Section 9 in Parambikulam-Aliyar Project (Regulation of Water-Supply) Rules, 1994
9. Submission of fortnightly reports.
- The Controlling Officer shall submit a fortnightly report containing the extract of water readings to the Chief Engineer (Irrigation) in the Form appended to these rules: -AppendixForm(See rule 9)Daily Water Report of thirumurthi Reservoir[To be submitted to Chief Engineer (Irrigation), fortnightly]| Date | Water level | Storage in M. Cft. | Increase (+) or decrease (-) high level inMcft. | Through high canal | Through common canal | Through the Dhali Channel system | Through spillway river sluice | Seepage | Total |
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) |
| (inflow in Mcft.) | (Rainfall in mm) | ||||||||
| From contour canal | Rom Palar catchment | Total | Tail end readings PMC Udumalpet canal | Palladam | Pongalur | Udumalpet | Dharapuram | Kundadam | Sultanpet | Kangeyam |
| (11) | (12) | (13) | (14) | (15) | (16) | (17) | (18) | (19) | (20) | (21) |
| Outflow in M.Cft. | ||||||||||