Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 1, Cited by 0]

National Green Tribunal

Sri Ajit Kumar Dhal vs State Of Odisha & Ors on 22 April, 2022

Item No. 06                                                      Court No.1

          BEFORE THE NATIONAL GREEN TRIBUNAL
             EASTERN ZONE BENCH, KOLKATA
               (Through Video Conferencing)
                    Original Application No. 10/2021/EZ
Ajit Kumar Dhal                                               Applicant(s)
                                   Versus
State of Odisha & Ors.                                         Respondent(s)

Date of hearing: 22.04.2022
CORAM:        HON'BLE MR. JUSTICE B. AMIT STHALEKAR, JUDICIAL MEMBER
              HON'BLE MR. SAIBAL DASGUPTA, EXPERT MEMBER

For Applicant(s)    : Ms. Mithu Bhattacharya, Advocate (on Virtual Mode)

For Respondent(s) : Mr. S.K. Nayak, AGA for R-1, 5 & 6 (on Virtual Mode)
                     Mr. N.C. Bihani, Advocate a/w Ms. Papiya Banerjee
                     Bihani, Advocate for R-2 to 4, (on Virtual Mode)
                     Mr. Ratnako Banerjee, Sr. Advocate (on Virtual Mode) a/w
                     Mr. Deepan Kumar Sarkar, Advocate, Mr. Matri Prasad
                     Advocate for R-9,

                                 ORDER

1. One additional affidavit dated 03.03.2022 along with a Report of an inspection carried out on 21.02.2022 has been filed on behalf of the Respondent No.2, Odisha State Pollution Control Board; the same is taken on record. The Observations of the Report read as under:-

A report on Low-lying a area reclamation site by utilizing ash by M/s. Vedanta Ltd., Junanimunda, Brajarajnagar, Jharsuguda in the matter of O.A. No.10/2021/EZ.
In response to the order dtd.21.01.2022 of the Hon'ble Green Tribunal, EZB, Kolkata in the matter of O.A. No. 10/2021/EZ and in reference to the report of the inspection conducted on 08.07.2021 by the Committee, a site visit was conducted on 21.02.2022 in and around the alleged site to verify the various aspects as pointed out in the aforesaid Hon'able NGT the order and following observations were made.
1
SI. Para of the Hon'ble NGT Observations No. the order dtd.21.01.2022
1. We find it very surprising • Thickness of ash that in one paragraph of the deposition at the land in report it is mentioned that question was 130cm at the thickness of ash western end near the deposition at the land in breach point down to 1 cm question was 1 cm to 130cm at the tail end on the in a slope. The thickness of Eastern Part in a slope ash deposition was 1 cm at manner.

the eastern end in the Kata • The parcel on which this and 130 cm at the western deposit had been spread end and deposited in a comprised of 17.21 acres manner of slope. However, in of Forest land, Kata land the subsequent para, it is of 04.70 acres out of the mentioned that during the total area of 07.00 acres field verification the ash and water stream (Nalah deposition was found to be area) 0.14 acres. It is over Government Forest pertinent to mention that Kisam land, water stream the Kata land in toto is land and the private kata 07.00 acres out of which land which have been the cover of ash was on removed by Ms/ Vedanta 04.70 acres. Now on site Ltd. at its own cost. visit it is ascertained and evident on the field that the entire ash deposition has been removed by M/s Vedanta Ltd. from the total parcel consisting of Govt. (Forest + Water Stream) and private (Kata land).

2. So far as the observations of • As per revenue record, the Committee and the Kata is a water body and remedial measures it is traditional water suggested by the Committee harvesting structure to that the kata (pond) in preserve the rainwater question shall be made through cross bond habitable for fish farming existed prior to 1982. and irrigation, the report is • The water sample from 2 silent in this regard and all the alleged kata land was that has been stated is that collected during the field as per the prevailing practice visit on 08.07.2021 for for pisciculture in the Govt. analysis and it is owned pond the same is revealed from the carried out by the Gram analysis report of the Panchayat concerned water sample that the through annual auction parameters are within the process. Whether the pond standard prescribed by has been excavated/cleaned CPCB for Pond water. for grant of auction and • Further, it is mentioned in whether the pond has been the last report that made habitable for fish "However, it is found on farming has also not been filed verification that the stated in the report. ash deposited over the government forest kisam, water stream land and the private kata land have already been removed by M/s Vedanta ltd. at its own cost."

• Again, it is verified by the Committee on 21.02.2022, the Kata land has been cleaned and o0nly clay was found as it has been dried up. This type of Kata land is not suitable for pisciculture as the property is not bound by bund on all sides. Bunds are present on two sides and other two sides are open. To make the pod suitable for pisciculture, certain conditions are required to be fulfilled as per the report of Fishery Department of Govt. of Odisha. Since this is a 3 private land it all depends upon the land owner whether he will be going for earth work at own investment for pisci-

                                                   culture in future. Detail
                                                   report of          the       same     is
                                                   enclosed for reference.
3.   The        remedial               action • The entire reclaimed area
     suggested by the Committee                    with        its        slope        was
     was   also         that the          entire   thoroughly               compacted,
     reclamation area along with                   leveled and covered with
     its   slope        be     thoroughly          soil     as            per       visual
     compacted, leveled uniformly                  observation on the day of
     with 300 mm of proper soil                    inspection. The Committee
     covering      to     prevent         such     is of opinion that a study
     incidence      in       future.        The    may be carried out to
     report is silent as to what                   verify the thickness of soil
     action has been taken in that                 covering          of     the     entire
     regard.                                       reclaimed               area         by
                                                   National               Accreditation
                                                   Board       for        Testing      and
                                                   Calibration             laboratories
                                                   (NABL)                         certified

Laboratories or Institute of National Repute like NITs/IITs at its own cost of the respondent industry. The detail report may be submitted directly to Hon'ble NGT by the respondent industry.

4 The remedial action further • It has provided a solid suggested was that the earthen embankment as a earthen embankment of protection measure. The adequate geotechnical Committee is of opinion strength has to be provided that a study may be and maintained at least up carried out to verify the to the end of one monsoon geotechnical strength of after completion of the work earthen embankment by 4 as per the Clause 4.6 (iv) of National Accreditation the Guidelines for Board for Testing and reclamation of low-lying Calibration laboratories areas and abandoned (NABL) certified quarries with fly ash of laboratories or Institute of SPCB, Odisha, the report is National Repute like silent in this regard. NITs/IITs by the respondent industry at its own cost. The detail report may be submitted directly to Hon'ble NGT by the respondent industry.

5 Ms. Papiya Banerjee Bihani, • A detail comprehensive learned Counsel appearing report on inspection dtd. for Odisha State Pollution 08.07.2021 has already Control Board as well as Mr. been submitted for all the Saubhagya Ketan nayak, points in the Terms of learned AGA appearing for Reference given in para State Respondents, Govt. of 10 & 11 of the order Odisha, pray for and are dated 15.06.2021. granted three weeks time for Further, clarification on filing further comprehensive the aforesaid report & a affidavits which should field verification report of include all the points in the 19.10.2021 has also been Terms of Reference given in submitted. para 10 & 11 of the order • Again, a field visit was dated 15.06.2021 and also conducted on 21.02.2022 showing compliance of the to verify the status of the remedial measures site and parawise suggested by the Committee observations has been for restoration of the damage mentioned. It is observed caused and recovery of the on the day of inspection Environmental Compensation i.e. 21.02.2022 tat the of Rs.26,19,725/- (Rupees ash deposited over the Twenty Six lakhs Nineteen government forest Kisam, Thousand Seven Hundren water stream land and Twenty Five). the private kata land have already been removed by M/s Vedanta Ltd. at its own cost.

5

• The entire reclaimed area with its slope was thoroughly compacted, leveled and covered with soil as per visual observation on the day of inspection. The Committee is of opinion that a study may be carried out to verify the thickness of soil covering of the entire reclaimed area and to verify the geotechnical strength of earthen embankment by National Accreditation Board for Testing and Calibration laboratories (NABL) certified laboratories or Institute of National Repute like NITs/IITs by the respondent industry at its own cost. The detail report may be submitted directly to Hon'able NGT by the respondent industry.

• There is no agriculture private land affected due to breach of the earthen embankment of reclamations site.

• The private kata land has been cleaned and only clay was found as it has been dried up. This type of kata land is not suitable for pisciculture as the property is not bound by bund on all sides.




6
                                                    Bunds are present on two
                                                   sides and other two sides
                                                   are open. To make the
                                                   pond        suitable             for
                                                   psiciculture,              certain
                                                   conditions are required to
                                                   be fulfilled as per the
                                                   report         of          Fishery
                                                   Department of Govt. of
                                                   Odisha. Since this is a
                                                   private land it all depends
                                                   upon     the        lad      owner
                                                   whether he will be going
                                                   for earth work at own
                                                   investment          for      pisci-
                                                   culture in future. Detail
                                                   report of       the       same    is
                                                   enclosed for reference.
6   We       also       find      that    this • To assess the damage
    amount         of     Rs.26.19,725/-           caused, three nos. of soil
    (Rupees Twenty Six lakhs                       sample @ one each from
    Nineteen        Thousand             Seven     the affected area of the
    Hundred Twenty Five does                       village forest land, Kata
    not refer to the inaction of the               land and one from the
    Respondent No.9 with regard                    unaffected      area of          the
    to   the            entire       remedial      Kata and water sample
    measures for restoration of                    was         collected            on
    the damage caused which                        08.07.2021          during       the
    we       have        already         noted     visit of the Committee. It
    hereinabove,            and          which     is    evident         from       the
    entail     a         fresh       financial     analysis reports that the
    assessment of the damage                       parameters are within the
    caused which is required to                    norms.
    be   recovered               from     M/s • There is no agricultural
    Vedanta Ltd.                                   private land affected due
                                                   to breach of the earthen
                                                   embankment                        of
                                                   reclamations site.
                                                 • The      Industry            (M/s.
                                                   Vedanta ltd.0 has done



                                 7
                                                all     the    remediation        &
                                               restoration cost at its own
                                               cost.         However,          the
                                               financial assessment was
                                               estimated          to     be    Rs.
                                               26,19,725/- as per the
                                               observation              of     the
                                               Committee.


                                               In view of the analysis
                                               results of soil & water
                                               sample ad observation of
                                               the      committee             made
                                               earlier on 08.07.2021, the
                                               ash deposition has not
                                               impacted to the fertility
                                               rate of soil of the affected
                                               Govt. land. Under such
                                               circumstances,            a    fresh
                                               financial           assessment
                                               based         on   the    previous
                                               observations made earlier
                                               on 08.07.2021 may not be
                                               feasible.




2. One affidavit dated 03.03.2022 has been filed on behalf of the Respondent No.6, Collector & District Magistrate, Jharsuguda; the same is taken on record.

3. One reply affidavit dated 05.04.2022 has been filed on behalf of the Applicant; the same is taken on record.

4. One affidavit dated 20.04.2022 has been filed on behalf of the Respondent No.9, M/s Vedanta Limited; the same is taken on record.

5. We have heard Ms. Mithu Bhattacharya, learned Counsel appearing in Virtual Mode for the Applicant and Mr. S.K. Nayak, Additional 8 Govt. Advocate appearing in Virtual Mode for the State Respondents, Govt. of Odisha, Mr. N.C. Bihani, learned Counsel alongwith Ms. Papiya Banerjee Bihani, learned Counsel appearing in Virtual Mode for the Odisha State Pollution Control Board and Mr. Ratnako Banerjee, learned Senior Counsel appearing in Virtual Mode assisted by Mr. Deepan Kumar Sarkar and Mr. Matri Prasad, learned Counsel for Respondent No.9, M/s Vedanta Limited.

6. Judgment reserved.

..................................... B. Amit Sthalekar, JM ................................... Saibal Dasgupta, EM April 22, 2022, Original Application No. 10/2021/EZ AK 9