Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Orissa High Court

An Application Under Article 4 Of The ... vs General Manager on 24 September, 2025

Author: S.K. Sahoo

Bench: S.K. Sahoo

           IN THE HIGH COURT OF ORISSA: CUTTACK

                 Writ Appeal No. 34 of 2015

An application under Article 4 of the Orissa High Court Order,
1948 read with Clause 10 of the Letters Patent Act, 1992 read
with Chapter III Rule 6 of the Rules of the High Court of Orissa,
1948.
                          ----------------------


    Gadadhara Biswal
    and others                    .........                    Appellants


                               -Versus-


    General Manager,
    Jagannath Area
    Mahanadi Coal Fields
    Ltd., Talcher,
    Angul and another             .........                    Respondents



        For Appellants:             -      Mr. S.P. Mishra
                                           (Senior Advocate)
                                           Mr. Soumya Mishra
                                           Ms. Sakshi Rout


        For Respondents:            -      Mr. K.M. Nataraj, A.S.G.I.
                                           Mr. Pitambar Acharya
                                           (Advocate General)
                                           Mr. Rakesh Sharma
                                           Mr. Soumyajit Pani
                                           Mr. Debraj Mohanty

                          ----------------------




Writ Appeal No.34 of 2015                               Page 1 of 135
         P R E S E N T:


                    THE HONOURABLE MR. JUSTICE S.K. SAHOO

                                                      AND

                   THE HONOURABLE MR. JUSTICE S.S. MISHRA

        ---------------------------------------------------------------------------------------------------
        Date of Hearing: 10.09.2025                         Date of Judgment: 24.09.2025
        ---------------------------------------------------------------------------------------------------

S.K. SAHOO, J.           "All is well that ends well" is not just a play written

        by William Shakespeare, the greatest English playwright but the

        proverb which signifies that if the final outcome of a situation is

        positive, then any previous struggles, setbacks, or difficulties are

        considered unimportant.

                         This case portrays a legal battle between the two

        parties which started much before 2004 when the homestead

        and agricultural lands of the Appellants situated in village

        Hensamul under Talcher Tahasil in Angul district were acquired

        under the Coal Bearing Areas (Acquisition and Development) Act,

        1957 (hereinafter referred to as „CBA Act‟) and the Land

        Acquisition Act, 1984 (hereinafter referred to as „LA Act‟) and

        vested to the Central Government and divested in favour of

        Mahanadi Coalfields Limited, Talcher (hereinafter referred to as

        „MCL‟).




        Writ Appeal No.34 of 2015                                                   Page 2 of 135
             The land losers are the Appellants who claimed that

in spite of acquisition of their lands, benefits under Odisha

Resettlement and Rehabilitation Policy, 2006 (hereafter „R & R

Policy,   2006‟)   were   not   provided    to   them      fully   by   the

Respondents causing injustice to them, whereas the case of the

Respondents is that even though the Appellants have been

provided with benefits under R & R Policy, 2006, they are

creating trouble in not vacating the houses and homestead lands

in the acquired area.

            The legal battle between the haves and have-nots

brings forth as to how economic inequality creates significant

barriers to justice for impoverished individuals and communities.

The   Government     formulates    the     policies   to    achieve     the

constitutional goals set out in Part IV of the Constitution of India

in the form of Directive Principles of State Policies and an

attempt is made to bridge the gaps between the haves and

have-nots. Those who are charged with the duty of giving effect

to the policies of the Government must act in such a manner

which should not create frustration of such policies of the

Government.

            This Court tried its best in the case in hand to see

that the financial barrier and power imbalances between the two



Writ Appeal No.34 of 2015                                  Page 3 of 135
 parties does not create hurdle on the path of the Appellants land

losers in getting their deserved constitutional and legal rights

and their right to life which includes right to livelihood, right to

shelter and right to healthy environment are protected.

            Rehabilitation is meant only for those persons who

have been rendered destitute because of a loss of residence or

livelihood as a consequence of land acquisition. The primary

purpose of rehabilitation and resettlement is to improve the

social and economic conditions of family displaced by land

acquisition for development projects, ensuring that they achieve

at least a previous, or ideally better standard of living and

earning capacity post-dislocation. The authorities are legally

bound to explore the avenues of rehabilitation by way of

employment,       housing,     investment    opportunities,     and

identification of alternative lands.

2.          In this writ appeal, 102 Appellants seek to set aside

the impugned judgment and order dated 13.01.2015 passed by

the learned Single Judge of this Court in W.P.(C) No.21006 of

2014 in dismissing the writ petition filed by them and rejecting

their prayer for a direction to the Respondents not to take any

coercive action against them by evicting them from their




Writ Appeal No.34 of 2015                           Page 4 of 135
 dwelling houses and/or by terminating their employment, till

they are physically allotted plots in the resettlement site.

            The 102 Appellants along with two others filed the

writ petition with the following prayers:

            "a.   why    the   letter    dated   31.07.2014    vide

            Annexure-12 to the extent challenged in the writ

            application, shall not be quashed;

            b. why the Opp. parties shall not be directed to

            reinstate the services of the Petitioners without

            attachment and imposition of any conditions and

            in accordance with letter dated 09.07.2014 of

            the Sub-Collector, issued in terms with the

            decisions     taken     in    the    meeting      dated

            06.07.2014;

            c. why the Opp. parties shall not be directed not

            to    take   any   coercive     action   against    the

            Petitioners till they are allotted plots physically

            in the resettlement site;

                   And in the event the Opp. parties fail to

            show cause or show insufficient cause, the said

            Rule be made absolute and




Writ Appeal No.34 of 2015                              Page 5 of 135
            a. the letter dated 31.7.2014 vide Annexure-12

            to the extent challenged in the writ application,

            be quashed;

           b. the Opp. Parties be directed to reinstate the

            services of the Petitioners without attachment

            and      imposition   of   any   conditions     and   in

            accordance with letter dated 09.07.2014 of the

            Sub-Collector, issued in terms with the decisions

            taken in the meeting dated 06.07.2014;

           c. the Opp. parties be directed to not take any

            coercive action against the Petitioners till they

            are allotted plot physically in the resettlement

            site."

3.         It is the case of the Appellants in the writ petition

that they are residents of village Hensamul (Talasahi), P.S.:-

Talcher Sadar in the district of Angul. The lands of the Appellants

were acquired in different phases both under the CBA Act and

the L.A. Act for the purpose of coal mining of Ananta OCP,

Bhubaneswari OCP and Lingaraj OCP of Mahanadi Coal Fields

limited. The lands were acquired in Hensamul village under the

land acquisition proceeding which started in the year 1987. As a

part of the Rehabilitation and Resettlement Schemes, on handing



Writ Appeal No.34 of 2015                                 Page 6 of 135
 over their respective agricultural lands situated in the village

Hensamul, the Appellants were appointed by the MCL Authority

in different phases. While the matter stood thus, the MCL

Authority issued notices on dated 12.07.2013, 13.07.2013,

14.07.2013, 12/14.07.2013 and 13/14.07.2013 to the residents

of Talasahi including the Appellants, placed within the village of

Hensamul to hand over the dwelling houses and vacate their

homestead    lands   for    enabling   the   MCL   Authority       for

commencement of mining activities over the said area. On their

own statements, the Appellants had already handed over their

agricultural lands to the MCL Authorities. Even though notices

were issued for handing over the dwelling houses/residential

areas, but such notices were not acted upon following a decision

of the Authority to hold on the same and to proceed with the

same only after a tripartite meeting was held between the MCL

Management, the villagers and the authorities of the State of

Odisha. The Respondents had zeroed on the site at Mouza

Gurujang, without preparing the list of sites which would have

been feasible for the purpose of resettlement of the members of

displaced community. Mouza Gurujang was more than 25

kilometers away from the place where the Appellants were

residing and it would have caused manifest harassment to the



Writ Appeal No.34 of 2015                          Page 7 of 135
 villagers,   which   was    also   contrary   to   the     schemes       of

rehabilitation and resettlement which required that lists of sites

for resettlement of members of displaced communities were to

be prepared after consulting the members before finalizing the

site.

             It is the further case of the Appellants that they

challenged the action of the management in issuing notices of

handing over possession of their dwelling houses situated in

village Talasahi in W.P.(C) No.17257 of 2013. In the said writ

petition, the Appellants also challenged the action of the

Respondents in forcing them to either accept plots at the

Gurujang Resettlement site or to accept „Swarna Yojana Package‟

for resettlement. The Appellants prevailed over MCL in the above

regard owing to inconvenient location and lack of amenities and

the resettlement site. While the matter stood thus, the MCL

Authority, particularly the Project Officer, Ananta OCP issued

letters of termination against the Appellants on the ground of

failure to hand over the possession of their dwelling houses to

the Respondents. Challenging the          aforesaid action of the

management, one Padmanava Biswal filed a writ petition before

this Court, which was registered as W.P.(C) No.9477 of 2014 and

this Court upon hearing the said matter on the question of



Writ Appeal No.34 of 2015                                Page 8 of 135
 admission, by order dated 05.05.2015 passed an interim order

directing the Project Officer, Ananta OCP not to give effect to the

same till the next date. In the meanwhile, a meeting was held on

dated 06.07.2014 between the residents of village Hensamul and

the MCL Management on the issue of selection of resettlement

site as well as on the aspect of termination of the land outsees.

It was resolved to look for an alternate site other than Gurujang

and Balandapasi. The Appellants further contended that in the

said meeting, it was also resolved as follows:

            "i. MCL authorities will reinstate the retrenched

            employees by 10.07.2014. These will be no

            break of service;

            ii. Collector, Angul will be requested to convene

            the meeting of the PLARC at the earliest to

            discuss and finalize in principle the rehabilitation

            site;

            iii. The MCL will start taking measures towards

            rendering the site from legal perspective;

            iv. The MCL authorities will arrange interim

            accommodation as will be decided by the PLRAC

            after the site is finalized in principle and on




Writ Appeal No.34 of 2015                            Page 9 of 135
             extension of such facilities, the villagers will

            start vacating their homestead land."

            It is the further case of the Appellants that in a

meeting held under the Chairmanship of Hon‟ble Minister,

Energy,   Government        of   Odisha   with    CMD-MCL,      Director

(Personal), MCL, Director (Technical), MCL in presence of MLA,

Talcher and the Principal Secretary, Energy Department on

16.07.2014, it was decided that the MCL authority was to

immediately issue letter of employment reinstating the displaced

household   persons   without      attaching     any   pre-condition   of

affidavit by the individual households. In the said meeting, it was

also resolved to write to the individual households regarding

allotment of lands in front of Balanda College for construction of

R & R Colony and to be allotted quarters in the residential colony

to accommodate the households till houses are constructed in

the R & R Colony. It is claimed by the Appellants that consequent

upon the development, the Appellants were issued with letters of

reinstatement in their services indicating that there shall be no

break in the service in respect of the Appellants. In addition to

such letters, the Appellants were also intimated to comply with

the agreed points as per the minutes of meeting held on

06.07.2014, subsequent letter dated 11.07.2014 of the Sub-



Writ Appeal No.34 of 2015                                Page 10 of 135
 Collector, Talcher as well as minutes of meeting held on

16.07.2014,     but     at   the   same     time,        the     MCL   authorities

demanded handing over physical possession of the dwelling

houses in favour of the MCL latest by 31.10.2014. Pursuant to

above   letters,    the      Appellants    joined        their   services   being

reinstated.

              It is the further case of the Appellants that while the

matter stood thus, the Appellants were communicated with a

letter dated 31.07.2014 of General Manager, Jagannath Area

(Respondent no.1) indicating therein the following:

              "i) Re-instatement all the terminated employees

              without break in service & with immediate

              effect;

              ii) The villagers will not have to submit affidavit

              for the same;

              iii) MCL has already agreed for allotment of R &

              R site situated in front of Balanda College as has

              been decided in PLRRC meeting on 19.07.2014.

              MCL will allot plot to the villagers at R & R site in

              front of Balanda College duly decided by PLRRC

              after obtaining clearance from Govt. of India

              and     diversion    of     forest    if     required.    MCL



Writ Appeal No.34 of 2015                                         Page 11 of 135
             management has already initiated action before

            the appropriate authority for allotment of the

            plots;

            iv) The villagers who are not having Company‟s

            accommodation        will    be   allotted   Company‟s

            quarters on priority basis and in minimum

            possible time as decided in the Sub-Collector‟s

            meeting on 06.07.2014;

            v) MCL has also agreed to adjust the period of

            absence due to termination from service with

            payment of leave in credit of the individual.

                     It was also brought to the notice of the

            Appellants that they were required to vacate

            their dwelling houses and hand it over to MCL

            for   continuation      of    mining     operation   of

            Bhubaneswari OCP latest by 31.10.2014."

           The Appellants being aggrieved by the conditions as

narrated hereinabove approached this Court on the premises

that the conditions/terms in reinstating the Appellants were

unconditional and having reinstated the Appellants in service, the

authorities were not justified to impose the conditions as

contained in the letter dated 31.07.2014. The Appellants claimed



Writ Appeal No.34 of 2015                                Page 12 of 135
 that conditions imposed in the said letter are illegal, arbitrary

and in colourable exercise of power and further runs contrary to

the time-to-time assurances given by the Company in different

meetings taken place. The Appellants claimed that the conditions

imposed   by   MCL     authority   defeated    the   assurances    and

objectives of the resettlement and rehabilitation policy.

4.          Counter affidavit was filed by the Respondents in the

writ petition wherein it is stated, inter alia, that the conditions

imposed in the letter dated 31.07.2014 has nothing to do with

the resettlement and rehabilitation of the Appellants. No action

of the MCL authorities was in contravention of the R & R Policy,

1989 or 2006. The lands in the village Hensamul being acquired,

the Appellants have no right to stay over the land and it would

delay in the allotment of land in favour of the Appellants as each

of them have been provided employment in the Company and

the   Company     is   providing   its   own    quarters    for   their

accommodation for the time being till the rehabilitation site is

made ready. Further as the Company is in urgent requirement of

mining in the locality, there is no illegality in issuing the

impugned letter to the appellants. The MCL authority also

contended that they were ready and willing to comply the

assurances in acquisition of the appellants land and as a major



Writ Appeal No.34 of 2015                             Page 13 of 135
 part     of     compliance,        apart     from     the     acquisition

money/compensation, the Appellants were provided with the

employment in the Company, but for some technical reasons,

provision for allotment of land in favour of the Appellants for

their resettlement was getting delayed. However, keeping in

view the urgency with the Company and the inconvenience

caused to the land oustees as they would have to vacate their

residential   houses,    the   Company       has    already   earmarked

particular quarters inside the company premises to be allotted to

the land outsees till they were provided alternate sites and as

such the Appellants should not have any grievance in the matter.

              It is further stated in the counter affidavit that the

Govt. of Odisha promulgated R & R Policy, 1989 for resettlement

and    rehabilitation   of   the    people   whose    agricultural   and

homestead lands including houses were acquired/are to be

acquired. As per the R & R Policy, 1989, one committee was

formed i.e. Rehabilitation Advisory Committee (RAC), headed by

concerned Revenue Divisional Commissioner, which was re-

named as Rehabilitation and Periphery Development Advisory

Committee (in short "RPDAC" as per R & R Policy 2006) along

with a Sub-Committee namely Project Level Rehabilitation and

Resettlement Committee (in short "PLRRC") headed by Collector



Writ Appeal No.34 of 2015                                Page 14 of 135
 of the District, who looks after the resettlement of the land

oustees and selection of resettlement site, which is made

available by the Government.

             It is further stated in the counter affidavit that the

Respondents discussed with the Collector, Angul for providing a

site to resettle the land oustees of village Hensamul and Jilinda

whose lands were acquired including the houses and accordingly,

the Revenue Authorities of Angul district allotted around 45

Acres of land for resettlement site at village Gurujang. Number

of meetings were held by the A.D.M, Angul, and other Revenue

Officers with the villagers of Hensamul and Jilinda and the A.D.M,

Angul, vide its letter dt.19.4.2010 intimated that villagers of

Hensamul and Jilinda have agreed to shift to the resettlement

site at Gurujang.

             It is further stated in the counter affidavit that the

Respondent         No.1   on    receipt    of    the   confirmation      letter

dt.19.10.2010 for resettlement site at Gurujang by the A.D.M.,

Angul for the land oustees of village Hensamul and Jilinda,

developed    the     resettlement     site      by   making    plots,   roads,

electrification,    school     building,     playground,      pond,     market

complex, temple and provision of water supply like deep bore




Writ Appeal No.34 of 2015                                     Page 15 of 135
 well with overhead tanks etc. by spending crores of rupees as

per the provisions of R & R Policy, 1989.

           It is further stated in the counter affidavit that apart

from re-settlement policy for providing housing plots to the land

oustees, whose lands were acquired for coal mining purpose, on

a fully developed resettlement site, the Board of Director of MCL

in its 128th meeting held on 26.03.2011, promulgated "SWARNA

YOJANA" wherein it was decided to enhance the compensation,

house building assistance, maintenance allowance, allowance for

temporary shed, transport allowance along with special incentive

for early vacation and handing over vacant possession of home/

homestead land, agricultural land etc., for those land oustees

who were not interested in the resettlement plot provided by

MCL with the aid and assistance of State Government. The said

decision of the Board of Directors of MCL held on 26.3.2011 was

approved in the Company Level Joint Consultative Committee

(J.C.C.) meeting held on 03.04.2011.

           It is further stated in the counter affidavit that after

the development of the resettlement site at Gurujang, the land

oustees of village Hensamul and Jilinda were asked either to

accept the homestead plot (10 decimals) at the resettlement site

at Gurujang or avail the SWARNA JYOJNA in lieu of the plot at



Writ Appeal No.34 of 2015                          Page 16 of 135
 resettlement site. Many land oustees of both the villages

preferred to accept the homestead plots at the resettlement site

at Gurujang and some accepted the SWARNA JYOJNA.

           It is further stated in the counter affidavit that the

Appellants who are some of the residents of village Hensamul

(Talasahi), even if were given appointments in MCL as per the R

& R Policy, 1989, refused to accept either the plots in the

resettlement site at Gurujang or avail SWARNA JYOJNA with a

plea that the resettlement site at village Gurujang is not

acceptable to them nor they are interested to avail SWARNA

JYOJNA, even though out of 285 families, 159 families have

availed the resettlement facilities. On such plea, the Appellants

refused to vacate the houses and homestead lands, which was

creating problem for the MCL authorities for operation of mining

of coal under Bhubaneswari OCP, by that process it was

becoming difficult to fulfill the target of coal production and to

provide coal to various power plants of the country.

           It is further stated in the counter affidavit that the

permission has been granted by Ministry of Coal, Government of

India on dated 11.07.2013 for mining of 25 million tons of coal

from Bhbaneswari OCP, and this OCP is the biggest supplier of

coal to various power plants of the country. If the Appellants



Writ Appeal No.34 of 2015                          Page 17 of 135
 would   not    vacate   their   homestead     lands      and   houses

immediately, the progress of mining at Bhubaneswari OCP could

not be done and that the excavation of 25 million tons of coal

per annum could not be possible.

           It is further stated in the counter affidavit that the

Respondents conducted various meetings with the Appellants for

handing over of their homestead lands along with houses, and

various notices were also served upon them for vacating the

same, but when the Appellants shown a deaf ear, termination

letter dt.05.05.2014 as per Annexure-5 was issued on the basis

of Clause-3 & 4 of the appointment letter. After termination of

the Appellants, the Appellants created various problems for

operation of Bhubaneswari OCP, by observing strikes and also

created law and order situation in the Area and accordingly, FIRs

were lodged against the Appellants and their leaders.

           It is further stated in the counter affidavit that due to

the disturbance at Bhubaneswari OCP created by the Appellants,

the   matter   was   brought    to   the   notice   of   the   district

administration for taking appropriate steps for smooth running of

the mining operation at Bhubaneswari OCP and accordingly a

meeting was held on 06.07.2014 in the chamber of the Sub-

Collector, Talcher in presence of the villagers and their leaders



Writ Appeal No.34 of 2015                             Page 18 of 135
 along with the officials of MCL. In the said meeting, discussions

were made regarding the re-instatement of the Appellants in

their services and regarding re-selection of resettlement site.

The Appellants in the said meeting claimed that they would

accept the site in front of Balanda College, Talcher. In the said

meeting, it was decided that MCL authorities would reinstate the

retrenched employees without any break of service. It was

further decided that MCL authorities would arrange interim

accommodation as would be decided by the PLRRC after the site

was finalized in principle and on extension of such facilities, the

villagers would start vacating their homestead lands and houses.

            It is further stated in the counter affidavit that as per

the decision taken by the Sub-Collector, Talcher, reinstatement

order was issued on 13.07.2014 with a condition that the

Appellants have to submit an affidavit as per the conditions of

the management of MCL, but the Appellants refused to give any

such affidavit and did not join in their service. Again another

meeting was held in the Chairmanship of Hon‟ble Minister of

Energy, Govt. of Odisha on dt.16.07.2014 in presence of C.M.D.,

Director (Personnel), Director (Technical), of MCL and M.L.A.,

Talcher, and it was decided that the MCL would immediately

issue   order   of   reinstatement   without   attaching   any   pre-



Writ Appeal No.34 of 2015                            Page 19 of 135
 conditions of filing affidavit and allocate quarters till houses were

constructed in the R & R Colony in front of Balanda College,

Talcher.

            It is further stated in the counter affidavit a further

meeting was held on 31.07.2014 in the office of the Sub-

Collector, Talcher, wherein certain questions raised by the

Appellants, were discussed and it was decided that in principle,

the PLRRC had agreed the site in front of Balanda College in the

meeting held on 19.07.2014 and the MCL authorities will take

proactive action for obtaining clearance from MOEF with regard

to non-forest use for the said land. It was further decided that

there would be phased vacation from the site of dwelling i.e.,

houses and homestead lands at village Hensamul by 31.07.2014

subject to arrangement of interim accommodation by MCL. In

the said meeting, the residents of village Hensamul who were on

strike consented to call off the strike and co-operate with the

MCL Management in smooth operation of mine.

            It is further stated in the counter affidavit that basing

upon the decision made in various meetings held with Sub-

Collector, Talcher on 06.07.2014 and 31.07.2014, as well as the

Minister of Energy, the        Respondent No.1 issued a letter

dt.31.07.2014 to the        Appellants   individually accepting the



Writ Appeal No.34 of 2015                            Page 20 of 135
 decisions   made   and      requested   them   to   join   in   service

immediately and vacate the houses and homestead land and

hand over it to MCL for continuation of mining operation of

Bhubaneswari OCP, latest by 31.10.2014.

            It is further stated in the counter affidavit that

pursuant to the letter dt.31.07.2014, allotment of quarters to the

Appellants were issued on 15.9.2014, 23.9.2014 & 28.9.2014. In

spite of the allotment of quarters, neither the Appellants came

forward to occupy the quarters nor vacated their homestead

lands and houses, rather created problem for operation of the

mines. The Appellants through their family members and

relatives created problem and made dharna in the mines on

31.10.2014 and damaged some machineries in the mining site,

and the mining operation was hampered. This incident was

brought to the notice of the police by filing FIR on 01.11.2014.

            It is further stated in the counter affidavit that the

conduct of the Appellants was derogative since they obstructed

the mining operation and damaged the machineries even after

the interim order was passed by this Court on 29.10.2014. Even

though the Respondents were co-operating with the Appellants

and the decisions of the State Authorities, it is not understood

what the intention of the Appellants was. According to the



Writ Appeal No.34 of 2015                             Page 21 of 135
 Respondents, the Appellants were not interested to vacate their

homestead lands and houses, after getting the reinstatement

order dt.22.07.2014 and joining in the service on dt.30.07.2014.

            It is further stated in the counter affidavit that the

due to the conduct of the Appellants, the MCL could not be able

to produce adequate quantity of coal and by that process, would

not be able to supply coal to various power plants of the country,

for which the power plants would not able to generate adequate

electricity and at large the public would suffer. If the Appellants

would not vacate the houses and homestead lands and stayed

there, their safety would be at a stake since the mining operation

of Bhubaneswari OCP, was going on adjacent to their houses.

Moreover, if they would not vacate their houses and homestead

lands, the mining operation would come to halt and by that

process, there would be loss of production and loss of revenue to

the Government and more importantly the public at large would

suffer.

5.          Rejoinder affidavit was filed by the Appellants in the

writ petition to the counter affidavit, wherein it is stated, inter

alia, that the acceptance of the resettlement site at Gurujang

was not with relation to the area of the Appellants i.e. Talasahi in

the village of Hensamul. Village Hensamul consisted of three



Writ Appeal No.34 of 2015                           Page 22 of 135
 parts namely, Talasahi, Saharasahi and Baidyasahi and in

relation to the villagers of Hensamul accepting the resettlement

site at Gurujang was never in connection with the villagers of

Talasahi. At no point of time, the land oustees of village

Hensamul (Talasahi) had accepted Gurujang as the site for the

purposes of their resettlement. As a matter of fact, the action of

the issuance of notices in favour of the Appellants and other land

oustees of the village regarding vacation of their respective

dwelling houses by the Respondents, was the subject matter of

challenge in a separate writ application, wherein the selection of

resettlement site at Gurujang by the Respondents without

consulting and discussing about the feasibility and workability of

the same with the members of the families who have been

displaced   by   virtue   of   the   acquisition   effected   by   the

Respondents in different phases was under challenge.

            It is stated in the Rejoinder Affidavit that as per

Clause 8 of the R & R Policy, 2006, site of resettlement habitat

shall be selected by the RPDAC in consultation with the displaced

families. It is stated in the rejoinder affidavit that the acceptance

of the resettlement site at Gurujang by the Appellants and other

land oustees is incorrect as the finalization of the resettlement

site at the said place was made without any consultation with the



Writ Appeal No.34 of 2015                             Page 23 of 135
 members of the land oustees and accordingly, unsustainable in

law as the same was done in contravention to the guidelines

issued under the R & R Policy, 2006.

           It is further stated in the rejoinder affidavit that

when the resettlement site at Gurujang was decided by the

Respondents    without   consultation   and   discussion   with   the

members of the displaced communities and the said site was

never acceded to by the Appellants and other land oustees of the

said village for the purposes of their resettlement, there was no

question of ensuring the habitability at the resettlement site for

the occupation of the land oustees by the Respondents. The

resettlement site at Gurujang was decided by the authorities

without consultation and discussion with the land oustees and

therefore, there arises no question of accepting plots made

available for occupation of the land oustees at Gurujang by the

Respondents and that the allegations leveled against the

Appellants and land oustees regarding their approach in not

vacating their residential plots in spite of the Respondents in

having offered them plots at the resettlement site is an act of

manifest misrepresentation of facts.

           It is further stated in the rejoinder affidavit that the

Respondents had fixed a target of excavation of 25 million tons



Writ Appeal No.34 of 2015                           Page 24 of 135
 of coal per annum over the agricultural and homestead lands of

the land oustees, which had been made a reality with the co-

operation of the villagers who had consented to such acquisition

in different phases by the Respondents.

            It is further stated in the rejoinder affidavit that the

very issuance of the letter of termination under clauses (3) and

(4) by the Respondents is an act of palpable arbitrariness in as

much as the as the language of clauses 3 and 4 are crystal clear

on the fact that the recorded tenants would have to vacate their

homestead lands and houses within 90 days of receipt of

resettlement benefits. Therefore, in view of the fact that no plots

were allotted to the Appellants as part of their resettlement dues

in the absence of finalization of the resettlement site, the

Appellants and other land oustees who were employees under

the Rehabilitation scheme, could not have been terminated from

their services in the guise of having violated the clauses (3) and

(4) of their appointment letters. The act of the Respondents in

terminating the services of the rehabilitated land oustees of the

said village was the subject matter of challenge before this Court

in W.P.(C) No.9477 of 2014.

           It is further stated in the rejoinder affidavit that the

Appellants refused to sign on any affidavit as per the conditions



Writ Appeal No.34 of 2015                           Page 25 of 135
 of the Respondents, since the reinstatement orders were passed

in accordance with the decisions taken by the Sub-Collector in

the meeting dated 06.07.2014 and there was nothing relating to

the signing of an affidavit accepting the conditions of the

Respondents in the said meeting.

           In relation to the averments taken in the counter

affidavit that it was decided to phase-wise vacate the homestead

lands at village Hensamul by 31.10.2014 subject to arrangement

of interim accommodation by the Respondents in the meeting

presided by the Sub-Collector on 31.07.2014, it is stated in the

rejoinder affidavit that when the aforementioned decision to

vacate the homestead lands on phase-wise basis was taken on

the meeting dated 31.07.2014, it was a matter of inconceivable

perplexity for the Appellants to fathom that a decision to the said

extent was taken by the Respondents and communicated to the

Appellants in the letters of reinstatement dated 22.07.2014,

which was obviously prior to the meeting with the Sub-Collector

dated 31.07.2014 wherein the said decision was taken and

decided to be implemented by the Respondents by way of

incorporating the same in their conditions.

           It is further stated in the rejoinder affidavit that the

Appellants and other land oustees of village Hensamul (Talasahi)



Writ Appeal No.34 of 2015                          Page 26 of 135
 have not been allotted their respective lands as part of their

entitlement under the resettlement policy of the Government and

in absence of even the resettlement site situated in front of

Balanda College been cleared by the Forest Department for use

of the land with regard to non-forest use, it is an act of manifest

arbitrariness and recalcitrance to guidelines governing the

procedure to be adopted by the authorities for the purposes of

rehabilitation and resettlement prescribed by the Government,

by the Respondents in forcing the Appellants to vacate their

homestead lands.

            It is further stated in the rejoinder affidavit that

Appellants and other land oustees of the concerned village never

created problems and staged a dharna at the mining site on

31.10.2014.    The    Respondents      have    resorted       to   similar

techniques in the past by way of filing F.I.R. before the

concerned I.I.C. to pose difficulties in the way of the Appellants

and other land oustees of the village when no such act has been

committed by them. It is stated that the land oustees of village

Hensamul (Talasahi) were ready and willing to vacate their

homestead     lands   subject   to   fulfillment   of   the    guidelines

governing the procedure to be adopted by the Respondents in

allotting them their respective lands in the resettlement site in



Writ Appeal No.34 of 2015                               Page 27 of 135
 the front of Balanda College by way of obtaining clearance from

the concerned department for the purpose of usage of the same

for non-forest use, pursuant to which, the Appellants shall vacate

their homestead lands and move to the interim accommodation

provided by the Respondents in the interim period till the time

the resettlement site is made habitable by the Respondents.

6.         Additional affidavit was filed by the Respondents in

the writ petition, wherein it is stated, inter alia, that land

measuring of 385.88 Acres were acquired under L.A. Act and

1653.325 Acres were acquired under the CBA Act of village

Hensamul. So far as the acquisition of land of village Hensamul

under CBA Act is concerned, first the acquired land was vested to

the Central Government under section 10 of the CBA Act, free

from all encumbrances. Under section 11 of the CBA Act, the

Central Government divested the acquired land under section 10

in favour of the MCL (previously CCL thereafter SECL) starting

from dt.09.11.1978 and the last being on dt.31.08.2004. Thus,

the Appellants cannot claim any relief under the R & R Policy,

2006.

           It is stated in the additional affidavit that so far as

acquisition of land under L.A. Act of village Hensamul is

concerned, the possession of lands was taken by the MCL by



Writ Appeal No.34 of 2015                          Page 28 of 135
 11.03.2005 and possession of only a small portion of land

measuring Ac.73.39 was taken on 27.09.2008 which were only

agricultural lands. The houses and homestead lands of village

Hensamul were acquired and possession was taken much before

2004 under the C.B.A. Act. The Appellants were creating trouble

in not vacating the houses and homestead lands claiming to avail

the benefits under R & R Policy, 2006, which should not be

entertained.

           It is further stated in the additional affidavit that

since the notification to acquire the agricultural land and

homestead land was much prior to 14.05.2006 i.e., the date

when R & R Policy, 2006 came into force, the Appellants have no

right to claim any benefits under 2006 Policy.

7.          The learned Single Judge considering the fact that

lands of the Appellants had already been acquired and that they

had been paid the land acquisition compensation amount besides

employment being provided to them and since they have also

been provided with alternate accommodation in the quarters of

the MCL, did not find any merit in the claim of the Appellants. It

was observed that the Appellants have no right to claim that

they would vacate the homestead lands under their occupation

only after they were provided with alternate house sites, which



Writ Appeal No.34 of 2015                          Page 29 of 135
 has no legs to stand. Recording the submission of MCL authority

that they were under process of allotting the alternate sites and

the same is being delayed for some technical reasons, the

learned Single Judge directed the State authority to co-operate

with the MCL authority in the matter of finalization of the

alternate sites under the particular rehabilitation package.

However, keeping in view that the MCL Company is in urgent

need of mining in the locality, which was definitely in the larger

interest of the country and further keeping in view that the MCL

Company      had     already    made      quarters    available     for

accommodation of the Appellants till they were provided with

alternate accommodation sites, the learned Single Judge was not

inclined to grant reliefs sought for by the Appellants and

accordingly, dismissed the writ petition vide impugned judgment

and order dated 13.01.2015.

8.          The Writ Appeal was filed on 22.01.2015 to set aside

judgment and order dated 13.01.2015 passed by the learned

Single Judge and for a direction to the Respondents not to take

any coercive action against the Appellants by evicting them from

their dwelling houses and/or by terminating their employment,

till they are physically allotted plots in the resettlement site.




Writ Appeal No.34 of 2015                             Page 30 of 135
             During pendency of the Writ Appeal, an additional

affidavit was filed by the Appellants on 06.09.2017, wherein it

was indicated that pursuant to the filing of the Writ Appeal,

several meetings were held between the State Government, MCL

Authorities and the villagers of Hensamul (Talasahi) regarding

shifting, rehabilitation and resettlement issues and eviction of

encroachment over the disputed lands. On 16.02.2015, a

meeting was held at the official chamber of the Sub-Collector,

Talcher wherein the Sub-Collector, Talcher requested both MCL

and the villagers to sort out the issues between them amicably

and in the same meeting, it was resolved that since the Writ

Appeal is pending before this Court, the final decision of this

Court shall be binding on both the villagers and MCL. Another

meeting of MCL was held on 17.06.2015 in the Collectorate,

Angul wherein a detailed discussion was made regarding the cut-

off date of village Hensamul, implementation of R & R Policy,

2006, shifting of village Hensamul (Talasahi) and other issues of

village   Hensamul.   Similarly,   one   meeting   was   held   on

29.10.2015 wherein discussion was made on PDF list, shifting of

village Hensamul (Talasahi) to the resettlement site located in

front of Balanda College and other issues. The important factor

of the meeting was that the Sub-Collector, Talcher requested the



Writ Appeal No.34 of 2015                          Page 31 of 135
 villagers to shift to the temporary accommodation provided by

MCL immediately for greater interest to which the villagers

responded that they would shift to the resettlement site once the

same is ready as per their demand. On 02.11.2015, a meeting

was held by MCL between its CGM/GMs wherein it was resolved

that shifting of Talasahi and Saharsahi should be expedited and

the existing R & R Policy, 2006 should be implemented in

finalizing the benefits to the displaced persons. On 13.11.2015,

another   meeting    was    held   regarding   3rd   Project   Level

Rehabilitation and Resettlement Committee of Jagannath Area,

MCL wherein shifting of P.D.Fs. of Hensamul (Talasahi) to the

allotted transit quarters, development of R & R site for PDFs of

village Hensamul, Talasahi were discussed. Regarding shifting of

village (Talasahi), a meeting was convened by the Collector,

Angul on 02.02.2016, wherein it was held that 106 plots have

been demarcated in the resettlement site as per approved lay

out plan which were free from encroachments and another

encroach free land for 21 plots was required to accommodate the

balance 127 project displaced families of village Hensamul

(Talasahi). On 29.03.2016, a meeting was held in the office of

the Sub-Collector, Talcher regarding the shifting of village

Hensamul (Talasahi) under the Chairmanship of Sub-Collector,



Writ Appeal No.34 of 2015                            Page 32 of 135
 Talcher. After substantial discussion, the Sub-Collector, Talcher

had suggested few points to facilitate the shifting of Hensamul

(Talasahi) village which was accepted by MCL. The points are

discussed below:

            I. The GM, Jagannath Area would follow up the

            transfer case of Sri Parsuram Sahoo as discussed in

            the    meeting   held    under   the   Chairmanship      of

            Collector, Angul on 23.02.2016 in the presence of

            Director Technical (P&P) and Director Personnel, MCL

            Headquarter;

            II. The PDF list would be finalised as early as

            possible. The special LAO (MCL) would call a meeting

            of GM (L & R) and village representatives of

            Hensamul (Talasahi) to finalise the list as per

            procedure;

            III. The GM, Jagannath Area will take initiative for

            eviction   of    the    encroachers    of    the   Balanda

            rehabilitation site to make the required plots free to

            accommodate the land losers of Hensamul after

            finalization of PDF list. The survey of the encroachers

            would be done within ten days in co-ordination with

            the local Revenue Inspector, Ghantapada Circle.



Writ Appeal No.34 of 2015                               Page 33 of 135
             Survey of the encroachers who have encroached the

            area approved by TAMDA would only be made to

            make it easier for eviction;

            IV. The GM, Jagannath Area would take proactive

            step for shifting of the existing Gram Panchayat

            office and High School in consultation with the EDO,

            Talcher, District Education Officer, Angul, Tahasildar,

            Talcher, village representative and President of the

            School within the time bound manner;

            V. As decided in the meeting held under the

            Chairmanship of Collector, Angul on 21.03.2016, the

            2006 R & R Policy would be applicable in case of

            eligible families after receipt of clearance from higher

            quarters;

           VI. After finalization of PDF list and development of

            the resettlement site in front of Balanda College, the

            villagers would vacate the village within a specified

            time;

           VII. It is broadly agreed by both MCL and village

            representatives of Hensamul (Talasahi) that after the

            finalization of PDF list and development of the

            resettlement site for them in front of Balanda



Writ Appeal No.34 of 2015                           Page 34 of 135
             College, the villagers would shift to the new site as

            early as possible.

           On 25.11.2016, the Collector, Angul sent a letter to

the General Manager, Jagannath Area, MCL, Talcher informing

therein that during the visit on 16.11.2016 to the resettlement

site in front of Balanda College for the PDFs of village Hensamul

(Talasahi), it could be noticed that no work was going on at the

site. The works such as road, drain, water supply and electricity

were yet to be started in spite of several persuasions and

discussions. The PDFs village Hensamul (Talasahi) are losing

faith and confidence on MCL for such inaction. The Collector,

Angul requested therein in to take necessary steps and complete

the minimum infrastructure development works immediately.

           In the Additional Affidavit, it is further stated that the

Collector, Angul vide its letter dated 30.03.2017 addressed to

the Sub-Collector, Talcher regarding the development of R & R

site at Balanda for PAF of Hensamul village stated therein that

G.M.,   Jagannath   Area    has   requested    vide    letter   dated

22.03.2017 to arrange for handing over the encroachment free

land to MCL to complete the infrastructure development work in

time at resettlement site in front of Balanda College. In the video

conferencing held on 17.02.2017, it was decided that MCL to



Writ Appeal No.34 of 2015                             Page 35 of 135
 complete   infrastructure   development     work    at    the   site   by

15.05.2017. District Administration would take necessary steps

to shift the PDFs of village Hensamul (Talasahi) to transit

accommodation allotted by MCL w.e.f 15.06.2017 and also to

take steps to evict the encroachers from the                 site w.e.f

15.03.2017 on payment of ex-gratia. However, not a single

encroacher had vacated the encroached land. The Collector in

such letter requested to take necessary steps and complete the

eviction of encroachers from the Resettlement site immediately

so as to hand over encroached free land to MCL for completion of

infrastructure development work in the scheduled time i.e.

15.05.2017.

            In the Additional Affidavit, it is further stated that the

General    Manager,   Jagannath     Area   vide    its    letter   dated

16.05.2017 addressed to the District Collector, Angul informed

therein that the development activities at Balanda R & R site are

in progress and are in various stages of completion. The

progress of main drain has been stopped since last four months

due to non-removal of encroachment at the site and road work is

also likely to be stopped, if the encroachment is not removed. At

the end, it was requested to look into the matter and arrange for




Writ Appeal No.34 of 2015                                Page 36 of 135
 handover the encroachment free land to MCL so that the balance

R & R activities would be completed at the earliest.

            In the Additional Affidavit, it is further stated that on

27.05.2017, a meeting was convened at the office of the Sub-

Collector, Angul regarding the difficulties faced by the villagers of

Hensamul Village wherein the demands of the villagers were

discussed and after a thorough discussion, it was concluded that

since the year 2012, no steps has been taken by the authorities

to resettle the villagers of Hensamul village in spite of repeated

request, therefore, the villagers requested the officials to

cooperate and take a decision.

            In the Additional Affidavit, it is further stated that the

General   Manager,    Jagannath     Area   vide   its    letter   dated

20.02.2017 addressed to the Special Land Acquisition Officer,

MCL, Angul requested to take necessary steps for eviction of 164

encroachers at the R & R site for the scheduled completion of

development works so that the shifting of the 105 employee

families can be done smoothly.

            The Collector & District Magistrate, Angul vide its

letter dated 02.06.2017 addressed to the Director, (Personal),

MCL informed therein that MCL had not taken any effective step

for vacation of the interim order granted by this Court in W.P.(C)



Writ Appeal No.34 of 2015                               Page 37 of 135
 No.15881 of 2015 wherein this Hon‟ble Court had directed not to

evict the petitioners therein i.e. the encroachers till the next date

of listing, for which the District Administration is at stake and

unable to render any assistance to the Project Officer -Cum-

Estate Officer for eviction of 21 encroachers.

               It is further stated in the Additional Affidavit that on

09.06.2017, the General Manager, Jagannath Area sent letter to

the Director Technical (Operation), MCL HQ, Burla informing

therein that the issue regarding the Appellants‟ village has been

finalized in the high-level meeting held with Chief Secretary,

Govt. of Odisha, MLA, Talcher and CMLD, MCL. MCL management

in the said meeting also requested to allow the balance 30

hectares of land at Coal Stockyard No.08 which was turned down

by the MLA and the villagers.

               On 12.07.2017, a meeting was convened between

the   M.L.A,     Talcher,   Superintendent   of   Police,   Angul   and

Chairman-Cum-Managing          Director,   MCL    wherein    the    Sub-

Collector, Talcher informed the House that due to the non-

finalization of the demands of the above village in time, the coal

production and smooth transportation of coal had been stopped,

which created law and order situation as well as loss of revenue

to both Govt. of India and State. Therefore, he requested the



Writ Appeal No.34 of 2015                              Page 38 of 135
 House to finalize the village wise issue for smooth running of coal

mining projects in Talcher Coalfields area and to avoid unhealthy

situation. In the said meeting, the village of the Appellants also

found place at Sl. No.7. While discussing about the same, the

authorities   decided     that   steps   to   be   taken   to   evict   the

encroachers either on payment of ex-gratia sanctioned by the

MCL or as per law and that the villages should shift to transit

accommodation provided by MCL immediately and to allow the

proposed area for extraction of coal for the interest of nation.

              It is stated in the Additional Affidavit that the land in

dispute had been encroached upon by the encroachers and MCL

had not made any endeavours to remove such encroachment

from the resettlement site in front of Balanda College. The Kisam

of the land being jungle together with illegal encroachment which

were yet to be evicted by following due process of law and there

existed no definite time within which, the resettlement site could

be finalised and the Appellants could be physically allotted with

their respective plots.

              It is stated in the Additional Affidavit that the

contention of the MCL that such situation was prevalent due to

the action of the Appellants in not vacating land which was

affecting the coal production thereby, hampering the interest of



Writ Appeal No.34 of 2015                                  Page 39 of 135
 the Country is per se misconceived and frivolous, which was

evident from the reports from the year 2013-14, 2014-15, 2015-

16 and 2016-17. The affected persons were not rehabilitated and

resettled and that there was no urgency of evicting them without

fulfilling prior commitments made by the Respondents.

             It is stated in the Additional Affidavit that the

Appellants without having received the benefits under the policy

and physical allotment of lands at resettlement site, the

conditions   imposed   by   the   Respondents   in   directing   the

Appellants to vacate their homestead lands was in blatant

violation of not only their own terms and conditions but also the

R & R Policy, 2006.

9.           In pursuance of the order dated 20.09.2022, the

Respondents filed an affidavit dated 12.01.2023, wherein it is

stated that all the Appellants had been allotted plots in the

resettlement site vide plot allotments letters dt.22.12.20I9 and

the same have been received by the Appellants.

             Out of the 102 appellants who have been allotted

plots at the Balanda resettlement site, 21 appellants (i.e.,

appellant nos.5, 40, 42, 43, 45, 47, 52, 54, 57, 62, 68, 69, 73,

74, 79, 80, 91, 93, 95, 99 and 102) had already constructed

houses over the plots allotted to them/constructing houses over



Writ Appeal No.34 of 2015                            Page 40 of 135
 the plots allotted to them and that out of the aforesaid

Appellants, the Appellant no.80 i.e., Sanata Kumar Biswal had

started living in the house constructed over the plot allotted to

him. All the eligible Appellants had been allotted quarters in

various   localities/colonies   of   MCL   and   a   majority   of   the

Appellants are staying in the said quarters allotted to them by

MCL as an alternative site in lieu of the plots allotted to them.

            In the affidavit, it is further stated that almost all the

plots allotted to the Appellants are free from all encumbrance.

Only five plots allotted to Appellant nos.9, 19, 22, 28 and 31

have been encroached which has been made by a private school

i.e., Nigamananda Little Star School (hereinafter for short „NLS

School‟) and that the said school had been issued notice for

eviction u/s.12 of the CBA Act, which has been challenged by the

said school in a writ petition bearing W.P. (C) No.8549 of 2019

before this Court. Those five Appellants have been provided

accommodation in the quarters of MCL colonies and they are

staying in the said quarters.

            In the affidavit, it is further stated that even though

resettlement plots have been allotted to the Appellants and

many of the Appellants have constructed houses over the plots

and almost all the Appellants are staying in the alternative



Writ Appeal No.34 of 2015                              Page 41 of 135
 accommodation provided by the Respondents in the quarters of

MCL colonies, the Appellants are not vacating their homestead

lands and not handing over possession in Hensamul (Talasahi),

which was causing a great hindrance to the progress of

Bhubaneswari Open Cast Project Coal Mines.

             It is further stated in the affidavit that the mining

face of Bhubaneswari OCP had reached near the residential

houses in Hensamul (Talasahi). As the Appellants are neither

vacating nor handing over their homestead lands in Hensamul

(Talasahi), the mining activity in Bhubaneswari OCP is being

seriously affected and within a short span of time, it would come

to a standstill position.

             It is further stated in the affidavit that Bhubaneswari

OCP is one of the biggest coal mines in Asia with a production

capacity of 28 million tones and is of strategic national

significance as major coal excavated from this mine was being

transported to major power houses producing electricity in India.

If the Appellants would not vacate their homestead lands and

buildings standing over there, the coal production in one of the

biggest coal mines in Asia i.e., Bhubaneswari OCP will come to a

standstill which may lead to power crises.




Writ Appeal No.34 of 2015                           Page 42 of 135
                It    is    further    stated       in   the   affidavit   that   the

resettlement site provided to the Appellants had basic amenities

such as road, electricity, boundary wall, concrete drainage

network, club house, Jagnya Mandap etc. In view of the

resettlement plots allotted to the Appellants, the prayer of the

Appellants in the writ appeal being not to take any coercive

actions against the Appellants by evicting them from their

dwelling houses and/or by terminating their employment till they

are physically allotted plots in resettlement site has become

infructuous.

               It is further stated in the affidavit that if the

Appellants did not vacate their homestead lands and buildings

standing thereon in Hensamul (Talasahi), the coal production in

Bhubaneswari OCP would be seriously affected and would come

to a standstill position which might lead to power crises all over

the nation. Therefore, the Appellants are to be directed to vacate

their   homestead          lands     and    buildings     standing    thereon     at

Hensamul (Talasahi) and hand over possession of the same to

the Respondents at the earliest.

10.            The        Appellants       filed    objection    affidavit   dated

23.03.2023 to the affidavit dated 12.01.2023 filed by the

Respondents, wherein it is stated that though the stand has been



Writ Appeal No.34 of 2015                                          Page 43 of 135
 taken by the MCL that Appellants had been allotted with plots in

the   resettlement   site   vide   plot   allotment    letter   dated

22/12/2019, however, those allotments have only been carried

out on documents but not in physical form and those sites are

not free from series of impediments both in the form of

feasibility, encroachment and encumbrances. MCL has not yet

cleared the encroachments over the Balanda Resettlement site.

There are fifteen numbers of plots in Balanda Resettlement Site

which have not been allotted in as much as, possession has not

been delivered due to the pendency of W.P.(C) No.8549 of 2019

filed by one of the encroacher NLS School against the State of

Odisha objecting to their eviction. The said NLS School is existing

over 15 plots i.e. Plot No.128, 129, 130, 131, 141, 140, 139,

138, 142, 143, 144, 145, 146, 121, 122 situated in the Balanda

Re-settlement site. In the said writ petition, this Court has

passed an interim order of status quo which is continuing.

            It is further stated in the objection affidavit that

there has been no construction of drainage/sewerage by MCL in

the allotted sites. Owing to dispute between the contractor

responsible for those civic constructions and MCL which is

pending before the learned Civil Judge (Sr. Division) in Civil Suit

No.410 of 2019 and C.S.(III)/608/2021 pending before the



Writ Appeal No.34 of 2015                             Page 44 of 135
 learned Commercial Court, Cuttack, such work is not gaining any

progress. Due to non-development of main drainage over the

site which is constructed, development works in respect of seven

plots i.e. Plot No.99, 100, 101, 102, 103, 104 and 105 have not

taken place.

            It is further stated in the objection affidavit that the

tenders have been called for and works have been awarded to

contractors to undertake site levelling work as plots are low

causing water logging. Such levelling work is ongoing and the

same would take more time to make it feasible for homestead

purpose. Furthermore, basic amenities such as drinking water,

electrification and road have not been developed. Though

contractors were engaged to perform those works but no such

work has commenced.

            In the 12th RPDAC meeting held on 31.08.2021, it

was decided by the RDC in respect of such agenda vide Sl. No.15

that MCL is to complete all the infrastructures and development

works within one month along with basic amenities etc., and

take steps for shifting of the PDFs. The left-out claims for

employment issues of Hensamul (Talasahi) shall be placed before

a joint committee under the chairmanship of Sub-Collector,

Talcher for finalization. Till date, no action has been taken by the



Writ Appeal No.34 of 2015                           Page 45 of 135
 district administration for providing employment to the eligible

family members of the Appellants under rehabilitation benefits.

            The minutes of meeting dated 26.10.2021 which was

held for discussion of temporary shifting of Panchayat Office of

Hensamul (Tahasil), has already been shifted with 14 families

with their dwelling houses, Shiva Temple & Pond to cooperate

the MCL Management to achieve their targeted coal production,

but in return, till date both resettlement & rehabilitation has not

yet been finalised.

            It is further stated in the objection affidavit that

though the resettlement plots were allotted, but till date, no

action had been taken to provide Record of Rights to the land

oustees. The said land was acquired by under the CBA Act, thus

appropriate steps were to be taken to refer the matter to the

State Government for issuance of Record of Rights, however, no

such steps were taken to such effect.

            It is further stated in the objection affidavit that the

stand taken by the Respondents that out of 102 Appellants, 21

Appellants have constructed houses and Appellant No.80 Sanata

Kumar Biswal has started living in the house constructed over

the plot allotted to him, is not correct. In fact, 21 Appellants

have started construction which are not yet to be completed and



Writ Appeal No.34 of 2015                           Page 46 of 135
 even if those constructions would be completed, they cannot

reside there due to lack of basic civil infrastructure such as water

supply, drainage, electricity connection, roads etc. So far as the

Appellant No.80 is concerned, he is unable to shift to his house

for the lack of the aforementioned facilities in the area.

              It is further stated in the objection affidavit that the

stand taken by the Respondents that majority of the Appellants

were staying in the quarters allotted to them by MCL as an

alternative site in lieu of the plots allotted to them is incorrect.

Those quarters were allotted to the MCL employees as a course

of their employment, but not as an alternative site in lieu of

plots. The quarters are small in size and cannot cater the

household goods, assets and cattle of the land oustees. In fact,

all the family members were required to be fit in those tiny

quarters which were never meant to be an alternative site. Only

six nos. of families were provided with Company alternative

accommodation at the time of shifting of Panchayat Office &

fourteen nos. of families to facilitate the mines for its coal

production.

              It is further stated in the objection affidavit that the

stand taken by the Respondents that almost all the plots are free

from all encumbrances and only five plots allotted to the



Writ Appeal No.34 of 2015                             Page 47 of 135
 Appellant Nos.9, 19, 22, 28 and 31 have been encroached is not

correct. There are litigations pending with respect to the lands,

wherein interim orders have been passed. CMD MCL assured to

pay compensation to the tune of Rs.1,00,000/- (rupees one lakh

only) to each of the encroachers which was also accepted by the

encroachers. After disposal of the W.P. (C) No.15881 of 2015, 87

encroachers      over    the     Balanda      site     have   accepted    the

compensation amount and have vacated. So far as the stand

taken that five appellants had been provided with quarters, it is

stated that those quarters are employees‟ quarters and not

allotted as an alternative site in lieu of the land allotted to them.

            It is stated that the production of MCL has increased

substantially in the recent years and they are comfortably

meeting their targets, thus the stand taken by MCL that the

Appellants were responsible for the loss to MCL is not correct.

            It    is    stated   that   the     said    Jagnya    Ghar   was

constructed by the land oustees and not by MCL. The club shown

at Balanda R & R site is at a dilapidated condition and cannot be

used. The road and electrification shown is an attempt to confuse

this Hon'ble Court. MCL is only showing the parts which are

favourable to them and not the actual facts. In majority part of

the sites, only electric polls have been installed and there is no



Writ Appeal No.34 of 2015                                     Page 48 of 135
 electricity connection, not even wire connection has been

provided. MCL is trying to play with the interest of land oustees

who have been fighting battles for their entitlement in lieu of

their lands.

               It is stated that the writ petition was disposed of in

view of the fact that MCL had already made quarters available

for accommodation of the Appellants till they were provided with

alternate accommodation sites, however, no site was available

for taking over physical possession so as to stay in those sites.

As a matter of fact, the quarters were also not safe for staying

which would be evident from the letters issued by MCL itself. In

addition thereto, there is no certain timeline fixed either by this

Court or by MCL by which time the resettlement/shifting shall be

undertaken from the interim quarters. It is admitted fact that the

Collector has not issued the completion of Resettlement Work

Certificate as per Clause 8 of the R & R Policy, 2006, thus, the

Resettlement work is not yet over. The MCL is required to take

necessary      steps   to   remove    the   encroachers   from    the

rehabilitation sites. The development work such as drainage,

sewerage, ground levelling work, connecting roads and facilities

such as drinking water and electricity supply etc. are to be

completed as early as possible.



Writ Appeal No.34 of 2015                             Page 49 of 135
 11.          The Respondents filed the reply on 04.07.2023 to the

objection affidavit dated 23.03.2023 of the Appellants, wherein it

is stated that after getting all the benefits such as land

compensation,    employment     and   residential   quarters,   the

Appellants were not vacating the homestead lands deliberately

and creating hindrance to the mining activities for which the

Respondents sustained huge loss as well as loss to the public

exchequer.

             The Appellants have been allotted plots in the

resettlement site vide plot allotments letters dated 22.12.2019

and the same have been received by the Appellants. Out of the

102 Appellants, who have been allotted plots at the Balanda

resettlement site, 21 Appellants i.e. Appellant nos.5, 40, 42, 43,

45, 47, 52, 54, 57, 62, 68, 68, 73, 74, 79, 80, 91, 93, 95, 99

and 102 have already constructed houses over the plots allotted

to them/constructing houses over the plots allotted to them and

out of the aforesaid Appellants, the Appellant no.80 Sanata

Kumar Biswal has started living in the house constructed over

the plot allotted to him and all the eligible appellants had been

allotted quarters in various localities/colonies of MCL and a

majority of the Appellants are staying in the said quarters

allotted to them by MCL as an alternative arrangement.



Writ Appeal No.34 of 2015                           Page 50 of 135
             It is stated that almost all the plots allotted to the

Appellants are free from all encumbrance and only 6 plots

allotted to the Appellant nos.9, 19, 22, 28, 31 and 82 have been

encroached. The said encroachment has been done by a private

school and the said school has been issued notice for eviction

under section 12 of the CBA Act, which was challenged by the

said school in W.P.(C) No.8549 of 2019, which is pending for

disposal.

            It is stated that the resettlement site at Balanda has

been provided to the Appellants with basic amenities such as

concrete road, electricity, boundary wall, club house etc. and

other amenities which are not been completed, would be

completed in course of shifting of the Appellants to the R & R

site. The Appellants have been allotted plots in the resettlement

site and almost all the plots allotted to the Appellants are free

from any encumbrance. Out of total 154 plots, only 12 plots i.e.

plot nos.128, 129, 130, 131, 138, 139, 140, 141, 142, 143, 144

and 145 were having encroachment by a private school, namely,

NLS School not fifteen plots as stated by the Appellants. The

encroachment has been done by NLS School and out of those

twelve plots, only six plots have been allotted to Appellant nos.9,

19, 22, 28, 31 and 82 are under encroachment. Many of the



Writ Appeal No.34 of 2015                          Page 51 of 135
 Appellants have constructed houses over the plots and all the

Appellants are staying in the company quarters provided by MCL,

but the Appellants are not vacating their homestead lands

stating they were staying in the village.

            It is further stated that the Appellants along with

their families are staying in the temporary accommodation

quarters allotted to them. However, the parents of some of the

Appellants are still residing at Hensamul (Talasahi) even after

getting all the benefits as per the policies prevalent at the

relevant point of time.

            It is further stated that a total 6769.50 mtrs. of

drainage/sewerage work has been completed and balance

drainage/sewerage work of 1085 mtrs. are yet to be completed

in the R & R site. The constructions of drainage, sewerage near

seven plots stated in the petition have not been made but MCL

has initiated process for construction of different infrastructures

at Balanda R & R site including aforesaid drainage and sewerage

works. The dispute between the contractor and MCL is pending

before the Commercial Court, Cuttack vide C.S. No.318 of 2019

but the same would not affect the developmental works at the

site.




Writ Appeal No.34 of 2015                          Page 52 of 135
               It is further stated that the leveling works has been

completed at the site and the site is ready to use for homestead

purpose. With regard to providing basic amenities such as

drinking water, the MoU between MCL and RWSS division, Angul

has been executed for providing drinking water to the R & R site

and accordingly, Executive Engineer (RWSS) has issued a work

order to the contractor and MCL has already released an amount

of Rs.2.18 crores towards first installment on dated 03.03.2022

and 70% of pipeline laying work i.e. 5219.00 mtrs. has been

completed     by   RWSS     and   80%   of   construction   work    of

underground     reservoir   and   50%   work    of   construction   of

overhead tank has been completed. Notwithstanding provision of

RWSS to provide drinking water to the site, the villagers are

being supplied water at their existing places of stay through

portable water tankers and they shall continue to be supplied

water till commencing of RWSS.

              So far as construction of road is concerned, it is

stated that 3280.61 mtrs. of concrete road has already been

completed in the R & R site and balance 955.00 mtrs. is yet to

be completed. MCL has initiated a scheme for construction of

different infrastructures at Balanda R & R site including concrete

road works.



Writ Appeal No.34 of 2015                             Page 53 of 135
             So far as electrification work is concerned, Tata

power has completed 70% of the total work which includes 11

KV   new    line   shifting   (length   0.550   km.),   distribution,

transformer, preliminary work for installation, erection of 40 nos.

poles of Low voltage transmission (LT) lines and removal of old

11 KV line from the R & R site etc. and the rest of the work is

pending due to hindrance caused by the villagers of Hensamul

(Talasahi). The TPCODL has stocked up the materials like poles,

cables and transformers at the resettlement site, but the

TPCODL intimated through mail dated 06.05.2023 that due to

non-clearance of the site, the execution of works at the site has

been stopped.

            It is stated that to complete the development works

at remaining places, a joint team comprising of Survey, Civil, L &

R & E & M department personnel along with representatives of

Tata Power went to the Balanda resettlement site on 24 th March

2023 for completion of the development works at the remaining

places and subsequently, on 31st May 2023 for measuring and

demarcation works, but the villagers of Hensamul (Talasahi)

prevented the team from the work and threatened the team to

hold hostage and of dire consequences for which the team

returned from the site to avoid any law and order situation. MCL



Writ Appeal No.34 of 2015                           Page 54 of 135
 has also appraised the situation to the Sub-Collector, Talcher and

sought his kind intervention in the matter for early resolution.

After getting entire benefits such as compensation, employment,

the Appellants and their family members along with villagers are

deliberately and unlawfully restraining the MCL personnel and

hindering the aforesaid development works with a malafide

intention not to allow the MCL for mining.

            It is further stated that due to acquisition of village

Hensamul    (Talasahi),     321    employments/cash     in    lieu   of

employments have been provided by MCL as per Orissa R & R

policies prevalent at the relevant point of time. There are no left

out eligible cases for employments remained in the village as per

the R & R policies, but the employment demands could not be

embroiled into the matter of resettlement. The resettlement site

has been provided with basic amenities such as road, electricity,

boundary wall, drainage in most of the places which were free

from   encroachment,      but     due   to   encroachment    of   eight

individuals and one private school, namely, NLS School over the

remaining areas, the development works could not be completed

at that time i.e. when the 12th RPDAC meeting took place

31.08.2021. Now, all the encroachers except NLS School have

been shifted/evicted from the site and in the meanwhile,



Writ Appeal No.34 of 2015                             Page 55 of 135
 necessary steps for drinking water and electrification works at

the site taken by MCL and these works have been outsourced to

RWSS and Tata Power for execution.

                It is further stated that twelve families have shifted

and not fourteen families. Out of these twelve families, who have

shifted, ten families i.e. Appellant nos.3, 4, 18, 20, 42, 43, 58,

70, 79 and 97 are the Appellants in the Writ Appeal. In spite of

providing all the R & R benefits, still 143 PDFs remained to be

shifted from the village. They have been raising irrelevant issues

to    justify    their   illegal   holding    onto   the   acquired    land.

Employment benefits and resettlement plots have been provided

to these twelve families as per Odisha R & R policy and all these

families        have     been      provided    company      quarters     for

accommodation.

                It is further stated that the resettlement site at

Balanda is situated over land acquired under CBA Act and there

is no provision to issue RoR under CBA Act acquired land and as

per    guideline       issued by    the   Ministry   of Coal   vide    letter

No.43022/1/2020-LAIR dated 22.04.2022, the land could be

leased out to land oustees for 99 years. As per clause 4(5)(e) of

the said guidelines, the allotted plots would be leased out in

favour of respective allottees only after shifting of the Appellants



Writ Appeal No.34 of 2015                                  Page 56 of 135
 to the site. As such, plot allotment orders have already been

issued in their names.

            It is stated that Appellant no.80 has constructed the

house over his allotment plot in R & R site and was staying in the

house and also rented out some part of the house, but after the

issue ventilated before this Court by MCL, the said Appellant has

now vacated his house in the R & R site and shifted and filed

declaration in order to support the case of the Appellants. All the

Appellants are allotted quarters for temporary accommodation till

they shift to the R & R site. In the meanwhile, some of the

Appellants have been allotted quarters as per their eligibility and

they have been shifted to their allotted quarters from temporary

accommodation (quarters). The resettlement site has been

provided with basic amenities such as road, electricity, boundary

wall and drainage in most of the places.

            It is stated that the leveling works has been

completed at the site and with regard to providing basic

amenities such as drinking water, a MoU between MCL and

RWSS division, Angul was signed for providing drinking water to

the site and accordingly, Executive Engineer (RWSS) has issued

a work order to the contractor dated 15.09.2022 and in that

respect, the MCL has also released an amount of Rs.2.18 crores



Writ Appeal No.34 of 2015                          Page 57 of 135
 towards first instalment. The declaration filed by the Appellants

is only with an intention to create hindrance in mining activities.

              It is further stated that all the Appellants have been

provided with temporary accommodations till the shifting to the

R & R site and not in due course of their employment. Only six

plots have been allotted to Appellant nos.9, 19, 22, 28, 31 and

82 and the same has been encroached by NLS School. Except

that portion of land encroached by NLS School, other lands are

free   from    encroachment     and   no    case      is    pending    for

encroachment of the R & R site. These Appellants are staying in

the    company     quarters   provided     by   MCL        as   temporary

accommodation and only NLS School‟s case vide W.P.(C)

No.8549 of 2019 is pending for disposal. So far as W.P.(C)

No.9006 of 2019 is concerned, the same has been disposed of

and the appeal under section 9 of the PP Act, 1971 preferred by

one Sagar Naik and another before the learned A.D.J., Talcher

and the same has also been dismissed as withdrawn and they

have vacated from the encroached area.

              It is further stated that Bhubaneswari OCP is one of

the biggest coal mines in India with a production capacity of 28

million tons and also major coal excavated from the mine is

being transported to major power houses producing electricity in



Writ Appeal No.34 of 2015                                  Page 58 of 135
 India. Last year owing non-vacation of acquired village land by

the villagers, MCL faced with tough task of achieving coal

production target to supply coal to power houses, but under

exigency circumstances, MCL had to scramble through whatever

little possible patches of land available in the mine to somehow

reach the production target with great difficulty. In the current

Financial Year, the production of the mine has been reduced to

more than 50% due to exigency of land with no other

alternatives available. MCL might not achieve the coal production

target due to non-availability of the land of village Hensamul

(Talasahi) and therefore, it is very urgent and necessary to shift

the villagers from Hensamul (Talasahi) to the R & R site for

continuance supply of coal to the power producing industries.

            It is further stated that the resettlement site at

Balanda   has been    provided to    the   Appellants with   basic

amenities such as road, electricity, boundary wall, drainage in

most of the places and total 6769.50 mtrs. of drainage/sewerage

work has been completed and balance drainage/sewerage work

of 1085 mtrs. is yet to be completed in the R & R site and

3280.61 mtrs. of concrete road has already been completed in

the R & R site and balance 955.00 mtrs. is yet to be completed.

The club house was constructed in the year 2016 in R & R site



Writ Appeal No.34 of 2015                          Page 59 of 135
 with all the basic facilities, but it has been remaining unutilized

till date for which some facilities/accessories of the club house

has been damaged and the same would be renovated before

shifting of the villagers to the R & R site.

              So far as construction of road, MCL has initiated a

scheme for construction of different infrastructures at Balanda R

& R site including drainage and sewerage works.

              All these families have been provided company

quarters for accommodation and they are staying in these

quarters with their families. All the Appellants have been

provided with R & R benefits including employment benefits and

they   have    been   allotted   resettlement      plots   at   Balanda

resettlement site and for temporary accommodation, these

Appellants have been provided company quarters and they are

also staying in these quarters along with their families but they

are deliberately not shifting to the R & R site.

              It is further stated that all the encroachers have

been removed from the site except NLS School. The villagers are

creating hindrances to complete the development works in the

remaining places in the site and taking frivolous pleas not to

vacate their homestead lands and they are creating hindrances

in the progress of Bhubaneswari Mine which is a mega project of



Writ Appeal No.34 of 2015                              Page 60 of 135
 India.   Due     to   non-shifting   of   the   villagers   of   Hensamul

(Talasahi), the mine has come to standstill position and the basti

of Hensamul (Talasahi) is situated at the edge of mine, which is

very unsafe and endanger to the lives of the villagers as well as

mine workers and thus, this Court might direct to the Appellants

to vacate their homestead land as well as abstain from

obstructing the development works at the R & R site for smooth

operation of coal mines and if the Appellants did not vacate their

homestead land and building standing thereon in Hensamul

(Talasahi), the coal production in Bhubaneswari OCP would be

seriously affected and would come to a standstill position which

might lead to power crises all over the nation.

12.            Appellants   filed    additional/reply   affidavit    dated

02.08.2023 to the reply affidavit dated 04.07.2023 filed by the

Respondents, wherein it is stated that the Appellants along with

other land oustees have not yet received basic amenities under

the R & R Policy, 2006.

               It is stated that the Appellants along with other land

oustees were always been cooperative with the Respondents and

are eager to shift to the Balanda Resettlement Site. The

Respondents are yet to provide the basic amenities such as

electricity connection, connecting roads and other facilities such



Writ Appeal No.34 of 2015                                   Page 61 of 135
 as drinking water, etc. The developmental work like the ground

leveling work, drainage and sewerage are yet to be completed.

As the Balanda Resettlement site has not been live worthy even

after a period of more than nine years, the Appellants who are

willing and cooperative with the Respondent authorities are not

able to relocate to the said site and due to such delay, the

Appellants and other land oustees are not able to trust the

conduct of the Respondent Authorities.

            It   is   further   stated   in   the   affidavit   that   no

developmental work has been done since the month of March

2023 and considering the grievances of the villagers of the

villages of Hensamul, Kalamachuin, Raghunathpur, Nakeipashi,

Padmabatipur, Mahendrapur, Patharamunda and Chhelia (which

have been acquired by MCL), a meeting was held on 08.06.2023

under the Chairmanship of the Collector, Angul, where the MLA,

Talcher, Sub-Collector, Talcher, Special Land Acquisition Officer,

MCL, Angul, Director (Technical), Director ( Personnel), MCL,

Burla, General Manager, Jagannath Area, MCL, Talcher and other

officials of MCL were present along with the representatives from

the villages of the aforesaid villages. In the said meeting, a

resolution was passed considering the facts and circumstances

mentioned by the villagers and accepted by the authorities. The



Writ Appeal No.34 of 2015                               Page 62 of 135
 decision relating to the present Appellants made in the said

resolution dated 08.06.2023 is summarized as follows:

            i.     MCL      Authorities    have    to     decide       the

            Employment       and   PDF    cases   of    the   people    of

            Hensamul village within a period of fifteen days and

            give a report to the District Administration;

            ii.    An agreement is to be drawn between the NLS

            School and the MCL Authorities to shift them to a

            temporary accommodation and MCL Authorities shall

            provide them a temporary accommodation till the

            matter is disposed of by this Court;

            iii.   There are allegations that the school building

            which has been constructed to shift the Panchayat

            High School, Hensamul, is of low quality. Hence, a

            Joint Committee including the representatives of the

            village, the authorities of MCL and the District

            Administration shall be constituted and the same

            committee shall submit a report on the issue. After

            delivery of possession of the Panchayat High School

            to the Government, the District Administration shall

            take steps to upgrade and repair the said school

            through Sarba Shiksha Abhiyan. It is also directed to



Writ Appeal No.34 of 2015                                Page 63 of 135
             the MCL Authorities to complete the boundary wall of

            the newly constructed and inaugurated Panchayat

            High School, Hensamul and then shift the same from

            the old location to the new location;

            iv.   The MCL Authorities have to take a decision in

            their Board in respect of the claim of 10 lakhs rupees

            each by the PDFs who have given their consent to

            receive the plots. It is noticed that the Balanda R & R

            Colony which is meant for the Hensamul (Talasahi)

            has not been provided with the basic amenities till

            date. Hence, it is directed to complete the same

            within a period of one month;

            v.    The grievances of the people in relation to

            Rehabilitation, Employment and Resettlement are to

            be mitigated by the Director (Technical) and Director

            (Personnel), MCL, Burla;

            vi.   MCL is directed to release the compensation

            amount to the public as early as possible in the event

            the MCL Authorities have already made a decision to

            give solatium and interest on the assessed value of

            the houses on the Government Land;




Writ Appeal No.34 of 2015                           Page 64 of 135
             vii.        The MCL Authorities have to take steps in

            obtaining ROR and NOC for the Panchayat High

            School and constructing the boundary wall after

            consultation with Sub-Collector, Talcher and SDPO,

            Talcher.

           Pursuant to the said meeting, the villagers of

Hensamul      provided       MCL     Authorities       with    an    area    of

approximately 40 Acres for the purposes of mining and the

building of Panchayat High School, Hensamul and Nodal U.P.

School, Hensamul, which were located within such area were

demolished.

            It     is    further   stated   in   the     affidavit   that   the

Respondents      have      portrayed   incorrect       facts   regarding    the

completion of land filling in the low-line areas in the Balanda R &

R Colony in order to cloud the judgment of this Court. The

Appellants have been provided with the description of work

allotted to the Contractor with the issuance of the work order

dated 21.02.2022 and the Summary Report of the Balanda R & R

site filling dated 25.05.2023 and the same shows that only a

volume of 20531.88 Cubic Meters out of 54013 Cubic meters has

been filled. The Project Engineer in his letter dated 27.07.2023

addressed to the contractor responsible for the earth filling at R



Writ Appeal No.34 of 2015                                      Page 65 of 135
 & R site has admitted that only 31% work has been completed.

The Respondents have not completed the works in relation to the

basic amenities and that the Collector has not issued the

Completion of Resettlement Work Certificate as per clause 8 of

the R & R Policy, 2006, which along with the clause 4 of the

resolution of the meeting dated 08.06.2023.

            It is further stated in the reply affidavit that the

Respondents have stated that all the Appellants have been

allotted with plots in the resettlement site vide Plot Allotment

Letter dated 22.12.2019 but such statement is taken by the

Respondents only to cloud the judgment of this Court. In fact,

the Respondents have only allotted those plots on paper.

            It is further stated that in the affidavit dated

04.07.2023 filed by the Respondents, it is stated that out of 102

Appellants, 21 Appellants have constructed houses and Appellant

No.80 has started living in the house constructed over the plot

allotted to him, but those 21 Appellants have recently started

construction   which   is   not   yet   complete.   Even   if   those

constructions would be completed, but they could not reside

there due to lack of basic civil infrastructure such as water

supply, drainage, electricity connection, roads etc. As far as




Writ Appeal No.34 of 2015                            Page 66 of 135
 Appellant no.80 is concerned, he is unable to shift to his house

for the lack of the aforementioned facilities in the area.

            It is stated in the reply affidavit that there are 15

plots including the land encroached by the NLS School, which

have not been made encroachment free. The Respondents have

also not cleared the encroachment made by the Police Garage

and Police Utility Centre situated at Plot No.121 and 122 which is

evident from the letter of Project Engineer (Civil), BBSRI OCP to

M/s. BMS Construction where it is clearly stated that only 26% of

the work is complete. Plot No.99 has a dilapidated building,

which was used as an Anganwadi has not been cleared from

encroachment and Plot Nos.100 to 105 which are yet to be

demarcated. The demarcation of such plots are dependent upon

completion work of the main drain and the main drain work has

come to stand still since 2016 due to the non-completion of the

land filling work. The stand taken by the Respondents that all the

plots in the Balanda R & R site are encroachment free from all

encumbrances, are not correct.

            It is stated in the reply affidavit that the stand taken

by the Respondents that a majority of the Appellants are staying

in the quarters allotted to them by MCL as an alternative site in

lieu of the plots allotted to them is not correct, but the same has



Writ Appeal No.34 of 2015                            Page 67 of 135
 been made to mislead this Court and cloud its judgment. In fact,

those quarters are allotted to the MCL employees as a course of

their employment but not as an alternative site in lieu of plots.

Those quarters are small in size and could not cater the

household goods, assets and cattle of the land oustees. Most of

the Appellants are farmers and have numbers of cattle and all

the family members are required to be fit in those tiny quarters

which were never meant to be an alternative site. Only six

numbers   of     families   were   provided    Company‟s    alternative

accommodation at the time of shifting of Panchayat Office and

Shiv   Temple.    The   quarters    which     were   provided   by   the

Respondents in Central Colony are in dilapidated condition and

MCL vide letter dated 14.09.2020 has already declared those as

'unsafe'. The House Building Assistance and other R & R benefit

including compensations and incentives are yet to be provided by

the Respondents for smooth relocation and resettlement of the

land oustees.

            It is stated in the reply affidavit that though a portion

of the drainage work has been completed by the Respondents,

but the main drain is yet to be completed which is hindered by

the non-completion of land filling work and has come to a




Writ Appeal No.34 of 2015                               Page 68 of 135
 standstill since 2016 and the development work is hindered due

to the said non-completion of the main drainage work.

             It is further stated in the reply affidavit that the

Appellants have been provided with the Summary Report of the

Balanda R & R site filling dated 25.05.2023, which shows that

only a volume of 20531.88 cubic Meters out of 54013 cubic

meters has been filled till that date. The Project Engineer in his

letter dated 27.07.2023 addressed to the contractor responsible

for the earth filling at R & R site has admitted that only 31%

work has been completed. The Appellants being aggrieved by the

inaction of the Respondents have made a representation dated

21.07.2023    where   the   Appellants   requested    the   General

Manager, Jagannath Area to complete the earth filling work

which shall ultimately assist in the execution of other works like

demarcation of plots, construction of roads, completion of

drainage work, supply of electricity and drinking water in the

area. The Respondents have not carried out any developmental

work since the month of March. The construction of roads,

completion of the provision of electricity connections, and

completion of main drain work is also being hindered by the non-

completion of filling of the low line area and the encroachment of

NLS School. The stand taken by the Respondents is that by



Writ Appeal No.34 of 2015                            Page 69 of 135
 virtue of the MOU with RWSS, the pipeline laying work i.e.

5219.00 mtrs. is complete and 80% construction work of

underground reservoir and 50% of overhead tank has been

completed. In fact, the construction of the same is not being

conducted as per the Scope of Work & Technical Specification of

the work order and the quality of material used in the ESR, UGR,

OHR, Compound Wall and Pump House are below standard.

When the contractor was directed to work in accordance with the

plan, he stopped the work and since the month of March, there is

no progress in the said work. The Appellants have also informed

the Executive Engineer, Rural Water Supply and Sanitation

Department, Angul describing the irregularity in the construction

process through a letter dated 21.07.2023.

           It is stated in the affidavit that the stand taken by

the Respondents is that the electrification work was outsourced

to Tata Power and when the same work could not be done due to

hindrance from the villagers of Hensamul, the TPCODL had sent

an email dated 06.05.2023 describing the cause of non-

completion of the electrification work wherein it was stated that

the same was due to non-clearance of the site. In fact, the stand

taken by the Respondents are misleading as the hindrance

caused is not by the Appellants but due to the encroachment of



Writ Appeal No.34 of 2015                         Page 70 of 135
 NLS School which is situated in between the approved plan for

electrification.

             It is stated in the affidavit that there was no

hindrance by the villagers in the Balanda R & R site and the

incident described in the said letters are prior to the Meeting

dated 08.06.2023 and nowhere there is mention about any

hindrance in the Minutes of Meeting where the Respondents were

directed to take steps to complete the work in order to provide

the basic amenities to the Appellants and other land oustees.

The villagers have never restrained the officials of Respondents

and they are not creating any hindrance in the development

works but the development work has been stopped since the

month of March. Being aggrieved by the actions of the

Respondents, the Appellants have also made a representation

dated 21.07.2023 to the Collector, Angul praying for the

implementation of the decisions taken in the meeting held on

08.06.2023. Pursuant to the letter of the Appellants, the letters

dated    27.07.2023   were   issued   which   indicate   that   the

Respondents have not taken any steps and the stand taken by

the Respondents that the Appellants have already been given all

the basic amenities is incorrect and were made only to cloud the

judgment of this Court.



Writ Appeal No.34 of 2015                          Page 71 of 135
             It is further stated in the reply affidavit that there

are 62 cases pending approval with the Respondents in respect

of employment and the same was also noticed in the meeting

dated   08.06.2023    where    the   Collector   has    directed   the

Respondents to mitigate the grievances of all such people. All the

143 PDFs have been cooperating with the Officials of the

Respondents and they have already vacated a large area for

mining activities. The Appellants are always been eager to shift

to the Balanda R & R site, but due to lack of basic amenities,

they are not able to shift to the said site. The stand taken by the

Respondents that the lands shall be leased out in accordance

with the Ministry of Coal guideline dated 22.04.2022. In fact, the

said law is not applicable in the present case and the Appellants

are entitled under the R & R Policy, 2006.

            It is stated in the affidavit that the Appellant No.80

renting out the house at R & R site is incorrect. The stand taken

by the Respondents is that a club house was constructed in the

year 2016 with all the basic facilities, in fact, the said club house

is in a dilapidated condition beyond repair and the execution of

electricity work has been hindered due to non-clearance of

encroachment by NLS School.




Writ Appeal No.34 of 2015                              Page 72 of 135
 Appointment of Advocate Commissioner:

13.         The Appellants filed an interim application i.e. I.A.

No.4823    of   2023    on   01.08.2023   for   appointment     of     a

Commission for local inquiry in respect of status of the land as

provided as part of the rehabilitation package.

            On 22.09.2023, this Court appointed an Advocate as

Commissioner for local inquiry to enquire into the following

aspects viz., (i) Whether the basic amenities have been

extended   over   the   land   proposed   for   the   settlement     or

rehabilitation; (ii) Whether the plots are demarcated by definite

boundaries; and (iii) Whether the land has been earmarked for

road and other community activities. It was further observed

that in such rehabilitation package, the road, electricity and

water supply including the drinking water shall have to be

provided, before the Appellants are asked to occupy the

demarcated plots for construction of their houses or shelters. It

transpired that dissatisfaction in respect of the proposed land

was on the non-availability of amenities. Till the inquiry is over,

this Court requested the counsel for both the parties to fully

cooperate with the Advocate Commissioner so that he could

prepare the inquiry report within a short time-frame and place it

before this Court. This Court also requested the Commissioner to



Writ Appeal No.34 of 2015                             Page 73 of 135
 make his observations regarding the position of the village vis-a-

vis the mining operation that was carried out by MCL. This Court

also   requested   Advocate       Commissioner      to    approach      the

Collector, Angul for providing him a technical person to aid and

assist him at the time of his field inquiry and the Collector, Angul

was directed to depute a technical person, if requested by the

Commissioner.

Report of Advocate Commissioner:

14.         Pursuant   to    the    order   dated     22.09.2023,       the

Advocate Commissioner filed his report dated 30.10.2023 after

local inquiry, the relevant parts are extracted herein below:

            ''Field Visit:

            1. The undersigned visited the village Hensamul

            and the resettlement site near Balanda College

            on 14.10.2023 along with officials of MCL, and

            villagers of Hensamul including the Sarpanch.

            The Sub-Collector, Angul as well as the District

            Mining Officer, Angul were also in attendance

            during the inspection.

                   Copies    of    the   attendance      sheets   are

            annexed herewith and marked as Enclosure-1.




Writ Appeal No.34 of 2015                                 Page 74 of 135
             2. Observations were taken in respect of each of

            the 154 plots allotted to villagers of Hensamul.

            Further,     the        undersigned          took        several

            photographs        of   village     Hensamul         and    the

            rehabilitation site.

                   Copy of the plan map of the resettlement

            site   is   annexed      herewith         and     marked     as

            Enclosure-2.

                   Copies of the photographs of Hensamul

            village are annexed herewith and marked as

            Enclosure-3 Series.

                   Copies      of    the      photographs         of    the

            resettlement site are annexed herewith and

            marked as Enclosure-4 Series.

            Findings & Observations:

           01.     Electricity:      Electric        poles    have     been

           erected in respect of all plots. However, some

           electric poles have not been wired and some

           others having wires are in a state of disrepair. It

           was stated by the MCL authorities that the

           repairing     and    stringing       of    wires     can    been

           completed within a short period of a few days.



Writ Appeal No.34 of 2015                                       Page 75 of 135
             02.   Water Supply: Community water tank is

            still under construction. No water pipes have

            been laid down for supply of water to the

            individual plots. Presently, allottees are availing

            water from two constructed wells and water

            tanker     services   only    for     the   purpose    of

            construction of houses. The water supply is

            wholly inadequate and makes the entire colony

            uninhabitable.

            03.   Sewerage and Drainage: All the plots

            have been provided with drainage sewers which

            are connected to a primary drain leading out of

            the resettlement colony. Three plots have been

            affected    by   waste   water      coming    from    the

            neighbouring      MCL        rescue     station.      MCL

            authorities stated that special drains will be

            made for the said plots.

            04.   Plot Levelling: Several complaints were

            received from allottees that the plots are not at

            the same level as the road and considerable

            investment had to be made towards levelling

            and compacting the plots. Although several plots



Writ Appeal No.34 of 2015                                Page 76 of 135
             did seem to be at a much lower level than the

            road, large number of allottees have constructed

            houses despite the same.

            05.    Plot     Demarcation:            Although          MCL

            Authorities     stated    that     plots       had        been

            demarcated back in 2014 but no such physical

            demarcation (except one or two dilapidated

            pillars) in respect of any of the plots was visible.

            The plots can be identified only through use of

            the resettlement colony plan map. It appears

            that   the    allottees   are    well    aware       of    the

            demarcation since around 60 houses are under

            different stages of construction.

            06.    Road     Connection:       All    the    plots      are

            connected by way of roads wide enough for

            vehicles. Only those plots, which have been

            encroached upon by the Nigamananda Little Star

            School have no roads connected.

            07.    Community Centre/Club: The building

            has been constructed. However, the same is

            presently in a state of disrepair due to lack of




Writ Appeal No.34 of 2015                                   Page 77 of 135
             use. Several cracks have also developed along

            the walls making the building unsafe.

            08.    School: The old Hensamul Upper Primary

            + High School has been shifted to an area 5 km.

            from the Resettlement Colony at the instance of

            the villagers of Hensamul. Besides, space has

            been    allotted       for   a    school   inside        the

            resettlement     colony      which    is   yet     to    be

            constructed.

            09.    Clinic/Dispensary:          Space    has         been

            allotted for a clinic inside the resettlement

            colony which is yet to be constructed.

            10.    Police:     A   police    outpost   is    available

            outside the entrance to the resettlement colony.

            11.    Religious Structures: Space has been

            allotted for a temple inside the resettlement

            colony which is yet to be constructed. A yajna

            mandap has also been constructed inside the

            colony. The old temple of the village has been

            shifted near the new Hensamul Upper Primary +

            High School at the instance of the villagers of

            Hensamul.



Writ Appeal No.34 of 2015                                   Page 78 of 135
             12.   Market Space: Space has been allotted

            for a market inside the resettlement colony

            which is yet to be constructed.

            13.   Park/Green Space: Separate spaces for

            a playground and a park have been allotted

            inside the resettlement colony which are yet to

            be constructed.

            14.   Panchayat Office: Office of the Gram

            Panchayat, Hensamul has been constructed next

            to the new Hensamul Upper Primary + High

            School, 5 km. from the rehabilitation site, at the

            instance of the villagers.

            15.   Anganwadi      Centre:   Space     has   been

            allotted for the centre inside the resettlement

            colony which is yet to be constructed.

            16.   Kalyan Mandap: Space has been allotted

            for a mandap inside the resettlement colony

            which is yet to be constructed.

            17.   Village Pond: Already in existence inside

            the colony.

            18.   Around 60 houses are in various stages of

            construction in the resettlement colony but no



Writ Appeal No.34 of 2015                            Page 79 of 135
             person is presently in habitation inside the

            colony.

            19.    It may be noted that encroachment in the

            form of the Nigamananda Little Star School

            covers across 12 plots over which no amenities

            or roads have been constructed. The issue

            eviction of Nigamananda Little Star School was

            pending adjudication before this Hon‟ble Court in

            W.P.(C) No.8549 of 2019 which has been

            disposed of vide order dated 09.10.2023.

            20.    Status of Village Hensamul: The village

            is    flanked   on   nearly   all   sides    by    the

            Bhubaneswari OCP, Lingaraj OCP, and Ananta

            OCP. The cliff edge of the mines is at a distance

            of just 100 meters from the village. Although

            several persons were seen in the village on

            14.10.2023, the dense undergrowth inside the

            village as well as the state of disrepair of the

            buildings indicates that most of the village is in

            a state of abandonment. Further, black coal dust

            blankets and pollutes the area in and around the




Writ Appeal No.34 of 2015                               Page 80 of 135
             village. It is imperative that the village may be

            vacated at the earliest.

            Conclusions:

            01.   Whether     the   basic      amenities   have

            been extended over the land proposed for

            resettlement or rehabilitation?

                  The reference may be answered in the

            negative due to the complete inadequacy in

            supply of water, and the electricity infrastructure

            being in a state of disrepair.

            02.   Whether the plots are demarcated by

            definite boundaries?

                  Although    no    physical    demarcation   is

            visible on the ground, demarcation can be made

            using the site map. Around 60 allottees have

            constructed houses on that basis.

            03.   Whether the land has been earmarked

            for road and other community activities?

                  The reference may be answered in the

            positive. All plots, except the plots encroached

            upon by the Nigamananda Little Star School are

            connected by way of roads. Space has been



Writ Appeal No.34 of 2015                            Page 81 of 135
             allowed for several community buildings which

            are yet to be constructed.

            04.   Observations regarding the position of

            the   village    vis-à-vis   mining        operations

            carried out by MCL.

                  In light of the pollution, physical state of

            the   village,   and   the      vicinity    of   mining

            operations, it is imperative that the village may

            be vacated at the earliest.‟‟

15.         Pursuant to the aforesaid report dated 30.10.2023 of

the Advocate Commissioner, the Appellants filed an affidavit on

06.12.2023, wherein it is stated that some of the facts require

clarifications and some relevant facts are required to be brought

on record for the purposes of facilitating this Court in effectively

and completely adjudicating the dispute between the parties

which are as follows:

            ‟‟(i) In reply to para 1 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, it is stated that though electricity

            polls have been erected as stated by the learned

            Advocate     Commissioner,        the      wiring   and

            electricity connections are not provided and the



Writ Appeal No.34 of 2015                                Page 82 of 135
             erection of electricity polls near most of the

            plots have been done recently pursuant to the

            appointment         of        the      learned         Advocate

            Commissioner vide order dated 22.09.2023 by

            this Court, but the work relating to the same is

            far   from   over       and    the     same      is    a    major

            impediment in the process of resettlement that

            remains unaddressed by MCL;

           (ii)    In reply to para 3 of the „Findings and

           Observations' in the aforesaid report dated

           30.10.2023, it is stated that in respect of

           sewerage and drainage, the primary drain has to

           be completed for the drainage of wastewater

           from    the   R      &    R     site,    but   due          to   the

           encroachment of NLS School, the said work has

           come to a halt;

           (iii) In reply to paras 4 and 5 of the „Findings

           and Observations' in the aforesaid report dated

           30.10.2023, it is stated that some land oustees,

           who     are   financially            sound,    have         started

           construction on some of the plots by taking

           personal loans from the Banks with higher



Writ Appeal No.34 of 2015                                         Page 83 of 135
            interest rates. The constructions on some of the

           plots    have    been   done    over    uneven     land.

           However, only 31% of Earth filling work has

           been done as per the records of MCL which was

           submitted before this Court in the previous

           affidavits and which is also confirmed by the

           learned Advocate Commissioner in his report.

                   It is further stated that the TAMDA Plan

            for the resettlement site was approved on

            05.12.2015, which has been produced by the

            learned Advocate Commissioner at Enclosure-2.

            Some     of    the   Land    oustees   had      started

            construction over encroachment free portions of

            the resettlement site in order to minimize the

            displacement process in good faith, but most of

            the plots could not be properly demarcated due

            to     encroachment     by     250     numbers       of

            encroachers including NLS School. Though most

            of the encroachments have been eventually

            cleared, the encroachments by the NLS School,

            one police garage and one old Anganwadi are

            yet to be cleared.



Writ Appeal No.34 of 2015                             Page 84 of 135
                    As per the order of this Court dated

            09.10.2023 passed in W.P.(C) No.8549 of 2019,

            the eviction of NLS School is not possible till the

            month of April 2024. Therefore, till the said

            encroachments are cleared, the demarcation of

            plots along with the provision of basic amenities

            has come to a halt;

            (iv) In reply to para 7 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, It is stated that the quality of the

            construction work made by MCL speaks for itself

            as it is evident from the report of the learned

            Advocate Commissioner;

            (v) In reply to para 8 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, it is stated that the UP school and

            Panchayat High school has been shifted to the

            area   where    other   villagers   of   Hensamul

            Panchayat are living. The said school has been

            functioning for the entire Hensamul Grama

            Panchayat. The said resettlement of UP School




Writ Appeal No.34 of 2015                            Page 85 of 135
             and Panchayat High school are not part of the

            resettlement of Hensamul village;

            (vi) In reply to para 11 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, it is stated that the Yagyan Mandap

            which is shown in the report of the learned

            Advocate Commissioner has been constructed

            by the villagers on a temporary basis for Bhumi

            Pujan Utsav by utilizing their own funds. The Old

            Siva Temple which has been shifted near the

            Hensamul    Panchayat    High   School      was   the

            worship place of whole Hensamul Panchayat;

            (vii) In reply to para 14 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, it is stated that shifting of the

            Panchayat Office was a conscious decision of the

            State   Government      and   the   role    of    MCL

            Authorities in the said process is none;

            (viii) In reply to para 17 of the 'Findings and

            Observations' in the aforesaid report dated

            30.10.2023, it is stated that though the learned

            Advocate Commissioner has noted that there is



Writ Appeal No.34 of 2015                              Page 86 of 135
             a village pond inside the colony, but there is no

            pond inside the colony and the waste water

            clogged   inside     the    colony     is   due    to   non-

            completion of main drain work. The water has

            been   clogged       in    the   low    line   areas    and

            necessary steps are required to be taken to fill

            those clogged areas with good earth before

            allotment of plots;

            (ix) In reply to paras 19 and 20 of the 'Findings

            and Observations" in the aforesaid report dated

            30.10.2023,     it    is    stated     that    during    the

            pendency of the case, the villagers including the

            Appellants have always cooperated to the MCL

            management without any hindrance for the coal

            production with a hope for early settlement of

            rehabilitation and resettlement issues of the

            village. As a result, the project is achieving its

            annual target each financial year.

            It is stated in the affidavit that learned Advocate

Commissioner after visiting the village and after considering the

aspects like pollution, physical state of the village and vicinity of

the mining operations, opined that the village might be vacated



Writ Appeal No.34 of 2015                                     Page 87 of 135
 at the earliest. In fact, the Appellants, though are eager to

vacate the village as soon as possible, are not able to shift to the

resettlement site as the resettlement site lacks basic amenities

like water, electricity etc. It is the mandate of law that no

physical displacement shall be made before the completion of

resettlement work approved by the RPDAC and the complete

physical displacement could be done only after issuance of

completion certificate by the Collector as per Para 7 clause (ii) of

the Odisha R & R Policy, 2006.

Highlights of reply affidavit filed by Respondents to the

Advocate Commissioner's report:

16.         Pursuant to the aforesaid report dated 30.10.2023

submitted by the Advocate Commissioner, the Respondents filed

an affidavit on 17.06.2025, wherein it is stated that in pursuance

to the order dt.22.09.2023, the learned Advocate Commissioner

visited village Hensamul (Talasahi) and resettlement site near

Balanda College on 14.10.2023 along with villagers of Hensamul

(Talasahi) including the Sarpanch, Government officials and

officials of MCL and given certain observations:

Observations:

            i.    With   regard   to   the   observation   made   by

            learned Advocate Commissioner, it is stated that



Writ Appeal No.34 of 2015                            Page 88 of 135
            some electric poles could not have been wired due to

           hindrance in the site. Moreover, on thirteen plots,

           which was encroached by Nigamananda Little Star

           School, electric poles and wires have not been

           erected. In pursuant to the direction of this Court

           dt.06.12.2024 passed in W.P.(C) No.9912 of 2024

           and W.P.(C) No.9921 of 2024, MCL has evicted and

           demolished the encroached area NLS school on

           24.12.2024 and after eviction, MCL authorities has

           issued the letters dt.07.01.2025 and 26.05.2025 to

           the allottees to take over the possessions of thirteen

           plots, but they are not showing interest to take

           possession of the said thirteen plots.

                 So far as erection of electric poles and cable

           wires in the rest part of the land including said 13

           plots is concerned, the MCL authorities along with

           authorities   of   Tata   Power   visited   the   spot   on

           12.06.2025 and demarcated the spot where the

           electric poles have to be erected and as discussed

           with Tata Power, all the pending works related to

           erection of the electric poles and cable wires for all

           the plots would be erected within one month. It is



Writ Appeal No.34 of 2015                              Page 89 of 135
            stated that no cable wires are in a state of disrepair

           as the cables used for wiring are of Aerial Bunch (AB)

           cable,   which      are   to   be    strengthened   during

           completion of the rest part;

            ii.   The       observation    of    learned    Advocate

           Commissioner regarding water supply to the R & R

           plots, it is stated that the overhead tank has already

           been constructed and the same is functional. The

           Superintending Engineer, RWS & S Division, Angul at

           Talcher, vide its letter dt.10.06.2025 has informed to

           the General Manager, Bhubaneswari Area stating

           therein that rural piped water supply to R & R site for

           village Hensamul (Talasahi), At-Koilanagar in front of

           Balanda College has been completed and at the stage

           of commissioning with the following details:

           a. 2.0 lakh ltr. capacity 15 mtr staging ESR -

           completed.

           b. 3.0 lakh ltr. capacity UGR - completed.

           c. Pump House - completed.

           d. Staff Quarter - completed.

           e. Compound Wall - completed.

           f. Rising Main - completed.



Writ Appeal No.34 of 2015                             Page 90 of 135
             g. Distribution system - completed.

            h. External Electrification with 25 KVA transformer &

                  internal Electrification - completed.

                    The main water pipelines have already been

           laid over the R & R site, the supply of water to the

           individual plots/house could be provided through

           Functional Household Tap Connection (FHTC) after

           submission       of   necessary   documents       along   with

           applications by the Appellants to the office of RWS &

           S Division, Angul, Talcher;

           iii.     The     observation      of   learned       Advocate

           Commissioner regarding sewerage & drainage to the

           R & R plots, it is stated that special drain has already

           been constructed for taking out the waste water

           coming from the neighbouring MCL rescue station of

           the three plots;

           iv.      The     observation      of   learned       Advocate

           Commissioner regarding plot levelling of the R & R

           plots, it is stated that all the R & R plots have been

           levelled to the road level including thirteen plots

           which were encroached by NLS;




Writ Appeal No.34 of 2015                                 Page 91 of 135
            v.    The        observation       of     learned    Advocate

           Commissioner regarding plot demarcation of the R &

           R plots, it is stated that there is no dispute regarding

           demarcation of plots between the allottees and MCL

           since several allottees (i.e. 60 nos.) have already

           constructed their houses in the R & R site;

                 After      eviction     of   NLS     school,   the   MCL

           authorities have demarcated thirteen plots by putting

           cement        pillars.      Letters      dt.07.01.2025     and

           26.05.2025 have been issued to the respective

           thirteen allottees to take over the possession of their

           allotted plots, but till date, they are not showing

           interest to take over the possession of the said plots;

           vi.   The        observation       of     learned    Advocate

           Commissioner with regard to road connection of the

           R & R plots, it is stated that concrete road connecting

           to the individual plots have been completed except

           the thirteen plots which was encroached by NLS

           School.

            It is stated in the affidavit that so far as other

development with regard to construction of balance concrete

road, Community Centre/Club. Primary Health Centre, Temple



Writ Appeal No.34 of 2015                                 Page 92 of 135
 (i.e., Maa Mangala and Maa Hingula Temple), Market Place,

Anganwadi Centre, Dolo Mandap, remaining main drain 90 m &

box culvert, Kothaghara are concerned, a tender has been

floated on 22.01.2025 and the said tender is with regard to

ancillary   developments    on   the   resettlement   site   and   the

construction of the same would be completed by the time houses

are constructed by the Appellants over the R & R site.

             It is further stated in the affidavit that all the

Appellants have been provided all the R & R benefits including

employment benefits. They have been allotted resettlement plots

at Balanda resettlement site and for temporary accommodation,

these Appellants have been provided company quarters/their

own accommodations, which has been given in details in affidavit

dated 12.01.2023 and they are also staying in these quarters

along with their families. They are deliberately not shifting to the

R & R site although the Appellants are serving in MCL since last

twelve years and so also staying in MCL quarters or self-

accommodation since last twelve years.

             It is further stated in the affidavit that the learned

Advocate Commissioner has rightly observed that the village

Hensamul (Talasahi) is flanked on nearly all the sides by the

Bhubaneswari OCP, Lingaraj OCP and Ananta OCP and the cliff



Writ Appeal No.34 of 2015                             Page 93 of 135
 edge of the mines is at a distance of just 100 Meters from the

village. From the paragraph 20 of the said report dt.30.10.2023,

it clearly reveals that villagers are not staying in the village

Hensamul (Talasahi) and all the villagers are staying in the

temporary    accommodation        provided      by     MCL    or     self-

accommodation. Some of the appellants i.e. more than 60 in

numbers have also constructed houses at the R & R site and the

Hensamul (Talasahi) is at the edge of mines and at any moment,

mining accident/untoward situation might happen if complete

village is not evacuated.

            The     Respondents        have   issued    notice      dated

12.06.2025 to many of the Appellants for acceptance of Ex-

gratia of Rs.5 Lakhs approved in favour of their children, who

were minor on the cut-off date of the acquisition of the land for R

& R benefits and also to vacate the premises by handing over the

possession of the vacated land to MCL and the Ex-gratia benefit

is beyond the R & R Policy 2006.

17.         Pursuant to the notice dated 12.06.2025 issued by

the Respondents, the Appellants filed an interim application i.e.

I.A. No.2939 of 2025 with a prayer to restrain the Respondents,

MCL   Authorities   from    evicting    the   Appellants     from   their

respective residential houses at village Hensamul (Talasahi) with



Writ Appeal No.34 of 2015                               Page 94 of 135
 a further prayer to restrain them from taking any coercive action

against the Appellants till disposal of the writ appeal.

            In the aforesaid interim application, the Respondents

intended to file objection and accordingly, this Court vide order

dated 19.06.2025 passed an order of status quo in respect of the

dwelling house in question as per Annexure-2 annexed in the

said interim application be maintained till the next date and the

status quo order was extended from time to time.

18.         The Respondents filed reply to I.A. No.2913 of 2025

and I.A. No.2939 of 2025 filed by the Appellants, wherein it is

stated that the Appellants filed W.P.(C) No.21006 of 2014 with

the following prayers:

            "(a) why        the   letter   dated   31.07.2014    vide

            Annexure-12 to the extent challenged in the writ

            application, shall not be quashed;

            (b)   why the Opp. parties shall not be directed to

            reinstate the services of the Petitioners without

            attachment and imposition of any conditions and in

            accordance with letter dated 09.07.2014 of the Sub-

            Collector, issued in terms with the decisions taken in

            the meeting dated 06.07.2014;




Writ Appeal No.34 of 2015                             Page 95 of 135
             (c)       why the Opp. parties shall not be directed to

            not       to   take   any   coercive    action     against   the

            Petitioners till they are allotted plots physically in the

            resettlement site."

            It is further stated that so far as prayers in the

W.P(C) No.21006 of 2014 at Sl. No.(a) and (b) are concerned,

the same relate to the letter dated 31.07.2014 and the condition

stipulated under the said letter are beneficial to the Appellants

and were agreed upon by the Appellants as has been noted by

the learned Single Judge in the impugned judgment.

            It is further stated that in respect of prayer at Sl.

No.(b), the Appellants have contended that the Respondents be

directed to reinstate the services of the Appellants without

attachment and imposition of any condition in accordance with

letter dt.09.07.2014 of the Sub-Collector, in terms of the

decision taken in the meeting dt.06.07.2014. In that regard, it is

stated   that   all    the   Appellants   have     been   reinstated     and

consequential benefits have been given to them as stated in

letter dt.31.07.2014.

            The aforesaid letter dated 31.07.2014 contained five

stipulations, which reads as follows:




Writ Appeal No.34 of 2015                                    Page 96 of 135
             "i)     Re-instatement      of    all     the       terminated

            employees without break in service and with

            immediate effect;

            ii)     The villagers will not have to submit

            affidavit for the same;

            iii)    MCL has already agreed for allotment of R

            & R site situated in front of Balanda college as

            has been decided in the PLRRC meeting on

            19.07.2014. MCL will allot plots to villagers at R

            & R site in front of Balanda College duly decided

            by PLRRC after obtaining clearance from the

            Govt.    of   India   and   diversion          of    forest,    if

            required. MCL management has already initiated

            action   before   the     appropriate          authority       for

            allotment of plots;

            iv)     The   villagers     who         are     not     having

            company‟s       accommodation           will    be     allotted

            company‟s quarters on priority basis and in

            minimum possible time as decided in the Sub-

            Collector‟s meeting on 06.07.2014;




Writ Appeal No.34 of 2015                                       Page 97 of 135
                 v)     MCL has also agreed to adjust the period

                of absence due to termination from service with

                payment of leave in credit of the individual."

                So far as stipulation at Sl. No. (i) of the aforesaid

letter dated 31.07.2014 relating to reinstatement of all the

terminated       employees       without    break      in   service   and   with

immediate       effect    is concerned, the         same      has been      duly

implemented. So far as stipulation at Sl. No. (ii) is concerned,

i.e., the villagers would not have to submit affidavit for the

same, has not been insisted upon. So far as Sl. No. (iii) is

concerned, all the Appellants except Sl. Nos.29 and 34, namely,

Pratima Sahoo and Dasarathi Sahoo have been allotted plots. So

far as Sl. No. (iv) is concerned, it is stated that for 97 Appellants,

in   addition     to     the   allocation   of   the    plots,    MCL   quarter

accommodation has been provided. So far as Sl. No. (v) is

concerned, it is stated that MCL has also agreed to adjust the

period of absence due to termination from service with payment

of leave in credit of the individual and the same also has also

been given effect to.

                It is further stated that the land in question has

already been acquired and stands vested with MCL and any




Writ Appeal No.34 of 2015                                        Page 98 of 135
 unauthorised occupancy and use would seriously prejudice and

hamper the interest of the State and the economy as a whole.

            It is further stated that out of 377 Project Displaced

Families (PDFs), 223 PDFs have opted for cash compensation of

Rs.6,32,000.00 paisa in lieu of Resettlement Plots and have

voluntarily vacated their lands, both agricultural and dwelling

house and given physical possession of the same to MCL and the

rest 154 PDFs have been allotted with the resettlement plots. All

the Appellants have been allotted the resettlement plots and only

Appellant no.34 has taken cash compensation of Rs.6,32,000.00

paisa in lieu of plot and Appellant no.29 is not eligible for

resettlement of plot.

            It is further stated that the W.P.(C) No.21006 of

2014 was filed basically being aggrieved by the timeline

stipulated in the letter dated 31.07.2014, wherein the Appellants

were required to vacate the properties/land before 31.10.2024.

            It is further stated that during the pendency of the

writ appeal, an Advocate Commissioner was appointed vide order

dated 22.09.2023 and was asked to submit a report on the

terms of reference. In pursuance         to the aforesaid order

dt.22.09.2023,   the    learned   Advocate   Commissioner   visited

village Hensamul (Talasahi) and resettlement site near Balanda



Writ Appeal No.34 of 2015                          Page 99 of 135
 College   on     14.10.2023    along   with   villagers   of   Hensamul

(Talasahi) including the Sarpanch, Government officials and

officials of MCL and filed his report giving certain observations.

               It is stated in the reply that the interim applications

have been filed with artificial and expanded prayer to the effect

that minor children of some of the Appellants who have now

attained majority and hence entitled to employment and till such

time as the said appointment is given, there could be no eviction

and that providing employment to children of the Appellants, is

beyond the scope of the Writ Appeal.

               The Additional Secretary to Govt. of Odisha, Revenue

and Disaster Management Department vide letter No.RDM-RRC-

CLRFIC-0002/2018-34288/R&DM             dt.05.11.2019,         issued   a

clarification on the decision taken in the 10th RPDAC meeting in

respect of MCL projects of Angul District held on 15.05.2018. In

the said clarification letter dt.05.11.2019 at Sl. No.4 has clarified

regarding "Fixation of Cut-off date for providing R & R benefits to

the eligible PAFs in accordance with the amendment made by the

Govt. in Revenue and Disaster Management Department".

            The Law Department has observed that the ORRP,

2006 came into effect from 14.05.2006 i.e., the date of its




Writ Appeal No.34 of 2015                                 Page 100 of 135
 publication in the gazette. In the said clarification, it has been

stated that-

               "     xxx               xxx                  xxx

                     In this connection, Law department has further

               observed that the purpose of declaring eligibility of R

               & R benefits, Para 2(c) of the ORRP, 2006 that

               determines    the    cut-off   date   has   undergone

               amendment     vide   resolution   dt.15.12.2017.   This

               resolution has a prospective effect. Time and again,

               the matter relating to the R & R benefits was placed

               before the RPDAC which has issued guidelines to the

               project proponent regarding expeditious grant of the

               benefits. Earlier, it had fixed the date of passing of

               the award as the cut-off date for R & R benefits. It

               appears that pursuant to these guidelines, the

               project proponent (here MCL Authority) has given

               employment to the affected and displaced families.

                     Now, the question arises as to whether the

               minor of the family which availed R & R benefits, on

               becoming major after the cut-off date is entitled for

               the R & R benefit in respect of the same project. The

               answer is certainly "No" in as much as the family of



Writ Appeal No.34 of 2015                             Page 101 of 135
             the minor having availed the benefits under the

            policy, on attaining majority cannot constitute a

            "separate family" within the meaning of the ORRP

            especially when the lands for the purpose of the

            benefits having already been acquired is no longer

            available for consideration of R & R benefits."

            It is stated in reply that in view of the above

clarification issued by the Govt. of Odisha, the present claim of

the Apellants to give employment to their children, who were

minor on the cut-off date i.e., 25.03.2007 and has attained

majority as on 01.01.2024, could not be entertained and the said

claim/prayer of the Appellants is liable to be rejected.

            It is further stated that the cut-off for extending the

benefit of employment is 25.03.2007. Family members of the

Appellants, who were eligible as on the said date have been

provided with employment. In addition the above benefits, an

ex-gratia amount of Rs.5,00,000/- (rupees five lakh only) has

been offered to many of the Appellants and their claimants vide

notice dt.12.06.2025 for acceptance of Ex-gratia of rupees five

lakhs approved in favour of their children, who were minor on

the cut-off date of the acquisition of the land for R & R benefits

and also to vacate the premises by handing over the possession



Writ Appeal No.34 of 2015                           Page 102 of 135
 of the vacated land to MCL and the Ex-gratia benefit is beyond

the R & R Policy 2006.

             With regard to issuance of the compliance certificate

by the concerned Collector of the District as per Clause-7(ii) of

the Resettlement and Rehabilitation Policy, 2006, it is stated that

the Collector, Angul had sent a letter dated 10.06.2025 to GM,

Bhubaneswari Area regarding submission of present status

report on completion of Balanda R & R site for resettlement of

154   PDFs    from   Hensamul       (Talasahi)   Basti    and    the    GM,

Bhubaneswari Area has informed the Collector, Angul vide letter

dated 19.06.2025 about the status report on resettlement of 377

PDFs from Hensamul (Talasahi), wherein it is indicated that out

of 377 PDFs, 223 PDFs have opted for cash compensation in lieu

of resettlement plot and the balance 154 PDFs have been

allotted plots @ Ac.0.10 decimals of land to each PDF at R & R

site, Balanda, as per their own demand.

             With    regard    to   MCL   extending      house    building

assistance   of Rs.14,50,000/- and Rs.25,00,000/- to                   those

displaced    families,   who   have    opted     for   self-relocation    is

misconceived and it is stated that the same has no application to

the present case.




Writ Appeal No.34 of 2015                                 Page 103 of 135
              In pursuance of the order dated 19.07.2010 passed

in SLP (C) No.6933 of 2007 by the Hon‟ble Supreme Court, the

Claims     Commission       constituted    for    determination      of

compensation and R & R benefits for the 14 villages only i.e.

Sardega,     Gopalpur,      Jhupurunga,     Ratnansara,      Tikilpara,

Bankibahal, Balinga, Kulda, Siarmal, Tumulia, Garjanbahal,

Bangurkela, Karlikachhar, Kiripsira and Laima (RF) in the district

of Sundargarh, Odisha. In the aforesaid villages, cut-off i.e.

September,    2010   has    been   fixed   by    the   Hon‟ble   Claims

Commission which has been approved by the Hon‟ble Supreme

Court for determination of the benefits. The Hon‟ble Supreme

Court vide its judgment dated 03.11.2022 has observed that as

far as the land owners, who cannot secure a plot, are concerned,

a lump sum compensation to the extent of Rs.25 lakhs should be

paid to them. It clearly reveals that all the land owners in the 26

villages are not entitled to Rs.25 lakhs. So far as Rs.14.50 lakhs

are concerned, the Hon‟ble Claims Commission enhanced the

house building assistance and the Hon‟ble Supreme Court has

observed the same in its judgment and no specific direction has

been given to that extent in the conclusion part of the Judgment.

The aforesaid 14 villages are special case under the supervision

of the Hon‟ble Supreme Court and judgment has been passed by



Writ Appeal No.34 of 2015                               Page 104 of 135
 the Hon‟ble Supreme Court under Article 142 of the Constitution

of India. It is stated that in view of the above, the Appellants are

not entitled to the benefits as per the village Gopalpur.

              So    far   as   non-receipt    of     any   House     Buildings

Assistance from MCL, it is stated that the House Buildings

Assistance to the tune of Rs.2,78,000.00 as per R & R Policy,

2006 has been sanctioned to all the PDFs and the same would be

disbursed, if the PDFs wants to avail the benefits with prior

application   before      shifting   from    their    dwelling   houses     at

Hensamul (Talasahi).

              With regard to existence of Govt. structures over plot

nos.99 and 100 at Balanda R & R Site, it is stated in the reply

that on the request of the villagers, the said Govt. structures had

not been demolished during demolition of 164 structures

encroached at the site in the year 2018 as the structure is an

Anganwadi Kendra and they requested that the Anganwadi

Kendra would be used for the benefits for the children of

Hensamul (Talasahi). If the village committee wants to demolish

the   same,        then    after     consultation      with    the    District

Administration, the aforesaid structure would be demolished and

to allot the same to the allottees of Plot Nos.99 and 100 and if

the Appellants did not want to demolish the said Anganwadi



Writ Appeal No.34 of 2015                                     Page 105 of 135
 Kendra, then two plots @ Ac.0.10 Dec. each could be allotted

within the resettlement site.

             With regard to safety of the villagers, it is stated that

the Commission has already submitted its report stating that the

village is flanked on nearly all sides by the Bhubaneswari OCP,

Lingaraj OCP and Ananta OCP and the cliff age of the mines is at

a distance of just 100 meters from the village. From the report of

the Commission, it is being confirmed that the village should also

be vacated from safety point of view.


19.          On 25.07.2025, in the midst of hearing, a proposal

was floated by the learned Advocate General that the matter

could possibly be sorted out by way of amicable settlement

between the parties. Accordingly, the matter was adjourned to

facilitate the parties to explore the same.

             It seems that a lengthy grievances/demands styled

as "Terms of Settlement" was placed by the Appellants on

08.08.2025 before the Respondents.

             The Respondents filed objection dated 02.09.2025 to

the proposed terms of settlement dated 08.08.2025 submitted

by    the   Appellants,   wherein   it   is   stated   that   purely   on

compassionate ground, the Respondents have addressed each

and every demand of the Appellants. The Appellants have


Writ Appeal No.34 of 2015                                Page 106 of 135
 availed all the benefits under the Rehabilitation and Resettlement

Package and most of the land losers have vacated dwelling

houses in the villages under acquisition following the due process

of   law   under       the   CBA   Act,    1957.     All   the   statutory

benefits/compensation including the benefits under Rehabilitation

and Resettlement Scheme have been fully granted to the land

losers and that nothing remained to be paid to anyone of them.

             It   is   further   stated   in   the   objection   that   the

compensation towards the land and the structures have been

paid to the Appellants and the building assistance has been

sanctioned for the Appellants towards shifting and construction

of houses. The area/resettlement site has been developed with

water supply and electricity connection along with other essential

amenities.

             It   is   further   stated   in   the   objection   that   on

13.08.2025, the learned Collector & District Magistrate, Angul

has issued Certificate of Completion of the Resettlement and

Rehabilitation (R & R) of the Project Displaced Families of village

Hensamul (Talasahi) under the provisions of para 7 (ii) of the

Odisha Resettlement and Rehabilitation Policy, 2006.

             It is further stated in the objection that 377 persons

were displaced because of the acquisition and the compensation



Writ Appeal No.34 of 2015                                  Page 107 of 135
 has been paid since 2007 after passing of the award. Despite

availing all the benefits under law, the Appellants still litigate

with intention of obstructing the industrial activity, which is

detrimental to the growth of national economy.

            It is further stated in the objection that taking a

compassionate view of the matter, though the Respondents had

expressed willingness to amicable settlement of the dispute and

a proposal was mooted but a lengthy grievance styled as "Terms

of Settlement" has been filed by the Appellants on 08.08.2025.

The unreasonable bargain of the Appellants is neither sanctioned

by law nor coming under the Rehabilitation and Resettlement

Scheme.

            It is further stated in the objection that the writ

appeal is camouflaged to build pressure on a leading public

sector undertaking of the Country and to deter the development

of the area. Coal being a major raw material for production of

energy, the conduct and action of the Appellants need to be

reprimanded in the highest terms and pursuing a frivolous

litigation for last ten years despite availing all benefits is nothing

but an attempt to abuse the process of law and therefore, while

opposing the writ appeal in its entirety, the Respondents are not




Writ Appeal No.34 of 2015                             Page 108 of 135
 in a position to accede to the so-called proposal for settlement

and therefore, the Writ Appeal should be dismissed.

Final Hearing dated 04.09.2025:

20.         The matter was listed on 04.09.2025 and heard in

presence of Mr. S.P. Mishra, learned Senior Advocate along with

Mr. Soumya Mishra and Ms. Sakshi Rout, learned Advocates

appearing on behalf of the Appellants and Mr. K.M. Nataraj,

learned A.S.G.I.,   Mr. Pitambar   Acharya, learned    Advocate

General along with Mr. Rakesh Sharma, Mr. Soumyajit Pani and

Mr. Debaraj Mohanty, learned Advocates appearing on behalf of

the Respondents.

            Mr. Sanjay Kumar Dey, Chief Manager (Mining)/Staff

Officer (L & R), Bhubaneswar Area, MCL and Mr. Abdaal M.

Akhtar, the Collector, Angul were also present in person on that

day.

            Mr. S.P. Mishra, learned Senior Advocate appearing

for the Appellants filed an affidavit dated 04.09.2025 by way of

an objection to the affidavit dated 02.09.2025 filed by the

Respondents wherein it is stated that all the demands as raised

by the Appellants are well within the parameters laid down in the

R & R Policy, 2006 and para 8 (ii) of the R & R Policy, 2006

which states that no physical displacement shall be made before



Writ Appeal No.34 of 2015                         Page 109 of 135
 completion of resettlement work as approved by RPDAC. The

certificate of completion of resettlement work would be issued by

the Collector. It is further stated in the affidavit that in the letter

dated 10.06.2025, the Collector & District Magistrate, Angul

sought    for     an   update   from    the   General   Manager,    MCL,

Bhubaneswari Area, Talcher regarding the status report on

completion of Balanda R & R site for resettlement of 154 PDFs

from Hensamul (Talasahi). In reply, the GM, MCL wrote a

vaguely worded letter dated 19.06.2025 stating, inter alia, that

no valid R & R demand is pending with the land acquisition

authority. Surprisingly, in the objection affidavit filed by MCL on

02.09.2025, a letter dated 13.08.2025 appears to have been

written by the Collector & District Magistrate, Angul addressed to

the GM, MCL, Bhubaneswari Area, Talcher wherein, a Certificate

of Completion of the Resettlement and Rehabilitation (R & R) of

the PDFs of village Hensamul (Talasahi) is stated to have been

issued.

                It is further stated in the affidavit that it is not known

as to under what circumstances, the said Certificate is stated to

have been issued when the resettlement site is bereft of basic

necessities like water and electricity supply to the plots allotted




Writ Appeal No.34 of 2015                                 Page 110 of 135
 in favour of the Appellants and other PDFs of village Hensamul

(Talasahi).

              It is further stated in the affidavit that having regard

to the fact that the Certificate of Completion of the Resettlement

work as mentioned under Para 7 (ii) of the R & R Policy relates to

the development of amenities/facilities at the resettlement site,

as mentioned under the provisions of the Third Schedule of the

Act, 2013, the Collector & District Magistrate, Angul could under

no   circumstances     whatsoever       have   issued   the     so-called

Certificate of Completion when there is absolutely nothing on

record to portray that the resettlement site has been developed

in terms of the facilities/amenities as provided under the

provisions of the Third Schedule of the Act, 2013, therefore, the

said letter dated 13.08.2025 is an act of conspicuous mala fides

and amounts to playing fraud on this Court. It is further stated

that the Certificate of Completion is an outcome of patent mala

fides and illegality, which has been created/manufactured by the

Collector & District Magistrate, Angul in order to subterfuge the

core issue involved in the captioned Appeal i.e. non-completion

of   work     qua   development    of    amenities/facilities    at   the

resettlement site.




Writ Appeal No.34 of 2015                               Page 111 of 135
             So far as non-allotment of company quarters to 25

numbers     of   PDFs    among     the   Appellants    as    transit

accommodation is concerned, it is stated in the affidavit that out

of 102 Appellants (PDFs), 25 Appellants (PDFs) have not been

provided with company quarters as transit accommodation prior

to being directed to vacate their lands in the acquired area i.e.

Hensamul (Talasahi).

            So far as House Building Assistance and Incentive in

lieu of displacement is concerned, it is further stated in the

affidavit that in terms of Para 7 (II)(f) of the R & R policy 2006,

each of the PDFs in the resettlement habitat shall be provided an

amount of Rs.1,50,000/- (Rupees One Lakh Fifty Thousand only)

towards House Building Assistance. This is notwithstanding as to

whether such displaced family is settling in the resettlement

habitat or opting for self-relocation elsewhere.

            By virtue of the 9th Biennial revision of Rehabilitation

Grants in Monetary Terms that came into operation vide

Resolution dated 18.11.2024 of the Revenue and Disaster

Management Department of Government of Odisha, the House

Building Assistance has been enhanced to Rs.3,39,383/- (Rupees

Three Lakhs Thirty Nine Thousand Three Hundred and Eighty

Three only). Having regard to the Maintenance Allowance for one



Writ Appeal No.34 of 2015                           Page 112 of 135
 year @ Rs.4,525/- per month, Assistance of temporary shed @

Rs.22,626/- and Transport Allowance @ Rs.4,525/-, the total

Assistance comes to the tune of Rs.4,20,834/- (Rupees Four

Lakhs Twenty Thousand Eight Hundred and Thirty Four only).

            So far as the incentive offered by MCL is concerned,

it was decided in the 12th RPDAC Meeting dated 31.08.2021 that

an amount of Rs.5,00,000/- (rupees five lakh only) would be

paid to each of the PDFs along with other resettlement benefits

on submission of an affidavit by the PDFs for shifting within six

months from the date of receipt of the said amount and the

balance of Rs.5,00,000/- (rupees five lakh only) be disbursed by

MCL in favour of the PDFs after complete shifting of the village.

            It is further stated in the affidavit that in the 13th

RPDAC meeting held on 15.02.2024, the earlier decision taken in

the 12th RPDAC meeting held on 31.08.2021 was modified to the

extent that as opposed to an incentive to               the   tune of

Rs.5,00,000/- (rupees five lakh only) being disbursed by MCL on

signing of a tripartite agreement with the PDFs and the

remaining to be disbursed to each of the PDFs upon shifting of

the entire village at one go, it was decided that pursuant to an

initial incentive of Rs.5,00,000/- (rupees five lakh only) having

been   disbursed   by   MCL   after   execution   of   the    tripartite



Writ Appeal No.34 of 2015                              Page 113 of 135
 agreement, the remaining Rs.5,00,000/- (rupees five lakh only)

was to be disbursed to the PDFs, who demolish their house in

the acquired area and shift from the village, irrespective of

whether or not the entire village shifts from the said acquired

area.

            Having regard to the decision taken in the 12th and

13th RPDAC meetings held on 31.08.2021 and 15.02.2024

respectively, MCL has offered incentive @ Rs.10,00,000/- to

PDFs in village Hiloi, which is apparent from a letter written by

MCL to one Satyaban Pradhan of the said village, calling him

upon to receive the said incentive along with other resettlement

benefits by demolishing the dwelling house and handing over

physical possession to MCL, particularly, the decision taken

during the said RPDAC meetings have also been mentioned in

the said letter, which depicts and demonstrates the fact that MCL

has implemented the decision taken in the said meetings.

            It is further stated in the affidavit that MCL in the

village of Gopalpur has extended benefits qua House Building

Assistance together with incentives to the tune of Rs.14,50,000/-

as well as lands measuring an area of Ac.0.10 decimals to PDFs

of the said village and an amount of Rs.25,00,000/- have been

provided to those PDFs, who have opted for self-relocation, but



Writ Appeal No.34 of 2015                         Page 114 of 135
 the Appellants in the present writ appeal are yet to receive their

House Building Assistance as well as the incentive as decided in

the RPDAC meetings.

            It is further stated in the affidavit that MCL has

resorted to an allegation during the pendency of the Writ Appeal

regarding the impediments in the mining operations caused by

the non-cooperation of the Appellants (PDFs) in moving out of

the acquired area, which is claimed to have caused them colossal

losses. A bare reading of the financial highlights over the past

ten years would depict that MCL has overachieved its target of

production, dispatch and sale of coal and as a matter of fact,

MCL has achieved more than 100% than what it ought to have

achieved as per their target. MCL has also achieved a Year-on-

Year growth of about 10% in 2024-25 compared to the last year.

           In the affidavit, reliance was placed on the judgment

in the case of Mahanadi Coalfields Ltd. & Anr. -Vrs.- Mathias

Oram & Ors. reported in A.I.R. 2022 S.C. 5723, wherein the

Hon'ble Supreme Court held that since the Orissa Resettlement

and Rehabilitation Policy does not indicate specific provisions

with respect of facilities and amenities that are to be developed,

therefore, the provisions of the Third Schedule to the R & R Act,

2013 which outlines 25 heads and indicate amenities, have to be



Writ Appeal No.34 of 2015                          Page 115 of 135
 fulfilled by the project proponent as part of the resettlement

work which reads as follows:

            "63. The Orissa Resettlement and Rehabilitation
            Policy does not indicate specific provisions with
            respect to facilities and amenities that are to be
            developed. Consequently, the provisions of the
            Third Schedule to the R & R Act, 2013 which
            outlines 25 heads and indicate amenities such as
            roads in the villages, appropriate drainage,
            provision for safe drinking water for each family,
            provision for drinking water for cattle, grazing
            land, reasonable number of fair price shops,
            community or panchayat ghars; village level
            post     offices,         seed-cum-fertilizer       storage
            facilities, provision for basic irrigation facilities,
            transportation to the newly resided areas, burial
            or cremation grounds, facilities for sanitation,
            including     individual      toilet   points,    individual
            single      electricity     connections,         anganwadi,
            providing child nutritional services, school, sub-
            health   centres     within     two    kilometer     range,
            Primary Health Centres in terms of the Central
            Government norms, play grounds for children,
            one community centre for every 100 families,
            places of worship, separate land for traditional
            tribal institutions, etc. In addition, forest dweller
            families must be provided with their forest on
            non-timber produce close to the new places of
            resettlement. Furthermore, appropriate security


Writ Appeal No.34 of 2015                                     Page 116 of 135
             arrangements are to be provided and service
            centre in accordance with the prescribed norms
            also has to be provided.
            64. In the present case, the materials on record
            show that those resettlement sites have been
            earmarked       and   are    at    different   stages    of
            development. The mandate of the law i.e., the
            Third Schedule to the R & R Act, 2013 is very
            clear in that all the amenities to the extent they
            conform to the population in each of the
            resettlement areas have to be provided. In
            these circumstances, there may be no escaping
            these   obligations.        The    State   Government,
            through its appropriate agencies should draw up
            a comprehensive plan for creation of such
            amenities and ensure that they are functional so
            as to complete rehabilitation and resettlement in
            a meaningful manner."

           Relevantly in the said affidavit, in Paragraph 10, the

Appellants precisely stated the terms of settlement/demands

raised by them which are as follows:

            "10. That, the deponent seeks leave of this

            Hon‟ble Court to place on record the following

            facts/clarification in respect of the Terms of

            Settlement      for   better      appreciation   of     this

            Hon‟ble Court:



Writ Appeal No.34 of 2015                                  Page 117 of 135
             (a)    That, the Appellants humbly state and

            submit that the following demands as raised by

            the Appellants are required to be brought to the

            knowledge of this Hon‟ble Court:

                  (i) Expeditious and timely completion

                  of work at the Resettlement Site as per

                  the approved plan, preferably within a

                  period of six months;

                  (ii) To provide company quarters as

                  Transit Accommodation for 27 Nos. of

                  Appellants    within   a    period     of     one

                  month, and subsequent to which, the

                  said Appellants shall vacate their lands

                  in the acquired area within a period of

                  one month hence;

                  (iii) Expeditious disbursement of House

                  Building Assistance @ Rs.3,39,383/-

                  (Rupees      Three     Lakhs        Thirty-Nine

                  Thousand Three Hundred Eighty-Three

                  only) to the Appellants as provided in

                  the    9th       Biennial      Revision         of

                  Rehabilitation     Grants      in    Monetary



Writ Appeal No.34 of 2015                                     Page 118 of 135
                    Terms          vide          Resolution       dated

                   18.11.2024        of     the        Revenue     and

                   Disaster Management Department of

                   Government of Odisha;

                   (iv) Incentive for early and expeditious

                   displacement of PDFs @ Rs.10,00,000/-

                   (Rupees Ten Lakhs only) as per the

                   decision    taken       in    the    12th   RPDAC

                   Meeting dated 31.08.2021 as well as

                   the     13th      RPDAC         Meeting       dated

                   15.02.2024."

21.          The Respondents filed an affidavit on 04.09.2025,

wherein it is stated that all the land losers have got the land

acquisition compensation in terms of the applicable law. Besides,

in terms of the policy, the eligible persons have been allotted

sites. It is further stated that the resettlement site work is in

advanced stage. In response to the precise demands raised in

the   affidavit   filed   by   the       Appellants,     the   MCL    Company

acknowledged the demands as mentioned in Paragraph-10(a)(i)

and (ii). It is stated that an earnest attempt would be made to

meet the demand of the land losers. So far as Paragraph-

10(a)(ii) is concerned, it is stated that out of all the persons in



Writ Appeal No.34 of 2015                                        Page 119 of 135
 terms of the list enclosed to the affidavit dated 04.09.2025, only

25 are stated to be not granted the alternative accommodation,

who would be provided with alternative accommodation within a

period of one month subject to their eligibility. The Appellants

would be given all the benefits in accordance with law subject to

their eligibility in terms of the law as applicable. It is stated in

the affidavit dated 04.09.2025 that the writ appeal be disposed

of by vacating the interim order to enable the Respondents to

proceed with hassle free mining operation in the site in question.

            Mr. Nataraj, learned A.S.G.I. and Mr. Acharya,

learned Advocate General also fairly submitted that in so far as

the demand nos.(i) and (ii) are concerned, the same would be

accepted as it is and in regard to the other demands of the

appellants, the same would be given as per their entitlements of

the Appellants in accordance with the R & R Rules, 2006 on the

basis of their individual entitlement/eligibility.

            After the judgment was reserved on 04.09.2025, the

matter was subsequently mentioned by the learned Senior

Advocate appearing for the Appellants for listing for certain

clarification and accordingly, it was taken up on 10.09.2025. The

apprehension     expressed    by   the   learned     Senior   Advocate

appearing for the Appellants is that so far as conditions nos.(i)



Writ Appeal No.34 of 2015                              Page 120 of 135
 and (ii) are concerned, the affidavit filed by the Respondents on

04.09.2025 does not expressly mention as to whether those two

conditions would be scrupulously complied with or not.

              Mr. Nataraj, learned ASGI and Mr. Pitamber Acharya,

learned     Advocate     General    appearing      for   the     Respondents

submitted that there is no quarrel or confusion in so far as

condition nos.(i) and (ii) are concerned. The affidavit may not be

happily    worded,     but    the   Respondents      shall     stick   to   the

undertaking given regarding the compliance of condition nos. (i)

and (ii). The Respondents shall comply with the same in letter

and spirit as has been deliberated and agreed upon during the

course of hearing on 04.09.2025.

Scope of intra-court appeal:

22.           We   have       carefully   considered     the     submissions

advanced by the learned Counsel for the parties and perused the

documents available on record.

              Let us first examine the power of the Division Bench

while     entertaining    a    Letters    Patent    Appeal       against    the

judgment/order of the learned Single Judge. This writ appeal has

been nomenclatured as an application under Article 4 of the

Orissa High Court Order, 1948 read with clause 10 of the Letters

Patent Act, 1992. Letters Patent of the Patna High Court has



Writ Appeal No.34 of 2015                                      Page 121 of 135
 been made applicable to this Court by virtue of Orissa High Court

Order, 1948. Letters Patent Appeal is an intra-court appeal

where under the Letters Patent Bench, sitting as a Court of

Correction, corrects its own orders in exercise of the same

jurisdiction as vested in the Single Bench. (Ref: (1996) 3

Supreme Court Cases 52 : Baddula Lakshmaiah -Vrs.- Shri

Anjaneya Swami Temple). The Division Bench in Letters

Patent Appeal should not disturb the finding of fact arrived at by

the learned Single Judge of the Court unless it is shown to be

based on no evidence, perverse, palpably unreasonable or

inconsistent with any particular position in law. This scope of

interference is within a narrow compass. Appellate jurisdiction

under Letters Patent is really a corrective jurisdiction and it is

used rarely only to correct errors, if any made.

            In   the   case   of   B.   Venkatamuni    -Vrs.-   C.J.

Ayodhya Ram Singh reported in (2006) 13 Supreme Court

Cases 449, it is held that in an intra-court appeal, the Division

Bench undoubtedly may be entitled to reappraise both questions

of fact and law, but entertainment of a letters patent appeal is

discretionary and normally the Division Bench would not, unless

there exist cogent reasons, differ from a finding of fact arrived at

by the Single Judge. Even a Court of first appeal which is the



Writ Appeal No.34 of 2015                           Page 122 of 135
 final Court of appeal on fact may have to exercise some amount

of restraint. Similar view was taken in the case of Umabai

-Vrs.- Nilkanth Dhondiba Chavan reported in (2005) 6

Supreme Court Cases 243. In the case of Commissioner of

Income Tax -Vrs.- Karnataka Planters Coffee Curing Work

Private Limited reported in (2016) 9 Supreme Court Cases

538, it is held that the jurisdiction of the Division Bench in a writ

appeal is primarily one of adjudication of questions of law.

Findings of fact recorded concurrently by the authorities under

the Act concerned (Income Tax Act) and also in the first round of

the writ proceedings by the learned Single Judge are not to be

lightly disturbed.

            Thus, a writ appeal is an appeal on principle where

the legality and validity of the judgment and/or order of the

Single Judge is tested and it can be set aside only when there is

a patent error on the face of the record or the judgment is

against established or settled principle of law. If two views are

possible and a view, which is reasonable and logical, has been

adopted by a Single Judge, the other view, howsoever appealing

may be to the Division Bench; it is the view adopted by the

Single Judge, which would, normally be allowed to prevail. If the

discretion has been exercised by the Single Judge in good faith



Writ Appeal No.34 of 2015                            Page 123 of 135
 and after giving due weight to relevant matters and without

being swayed away by irrelevant matters and if two views are

possible on the question, then also the Division Bench in writ

appeal should not interfere, even though it would have exercised

its discretion in a different manner, were the case come initially

before it. The exercise of discretion by the Single Judge should

manifestly be wrong which would then give scope of interference

to the Division Bench.

23.         The prayer in the writ petition filed by the Appellants

precisely was to quash the letter dated 31.07.2014 issued by

Respondent no.1 to the extent challenged in the writ application

and for a direction to the Respondents to reinstate the Appellants

in the services without attachment and imposition of any

conditions and in accordance with letter dated 09.07.2014 of the

Sub-Collector, Talcher issued in terms of the decisions taken in

the meeting dated 06.07.2014 held in presence of the residents

of village Hensamul (Talasahi), the Director Technical, MCL,

Burla and MLA, Talcher on selection of resettlement site and on

the issue of termination of 127 employees of MCL. The further

prayer in the writ petition was to direct the Respondents not to

take any coercive action against the Appellants till they are

allotted plots physically in the resettlement site.



Writ Appeal No.34 of 2015                             Page 124 of 135
              The decisions which were taken in the aforesaid

meeting dated 06.07.2014 were as follows:

             (i)    MCL authorities will reinstate the retrenched

             employees by 10.07.2014. There will be no break of

             service;

             (ii)   Collector, Angul will be requested to convene

             the meeting of the PLARC at the earliest to discuss

             and finalise in principle the rehabilitation site;

             (iii) The MCL will start taking measures towards

             rendering the site hassle-free from legal perspective;

             (iv)   The   MCL     authorities   will   arrange    interim

             accommodation as would be decided by the PLRAC

             after the site is finalised in principle and on extension

             of such facilities, the villagers will start vacating the

             homestead land.


             The learned Single Judge found that the lands of the

Appellants had been acquired and that they had already been

paid   the   land   acquisition    compensation        amount     besides

employment being provided to them and that they have also

been provided with alternate accommodation in the quarters of

the MCL. MCL authority submitted before the learned Single

Judge that they were under process of allotting the alternate


Writ Appeal No.34 of 2015                                Page 125 of 135
 sites and the same was being delayed for some technical

reasons. The learned Single Judge directed the State authority to

co-operate with the MCL authority in the matter of finalization of

the alternate sites under the particular rehabilitation package.

The Court found that MCL Company was in urgent need of

mining in the locality, which was definitely in the larger interest

of the country. The Court further held that the Appellants have

no right to claim that they would vacate the homestead lands

under their occupation only after they were provided with

alternate   house    sites.   Accordingly,   the   writ    petition   was

dismissed vide impugned judgment and order dated 13.01.2015.

               The Writ Appeal was filed not only to set aside

judgment and order dated 13.01.2015 passed by the learned

Single Judge but also for a direction to the Respondents not to

take any coercive action against the Appellants by evicting them

from   their    dwelling   houses   and/or    by    terminating       their

employment, till they are physically allotted plots in the

resettlement site.

               From the affidavit filed by the Respondents in the

Writ Appeal, it appears that most of the Appellants have

constructed houses over the plots allotted to them at R & R site

and the Appellants are also staying in the company quarters



Writ Appeal No.34 of 2015                                 Page 126 of 135
 provided by MCL. Due to acquisition of village Hensamul

(Talasahi), 321 employments/cash in lieu of employments have

been provided by MCL as per Orissa R & R policies prevalent at

the relevant point of time. It is further stated in the affidavit that

there is no provision to issue ROR under CBA Act acquired lands

and as per guidelines issued by the Ministry of Coal vide letter

No.43022/1/2020-LAIR dated 22.04.2022, the land could be

leased out to land oustees for 99 years. As per clause 4(5)(e) of

the said guidelines, the allotted plots would be leased out in

favour of respective allottees only after shifting of the Appellants

to the site and as such, plot allotment orders have already been

issued in their names. All the Appellants were allotted quarters

for temporary accommodation till they shift to the R & R site.

The quarters were allotted as per their eligibility and they have

shifted to their allotted quarters.

            The Advocate Commissioner indicated in his report

that some electric poles have not been wired and that some

other electric poles were having wires in a state of disrepair and

that no water pipes had been laid down for supply of water to

the individual plots and that the water supply is wholly

inadequate and made the entire colony uninhabitable. The report

further indicated that three plots had been affected by waste



Writ Appeal No.34 of 2015                             Page 127 of 135
 water coming from the neighbouring MCL rescue station and MCL

authorities stated that special drains would be made for the said

plots. The report further indicated that there were some issues

relating to levelling and compacting the plots and that though

the plots had been demarcated way back in 2014 but no such

physical demarcation (except one or two dilapidated pillars) in

respect of any of the plots was visible.

            The Appellants filed affidavit indicating therein that

though they were eager to vacate the village as soon as possible,

but are not able to shift to the resettlement site as the

resettlement site lacks basic amenities like water supply,

electricity etc. which were required to be provided to them as per

rehabilitation package before they are asked to occupy the

demarcated plots for construction of their houses or shelters.

            Respondents filed affidavit indicating thein that MCL

has evicted and demolished the encroached area NLS School on

24.12.2024 and after eviction, MCL authorities issued the letters

dt.07.01.2025 and 26.05.2025 to the allottees to take over the

possessions of thirteen plots. All the pending works relating to

erection of the electric poles and cable wires for all the plots

would be erected within one month. The overhead tank has

already been constructed and the same is functional. The



Writ Appeal No.34 of 2015                          Page 128 of 135
 Superintending Engineer, RWS & S Division, Angul at Talcher,

vide its letter dt.10.06.2025 has informed the General Manager,

Bhubaneswari Area stating therein that rural piped water supply

to R & R site for village Hensamul (Talasahi) in front of Balanda

College has been completed and at the stage of commissioning.

The main water pipelines have already been laid over the R & R

site and the supply of water to the individual plots/house could

be provided through Functional Household Tap Connection

(FHTC) after submission of necessary documents along with

applications by the Appellants to the office of RWS & S Division,

Angul, Talcher. Special drain has already been constructed for

taking out the waste water coming from the neighbouring MCL

rescue station to the three plots. All the R & R plots have been

levelled to the road level including thirteen plots which were

encroached by NLS School. It is further stated that there is no

dispute regarding demarcation of plots between the allottees and

MCL   since   several     allottees   (i.e.    60     nos.)    have     already

constructed their houses in the R & R site. After eviction of NLS

school, the MCL authorities have demarcated thirteen plots by

putting   cement    pillars.   Tender         with    regard     to    ancillary

developments on the resettlement site has been floated on

22.01.2025    and   the    construction        of    the   same       would   be



Writ Appeal No.34 of 2015                                      Page 129 of 135
 completed by the time houses are constructed by the Appellants

over the R & R site. The Appellants have been provided all the R

& R benefits including employment benefits. They have been

allotted resettlement plots at Balanda resettlement site and for

temporary accommodation, the Appellants have been provided

company quarters/their own accommodations. All the Appellants

have been reinstated and consequential benefits have been given

to them as stated in letter dt.31.07.2014. It is further stated

that Hensamul (Talasahi) is at the edge of mines and at any

moment, mining accident/untoward situation might happen if

complete village is not evacuated.

             It further appears from the affidavit filed by the

Respondents that so far as the stipulation at Sl. No.(i) of the

letter dated 31.07.2014 relating to reinstatement of all the

terminated   employees      without   break   in   service   and   with

immediate    effect   is concerned, the       same   has been      duly

implemented. So far as stipulation at Sl. No.(ii) is concerned,

i.e., the villagers would not have to submit affidavit for the

same, has not been insisted upon. So far as Sl. No.(iii) is

concerned, all the Appellants except Sl. Nos.29 and 34, namely,

Pratima Sahoo and Dasarathi Sahoo have been allotted plots. So

far as Sl. No.(iv) is concerned, it is stated that for 97 Appellants,



Writ Appeal No.34 of 2015                              Page 130 of 135
 in   addition   to   the    allocation   of   the    plots,    MCL   quarter

accommodation has been provided. So far as Sl. No.(v) is

concerned, it is stated that MCL has also agreed to adjust the

period of absence due to termination from service with payment

of leave in credit of the individual and the same also has also

been given effect to.

            The affidavit filed by the Respondents further indicate

that out of 377 Project Displaced Families (PDFs), 223 PDFs have

opted for cash compensation of Rs.6,32,000.00 paisa in lieu of

Resettlement Plots and have voluntarily vacated their lands, both

agricultural and dwelling houses and given physical possession of

the same to MCL and the rest 154 PDFs have been allotted with

the resettlement plots. Compensation for land and the structures

have been paid to the Appellants and the building assistance has

been    sanctioned    for    the   Appellants       towards    shifting   and

construction of houses.

            On 13.08.2025, the Collector & District Magistrate,

Angul has issued Certificate of Completion of the Resettlement

and Rehabilitation (R & R) of the Project Displaced Families of

village Hensamul (Talasahi) under the provisions of para 7 (ii) of

the R & R Policy, 2006.




Writ Appeal No.34 of 2015                                     Page 131 of 135
              The Appellants finally filed an affidavit raising four

precise demands, inter alia, firstly, expeditious and timely

completion of work at the Resettlement Site as per the approved

plan preferably within a period of six months; secondly, to

provide company quarters as transit accommodation for 27 Nos.

of Appellants within a period of one month, subsequent to which,

the said Appellants shall vacate their lands in the acquired area

within a period of one month.

             In response to such precise demands raised by the

Appellants, the Respondents filed an affidavit on 04.09.2025

acknowledging both the demands. It is stated therein that an

earnest attempt would be made to meet the demand of the land

losers. So far as second demand of the Appellants is concerned,

it is stated that out of all the persons in terms of the list enclosed

to the affidavit dated 04.09.2025, only 25 are stated to be not

granted the alternative accommodation, who would be provided

with alternative accommodation within a period of one month

subject to their eligibility.

             From the affidavit filed by the Respondents, it

appears that all the land losers have got the land acquisition

compensation in terms of the applicable law. Besides, in terms of

R & R Policy, the eligible persons have been allotted plots in front



Writ Appeal No.34 of 2015                             Page 132 of 135
 of Balanda College for construction of R & R Colony. It is further

stated that the resettlement site work is in advanced stage.

Learned counsel for the Respondents also specifically stated that

in so far as the first and second demands of the Appellants are

concerned, the same would be accepted as it is. In regard to the

other demands of the appellants, the same would be given as

per the entitlements of the Appellants in accordance with the

Odisha R & R Policy, 2006 on the basis of their individual

entitlement/eligibility. When the matter was listed again on

10.09.2025 on being mentioned, the learned counsel for the

Respondents reiterated that the Respondents shall stick to the

undertaking given regarding the compliance of first and second

demands of the Appellants.

Conclusion:

24.        In view of the foregoing discussions, since during

pendency of the Writ Appeal, the Respondents have taken

effective steps not only in reinstating all the terminated

employees without break in service; allotment of the plots to the

eligible Appellants at the R & R site; providing company quarters

as transit accommodation; taking expeditious steps in making

the R & R site habitable for which several allottees i.e. 60 nos.

have already constructed their houses in such site and that the



Writ Appeal No.34 of 2015                          Page 133 of 135
 Respondents have assured this Court to undertake further

expeditious and timely completion of work at the resettlement

site as per the approved plan preferably within a period of six

months    and    to   provide   company     quarters    as   transit

accommodation to the rest of the deserved Appellants within a

period of one month, no further order is required to be passed in

the case. This Court expects that the Respondents shall not take

any coercive action against the Appellants till the rest of the

Appellants (which according to the Appellants are twenty-five in

numbers), are provided with alternative accommodation within a

period of one month subject to their eligibility. All the Appellants

shall vacate their homestead lands and houses in the acquired

area within a month thereafter so that the Respondent Company

can physically occupy the same for continuation of mining

operation of Bhubaneswari OCP in a peaceful manner. The

Respondent Company shall carry out expeditious and timely

completion of all the left out work at the resettlement site as

undertaken. This Court sincerely believes that haves should

follow their Dharma and extend the helping hands to the have-

nots with compassion and on the basis of ethics, responsibility

and commitment to the common good keeping ego aside.




Writ Appeal No.34 of 2015                           Page 134 of 135
                                     Before    parting   with   the   case,   we     record      our

                   unreserved and uninhibited appreciation for the positive and

                   responsive attitude, the efforts, the intelligence and the maturity

                   shown by Mr. S.P. Mishra, learned Senior Advocate for the

                   Appellants and Mr. K.M. Nataraj, learned Additional Solicitor

                   General of India and Mr. Pitamber Acharya, learned Advocate

                   General appearing for the Respondents for their able and

                   valuable assistance without which it would have been extremely

                   difficult to settle the long drawn legal battle between the parties.

                                    Accordingly, the Writ Appeal is disposed of with a

                   positive hope that the entire dispute shall be put a quietus.




                                                                        ............................
                                                                            S.K. Sahoo, J.

S.S. MISHRA, J. I agree.

............................ S.S. Mishra, J.

Orissa High Court, Cuttack The 24th September 2025/RKMishra Signature Not Verified Digitally Signed Signed by: RABINDRA KUMAR MISHRA Designation: Personal Assistant Reason: Authentication Location: HIGH COURT OF ORISSA, CUTTACK Date: 24-Sep-2025 10:44:55 Writ Appeal No.34 of 2015 Page 135 of 135