State of Odisha - Subsection

Section 12(1)(iv) in Orissa Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulation, 2005

(iv)Based on system studies conducted in consultation with other agencies involved including other transmission and distribution licensees, the nodal agency shall, within 30 days of receipt of the application, intimate to the applicant whether or not the long-term access can be allowed without further system strengthening ;