- and had received payment for not less than 75% of the

contract value of the present project. In support of such technical capacity

the bidder was to furnish information as per Annexure IV of Appendix IA.

The certificate dated 14th June 2023 at page 47 of the petition

demonstrated the eligibility of the petitioner No.1 under clause 2.2.2.1 (ii).

11.   According to Mr. Mitra, in order to satisfy the eligibility of the

petitioner No.1 under clause 2.2.2.1(i), the petitioners submitted the

contract wise payment received in the past five years in Annexure II of

Appendix 1, 1A,        showing receipt of Rs.788.96 crores, which was

significantly more than the technical capacity threshold of the subject

tender. The petitioners submitted several documents, namely, a certificate

from south-eastern railway dated June 14, 2023, which showed the contract

value of eligible project was Rs.98.74 crores (more than 35% of the

estimated project cost) and also payment received of Rs.74.29 crores (more

than 75% of the contract value of the project). Annexure IV of Appendix 1A

of the bid documents showed the details of the eligible project. The eligible

project relied upon by the petitioners did not have any provision for part

payment on procurement of goods and equipment on the basis of indemnity

bond/bank guarantee. The petitioners had received a total of Rs.74.29
                                         8


crores and such payment was not referable to either any indemnity bond or

a bank guarantee.

12.   Mr. Mitra submitted that the only ground for cancellation as would be

evident    from     the   affidavit-in-opposition   filed   by    the    railway

authorities/tendering authorities, was that the petitioner No.1 had failed to

demonstrate eligibility in terms of the illustration to clause 2.2.2.1(ii) of the

RFP. Such contention of the railways was on the face of record, contrary to

the provisions of clause 2.2.2.1(ii). The illustration could not be pressed into

service by the railways, in order to whimsically reject the bid of the

petitioners, when the illustration was not applicable at all. The illustration

could neither expand nor curtail the main provision. The illustration could

at best be an explanation to the provisions of the main clause.

13.    Mr. Mitra referred to the decisions, of Aniruddha Mitra vs

Administrator-General of Bengal reported in AIR 1949 PC 244 and Ram

Gopal Sen vs Abhoya Charan Ghose and Ors. reported in AIR 1915 Cal

594 for the proposition that an illustration could not have the effect of

modifying the language of the original section of a statute. Mr. Mitra also

relied on the decisions Union of India vs. A.L. Rallia Ram, reported in AIR

1963 SC 1685 and Lalit Mohan Pandey vs Pooran Singh reported

in(2004) 6 SCC 626. According to Mr. Mitra, the other contention of the

railways that the petitioners had not received payment of at least Rs.27

crores from construction work was also baseless. Article 1.2(f) of the RFP

defined construction to include survey, investigation, design, developing,

engineering, procurement, supply of plant materials, equipment, etc. The

railways tried to create a confusion by making a distinction between the
                                         9


expressions 'construction' and 'procurement', in order to justify the rejection

of the technical bid of the petitioners. They combined the qualifications

prescribed under the illustration to clause 2.2.2.1(ii) and those under clause

2.2.2.5 of the RPF. The railways did not ever raise any dispute that the

project relied upon by the petitioners was not an eligible project. Such was

not the reason for rejection of the technical bid as per the averments in the

affidavit-in-opposition, but a statement from the bar. The railways did not

mention that the petitioners did not qualify under clause 2.2.2.1(i) of the

RFP. Eligible project was defined under clause 2.2.2.4 (i) and (ii) read with

clause 2.2.2.5(ii) A or B. Most importantly, the submissions of the

respondent No.4 were adopted by the railways at the stage of arguments,

although, the railways had never raised the question of eligibility of the

project in respect of which experience was claimed to have been acquired by

the petitioners.

14.   With regard to the submissions of Mr. S. N. Mukherjee, learned Senior

Advocate for the respondent No.4, Mr. Mitra urged that the reasons provided

by the railways in respect of their decision, must be looked into by this

court. The submissions of the added respondent were not relevant. The

respondent No.4 did not have the authority to analyse, explain, elaborate

and justify the decision of the tendering authority. The decision of the

tendering authority had to be independent, based on the clauses of the RFP

and not on the grounds which were beyond the terms and conditions of the

RFP. The contentions of the respondent No.4 were contrary to the literal

interpretation of clause 2.2.2.1(ii).
                                          10


15.   The respondent No.4 attempted to create a confusion by submitting

that to qualify under Clause 2.2.2.1(ii), the Eligible project Undertaken by

the petitioner must be one qualifying under Category 3 of Clause 2.2.2.5 of

the RFP, thus making it compulsory that payment of at least Rs.27 Crores

(approx.) on account of construction work should have been received by the

bidder. Such was not the case run by the railways. Mr. Mitra submitted that

to qualify under Clause 2.2.2.1(i), an Eligible Project of Railway Sector was

as mentioned in clause 2.2.2.4/iii, which did not require qualification as per

Category 3 under clause 2.2.2.5(ii)(A) or (B). Only for qualification under

Clause 2.2.2.1(i), an Eligible Project should be as those mentioned in clause

2.2.2.4(i) and (ii), which expressly required further qualification under

clause 2.2.2.5. The petitioner had, in fact, submitted all required forms

including Annexure-ll and Annexure-IV of Appendix IA. Thus, for a project

to be eligible under clause 2.2.2.1(ii), clause 2.2.2.5(ii) (A) or (B) was

inapplicable and accordingly the requirement of receipt of Rs. 27 crores for

construction work was also inapplicable. As per clause 2.2.2.5(i) (A) or (B),

the exclusion of supply of materials from the word 'construction' was

confined only to such contracts which were neither construction contracts

(on Turnkey basis) nor EPC contracts. The certificates produced by the

petitioners were evidence of them having qualified in an eligible project and

the works undertaken under different contracts cited in different certificates

were all in respect of Turnkey Projects/EPC contracts. Hence, the qualifying

words of clause 2.2.2.5(ii) (A) and (B) were not applicable to the petitioners

at all, for fulfilling the criterion under Clause 2.2.2.1(ii).
                                       11


16.   The term 'construction' as defined in the contract would also include

supply. The decision of the railways was ex facie contrary to the tender

terms. The issue was not with regard to interpretation of the terms, but with

regard to justification of the decision of the railways by wrongly applying

those terms, which did not have a bearing on the eligibility of the bidders.

The railways had arbitrarily rejected the bid on an incorrect reading of

clause 2.2.2.1 (ii). The decision was taken by the authorities only to favour

the respondent No.4.

17.   Mr. Debashis Kundu, learned Senior Advocate appeared on behalf of

the railway authorities, that is, the respondent Nos.1, 2 and 3. According to

Mr. Kundu, four bidders had submitted their respective bids, including the

petitioners. At a pre-bid conference, all the bidders participated. Neither any

query nor any clarification was sought for by the petitioners after meaning

thereby, the petitioners were well-acquainted with the clauses and terms

and conditions of the RFP. The tender document had two parts. The first

part was the RFP and the second part was the agreement, which was to be

signed by the successful bidder and railway authorities, after selection of the

bidder.

18.   The interpretation of the terms and conditions in the RFP and in the

agreement, were significantly different. For example, the expression

'construction' in the RFP was defined as construction and payments

received on account of construction, excluding supply of equipment.

Whereas, in the agreement, construction included supply. Reliance of the

petitioner on the definition of construction, as provided in the agreement,

was misplaced.
                                        12


19.   By the letter dated March 18, 2024, the railway authorities called

upon the petitioners to submit an undertaking in the format attached to the

letter with the project code and project name, in respect of which the

petitioners were claiming fulfilment of clause 2.2.2.1 (ii) of the RFP. It was

submitted by Mr. Kundu that in order to demonstrate technical capacity

and experience, the bidder was required to satisfy the authorities that

during the previous five financial years and in the current financial year up

to the base month, the bidder had received payments for construction of

eligible projects and the sum total thereof, was more than 2.5 times the

estimated project cost, that is, Rs.685,86,00,026/-. Reliance was placed on

clause 2.2.2.1.

20.   The clause further provided that payment of one-fourth of the

threshold capacity should have been received from the eligible project, either

in category 1 and or category 3 specified in clause 2.2.2.4 (i) and (ii). To

satisfy such eligibility, the bidder would have to also show that the bidder

had undertaken one eligible project of the railway sector as mentioned in

clause 2.2.2.4/iii of value of not less than 35 % of the estimated cost, that

is, Rs.960,204,003/- and had received payments for not less than 75% of

the present contract value, excluding payments made after adjustment of

price variation of such project. The illustration only clarified the above term.

21.   By a letter dated April 9, 2024, the petitioners refused to provide such

undertaking on the ground that the illustration as cited under clause

2.2.2.1 (ii) was not applicable. All the other participants had submitted such

undertaking, including the respondent No.4.
                                               13


22.     According to the railway authorities, the terms and conditions of the

tender document were read as a whole. The decision of the authority was

based on a composite reading of the terms and conditions of the contract

and not on the basis of the illustration. First and foremost, the writ

petitioners refused to submit the undertaking as was required from them

under    clause    2.2.2.1(ii).   On    the        ground   of   non-furnishing   of   the

undertaking, the railway authority was entitled to invoke the provisions of

clause 2.6.2 of the RFP. The clause gave the right to the railways to reject

any bid and bar a bidder from participating in any tender under the Union

Railway, for a period of 12 months from the date of such banning. The

conditions of the RFP required the petitioners to satisfy the evaluation

committee of their technical capacity under Annexure II and of having

participated in an eligible project. The tender document indicated that

emphasis     was    supplied      on   'construction'.      The    conditions   that   the

participating bidders would have to indicate that they had received 75%

payment of the present contract value solely on account of construction, and

the composite amount received for both construction and supply of goods

would not be taken into account to evaluate the technical capacity, were

clearly spelt out in the tender document.

23.     According to the railways, such requirement was incorporated in order

to ensure that a successful bidder, after having supplied the goods and

equipments (which could have been a major part) in the prior project, had

not abandoned the project without undertaking the construction work.

24.     Reliance was placed on clauses 2.2.2.1, 2.2.2.4, which dealt with the

factors for evaluation and clause 2.2.2.5, which dealt with eligible
                                         14


experience and eligible projects. Clause 2.2.2.6, Annexure II of Appendix 1A

and Annexure IV of Appendix 1A were also relied upon to demonstrate the

meaning of the expressions 'technical capacity' and 'eligible project'.

25.   Referring to clause 2.2.2.5 (ii) (B), Annexure II of Appendix 1A and

Annexure IV of Appendix 1A, Mr. Kundu submitted that construction did

not include supply of goods. Thus, payments received in respect of

constructions, were taken into consideration to evaluate the technical

capacity. The writ petitioners did not fulfil the essential terms and

conditions. The parameters which were part of the technical capacity were

not fulfilled. The railway authorities had made an enquiry in terms of clause

2.6.1 of the RPF, into the veracity of the projects relied upon by the

petitioners. The outcome of such enquiry went against the petitioners.

26.   The details of such findings and the deficiencies, had been discussed

in the affidavit-in-opposition. All the terms and conditions of the contract

were harmoniously construed by the evaluation committee to come to a

finding that the payment received by the petitioners for construction of the

prior eligible project, did not reach the eligibility threshold.

27.   Mr. Kundu submitted that the illustration was not the only reason for

rejecting the bid of the petitioners. The authorities had come to the decision

that the techno-commercial bid of the petitioners was not viable, as per their

interpretation of the terms and conditions. Two bidders were found

technically suitable amongst four. Thus, the question of singling out the

petitioners, did not arise. Another bid was also found to be techno-

commercially unsuitable.
                                       15


28.   The work involved public interest. Unless, the decision of the

authority in cancelling the technical bid of the petitioners was adverse to

public interest, the decision should not be interfered with by a writ court.

The basis for rejection was that, the petitioners had not received substantial

amount of payment from construction work in an eligible project. The

authorities laid emphasis on the construction part of the prior experience. In

terms of the various clauses of the terms and conditions of the contract,

method of evaluation of the eligible project and technical capacity were

justified. This was done to ensure that the selected bidder had completed

major portion of the construction work in such prior eligible project and had

executed the project satisfactorily. Work relating to supply of plants,

machines and equipments and the income therefrom were not the primary

eligibility criteria. The tendering authority was justified in laying stress on

the construction aspect, as per their wisdom, knowledge and expertise.

29.   Mr. Kundu relied on the following decisions:-

   a. Shilppi Constructions Contractors vs. Union of India            & Anr.

      reported in (2020) 16 SCC 498,

   b. N.G. Projects Limited vs. Vinod Kumar Jain. reported in (2022) 6

      SCC 127.

   c. Maharashtra State Electricity Distribution Company Limited vs.

      Ratnagiri Gas and Power Private Limited & Others reported in

      (2024) 1 SCC 333 .



30.   Mr. S. N. Mookherji, learned Senior Advocate appeared on behalf of

the respondent No.4 and submitted that the petitioners did not qualify for
                                       16


various reasons. The petitioners had not undertaken at least one eligible

project of the railway sector as mentioned in clause 2.2.2.4 /iii of value of

not less than 35% of the estimated project cost. The petitioners had neither

undertaken at least one eligible project of the railway sector nor had they

received payment of not less than 75% of the present contract value, for the

work of commissioning, installation etc.

31.   Mr. Mookherji submitted that clause 2.2.2.4, provided the factors and

categories for evaluation of the technical capacity. The subject work fell

within Category 3 project, of clause 2.2.2.4. The petitioners submitted a

certificate in support of their claim to have qualified the dual test as

required under clause 2.2.2.1(ii) and clause 2.2.2.5(ii). The said certificate

was not in respect of an eligible project. According to Mr. Mookherji, to

qualify technically under RFP, the petitioners were required to satisfy other

conditions. In terms of clause 2.2.2.1 (ii), the petitioners should have

undertaken at least one eligible project of the railways sector, as mentioned

in clause 2.2.2.4/iii of value of lot less than 35% of the estimated project

cost, that is Rs.96,02,04,003/- and further, should have received payments

for not less than 75% value of the present contract value.

32.   In the event, the petitioners received payment for procurement of

goods and equipment, the petitioners should have received not less than

75% payment of the present contract value under procurement of goods and

equipment as well as not less than 75% payment of the present contract

value for execution, installation and commission. In terms of clause 2.2.2.5

(ii), (B), the petitioners should have actually received cumulative payments

of more than Rs.27 crores, as payment for construction work executed
                                       17


during the last five years. Construction would not include supply, unless

such supply was in an EPC contract.

33.   As per pages 47 and 48 of the writ petition, the cost of the earlier

project undertaken by the petitioners was Rs.98,74,31,628.32/-. The total

cost of supply portion was Rs.81,55,281.54/- and the total cost of

construction was Rs.17,19,03,473.78/-. Out of total cost of supply, the

petitioners had received Rs.75,36,66,769.70/- and out of total cost of

construction, the petitioners had received Rs.4,95,74,193.22/-. Thus,

admittedly, the petitioners had received much less than the required

payment of Rs.27 crores.

34.   The petitioners admitted in their pleadings that the prior project was a

GCC contract and not an EPC one. The petitioners wrongly relied on the

definition of 'construction' in the agreement part, which was inapplicable.

The definition of 'construction' in the RFP was taken into consideration at

the time of evaluation of the bid. Clause 2.2.2.6 required the bidders to

submit their technical bids as per the format at Annexure II of Appendix 1A

and Annexure IV of Appendix 1A. Annexure II to Appendix 1A indicated that

the bidder was required to submit details of payment for construction of

eligible projects and the annexures further clarified that construction would

not include supply of goods and equipments except when such supply goods

and equipments did not form part of a turn-key construction/EPC contract.

Further, Annexure IV of Appendix 1A, made it clear that in cases of

Categories 3 and 4, payment received only in respect of construction should

be provided.
                                        18


35.   Mr. Mookherji argued that upon reading clauses 2.2.2.1, 2.2.2.5 and

Annexures II and IV of Appendix 1A, it was evident that the tender

evaluating committee wanted to ensure that the bidder, who had

undertaken an eligible project had received at least Rs.27,43,44,001/- from

construction work. The railways reserved the right to reject the bid. The

railways were within their right to invoke such provision. The interpretation

of the clauses in the bid document was best left to the wisdom of the author

of the document. The view taken by the tendering authority was a possible

view and judicial review was not permissible.

36.   The issue before this court is whether the respondent Nos.1 to 3 had

acted arbitrarily in rejecting the bid of the petitioners on the ground that the

bid was not technically suitable. Although, the petitioners claimed on the

basis of the documents furnished by them that, the technical capacity under

clause 2.2.2.1 of the Request for Proposal had been satisfied, the railway

authorities and the respondent No.4 have relied on several clauses of the

RFP and submitted that the petitioners did not meet the requirements under

various clauses of the said RFP. The disqualification was not only on the

ground of non-compliance of the illustration under clause 2.2.2.1 (ii), but for

other non-compliances as well.

37.   The evaluation of the technical capacity of the petitioners was done on

the basis of clause 2.2.2.4 and the sub-clauses thereunder. Other clauses of

the document of the RFP, including the undertakings to be given in the

format provided as annexures were also considered and the petitioners were

found technically ineligible. To demonstrate the eligibility under clause

2.2.2.1(i), the petitioners contended to have submitted contract-wise
                                           19


payment in the previous five years vide Annexure II Appendix 1A, showing

receipt of Rs.788.96 crores, which was significantly more than the threshold

technical capacity. The petitioners claimed to have submitted the relevant

documents and certificates.

38.   To demonstrate eligibility as per clause 2.2.2.1(ii) the petitioners relied

on Annexure P7 and P8 of the writ petition. The certificate issued by the

Deputy Chief Signal and Telecom Engineer (Construction) South-eastern

Railway, Kharagpur. The said certificate contained the information with

regard to the work done by the petitioners and the same is quoted below:-

  Certificate No.: S&T/Con/KGP/NSI-ROP/MRT/01                      Date: 14.06.2023

                            TO WHOM IT MAY CONCERN

  This is to certify that M/s. MRT Signals Ltd., 2, Raja Woodmount Street, Kolkata -
  700001 is a working Contractor of this Unit and the following is given:-
         1.       Name of work                 Work for provision of New Electronics
                                               Interlocking at NEKURSENI, DANTAN,
                                               LAKSHANNATH          ROAD,        JALESWAR,
                                               AMARDA ROAD, BASTA and ROPSA in
                                               connection     with    3rd    line   between
                                               Narayangarh-Bhadrak         in     Kharagpur
                                               Division of South Eastern Railway. This
                                               includes provision of Double Distant Signal
                                               in the existing Signalling installation of
                                               section prior to providing new EI.
         2.       LOA No. & Date               SER-CONST-HQ-S AND T/ST-CON-KGP-
                                               20-EI-NSI-ROP00827810034182            Dated
                                               06.04.2021
         3.       Contract                     S&T/CON/KGP/NSI-ROP/8-STN/20-
                  Agreement No. &              21/07 dated 08.09.2021
                  Date
         4.       Contract Value at            Rs. 98,74,31,628.33/- (ORIGINAL)
                  the time of award
                  of work (Original)
         5.       Revised Value of             Rs. 98,74,31,628.33/- (ORIGINAL)
                  the Contract
         6.       Date               of        06.04.2021
                  Commencement
         7.       Original date of             05.04.2023 (24 Months from the date of
                  Completion as per            issue of LOA)
                  Contract
                  Agreement
         8.       Total     payment            Rs. 74,29,14,380/- (As on 14.06.2023)
                                             20


                    made to the Firm
                    against the work
                    as on 14.06.2023
          9.        Status of Work               1. MRT has completed and Commissioned
                                                 the Double Distant work in the entire
                                                 section.
                                                 2. Station NEKURSENI commissioned on
                                                 21.04.2023
          10.       Remarks        on            Satisfactory
                    performance and
                    workmanship     of
                    the Contractor


  This certificate is issued on the request of the Firm M/s. MRT Signals Ltd. Kolkata

                                                                    VIKAS KUMAR SINGH
                                       Dy. Chief Signal & Telecom Engineer (Construction)
                                                        South Eastern Railway, Kharagpur

39.    Annexure P8 at page 48 was relied upon by the petitioners as per

clause 2.2.2.1 (ii), which is also a certificate dated June 14, 2023, issued by

the Chief signal and Telecom Engineer of South-eastern Railway.

      The certificate reads as follows:-

      "Contract Agreement No. S&T/CON/KG/ NSI-ROP/8 -STN/20-21/07,
      Dated.08/09/2021

      Name of the work: "Provision of New Electronics Interlocking at
      NEKURSENI, DANTAN, LAKSHANNATH ROAD, JALESWAR, AMARDA
      ROAD, BASTA and ROPSA in connection with 3rd line between
      Narayangarh-Bhadrak in Kharagpur Division of South Eastern Railway.
      This includes provision of Double Distant Signal in the existing
      signalling installation of section prior to providing new El."
      Name of the Contractor :            M/S.M.R.T. Signals Ltd,
         2,Raja Woodmunt street,
         Kolkata - 700001.

      Value of the Contract :            Rs 98,74,31,628.33/-
      Amount of total security Money : Rs. 4,93,71,581.41/-
      Completion Period:                24( Twenty Four ) Months i.e. up to
      05/04/2023.
      Estimate No. & Allocation:        4283/Sig/DPR/16/Modi/18 & CAP -
      1500
                                          (EBR IF )
      Authorized Signature of Contractor

                                                                   (Jai Prakash Shivaji)
                                       21


                                        Chief Signal & Telecom Engineer/Con
                                                      South Eastern Railway"

40.    Relying on the above documents, the petitioners contended that the

contract value of the eligible project was more than Rs.98 crores and out of

the said contract value, the petitioners had received more than Rs.74 crores

as    payment.    The   advertised   value   of   the   subject   tender   was

Rs.2,74,34,40,110/- and 35 % thereof, was Rs.96,02,04,003/-. The contract

value of the prior project was more than 35% of the advertised value of the

subject tender and the petitioners had received payment of more than Rs.74

crores meaning thereby, more than 75 % of the value of the project.

41.    The other contention of the petitioners was that the illustration would

not be applicable as the prior project executed by the petitioners were

eligible projects and there was no separate mode of payment on

procurement of goods and equipment on the basis of an indemnity bond or

bank guarantee.

42.    Reliance was placed on the payments clause of such prior project,

which is quoted below:-

      "No advance payment will be made by Railways to the Contractor.
      Payment shall be made quarterly after satisfactory completion of
      maintenance period of each quarter on submission of monthly audit
      reports/Site Register. The Measurement Book and Bills will have to be
      signed by Power of Attorney holders of the contractor. The power of
      attorney has to be submitted at the time of Measurement Book entry.
      In case the contractor fails to maintain (due to any reason whatsoever)
      no payment shall be made. However all penalty on the contractor shall
      continue as per the penalty clause mentioned in clause-F of Special
      Condition of Contract & shall be recovered even after termination of the
      contract and the same shall be recovered from any other bill or Security
      Deposit against this or other contracts and from other sources."

43.    Main thrust of the argument of Mr. Mitra, learned Senior Advocate

was that the illustration could not restrict the applicability of the main
                                         22


provision of clause 2.2.2.1 (ii). The petitioners had received more than 75%

of the present contract value, from a prior project.

44.    To counter such contention, the railways categorically explained the

reasons as to why the petitioners were not found to be technically eligible. In

the affidavit-in-opposition, the railways considered the documents relied

upon by the petitioners, which have been quoted hereinabove, and recorded

their reasons for not finding the contents of the said documents to be

adequate qualification, to cross the technical capacity threshold.

45.    The relevant paragraphs of the affidavit-in-opposition, in this regard

are quoted below:-

      "(d) the writ petitioner, in support of the tender, submitted the
      credentials of the two works being ;-
      (A) Provision for new electronic interlocking at Nekurseni, Dantan,
      Lakshannath Road, Jaleswar, Rajghat, Amarda Road, Basta, Ropsa in
      connection with 3rd line between Narayangarh-Bhadrak in Kharagpur
      Division of South Eastern Railway and against the said project, the
      petitioner had shown receipt of Rs.78.32 crores. But on verification
      from petitioner's said client, it was found that out of the total cost of
      work being Rs.98,74,31,628.32/-, the total cost for supply portion is
      Rs.81,55,281.54/-       and      the    total    cost     for   execution/
      installation/commissioning is Rs.17,19,03,473.78/-. Out of the total
      cost for supply, the petitioner was paid Rs.75,36,66,769.70/- being
      92.41% of the total cost for supply and out of the aforesaid total cost
      for execution/ installation/commissioning, the petitioner was paid
      Rs.4,95,74,193.22/- being 28.84% of the total cost for execution/
      installation/commissioning, which practically the total cost on
      construction work.
      (B) Provisions for new electronic interlocking at Haldipada, Balasore,
      Nilgiri Road, Khantapara, Bahanagabazar, Soro, Sabira and Markona in
      connection with 3rd line between Narayangarh - Bhadrak in Kharagpur
      division of SouthEastern Railways. Against the said project, the
      petitioner had shown receipt ofRs.79.16 Crore. But on verification from
      the petitioner's said client it was revealed that the total cost of work in
      the said project is Rs. 1044038654.74/-, out of which, cost of supply
      portion isRs.816399486.60/- and cost for execution/ installation/
      commissioning is Rs. 227639168.20/- and the petitioner received Rs.
      730663729.70/- being 89.50% of the total cost for supply and received
      Rs.60967119,60/-,       being     28.61%      of  the    total   cost   for
                                             23


      execution/installation /commissioning, which actually the payment on
      construction."

46.    With regard to the work of interlocking at Nekurseni, Dantan it was

found that out of the total cost for supply, the petitioners were paid

Rs.75,36,66,769.70/- being 92.41% of the total cost for supply and out of

the total cost for execution, installation and commissioning, the petitioners

were paid Rs.4,95,74,193.22/- being 28.84% of the total cost. Thus, the

total cost on construction was found to be far less than the required

percentage.

47.    With regard to the construction of new interlocking at Haldipara,

Balasore,     Nilgiri,   it    was   revealed       that     the   petitioners   received

Rs.60967119.60/- that is, 28.61% of the total cost, for execution,

installation and commission. The authorities were of the view that the

payment     received     for   execution,    installation      and   commission     were

practically the cost received for construction work undertaken by the

petitioners in each of these projects, and the amount received was far less

than the requirement under the RFP, that is, 75% value of the present

contract.

48.    The authorities were of the firm view that, the petitioners could not

satisfy the tender evaluating authority that they had undertaken at least one

eligible project of the railway sector as mentioned in the RFP, of value of not

less than 35% of the estimated project cost and had received the payment of

not less than 75% of the present contract value under execution, installation

and    commission,       which   was    an       essential    requirement,   specifically

mentioned in the different clauses as well as the prescribed formats at
                                         24


Appendix 1A and Annexures thereto. As the work was of high priority,

relating to public safety, the requirement of execution of substantial

construction work including survey, investigation, design, development,

engineering, installation, processing, fabrication, testing and commissioning

of railway projects, was an essential condition of the tender.

49.    Mere supply of goods was not sufficient for selection of the bidder for

the project. The relevant clauses of the RFP were to be construed as a whole,

to    understand   the   requirements    of   the   authorities.   Experience   in

construction had been given a primacy in all of such clauses and the railway

authorities had laid great emphasis on such requirement. Further

opportunity was given to the petitioners by a letter dated 18th March, 2024,

to provide a breakup of the receipt of payment for supply and for

construction. The petitioners neither submitted the breakup nor the

undertaking, although, all the other three bidders had done so. Two bidders

qualified in the technical round and two did not. The bids of the petitioners

and another bidder were found to be technically not viable.

50.    The fact that the petitioners did not submit the breakup and instead

responded by saying that the illustration would not be applicable, is a

violation of the requirements. The tendering authority was the supreme

authority to decide how the clauses should be interpreted. The bidders

would have to satisfy the tender evaluation committee with relevant records

and documents. The tendering authority had acted within its jurisdiction to

require the petitioners to furnish the undertaking and non-compliance of

such instruction, could well be a ground for the authorities to disqualify the

petitioners.
                                        25


51.    The relevant clauses of the R.F.P. relating to eligibility requirements of

the bidders are extracted below:-

      "2.2.2 Qualification requirements of Bidders: To be eligible for
      Qualification an individual Bidder or a Consortium/Joint Venture as
      whole as per clause 2.1.11(c), shall fulfil the following conditions of
      eligibility:
      2.2.2.1 Technical Capacity- For demonstrating Technical Capacity and
      experience (the "Technical Capacity"), the Bidder shall, during the last
      5(five) previous financial Years and the current financial year up to the
      Base month(not to be read with para-2.1.13).

      (i)have received payments for construction of Eligible Project(s), or has
      undertaken construction works by itself in a PPP project, such that the
      sum total thereof, as further adjusted in accordance with clause 2.2.2.4
      (i) & ii), is more than 2.5 (two and half) times the Estimated Project
      Cost i.e. Rs 685,86,00,026/- (Rs Six Eight Five Crore Eighty Six Lakhs
      and Twenty Six only) (the "Threshold Technical Capacity").
      Provided that at least one fourth of the Threshold Technical Capacity
      shall be from the Eligible Projects in Category 1 and/ or Category 3
      specified in Clause 2.2.2.4 (i) & (ii).

      (ii) Undertaken at least one Eligible Project of Railway Sector as
      mentioned in clause 2.2.2.4/iii of value of not less than [35% (thirty
      five) per cent] of the Estimated Project Cost i.e. Rs 960204003/- (Rs.
      Ninety Six Crores Two Lakhs Four Thousand and Three only) and have
      received payments for not less than 75% (seventy-five) per cent value of
      present Contract Value(excluding the payment made for adjustment of
      Price variation (PVC), if any) of such project.
      Illustration for received payments for not less than 75(seventy-five)
      percent:
      For contract wherein there is provision for part payment on
      'procurement of goods and equipment' on basis of indemnity bond
      /Bank Guarantee. In all such contract received payments for not less
      than 75(seventy-five) percent value of present Contract Value payment'
      means not less than 75% payment received under 'procurement of
      goods and equipment' as well as not less than 75% payment received
      under 'execution/installation/commissioning'

      [Note:- For composite works of New lines, Guage Conversion, Doubling,
      3rd line, 4th line etc. with Railway electrification and/or Signalling and
      telecommunication works..."

52.    The work falls under category 3 project, of clause 2.2.2.4. Clause

2.2.2.4 is quoted below:-

       "2.2.2.4Categories and factors for evaluation of Technical Capacity:
                                   26


Subject to the provisions of Clause 2.2.2, the following categories of
experience would qualify as Technical Capacity and eligible experience
(the "Eligible Experience") in relation to eligible projects as stipulated
in Clauses (i) and 2.2.2.5 (ii) (the "Eligible Projects"):
Category 1:Project experience on Eligible Projects in Railways sector
that qualify under Clause 2.2.2.5 (i)
Category 2:Project experience on Eligible Projects in core sector that
qualify under Clause 2.2.2.5 (ii)
Category 3:Project experience on Eligible Projects in Railways sector
that qualify under Clause 2.2.2.5 (ii)
Category 4:Project experience on Eligible Projects in core sector that
qualify under Clause 2.2.2.5 (ii)
(i)   In case the Bidder has experience across different categories,
      the experience for each category would be computed as per
      weight of following factors to arrive at its aggregated Eligible
      Experience:
       Category       Project    experience    on   Eligible   Factors
                      Projects
       1              Project in Railway sector that qualify   1
                      under Clause 2.2.2.5(i)
       2              Project in core sector that qualify      0.75
                      under Clause 2.2.2.5 (i)
       3              Project in Railways sector that          1
                      qualify under Clause 2.2.2.5 (ii)
       4              Project in core sector that qualify      0.75
                      under Clause 2.2.2.5(ii)

(ii)   The Technical capacity in respect of an Eligible Project situated
       in a developed country which is a member of OECD shall be
       further multiplied by a factor of 0.5 (zero point five) and the
       product thereof shall be the Technical capacity for such Eligible
       Project.
(iii)  For the purpose of this RFP:
(iv)   Railway& Core Sector is defined as under:
  Railway & Core Sector is defined as under:
(i)    Railways sector would deemed to include S&T work involving
indoor and outdoor work like Relay based interlocking work or
Electronic interlocking work or colour light signaling work or
Automatic Signalling work or Intermediate Block Signalling work or
Track circuiting work (using any AFTCs or any Axle Counters or DC
track circuits) involving Indoor & outdoor work for Indian
Railways/Metro/Suburban Transit/High Speed Railway executed as a
standalone work or as part of composite work. In case of above S&T
work executed in composite work only relevant S&T work shall be
considered for evaluation.
(ii)   Core     sector     would      be     deemed       to     include
Railways/Power/Telecom/ Defence/Ports/Airports/ Metro Rail/ Oil/
Gas pipeline and highways.
(iii)  The successful bidder shall submit an undertaking from RDSO
approved MSDAC OEM covering supply of the equipment, installation,
                                         27


      testing and commissioning by the same RDSO approved source
      including after sales support required during the warranty period and
      also to confirm compliance with extant RDSO guidelines and to meet
      contract specific requirements before supply of equipment
      undertaken. The above undertaking (refer Appendix 1A Annexure-VIII)
      shall be submitted by bidder to Railway before supply of equipment,
      failing which materials will be rejected."

53.    Clause 2.2.2.1 (i) also lays emphasis on construction. The proviso is

relevant in this regard. The petitioners, were required to satisfy clause

2.2.2.1 (i), 2.2.2.1 (ii), and clause 2.2.2.5 (ii) and 2.2.2.6. In terms of clause

2.2.2.1 (ii), the petitioners were required to undertake at least one eligible

project of the railway sector as mentioned in clause 2.2.2.4/iii of value not

less than 35% of the estimated project cost, that is, Rs.96,02,04,003/- and

further should have received more payments of not less than 75% value of

the present contract value. As the authorities found that the petitioners

received more payment for procurement and supply and less payment for

construction, and that the payment received for construction was negligible

compared to the present contract value, the authority thought it fit to

disqualify the petitioners, inter alia, on the ground that the payment

received from construction indicated that the petitioners did not have the

required technical qualification.

54.   Clause 2.2.2.5 deals with eligible experience and eligible project under

each category. Clause 2.2.2.5 (ii) B, which is relevant in this regard is

quoted below:-

      "B. For Railway electrification works: the Bidder should have received
      cumulative payments from its client(s) for construction works
      executed, fully or partially, during the last 5 (five) previous financial
      Years and the current financial year up to the Base month (not to be
      read with para-2.1.13), and only the amounts (gross) actually
      received, during such years shall qualify for purposes of computing
      the Technical Capacity. However, receipt of less than [Rs.
                                        28


       274344001/- (Rs. Twenty Seven Crore Forty Three Lakh Forty Four
       Thousand and One Only)] shall not be reckoned as receipts/execution
       of Eligible projects. For the avoidance of doubt, construction work
       shall not include supply of goods or equipment except when such
       goods or equipment form part of a turn-key construction
       contract/EPC contract for the project.]"

55.    Clause 2.2.2.6 is quoted below :-

       "2.2.2.6 Submission in support of Technical Capacity

       (i)The Bidder should furnish the details of Eligible Experience for the
       last 5 (five) previous Financial Years and the current financial year up
       to the Base month (not to be read with para-2.1.13).

       (ii)The Bidder must provide the necessary information relating to
       Technical Capacity as per format at Annex-II of Appendix-IA.

       (iii) The Bidder should furnish the required Project-specific
       information and evidence in support of its claim of Technical Capacity,
       as per format at Annex -IV of Appendix-IA."

56.    Clause 2.2.2.5 (ii) (B) required the petitioners to have actually received

cumulative payments for more than Rs.27,43,44,001/-, as payments for

construction work during the last five years, which did not include supply.

This according to the authorities was also an essential requirement.

57.    Clause 2.6 deals with the verification and disqualification clause and

under clause 2.6.1, the authority reserved the right to verify the statements,

information and documents submitted by the bidder. In this case, the

authorities verified the documents and the break-up of the payments

received in the prior projects. Upon ascertaining that the amount received

for construction was much below the requirement in the present RFP, the

petitioners' bid was found to be technically unsuitable.

58.    The relevant provision of clause 2.6.1 is quoted below:-

      2.6 Verification and Disqualification
      2.6.1 The Authority reserves the right to verify all statements,
      information and documents submitted by the Bidder in response to the
                                             29


      RFP and the Bidder shall, when so required by the Authority, make
      available all such information, evidence and documents as may be
      necessary for such verification. Any such verification or lack of such
      verification, by the Authority shall not relieve the Bidder of its
      obligations or liabilities hereunder nor will it affect any rights of the
      Authority there under."


59.    Under Clause 2.6.2 the authority reserved the right to reject any bid

and bar the bidder from submission of bids in any works/ service tender

issued by the Indian Railway for a period of 12 months from the date of

banning, on two grounds. In this case, ground 'b' is relevant, which is

quoted below:

      "(b) the Bidder does not provide, within the time specified by the
      Authority, the supplemental information sought by the Authority for
      evaluation of the Bid.
      Such misrepresentation/ improper response shall lead to the
      disqualification of the Bidder. If the Bidder is a Consortium/Joint
      Venture, then the entire Consortium/Joint Venture and each member
      of the Consortium/Joint Venture may be disqualified/ rejected. If such
      disqualification/rejection occurs after the Bids have been opened and
      the lowest Bidder gets disqualified / rejected, then the Authority
      reserves the right to annul the Bidding Process and invites fresh Bids."


60.    In this case, the bidder did not provide the supplemental information

sought for by the authorities, for evaluation of the bid.

61.    Annexure II Appendix 1A mentions the information to be given by the

bidder in support of the technical capacity. The table is set out for

convenience.

                                         "ANNEX-II
                             Technical Capacity of the Bidder
                 (Refer to Clauses 2.2.2.1, 2.2.2.4 and 2.2.2.6 of the RFP)
        Bidder       Project Code      Categor      %        Experience       Technical
        type                           y            shar     (Equivalent      capacity
        #                                           e        Rs. Crore)
                                                             Payments         Value     of
                                                             received for     self-
                                                             constructio      constructio
                                                             n of             n Eligible
                                             30


                                                           Eligible         projects in
                                                           Projects in      Categories
                                                           Categories       1 & 2 duly
                                                           3 & 4 duly       multiplied
                                                           multiplied       by    factor
                                                           by factor        mentioned
                                                           mentioned        in clause
                                                           in clause        2.2.2.4(i)
                                                           2.2.2.4(i)
        (1)          (2)             (3)           (4)     (5)        (6)   (7)=4*0.5
                                                                            (for
                                                                            OECD)/1
                                                                            (non)
                                                                            OECD)
        Single       a
        entity       b
        Bidder
        Or           c
        Member       d
        s of the
        Consorti     e
        um/Join      f
        t
        Venture
                                       Aggregate Technical capacity=



62.   As per the Annexure II, under the column Technical Capacity, the

bidder was required to mention payments received for construction of

eligible projects in category 3 and 4, duly multiplied by the factor mentioned

in clause 2.2.2.4(i).

63.   Annexure IV, Appendix 1A is quoted below :-

                                                                     Particulars of the
                   Item                    Refer Instruction
                                                                          Project
                    (1)                            (2)
                                                                            (3)
      Tile & nature of the project
                Category                          5
        Year-wise (a) payments
       received for construction,
                   Or
           (b) expenditure on                     6
          construction works
       undertaken by itself in a
               PPP project.
          Entity for which the
                                                  7
        project was constructed
                                        31


               Location
              Project cost                   8
                Date of
                                             9
      completion/commissioning
       Equity shareholding (with
      period during which equity             10
               was held)
        Whether credit is being
         taken for the Eligible
                                             16
      Experience of an Associate
               (Yes/No)


64.    Instructions 1, 6 and 9 to the bidders are quoted below:-

      "1. Bidders are expected to provide information in respect of each
      Eligible Projects in this Annex. The projects cited must comply with the
      eligibility criteria specified in Clause 2.2.2.5 of the RFP, as the case
      may be. Information provided in this section is intended to serve as a
      backup for information provided in the Bid. Bidders should also refer to
      the Instructions below.
      6.       The total payments received and/ or expenditure incurred on
      construction works undertaken by itself in a PPP project are to be
      stated for each Eligible Project in Annex-IT of this Appendix-IA. The
      figures to be provided here should indicate the break-up for last 5 (five)
      previous Financial Years & the current financial year upto the base
      month (not to be read with para-2.1.13). For Categories 1 and 2,
      expenditure on construction of the project by the Applicant itself
      should be provided, but only in respect of projects having an estimated
      capital cost exceeding the amount specified in Clause 2.2.2.5 (i)/(c). In
      case of Categories 3 and 4, payments received only in respect of
      construction should be provided, but only if the amount received
      exceeds the minimum specified in Clause 2.2.2.5 (ii). Receipts for
      construction works should only include capital expenditure, and
      should not include expenditure on repairs and maintenance.
      9.       For Categories 1 and 2, the date of commissioning of the
      project, upon completion, should be indicated. In case of Categories 3
      and 4, date of completion of construction should be indicated. In the
      case of projects under construction, the likely date of completion or
      commissioning, as the case may be, shall be indicated."

65.    As per instruction 6, the total payment received and/or expenditure

incurred on construction work undertaken for each eligible project was to be

provided. In case of categories 3 and 4, (in this case category 3), payments

received only for construction work, were to be provided.
                                       32


66.   Instruction 9 required that in case of categories 3 and 4, date of

completion of construction should be indicated. In case of projects under

construction, the likely date of completion or commissioning as the case

may be, should be indicated.

67.   Thus, from a conjoint reading of the provisions of the RFP, which have

been quoted below hereinabove, as also the provisions of the Appendix 1A

and the annexures thereto, it is evident that the authorities had given

importance to the experience of the bidders in construction works

undertaken in the eligible project. On verifying the documents supplied by

the petitioners, the authority made an enquiry and discovered that the

break-up of the payments received indicated that a minuscule portion of the

payment was in respect of construction work. When the petitioners were

asked to explain the same by providing an undertaking, the petitioners

refused to do so. Thus, the authorities decided to disqualify the petitioners

upon an interpretation of the clauses and the essential conditions. The

question of singling out the petitioners does not arise because another

person was also found to be ineligible in the technical round.

68.   In this case, the power of judicial review cannot be invoked to set

aside the decision of the tendering authority on the ground that the

interpretation of the clauses were either faulty or because another view was

also possible. The court cannot scan the RFP with a magnifying glass to

assess whether another interpretation of the terms and conditions was

available. Some play in the joints should be permitted to the government in

commercial matters. The court is not an appellate authority. The case of the

petitioners is based on the interpretation of the clauses and this court does
                                         33


not find perversity in the decision of the authorities. The authorities did not

act on any extraneous considerations, but on its own interpretation of the

bid document. The experts who authored the document interpreted the

same as per their wisdom, understanding and requirements.

69.    In Silppi Constructions Contractors vs. Union of India, reported in

(2020) 16 SCC 489, the Hon'ble Apex Court held as follows:-

      "19. This Court being the guardian of fundamental rights is duty bound
      to interfere when there is arbitrariness, irrationality, mala fides and
      bias. However, this Court in all the aforesaid decisions has cautioned
      time and again that courts should exercise a lot of restraint while
      exercising their powers of judicial review in contractual or commercial
      matters. This Court is normally loathe to interfere in contractual
      matters unless a clear-cut case of arbitrariness or mala fides or bias or
      irrationality is made out. One must remember that today many public
      sector undertakings compete with the private industry. The contracts
      entered into between private parties are not subject to scrutiny under
      writ jurisdiction. No doubt, the bodies which are State within the
      meaning of Article 12 of the Constitution are bound to act fairly and are
      amenable to the writ jurisdiction of superior courts, but this
      discretionary power must be exercised with a great deal of restraint and
      caution. The Courts must realize their limitations and the havoc which
      needless interference in commercial matters can cause. In contracts
      involving technical issues the courts should be even more reluctant
      because most of us in judges' robes do not have the necessary expertise
      to adjudicate upon technical issues beyond our domain. As laid down
      in the judgments cited above the courts should not use a magnifying
      glass while scanning the tenders and make every small mistake appear
      like a big blunder. In fact, the courts must give "fair play in the joints"
      to the government and public sector undertakings in matters of
      contract. Courts must also not interfere where such interference will
      cause unnecessary loss to the public exchequer.
      20. The essence of the law laid down in the judgments referred to above
      is the exercise of restraint and caution; the need for overwhelming
      public interest to justify judicial intervention in matters of contract
      involving the State instrumentalities; the courts should give way to the
      opinion of the experts unless the decision is totally arbitrary or
      unreasonable; the court does not sit like a court of appeal over the
      appropriate authority; the court must realise that the authority floating
      the tender is the best judge of its requirements and, therefore, the
      court's interference should be minimal. The authority which floats the
      contract or tender, and has authored the tender documents is the best
      judge as to how the documents have to be interpreted. If two
      interpretations are possible then the interpretation of the author must
                                         34


      be accepted. The courts will only interfere to prevent arbitrariness,
      irrationality, bias, mala fides or perversity. With this approach in mind
      we shall deal with the present case."

70.    In the decision of Montecarlo Limited vs. National Thermal Power

Corporation Limited, reported in (2016) 15 SCC 272, the Hon'ble Apex

Court held that the tender inviting authority was the best person to

understand and appreciate its requirements. The tendering authority had

the freedom to enter into contracts.


71.    In Jagdish Mandal v. State of Orissa reported in (2007) 14 SCC

517 the Hon'ble Apex Court held as follows:-

      "22. ... A contract is a commercial transaction. Evaluating tenders and
      awarding contracts are essentially commercial functions. Principles of
      equity and natural justice stay at a distance. If the decision relating to
      award of contract is bona fide and is in public interest, courts will not,
      in exercise of power of judicial review, interfere even if a procedural
      aberration or error in assessment or prejudice to a tenderer, is made
      out."

72.    In Afcons    Infrastructure     Ltd. v. Nagpur   Metro    Rail   Corpn.

Ltd. reported in (2016) 16 SCC 818, the Hon'ble Apex Court held as

follows:-

      "15. We may add that the owner or the employer of a project, having
      authored the tender documents, is the best person to understand and
      appreciate its requirements and interpret its documents. The
      constitutional courts must defer to this understanding and
      appreciation of the tender documents, unless there is mala fide or
      perversity in the understanding or appreciation or in the application of
      the terms of the tender conditions. It is possible that the owner or
      employer of a project may give an interpretation to the tender
      documents that is not acceptable to the constitutional courts but that
      by itself is not a reason for interfering with the interpretation given."
                                        35


73.    In National High Speed Rail Corpn. Ltd. v. Montecarlo Ltd. and

Anr. reported in (2022) 6 SCC 401, the Hon'ble Apex Court held as

follows:-

      "22. ..... whether a bidder satisfies the tender condition is primarily
      upon the authority inviting the bids. Such authority is aware of
      expectations from the tenderers while evaluating the consequences of
      non-performance. In the tender in question, there were 15 bidders.
      Bids of 13 tenderers were found to be unresponsive i.e. not satisfying
      the tender conditions. The writ petitioner was one of them. It is not the
      case of the writ petitioner that action of the Technical Evaluation
      Committee was actuated by extraneous considerations or was mala
      fide. Therefore, on the same set of facts, different conclusions can be
      arrived at in a bona fide manner by the Technical Evaluation
      Committee. Since the view of the Technical Evaluation Committee was
      not to the liking of the writ petitioner, such decision does not warrant
      for interference in a grant of contract to a successful bidder.
      ***

***

48. Even while entertaining the writ petition and/or granting the stay which ultimately may delay the execution of the Mega projects, it must be remembered that it may seriously impede the execution of the projects of public importance and disables the State and/or its agencies/instrumentalities from discharging the constitutional and legal obligation towards the citizens. Therefore, the High Courts should be extremely careful and circumspect in exercise of its discretion while entertaining such petitions and/or while granting stay in such matters. Even in a case where the High Court is of the prima facie opinion that the decision is as such perverse and/or arbitrary and/or suffers from mala fides and/or favouritism, while entertaining such writ petition and/or pass any appropriate interim order, High Court may put to the writ petitioner's notice that in case the petitioner loses and there is a delay in execution of the project due to such proceedings initiated by him/it, he/they may be saddled with the damages caused for delay in execution of such projects, which may be due to such frivolous litigations initiated by him/it. With these words of caution and advise, we rest the matter there and leave it to the wisdom of the Court(s) concerned, which ultimately may look to the larger public interest and the national interest involved."

74. In the matter of Uflex Ltd. vs Government of Tamil Nadu and Ors.

decided in Civil Appeal No. 4862-4863 of 2021, the Hon'ble Apex Court held as follows:-

36
"1. The enlarged role of the Government in economic activity and its corresponding ability to give economic 'largesse' was the bedrock of creating what is commonly called the 'tender jurisdiction'. The objective was to have greater transparency and the consequent right of an aggrieved party to invoke the jurisdiction of the High Court under Article 226 of the Constitution of India (hereinafter referred to as the 'Constitution'), beyond the issue of strict enforcement of contractual rights under the civil jurisdiction. However, the ground reality today is that almost no tender remains unchallenged. Unsuccessful parties or parties not even participating in the tender seek to invoke the jurisdiction of the High Court under Article 226 of the Constitution. The Public Interest Litigation ('PIL') jurisdiction is also invoked towards the same objective, an aspect normally deterred by the Court because this causes proxy litigation in purely contractual matters.
2. The judicial review of such contractual matters has its own limitations. It is in this context of judicial review of administrative actions that this Court has opined that it is intended to prevent arbitrariness, irrationality, unreasonableness, bias and mala fide. The purpose is to check whether the choice of decision is made lawfully and not to check whether the choice of decision is sound. In evaluating tenders and awarding contracts, the parties are to be governed by principles of commercial prudence. To that extent, principles of equity and natural justice have to stay at a distance.
3. We cannot lose sight of the fact that a tenderer or contractor with a grievance can always seek damages in a civil court and thus, "attempts by unsuccessful tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted.
***
40. We must begin by noticing that we are examining the case, as already stated above, on the parameters discussed at the inception. In commercial tender matters there is obviously an aspect of commercial competitiveness. For every succeeding party who gets a tender there may be a couple or more parties who are not awarded the tender as there can be only one L-1. The question is should the judicial process be resorted to for downplaying the freedom which a tendering party has, merely because it is a State or a public authority, making the said process even more cumbersome. We have already noted that element of transparency is always required in such tenders because of the nature of economic activity carried on by the State, but the contours under which they are to be examined are restricted as set out in Tata Cellular26 and other cases. The objective is not to make the Court an appellate authority for scrutinizing as to whom the tender should be awarded. Economics must be permitted to play its role for which the tendering authority knows best as to what is suited in terms of technology and price for them."
37

75. The Hon'ble Apex Court in the matter of N.G. Projects Limited versus Vinod Kumar Jain and Others reported in (2022) 6 SCC 127 held as follows:-

"22. The satisfaction whether a bidder satisfies the tender condition is primarily upon the authority inviting the bids. Such authority is aware of expectations from the tenderers while evaluating the consequences of non-performance. In the tender in question, there were 15 bidders. Bids of 13 tenderers were found to be unresponsive i.e. not satisfying the tender conditions. The writ petitioner was one of them. It is not the case of the writ petitioner that action of the Technical Evaluation Committee was actuated by extraneous considerations or was mala fide. Therefore, on the same set of facts, different conclusions can be arrived at in a bona fide manner by the Technical Evaluation Committee. Since the view of the Technical Evaluation Committee was not to the liking of the writ petitioner, such decision does not warrant for interference in a grant of contract to a successful bidder.
23. In view of the above judgments of this Court, the writ court should refrain itself from imposing its decision over the decision of the employer as to whether or not to accept the bid of a tenderer. The Court does not have the expertise to examine the terms and conditions of the present day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands, rather the Court should examine as to whether the decision- making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a mala fide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the State and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived 38 of the infrastructure for which the present day Governments are expected to work."

76. Under such circumstances, the writ petition is dismissed. Interim order stands vacated.

77. There will be no order as to costs.

78. Parties are directed to act on the server copy of this judgment.

(Shampa Sarkar, J.) Later:-

Learned Advocate for the petitioner prays for stay of operation of the judgment.
The prayer is considered and rejected.
(Shampa Sarkar, J.)