Supreme Court of India

M/S. U. P. Electric Supply Co., Ltd vs The Workmen Of M/S. S. N. ... on 8 March, 1960

Equivalent citations: 1960 AIR 818, 1960 SCR (3) 189, AIR 1960 SUPREME COURT 818, 1960 SCJ 705, 1960 3 SCR 189, 1960 (1) LABLJ 806

Author: K.N. Wanchoo

Bench: K.N. Wanchoo, P.B. Gajendragadkar

           PETITIONER:
M/s.  U. P. ELECTRIC SUPPLY CO., LTD.

	Vs.

RESPONDENT:
THE WORKMEN OF M/s.  S. N. CHOUDHARY,CONTRACTORS AND ANOTHER

DATE OF JUDGMENT:
08/03/1960

BENCH:
WANCHOO, K.N.
BENCH:
WANCHOO, K.N.
GAJENDRAGADKAR, P.B.

CITATION:
 1960 AIR  818		  1960 SCR  (3) 189


ACT:
Industrial  Dispute-Tyibunal deciding issue not referred  to
it--jurisdiction-U.P.  Industrial Dispute Act, 1947  (XXVIII
Of 1947), ss. 34 (Proviso) 5, 8.



HEADNOTE:
The  appellant company used to employ Messrs.  S.  M.  Chou-
dhary  as its contractors for doing certain work for it	 and
the contractors in their turn used to employ some workmen to
carry  out the work which they took on contract.  A  dispute
having	arisen between the contractors and their workmen  an
application  was made before the conciliation board  by	 the
workmen	 in which both the company and the contractors	were
parties and four matters were referred, namely, non-grant of
bonus  for two years, non-grant of festival  holidays,	non-
fixation  of minimum wages of those workmen at par with	 the
workmen	 of  the company and non-abolition of  the  contract
system.	 As conciliation failed the Government referred	 the
dispute to the Industrial Tribunal under the U.P. Industrial
Disputes  Act  in which only three points out  of  the	four
mentioned  above  were	referred and the  question  of	non-
abolition  of  the contract system was	not  referred.	 The
parties	 to  this reference were the contractors  and  their
workmen	 and  not the appellant company.   By  a  subsequent
notification, however, the Government impleaded the  Company
as  a  party to the dispute but did not amend  the  previous
referring order by
190
adding	the  fourth point of dispute which  was	 before	 the
conciliation   board,  namely,	the  non-abolition  of	 the
contract system.  The Industrial Tribunal framed a number of
issues	the most important of which was whether the  workmen
concerned were the employees of the appellant company or  of
the  contractors  and  came to	the  conclusion	 that  those
workmen	 were  in fact and in reality the employees  of	 the
company.  On appeal by the company by special leave,
Held,	that  on  such	a  reference  there  could   be	  no
jurisdiction in the tribunal to decide the question  whether
these  workmen	were the workmen of the company	 or  of	 the
contractors,  for  such a question was not referred  to	 the
tribunal.



JUDGMENT:

CIVIL APPELLATE, JURISDICTION: Civil Appeal No. 481 of 1958. Appeal by special leave from the Award dated June 29, 1957, of the State Industrial, Tribunal U.P. Allahabad, in Ref. No. 98 of 1956.

M.C. Setalvad, Attorney-General for India, S. N. Andley, J. B. Dadachanji, Rameshuar Nath and P. L. Vohra, for the, appellants.

A. D. Mathur, for respondent No. 1.

G. C. Mathur and C. P. Lat, for respondent No. 2. G. N. Dikshit and C. P. Lal, for the intervener. 1960. March, 8. The Judgment of the Court was delivered by WANCHOO, J.-This is an appeal by special leave against the order of the Industrial Tribunal, Allahabad. The appellant is the U. P. Electric Supply Co. Ltd., Lucknow, (hereinafter called the company). It appears that the company used to employ Messrs. s M. Choudhary (hereinafter referred to as the contractors) as its contractors for doing certain work for it. The contractors in their turn used to employ a number of persons to carry out the work which they had taken on contract. A dispute arose between the contractors and their workmen in 1956 and an application was made on June 6, 1956, by the workmen before the conciliation board. To this application both the company as well as the contractors were parties and four matters were referred by the workmen to the conciliation board, namely, (i) non-grant of bonus for the years 1953-54 and 1954-55; (ii) nongrant of festival holidays; (iii) non-fixation of minimum wages of these workmen at par with the 191 workmen employed by the company; and (iv) nonabolition of the contract system. Efforts at conciliation failed and thereupon the Government of Uttar Pradesh made a reference to the Industrial Tribunal under the U. P. Industrial Disputes Act, No. XXVIII of 1947, (hereinafter called the Act). In this reference only three points were referred out of the four which were before the conciliation board, namely, those relating to bonus, festival holidays and payment of wages to these workmen at par with the workmen of the company. The fourth point which was raised before the conciliation board (namely, non-abolition of the contract system) was not referred. The parties to this reference were two, namely-(i) the contractors and (ii) their workmen. The appellant was not a party to this reference. On August 13, 1956, another notification was issued by the U. P. Government under ss. 3, 5 and 8 of the Act by which the company was impleaded as a party to the dispute referred by the notification of July 31, 1956. It is remarkable, however, that the matters of dispute which were specified in the reference dated July 31, 1956, were not amended as they could have been under the proviso to s. 4 of the Act, by adding the fourth point 'of dispute before the conciliation board, namely, the non-abolition of the contract system. When the matter came up before the industrial court it framed a number of issues; and the first and most important issue ran thus: "Are the workmen concerned employees of the U. P. Electric Supply Co. Ltd., Lucknow or of Messrs. S. M. Chaudhary, contractors ? "

The main objection of the company was that the dispute, if any was between the contractors and their employees and that there was no dispute between the company and its workmen. It was further objected that there was no valid or legal order of the Government referring any dispute between the company and its workmen to the tribunal and therefore the tribunal had no jurisdiction. On the merits it was urged that the workmen concerned were not the workmen of the company and there was no relationship of employer and employee between the company and these workmen and therefore the company could not be regarded 192 as a party to the dispute between the contractors and their workmen.
It is therefore clear that the main question which was considered by the tribunal was whether the workmen concerned were the workmen of the company or of the contractors. As the tribunal itself says, " the crux of the whole case was whether the workmen concerned were the employees of the company ". The tribunal went into the evidence in this connection and came to the conclusion that these workmen were in fact and in reality the employees of the company. The main contention on behalf of the company before us is that even assuming that the Government had power under s. 5 read with cl. 12 of G. O. No. U-464 (LL)XXXVI-B- 257(LL)/1954, dated July 14, 1954, to implied the company as a party, the main issue decided by the tribunal was not referred to it and the tribunal could only decide the three matters of dispute included in the order of reference of July 31, 1956. Therefore, in so far as the tribunal went beyond the, three matters of dispute specified in the reference and decided the question whether the workmen concerned were in the employ of the company or of the contractors it was acting without jurisdiction as this matter was never referred to it.
We are of opinion that this contention must prevail. As we have already pointed out, there were four matters before the conciliation board including the question of non-abolition of the contract system. Further before the conciliation board not only the contractors but the company was also a party, for obviously the question of non-abolition of the contract system would necessitate the presence of the company as a party to the proceedings. When however the Government referred the dispute to the tribunal on July 31, it did not include the fourth item which was before the conciliation board relating to the non-abolition of the contract system among the matters in dispute. It also did not include the company as one of the parties to the dispute, for the reference-order refers only to two parties to the dispute, namely, the contractors and their workmen. On such a reference there could be no jurisdiction in 193 the tribunal to decide the question whether these workmen were the workmen of the company or of the contractors, for such a question was not referred to the tribunal. It is true that on August 13, 1956, the company was impleaded as a party to the dispute referred by the notification of July 31 ; but the matters in dispute remained unmended, and the question of non-abolition of the contract system or the question whether these workmen were the employees of the company in fact and in reality was not included in the matters of dispute by amendment under the proviso to s. 4 of the Act. In these circumstances it is immaterial to consider whether the impleading of the company as a party on August 13, 1956, was legal and valid or not. Assuming that it was legal and valid, the fact remains that issue No. 1 set out above by us which is undoubtedly the crux of the question in this case was not referred to the tribunal at all and did not arise out of the three matters of dispute specified in the reference order of July 31, 1956. In these circumstances the order of the tribunal by which it held that these workmen were the workmen of the company was beyond its jurisdiction. The entire order of the tribunal is directed against the company and must therefore be set aside in whole as without jurisdiction and we need not express any opinion on the merits. We therefore allow the appeal and set aside the order of the tribunal against the appellant. In the circumstances we pass no order as to costs.
Appeal allowed.