Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 9, Cited by 0]

Bangalore District Court

M/S. Srinivasa Construction vs The Mysuru And Chamarajanagara on 6 November, 2019

IN THE COURT OF THE LXXXIII ADDITIONAL CITY CIVIL
  AND SESSIONS JUDGE AT BENGALURU CITY[CCH-84]

PRESENT:   Sri S.A. HIDAYATHULLA SHARIFF,
                                   B.A., LL.M.,
           LXXXIII Additional City Civil and
           Sessions Judge

      Dated this the 6th day of November 2019

                COM.A.S.No.93/2019
                 (A.S.No.04/2018)

PLAINTIFFS:    1.    M/s. Srinivasa Construction, a
                     registered Partnership Firm having
                     its office at 1st Floor, No.427,
                     Sanmarga,          7/A       Cross,
                     Siddarthanagar,     Mysuru­570011.
                     Represented     by   its  Managing
                     Partner Nikhil .G.

               2.    Nikhil .G, Managing Partner of M/s.
                     Srinivasa Construction, S/o late C.
                     Gopalakrishna, aged about 28
                     years, R/at No.427, Sanmarga, 7/A
                     Cross, Siddarthanagar, Mysuru­
                     570011.

               3.    Nithin .G, partner of M/s. Srinivasa
                     Construction,     S/o     late    C.
                     Gopalakrishna, aged about 28
                     years, R/at No.427, Sanmarga, 7/A
                     Cross, Siddarthanagar, Mysuru­
                     570011.

                     Currently R/at No.1207, East 8th
                     Street, Apartment 207, Temple
                     Arizona 85281, United States of
                        2
                      CT 1390_Com.A.S.93­2019_Judgment .doc


                  America.

             4.   Swetha Raajesh, Partner of M/s.
                  Srinivasa Constructions W/o Rajesh
                  Manivannan, aged about 33 years,
                  permanently residing at No.427,
                  Sanmarga,        7/A        Cross,
                  Siddarthanagar, Mysuru­570011.

             5.   N. Harish, Partner of M/s. Srinivasa
                  Construction.         S/o        late
                  K.N.Narayanaswamy, aged about 47
                  years, R/at No.2865, Varshadhare,
                  1st   Cross,   Raja     Kempegowda
                  Extension, Channapatna.



                  [By Sri.A.V.J.R, Advocate]

                   /v e r s u s/

DEFENDANT:         The Mysuru and Chamarajanagara
                   District School teachers House
                   Building    Co­operative    Society
                   Limited.    Formerly the Mysore
                   District School Teachers House
                   Building    Co­operative    Society
                   Limited,     represented      under
                   Karnataka Co­operative Societies
                   Act, 1959, No.114, Vivekananda
                   Block, Dr. S. Radhakrishnan
                   Nagar, Teacher's Layout, Mysuru­
                   570011. Represented by its Chief
                   Administrative Officer/ Secretary.
                           3
                          CT 1390_Com.A.S.93­2019_Judgment .doc


                           [By Sri.J.S.D, Advocate]

Date of institution of the :   14/6/2019(23/4/2018)
suit
Nature of the suit         :    Arbitration Suit under
                                   Arbitration Act
Date of commencement of :                 ­­­
recording of the evidence
Date    on    which    the :        6/11/2019
Judgment               was
pronounced.
                           : Year/s Month/s Day/s
Total duration
                               01      06     14



                       (S.A. Hidayathulla Shariff)
                     LXXXIII ACC & SJ: Bengaluru




     The plaintiff construction firm has filed this suit

U/S.34 of the Arbitration & Conciliation Act 1996, to set

aside the arbitral award dated 30/1/2018, passed by the

Arbitrator. Originally suit was filed in the court of Prl.

District & Sessions Judge, Mysuru and suit was

numbered as A.S.No.4/2018.        Thereafter, the suit was

transferred to I Addl. District Judge, Mysuru.            After

establishment of this court to try commercial disputes,
                            4
                          CT 1390_Com.A.S.93­2019_Judgment .doc


on the point of territorial jurisdiction the suit is

transferred to this court and renumbered as Commercial

OS No.93/2019.

     2.   The case of plaintiff construction firm in brief

as stated in the present petition is that it is a registered

partnership   firm    doing    business    as    Engineering

Contractor doing estate agency and carrying out the work

of formation of private layouts.       The defendant is a

registered house building cooperative society registered

under the Karnataka Cooperative Societies Act and its

main object is to procure lands round about Mysuru and

to form layouts and sites and to cater to the needs of its

members by allotting sites.    The defendant society had

entered into agreements with various land owners of

Yaraganahalli village for purchase / acquisition of their

lands for its use.   The defendant had invited offers for

undertaking the time bound formation and the offer of

the plaintiff construction firm to form the layout and do

other connected matters at the rate of Rs.105/­ per
                           5
                          CT 1390_Com.A.S.93­2019_Judgment .doc


square yard of actual sital area was accepted by the

defendant. On 5/9/1988, a development agreement was

entered into between the plaintiff construction firm and

the defendant society to develop the lands into a housing

layout. According to the terms of the above mentioned

agreement, the plaintiff construction firm was to procure

and   develop   agricultural   lands    identified    by    the

defendant society. The plaintiff was entrusted with the

work of getting the land acquired through acquisition

proceedings, forming layout in the acquired land as

litigation free land. The plaintiff was required to pay the

land lords and deposit to MUDA and other government

authorities, deposit with MUDA towards scrutiny fee,

supervision charges, tree planting, formation of CA sites,

street lighting and maintenance of layout, execution of

civil portion of layout works such as roads, drains,

culverts and providing and laying of water supply by cast

iron pipes and providing the laying of sewerage pipes.

The defendant society had identified the land bearing
                            6
                           CT 1390_Com.A.S.93­2019_Judgment .doc


Sy.No.55/3, 58/4, 62/1, 62/2, 62/3, 65, 66/1, 67/3A,

68/2B and 63/1 of Yaraganahalli village, Kasaba Hobli,

Mysuru Taluk, Mysuru suitable for its use.

     3. It is further case of the plaintiff construction firm

that as the work progressed, the terms and conditions of

the development agreement dated 5/9/1988 was revised

by   execution   of   supplementary      agreements       dated

13/1/1990, 14/10/1991, 3/12/1993, 15/3/1995 and

31/12/1995.      In the final supplementary agreement

dated 31/12/1995, the period for execution of the work

was extended upto 31/3/1996.

     4. It is further case of the plaintiff construction firm

that it was regularly in touch with the defendant society

and informed the defendant society from time to time

regarding the progress of the work. Inspite of completing

most of the work, the defendant society was not

forthcoming with the payments commensurate with the

work completed by it.    The condition precedent for the

entire agreement to be completed was the timely payment
                            7
                           CT 1390_Com.A.S.93­2019_Judgment .doc


of the bills to it.   The defendant society had thereby

caused breach of the contract.         The partners of the

plaintiff construction firm who were the members of the

defendant society raised a dispute under Section 70(2) of

Karnataka Cooperative Societies Act before the Joint

Registrar of Cooperative Societies, Mysuru in case

No.JRM/DDS/862/96­97 seeking relief in the form of

direction to the defendant society to allow the plaintiff

construction firm to complete the project within the time

stipulated by the authority and also sought for an order

for payment of a sum of Rs.2,12,48,283/­, which is due

from the defendant society together with interest @ 21%

per annum.     The defendant society has contested the

above   mentioned     dispute.   The    Joint    Registrar     of

cooperative society after full­fledged trial by its order

dated 2/8/2008 passed an award directing the defendant

society to pay a sum of Rs.5,85,934/­ to the plaintiff

construction firm along with interest @ 14% per annum.

After passing of the above mentioned award, the
                             8
                            CT 1390_Com.A.S.93­2019_Judgment .doc


defendant society paid a sum of Rs.15,37,044/­ to the

plaintiff   construction   firm   and    purported     to   have

terminated the contract by issuing a letter dated

20/8/2008 to the plaintiff construction firm.                The

purported termination of the contract between the

plaintiff construction firm and the defendant society was

subjudice and was subsequent to the raising of dispute

between the parties.

      5. It is further case of the plaintiff construction firm

that aggrieved by the award passed by the Joint Registrar

of Cooperative Societies, it has approached the Hon'ble

Karnataka Appellate Tribunal in Appeal No.594/2008.

The Hon'ble Karnataka Appellate Tribunal by its order

dated 29/8/2013 has held that the plaintiff construction

firm was not a member of the defendant society and the

matters involved are not concerned with the affairs of the

defendant society.      The Hon'ble Karnataka Appellate

Tribunal by its order dated 29/8/2013 has dismissed the
                             9
                            CT 1390_Com.A.S.93­2019_Judgment .doc


appeal of the appellant - plaintiff construction firm and

also dismiss the dispute No.862/1996­97.

      6. It is further case of the plaintiff construction firm

that subsequent to the order passed by the Karnataka

Appellate Tribunal, it has approached Hon'ble High Court

of Karnataka with a petition U/S.11 of the Arbitration &

Conciliation Act seeking appointment of arbitrator. The

Hon'ble High Court of Karnataka by its order dated

20/9/2016 allowed the petition and appointed Hon'ble

Justice Sri.A.V.Chandrashekar as the sole Arbitrator

with a direction to enter upon the reference and to

resolve the dispute between the parties. Hon'ble Justice

Sri.A.V.Chandrashekar who was appointed as a sole

arbitrator by its order dated 6/6/2017 passed in

A.C.No.135/2016, allowed the application filed by the

applicant/ claimant for condonation of delay U/S.14 of

the   Limitation    Act   and    posted      the   matter      for

commencement of evidence by framing issues. In view of

inability of Hon'ble Justice Sri. A.V.Chandrashekar to
                             10
                            CT 1390_Com.A.S.93­2019_Judgment .doc


proceed with the arbitration proceedings, the Hon'ble

High Court of Karnataka by its order dated 20/7/2017

has directed substitution of the Arbitrator and appointed

Hon'ble   Justice   Sri.   A.N.Venugopal       Gowda     as    an

Arbitrator. The claimant/ plaintiff construction firm filed

its claim statement        on 21/11/2016 requesting the

Tribunal to direct the defendant to pay a sum of

Rs.27,49,06,124/­ together with interest @ 21% per

annum.

     7. It is further case of the plaintiff construction firm

that the agreement with the defendant society makes it

clear that if its work found to be not satisfactory or if

sub­standard materials are found to have been used, the

amount shall be withheld until it completes the work

within the specified period to the satisfaction of the

concerned authorities and in case of default, the

defendant society shall have the right to get the work

done by itself, in which event, retention money may be

used for the said work and of the amount found to be
                          11
                          CT 1390_Com.A.S.93­2019_Judgment .doc


insufficient the plaintiff construction firm to make good

to the defendant society the loss and damages along with

costs. The defendant society was entitled to deduct 2% of

the amount from the payments made, towards payment

of income tax and remit the same to the concerned

authority. The agreement provides for the termination of

the contract by the defendant society only in case of the

contractor was unable to carry out all or any work

entrusted to it within stipulated period and or on account

of executing any substandard work or violation of any

specifications of MUDA or any concerned authority. The

plaintiff construction company had not challenged the

purported termination of the agreement by the defendant

society. In fact, it had claimed a sum of Rs.3,00,000/­

being the value of its materials which it had left in the

work place.    Therefore, no dispute was raised by it

regarding the termination of agreement before the

arbitrator.   Further even the defendant society in its

objection had not raised any contentions before the
                           12
                          CT 1390_Com.A.S.93­2019_Judgment .doc


arbitrator regarding termination of the contract between

the parties.   On the other hand, it had reiterated the

contentions which it had raised before the Joint Registrar

of Cooperative Societies, Mysuru. The Arbitrator passed

an award on 30/1/2018 rejecting the claim petition of

the plaintiff construction firm on the ground that it ought

to have sought for the relief of declaration, declaring that

the termination of joint development agreements by the

defendant society is not maintainable in law.           In the

absence of any plea raised by the defendant society

regarding the maintainability of the claim of the plaintiff

construction firm for not seeking declaration that the

termination of the agreement is void in law, the arbitrator

has dealt with a matter not contemplated by or not falling

within the terms of the submission to arbitration and the

award contains the decisions on matter which is beyond

the scope of the submission to arbitration. The dispute

with the plaintiff construction firm raised before the

Arbitrator was concerning to the period prior to the date
                                 13
                                CT 1390_Com.A.S.93­2019_Judgment .doc


of cancellation of the agreement. It had not raised any

dispute regarding the cancellation of the agreement and

it was not a bone of contention within the parties. It had

claimed the amount for the works it had done prior to the

date of cancellation of the contract. The impugned award

passed by the Arbitrator is bad in law and liable to be set

aside.

      8.In response to the court notice, the secretary of

the defendant society appeared before the court and has

filed his objections statement to the petition filed by the

plaintiff     U/S.34 of the Arbitration & Conciliation Act

1996.       The defendant society in its objection statement

has not disputed the petition averments with regard to

the development agreement dated 5/9/1988 entered

between the plaintiff construction firm and the defendant

society      and   also   not     disputed     the    execution     of

supplementary        agreements        between         the   plaintiff

construction firm and the defendant society.                      The

defendant       society   in    its   objections     statement    has
                           14
                          CT 1390_Com.A.S.93­2019_Judgment .doc


contended that the plaintiff construction firm could not

complete the developmental work within the time fixed by

the parties under original development agreement dated

5/9/1998.     For one or the other reason, the plaintiff

construction firm had been delaying the construction

work with a sole intention to obtain construction cost at

enhanced rates.     With an intention to complete the

formation of proposed layout project, it has compelled to

extend the time for completion of the project periodically,

as such, the defendant society was constrained to

execute   5   supplementary    agreements.         Inspite    of

extension of time for completion of development work, the

plaintiff construction firm did not complete even 50% of

the work entrusted.    On the other hand, the plaintiff

construction firm once again sought for extension of time

and to enhance the rate of construction cost.                The

plaintiff construction firm committed breach of terms of

development agreement.      When the defendant society

refused to accede to the unreasonable demand of the
                           15
                          CT 1390_Com.A.S.93­2019_Judgment .doc


plaintiff construction firm, the then partners of the

plaintiff construction firm invoked          Section 21 of

Arbitration & Conciliation Act and issued notice dated

22/6/1996 on the defendant to refer the dispute to

arbitration that has arisen between the parties, with a

sole intention to put an end to the developmental work.

Thereafter, instead of proceeding for settlement of dispute

through arbitration, the plaintiff construction firm has

approached the Joint Registrar of Cooperative Societies

U/S.70(2) of Karnataka Cooperative Societies Act. Both

the parties subjected to the jurisdiction of the Joint

Registrar of Cooperative Societies for dispute resolution.

In case No.JRM/DDS/862/96­97, the Joint Registrar of

Cooperative Societies passed an order dated 2/8/2008,

directing   the defendant society to pay a sum                of

Rs.5,85,934/­ to the plaintiff construction firm with 14%

interest. The above mentioned order was duly complied

by the defendant society.      Thereafter, as per the board

resolution, the defendant society has issued termination
                           16
                           CT 1390_Com.A.S.93­2019_Judgment .doc


notice dated 20/8/2008 to the plaintiff construction firm

and terminated the development agreements.                  The

plaintiff construction firm after reaping the fruits of the

order dated 2/8/2008 passed in case No.862/96­97 had

preferred an appeal before the Karnataka Appellate

Tribunal in Appeal No.594/2008. The above mentioned

appeal was dismissed on 29/8/2013. At this juncture to

get over the hurdle of limitation, the plaintiff construction

firm got issued a notice for appointment of arbitrator on

28/9/2013.      Subsequently, the Hon'ble High Court of

Karnataka has appointed the arbitrator who decided the

reference in A.C.No.135/2016 and ultimately the award

was passed on 30/1/2018.

     9. The defendant society in its objection statement

has further contended that the averments made in the

petition reveals that the plaintiff construction firm

challenged the impugned award U/S.34 (2) (iv) of

Arbitration & Conciliation Act. The grounds urged by the

plaintiff construction firm in challenging the impugned
                           17
                          CT 1390_Com.A.S.93­2019_Judgment .doc


award are untenable.      The plaintiff construction firm

which has sought the declaratory relief before the Joint

Registrar of Cooperative Societies in Case No.862/96­97

has intentionally and deliberately has not sought the

foundational relief before the arbitrator. The Arbitrator

has rightly pointed out the apparent defect on the part of

the plaintiff construction firm in not seeking foundational

relief has rightly come to the conclusion that in view of

the ratio of the decision reported between I.S.Sikandar

Vs. Subramani and others reported in 2013 (15) SCC 27

is not entitled to seek the consequential relief without

seeking the foundational relief of declaration.            The

arbitrator has properly considered the legal position to

the effect that in the absence of seeking foundational

relief, the claimants are not entitle for consequential

relief. The arbitrator has properly dealt within the terms

of submission to arbitration by the parties in accordance

with law and he has not dealt with any matter not falling

within the terms of submission to arbitration.             The
                                18
                                  CT 1390_Com.A.S.93­2019_Judgment .doc


arbitrator has not exceeded his jurisdiction.                       The

arbitrator has confined his award within the framework

of the reference made to him. The award is inconsonance

with the provisions of substantive law and the same is

not patently illegal and decision of the arbitrator is not

beyond the scope of reference.

      10. The defendant society in its objection statement

has further contended that the arbitrator has properly

applied his mind to the matter before him and followed

the   legal   position      and     consequently      came     to   the

conclusion that the plaintiff construction firm without

seeking foundational relief of declaration is not entitled to

consequential reliefs and hence claim petition filed

without seeking the main and foundational relief of

declaration     is    not    maintainable.           The    scope     of

interference U/S.34 of Arbitration & Conciliation Act is

very limited.        While exercising the power U/S.34 of

Arbitration & Conciliation Act, the court cannot be

justified in re­appreciating the material on record and
                              19
                             CT 1390_Com.A.S.93­2019_Judgment .doc


substituting its own view in place of the arbitrators view.

On   these grounds,        the     defendant   has   sought     for

dismissal of the petition.

     11. Based on the above pleadings of the parties, the

points that arises for consideration of this court are :

     1)   Whether     in     the     impugned     award     dated

30/1/2018 passed by the Arbitrator in A.C.No.135/2016,

the arbitrator dealt with the dispute not contemplated or

not falling within the terms of the submission of

arbitration or it contains decisions on matters beyond he

scope of submission of arbitration?

     2) What order?

     12. Heard learned counsel for the plaintiff and

learned counsel for the defendant. Perused the materials

on record.

     13. My findings on the above points are as follows:

     Point No.1 : In the negative.

     Point No.2 : As per final order for the following:
                              20
                             CT 1390_Com.A.S.93­2019_Judgment .doc


                        REASONS

     14. POINT No.1 : A perusal of the materials on

record discloses that there are certain undisputed facts

between the parties to the present suit. The fact that on

5/9/1988, Ex.P.1 ­ Joint Development Agreement was

entered between the plaintiff construction firm and the

defendant     society   to    develop     the    land     bearing

Sy.No.55/3, 58/4, 62/1, 62/2, 62/3, 65, 66/1, 67/3A,

68/2B and 63/1 of Yaraganahalli village, Kasaba Hobli,

Mysuru Taluk, Mysuru into a housing layout is not in

dispute.    Further fact that the terms and conditions of

the Joint Development Agreement dated 5/9/1988 was

revised by execution of Ex.P.2 to P.6 supplementary

agreements dated 13/1/1990, 14/10/1991, 3/12/1993,

15/3/1995 and 31/12/1995 is also not in dispute.

Further fact that the plaintiff construction firm raised a

dispute U/S.70(2) of Karnataka Cooperative Societies Act

before the Joint Registrar of Cooperative societies,
                                 21
                                CT 1390_Com.A.S.93­2019_Judgment .doc


Mysuru District, Mysuru, alleging breach of contract by

the defendant society is also not in dispute. Further fact

that the Joint Registrar of Cooperative Societies in Case

No.862/96­97 has passed an award dated 2/8/2008,

directing   the defendant society to pay a sum                      of

Rs.5,85,934/­     along    with      interest    to   the   plaintiff

construction firm is also not in dispute. Further fact that

upon   disposal    of     the     dispute    No.862/96­97,        the

defendant society has paid a sum of Rs.15,37,044/­ to

the plaintiff construction firm by duly complying the

award is also not in dispute.             Further fact that the

defendant society by passing Ex.R.57 resolution dated

3/8/2008 has terminated Ex.P.1 to P.6 the joint

development agreements and subsequent supplementary

agreements entered with the plaintiff construction firm

and communicated the same to the plaintiff construction

firm through Ex.P.118 - letter is also not in dispute.

Further fact that the plaintiff construction firm aggrieved

by the award passed by the Joint Registrar of Cooperative
                           22
                          CT 1390_Com.A.S.93­2019_Judgment .doc


Societies in Case No.862/96­97 had preferred an appeal

before the Karnataka Appellate Tribunal in appeal

No.594/2008 is also not in dispute. Further fact that the

Karnataka    Appellate   Tribunal    by   its   order     dated

29/8/2013 had dismissed the said appeal filed by the

appellant - plaintiff construction firm is also not in

dispute. Further fact that the plaintiff construction firm

has filed petition U/S.11 of the Arbitration & Conciliation

Act before Hon'ble High Court of Karnataka in CMP

No.168/2014 is also not in dispute.       The Hon'ble High

Court of Karnataka by its order dated 20/9/2016, passed

in   CMP    168/2014     has    appointed       Hon'ble     Sri.

A.V.Chandrashekar, Former Judge, Hon'ble High Court

of Karnataka as the sole arbitrator to decide the dispute

between the parties to the suit is also not in dispute.

Further fact that during the course of arbitration

proceedings, Hon'ble Sri. A.V.Chandrashekar, Former

Judge of Hon'ble High Court of Karnataka was appointed

as the judicial member of KAT, as such, the Hon'ble High
                           23
                          CT 1390_Com.A.S.93­2019_Judgment .doc


Court of Karnataka by its order dated 20/7/2017 has

ordered for substitution of arbitrator and appointed

Justice Sri. A.N.Venugopal Gowda as the sole Arbitrator

is also not in dispute. Justice Sri. A.N.Venugopal Gowda,

Former Judge, High Court of Karnataka has passed

award on 30/1/2018 in A.C.No.135/2016 by rejecting

the claim petition filed by the claimant / plaintiff

construction firm is also not in dispute. Aggrieved by the

award dated 30/1/2018 passed in A.C.No.135/2016, the

claimant/ plaintiff construction firm has filed the present

suit U/S.34 of the Arbitration & Conciliation Act 1996.

In the present suit, the main objection raised by the

plaintiff against the arbitral award is that the arbitral

award deals with a dispute not contemplated by law or

not falling within the terms of the submission to

arbitration and it contains decision on mattes beyond the

scope of the submission to arbitration.

     15. The learned counsel for the plaintiff has argued

that the joint development agreement entered between
                               24
                              CT 1390_Com.A.S.93­2019_Judgment .doc


the   claimant/   plaintiff    construction      firm     and   the

defendant society provides for termination of contract by

the   defendant   society      only     in   case    of    plaintiff

construction firm was unable to carry out all or any work

entrusted to it within the stipulated period or execution

of substandard work or violation of any specifications of

MUDA or concerned authority. It is further argued that

before the arbitrator, the claimant / plaintiff construction

firm had not challenged the purported termination of the

agreement by defendant society. Before the arbitrator the

claimant/ plaintiff construction firm has not raised any

dispute regarding termination of the agreement by the

defendant society.    Even the defendant society in its

objection filed before the arbitrator has not raised any

contention regarding termination of the contract between

the parties. The alleged termination of the contract was

not a bona of contention between the parties before the

arbitrator. The dispute raised by the claimant before the

arbitrator was concerning to the period prior to the date
                           25
                          CT 1390_Com.A.S.93­2019_Judgment .doc


of cancellation of the agreement. The claimant was only

claiming the amount for the work it had done prior to the

date of the cancellation of the contract. In the absence of

any plea raised by the defendant society regarding the

maintainability of the claim of the claimant / plaintiff

construction firm for not seeking declaration that the

termination of agreement is void in law, the Arbitrator

has dealt with the matter not contemplated or not falling

within the terms of the submission to the arbitration and

passed an impugned award rejecting the claim petition

on the ground that the claimant / plaintiff construction

firm ought to have sought for relief of declaration

declaring that the termination of the joint development

agreement by the defendant society is not maintainable

in law.   It is further argued that the impugned award

passed by the Arbitrator contains the decision of matter

which is beyond the scope of the submission to

arbitration.
                           26
                          CT 1390_Com.A.S.93­2019_Judgment .doc


     16. The learned counsel for the plaintiff has further

argued that the Arbitrator had no power to adjudicate

upon the dispute pertaining to the legal validity of

arbitration agreement.    It is further argued that the

arbitrator had no authority to pass declaratory award. It

is further argued that the arbitrator has erred in not

answering the vital issues framed to adjudicate the

matter in dispute. It is further argued that the Arbitrator

has traveled beyond the term of reference and the finding

given by the Arbitrator is perverse and hence court

required to interfere U/S.34(2) of the Arbitration &

Conciliation Act against the impugned award.

     17. In support of his arguments, the learned

counsel for the plaintiff construction firm has relied on

following decisions:

     1) Between Suwalal Jain Appellant v. Clive Mills Co.
Ltd. Respondent reported in       AIR 1960 Calcutta 90,
wherein, it was held that the Arbitrator has no power to
adjudicate upon the legal validity of the submission. The
dispute as to the legal validity of the arbitration
                            27
                            CT 1390_Com.A.S.93­2019_Judgment .doc


agreement as to the existence of fact which render it
illegal and void must be determined by court and not by
the Arbitrator just as disputes as to its factual existence
can be determined only by the court and not by the
arbitrator.   The arbitrator cannot by his own finding
clothe himself with jurisdiction.        Supposing that the
arbitrator finds that the arbitration agreement is valid,
such a finding cannot bind the parties.
      2) Between Padam Chand Jain appellants v. Hukam
Chand Jain respondent reported in AIR 1999 Delhi 61,
wherein, it was held that the arbitrator has no authority
to pass declaratory award.
      3) Between Oil and Natural Gas Corporation Limited
appellant v. SAW Pipes Limited respondent reported in
AIR 2003 SC 2629, wherein, the Apex court of the land
has held that if the arbitral award is contrary to the
substitutive provision of law or the provision of the act or
against the terms of the contract, it would be patently
illegal,   which   could   be   interfered    U/S.34     of   the
Arbitration & Conciliation Act 1996.
      4) Between M/s. MSK Projects (I) (JV) Ltd. v. State
of Rajasthan and another reported in AIR 2011 Supreme
Court 2979, wherein, the Apex Court of the land has held
that the arbitration award passed contrary to the
provisions of law or against terms of contract or public
                           28
                           CT 1390_Com.A.S.93­2019_Judgment .doc


policy would be patently illegal and court could interfere
U/S.34(2) against the said award.
     5) Between Oil and Natural Gas Corporation Ltd. v.
Western Geco International Limited reported in AIR 2015
Supreme Court 363, wherein, Apex Court of the Land has
held that the Fundamental Policy of Indian Law include
all such fundamental principles as providing a basis for
administration of justice and enforcement of law in
country. The requirement that adjudicatory authority
must apply its mind ­ can be described as fundamental
policy of Indian Law - When arbitrators committed error
resulting in miscarriage of justice and also failed to
appreciate and draw logical inference from proved facts
then arbitral award liable to be interfered.
     6)   Between    ONGC      ltd.   v.   Garware    Shipping
Corporation Limited      reported in AIR 2008 Supreme
Court 456, wherein, the Apex Court of the Land has held
that an award based on wrong basis and perverse
conclusions liable to be set aside.        It was further held
that no proposition that courts could be slow to interfere
with arbitrator's award, even in such cases.

     18. On the other hand, the learned counsel for the

defendant society has argued that U/S.34 of the

Arbitration & Conciliation Act 1996 an arbitral award can
                          29
                          CT 1390_Com.A.S.93­2019_Judgment .doc


be set aside only on the ground mentioned in the sub

sections in the said section.    In the present case, the

plaintiff has not made out a case in terms of Section 34

of the Act.   The grounds raised by the plaintiff in the

present suit challenging the arbitral award are totally

outside the scope, purview and ambit of Section 34 of the

Act, therefore, there are no grounds for setting aside the

impugned award.

     19. In support of his arguments, the learned

counsel for the defendant society has relied on following

decisions:

     1) Between I.S.Sikandar (dead) by LRs v. K.
Subramani and others reported in (2013) 15 Supreme
Court Cases 27, wherein, the Apex Court of the Land has
held that in a suit for specific performance of contract
when the agreement was already terminated by the
defendant vendor, in the absence of plaintiff's prayer
seeking declaratory relief that the termination of the
agreement was bad in law, suit for specific performance
is not maintainable.
                                30
                               CT 1390_Com.A.S.93­2019_Judgment .doc


     2)   Between      State    of   Orissa     and    another     v.
Surendranath Kanungo reported in AIR 2004 Orissa 153,
it was held that the dispute regarding arbitration clause
in question as to whether the same was scored out at the
time of execution of agreement between the parties can
be   decided     by   arbitrator     who   has    jurisdiction     to
adjudicate.
     3) Between Ram Nath International Construction
Pvt. Ltd. v. Stat of UP reported in AIR 1998 Supreme
Court 367, wherein, the Apex Court of the land has held
that the dispute as to payment of extra item of work, not
specific in the agreement and dispute as to whether work
in question was extra work or not was specifically
referred to arbitrator by parties.          Parties arguing the
question before arbitrator, speaking award given with
details as to why work was extra work and payment was
required to be made.        It is matter of interpretation of
contract and was referred by the parties to arbitrator.
The dispute cannot said to be beyond scope of reference
to arbitrator.

     20. It is pertinent to note that an arbitral award

may be set aside by the court only on the ground

mentioned U/S.34 of the Arbitration & Conciliation Act
                                 31
                                CT 1390_Com.A.S.93­2019_Judgment .doc


1996. U/S.34(2) of the Act an arbitral award may be set

aside by the court only if ­

     a) the party making the application furnishes proof
that ­
     i) a party was under some incapacity; or
     ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing any
indication thereon, under the law for the time being in
force; or
     iii) the party making the application was not given
proper notice of the appointment of an arbitrator or of the
arbitral proceedings or was otherwise unable to present
his case; or
     iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of the
submission to arbitration, or it contains decisions on
matters     beyond   the    scope       of   the    submission     to
arbitration;
     Provided that, if the decisions on matters submitted
to arbitration can be separated from those not so
submitted, only that part of the arbitral award which
contains    decisions      on    matters      not    submitted     to
arbitration may be set aside; or
                           32
                          CT 1390_Com.A.S.93­2019_Judgment .doc


     v) the composition of the arbitral tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement was in
conflict with a provision of this part from which the
parties cannot derogate, or, failing such agreement, was
not in accordance with this part; or
     b) the Court finds that ­
     I) the subject matter of the dispute is not capable of
settlement by arbitration under the law for the time being
in force, or
     ii) the arbitral award is in conflict with the public
policy of India.


     21. A perusal of the materials on record discloses

that the plaintiff construction firm has challenged the

impugned award U/S.34(2)(iv) of the Arbitration &

Conciliation Act on the ground that the arbitral award

deals with dispute not contemplated by or not falling

within the terms of the submission to arbitration, or it

contains decisions on matters beyond the scope of the

submission to arbitration.
                           33
                          CT 1390_Com.A.S.93­2019_Judgment .doc


     22. At this stage, it is relevant to go through the

decision of Apex Court of the land on the aspect of

considering the legality and validity of the arbitration Act

U/S.34 of the Arbitration & Conciliation Act 1996. In the

decision reported between Puri Constructions Private

Limited v. Union of India reported in (1989) 1 Supreme

Court Cases 411, wherein, the Apex Court of the Land

has held that when a court is called upon to decide the

objection raised by a party against an arbitration award,

the jurisdiction of the court is limited as expressly

indicated in the arbitration act and it has no jurisdiction

to sit in appeal and examine the correctness of the award

on merits with reference to the materials produced before

the arbitrator. The court cannot sit in appeal over the

view of the arbitrator by re­examining and re­assessing

materials.

     23. In the light of the arguments advanced by the

learned counsel for the plaintiff construction firm and

learned counsel for the defendant society, a perusal of
                           34
                          CT 1390_Com.A.S.93­2019_Judgment .doc


the materials on record discloses that the claimant/

plaintiff construction firm has filed claim petition before

the arbitrator seeking direction to the defendant society

to pay a sum of Rs.27,49,06,124/­ together with future

interest @ 21% per annum. The claim sought for by the

claimant / plaintiff construction firm was based on the

allegations of breach of contract by the defendant society.

On the other hand, the defendant society has contested

the claim petition by denying the allegations of breach of

contract made against it and further contended that it

had already canceled the joint development agreements

entered with the claimant/ plaintiff construction firm and

hence the claim petition is not maintainable.

     24. A perusal of the impugned award passed by the

Arbitrator discloses that the Arbitrator has framed 6

issues and one additional issue pertaining to the matter

in dispute referred to him.    Issue No.1 framed by the

Arbitrator pertaining to the claim of the claimant /

plaintiff construction firm that it had executed all the
                           35
                          CT 1390_Com.A.S.93­2019_Judgment .doc


works entrusted to it under main agreement dated

5/9/1998 and supplementary agreement and the works

were executed in time.    By considering the contents of

Ex.P.1 to P.6 undisputed joint development agreement

and supplementary agreements and by considering the

oral and documentary evidence produced on record, the

Arbitrator has given a finding that the claimant / plaintiff

construction firm has not executed all the work entrusted

to it under Ex.P.1 and other supplementary agreements.

The finding of the arbitrator on issue No.1 to the effect

that the claimant / plaintiff construction firm has failed

to prove that it has executed all the works entrusted to it

under the joint development agreement dated 5/9/1988

and other supplementary agreements is not seriously

challenged in the present suit.

     25. A perusal of the impugned award passed by the

Arbitrator discloses that the 3rd recasted issue framed by

the arbitrator pertains to the aspect of payment of a sum

of Rs.76,92,506/­as on 18/3/1998 by the defendant
                           36
                           CT 1390_Com.A.S.93­2019_Judgment .doc


society to the claimant/ plaintiff construction firm and

the claim of the defendant society that it had paid excess

amount of Rs.1,28,346/­ to the claimant / plaintiff

construction firm.     On this recasted issue No.3 by

considering the contents of Ex.R.11 - eighteen vouchers

under which the defendant society had made payment to

the claimant / plaintiff construction firm and by

considering the other documentary evidence produced on

record, the arbitrator has given a finding to the effect that

the defendant society has proved that as on 18/3/1998,

it had made payment of Rs.76,13,476/­ to the claimant /

plaintiff construction firm and failed to prove that there is

excess payment of Rs.1,28,346/­.        Even this finding of

the arbitrator of recasted issue No.3 is also not seriously

disputed in the present suit.

     26. The main objection raised by the plaintiff in the

present suit pertaining to finding given by the arbitrator

on maintainability of the claim petition. On the aspect of

maintainability of the claim petition, the arbitrator has
                            37
                               CT 1390_Com.A.S.93­2019_Judgment .doc


given a finding to the effect that in the absence of the

claimant prayer to declare the cancellation of the joint

development agreements as illegal or void in law, the

claim of the claimant for consequential relief to pass

award for monitory relief based on alleged breach of

contract is not maintainable. On the maintainability of

the claim petition, the Arbitrator has given a finding to

the effect that in the absence of the claimant seeking

foundational relief of declaration, he is not entitle for

consequential relief of award for monitory relief for

alleged breach of contract. This finding of the arbitrator

is based on the decision of the Apex Court of the Land

rendered between I.S.Sikandar (dead) by LRs v. K.

Subramani and others reported in (2013) 15 Supreme

Court Cases 27, wherein, it was held that in a suit for

specific performance of contract subsistence of contract

is essential precondition. When the agreement is already

terminated by the defendant vendor, in the absence of

plaintiff   prayer   seeking     declaratory     relief   that   the
                            38
                           CT 1390_Com.A.S.93­2019_Judgment .doc


termination of the agreement was bad in law, suit of

specific performance is not maintainable.

     27. A perusal of the materials on record discloses

that after passing of the award dated 2/8/2008 by the

Joint Registrar of Cooperative Society to pay a sum of

Rs.5,85,934/­   along     with   interest   to   the   plaintiff

construction firm, the defendant society has satisfied the

said award by paying a sum of Rs.15,37,044/­ to the

plaintiff construction firm is not in dispute. A perusal of

the materials on record discloses that thereafter through

Ex.R.57 resolution dated 3/8/2008 passed by the

managing committee of the defendant society, the joint

development agreement dated 5/9/1988 and subsequent

supplementary agreements were rescinded and recession

of   these   agreements    was     communicated        through

Ex.P.118 to the plaintiff construction firm. A perusal of

the materials on record discloses that in para 91 of the

claim statement, the claimant/ plaintiff construction firm
                           39
                          CT 1390_Com.A.S.93­2019_Judgment .doc


has admitted about the receipt of Ex.P.118 notice

intimating termination of agreement.

     28. A perusal of the materials on record discloses

that on 20/8/2008 itself through Ex.R.57, the defendant

society has rescinded the joint development agreement

and supplementary agreements and intimated the said

fact to the plaintiff construction firm through Ex.P.118

letter. In the present case on the application filed by the

claimant/ plaintiff construction firm, the Hon'ble High

Court of Karnataka by its order dated 20/9/2016 has

appointed the Arbitrator with a direction to enter upon

the reference and to resolve the dispute between the

parties.

     29.   On   21/11/2016,      the    claimant/      plaintiff

construction firm has filed the claim petition before the

arbitrator for recovery of a sum of Rs.27,49,06,124/­

together with interest @ 21% per annum on the

allegations of breach of contract by the defendant society.

At the time of filing of the claim petition, the claimant /
                            40
                            CT 1390_Com.A.S.93­2019_Judgment .doc


plaintiff construction firm was aware of the fact that

Ex.P.1 to P.6 the joint development agreement and

supplementary agreements were already rescinded by the

defendant society on 20/8/2008.                 However, without

seeking foundational relief of challenging the recession of

the joint development agreement and supplementary

agreements, the claimant/ plaintiff construction firm has

sought for only consequential relief of recovery of money

in the form of damages from the defendant society.

       30. A perusal of the impugned award passed by the

Arbitrator discloses that the Arbitrator by considering the

contents of Ex.R.57 resolution passed by the managing

committee of the defendant society canceling the joint

development agreement and supplementary agreements

entered with the claimant / plaintiff construction firm

which was communicated to the plaintiff construction

firm under Ex.P.118 letter and further considering the

fact   that   the   claimant    inspite    of    having   specific

knowledge     of    termination   of      the    agreements    on
                                41
                               CT 1390_Com.A.S.93­2019_Judgment .doc


20/8/2008       instead   of     seeking     foundational        relief

challenging the said termination have chose only to seek

consequential relief of recovery of damages for breach of

contract. In the impugned award, the Arbitrator has held

that the foundation for the claim made by the claimant

before him is Ex.P.1 to P.6 agreements.                By alleging

breach of the terms of said agreement, claim statement

has been filed to pass award.              When Ex.P.1 to P.6

agreements have already been rescinded as per Ex.R.57

and communicated to the claimant as per Ex.P.118,

inspite of the rescission of the contract there been no

challenge put­forth to Ex.R.57 resolution of rescission of

contract, it is not permissible for him to go through the

validity   or   otherwise      of   the    cancellation     of     the

agreements.

     31. A perusal of the impugned order passed by the

Arbitrator discloses that based on the ratio of the

decisions reported between I.S.Sikandar (dead) by LRs v.

K. Subramani and others reported in (2013) 15 Supreme
                           42
                           CT 1390_Com.A.S.93­2019_Judgment .doc


Court Cases 27, the Arbitrator has come to the

conclusion that in the absence of the prayer to declare

the cancellation communicated vide Ex.P.118 as illegal or

void in law, the claim of the claimants for consequential

relief to pass the award for monitory relief only alleging

breach of contract is not maintainable as the essential

foundational relief of declaration has not been sought.

The Arbitrator has further held that the relief sought in

the claim petition was being with reference to Ex.P.1 to

P.6 the non existing document on account of Ex.R.57

resolution read with Ex.P.118 communication, the claim

of the claimant had no legal foundation. The arbitrator

has further held that if the declaratory relief has been

sought    and   Ex.R.57     read    with     Ex.P.118      upon

adjudication, held as illegal or void abinatio, the claim for

award of damages as claimed in the claim petition would

have certainly received his consideration in accordance

with law for grant of appropriate relief as both sides have

adduced evidence and addressed arguments.                   The
                            43
                           CT 1390_Com.A.S.93­2019_Judgment .doc


Arbitrator has further held that the settled position of law

is that the arbitrator cannot go beyond the contract as

clause 19 of Ex.P.1 agreement provides for termination of

the contract by the defendant society and there being no

challenge to the termination effected, on the ground

permissible in law, there cannot be any finding with

regard to illegality, if any, of the society in the matter of

canceling of Ex.P.1 to P.6 agreements as per Ex.R.57

resolution communicated to the claimant vide Ex.P.118.

     32. The Arbitrator by considering the fact that in

the absence of the claimant seeking foundational relief

pertaining to the Ex.P.1 to P.6 which were rescinded by

the defendant society, the claimant is not entitle for

consequential relief of recovery of money by way of

damages has come to the conclusion that the claim of the

claimant   for   passing   of   monitory      award     is   not

maintainable. Considering his finding on maintainability

of the claim petition, the Arbitrator has recorded a

finding that it is impermissible in law to record finding on
                               44
                              CT 1390_Com.A.S.93­2019_Judgment .doc


issues 2,4 and 5 pertaining to the aspect of granting

monitory relief to the claimant and rejected the claim

petition.

        33. It is pertinent to note that the claimant -

plaintiff construction firm has filed the claim petition

before the arbitrator seeking monitory relief in the form of

damages for the alleged breach of terms of Ex.P.1 to P.6

joint     development     agreement          and      subsequent

supplementary agreements by the defendant society.

Though, the claimant - plaintiff construction firm had

knowledge of recession of Ex.P.1 to P.6 contract by the

defendant society prior to filing of the claim petition has

not chosen to challenge the recession of the contracts,

which was the foundational relief instead it proceeded

only to seek monitory relief in the form of damages for

breach of terms of the contract which were already

rescinded. The aspect of granting monitory relief which

is   consequential   relief    in   the   absence     of   seeking

foundational relief by the claimant was certainly within
                             45
                            CT 1390_Com.A.S.93­2019_Judgment .doc


the terms of the submission of arbitration to the

arbitrator who was appointed to resolve the dispute

between the parties.    The finding of the arbitrator with

regard to maintainability of the claim petition is certainly

within the scope of the submission to arbitration and it

was not beyond the scope of submission to arbitration as

alleged by the plaintiff - claimant in the present suit.

      34. A perusal of the materials on record discloses

that the defendant society in its objection statement filed

before the arbitrator has specifically contended about the

termination of Ex.P.1 to P.6 agreements under Ex.R.57

resolution and communication of the same to the

claimant under Ex.P.118 communication. The objection

statement filed by the defendant society discloses that it

has   taken   a   defence    that   the    petition    was    not

maintainable in law. A perusal of the materials on record

discloses that the aspect of the termination of Ex.P.1 to

P.6 joint development agreement and supplementary

agreements was in dispute between the parties before the
                            46
                           CT 1390_Com.A.S.93­2019_Judgment .doc


arbitrator. Hence the contention of the plaintiff that the

cancellation of the agreements was not a bone of

contention within the parties before the arbitrator cannot

be accepted.

      35. A perusal of the impugned award passed by the

Arbitrator discloses that the arbitrator has properly

considered the legal position under the facts of the case

and rightly rejected the claim of the plaintiff for monitory

relief without seeking foundational relief pertaining to

recession of Ex.P.1 to P.6 joint development agreement

and supplementary agreements.

      36. A perusal of the impugned award discloses that

the   arbitrator   has   not    dealt   with   a   matter    not

contemplated or not falling within the term of submission

to arbitration as alleged by the plaintiff in the present

suit. The impugned award do not contains the decision

of matter which is beyond the scope of submission to

arbitration as alleged by the plaintiff in the present suit.
                           47
                          CT 1390_Com.A.S.93­2019_Judgment .doc


     37. By perusing the materials produced on record,

this court is of the opinion that the claimant/ plaintiff

has failed to prove that the impugned arbitral award

deals with a dispute not contemplated by or not falling

within the term of the submission to arbitration or it

contains decision of matters beyond the scope of the

submission to arbitration.

     38. By perusing the materials produced on record,

this court is of the opinion that the plaintiff has not

shown any ground U/S.34 of Arbitration & Conciliation

Act 1996 to interfere with the impugned award passed by

the Arbitrator. With these observations, I answer point

No.1 in the negative.

     39. POINT No.2 : In view of my findings on point

No.1 and the reasons assigned thereon, I proceed to pass

the following:

                        ORDER

The suit filed by the plaintiff U/S.34 of the Arbitration & Conciliation Act 1996 is dismissed. 48

CT 1390_Com.A.S.93­2019_Judgment .doc Parties are directed to bear their own costs. Draw decree accordingly.

[Dictated to the Judgment Writer; transcript thereof corrected, initialed and then pronounced by me, in the Open Court on this the 6th day of November 2019] [S.A.Hidayathulla Shariff] LXXXIII Additional City Civil Judge.

BENGALURU.