State of Bihar - Section

Section 12 in Bihar Electricity Regulatory Commission (Demand Side Management) Regulations, 2014

12. Approval of DSM programme Document.

- 12.1 Prior to implementing any DSM programme, Distribution Licensee must obtain approval of the Commission.
12.2Each Programme Document shall include the following:
(i)Description of the programme;
(ii)Objective and rationale for the programme;
(iii)Consumer segments and estimated level of participation;
(iv)Estimate of baseline;
(v)Assessment of programme in line with Cost Effectiveness Guidelines issued by the Commission;
(vi)Mechanism for recovery of cost and performance incentives;
(vii)Marketing, delivery strategy and Implementation schedule;
(viii)Implementation mechanism e.g. Energy Service Companies, DSM Bidding, DSM Resource Acquisition, etc;
(ix)Monitoring and evaluation plan; and
(x)Plan for Training/ Seminars/ Workshops to increase consumer awareness.
12.3The Commission shall approve a DSM program if it is in line with the objectives set out in Section-3 of the Regulations. The Commission may direct modifications to proposed or on-going programmes to ensure consistency with the DSM Objectives. However, the Commission shall allow Distribution Licensee adequate time to notify such activities.