State of Uttar Pradesh - Section

Section 16 in UPERC (Captive and Renewable Energy Generating Plants) Regulations, 2014

16. Surcharge and Additional Surcharge.

- 1. A Captive Power plant shall not be liable to pay surcharge over and above transmission and/or wheeling charges for carrying the generated electricity from its plant to the destination of its own use or for the use of its members, as prescribed under the Act:Provided that in case of supply of power to a consumer or to a person other than its members, such consumer or person shall pay surcharge over and above transmission and wheeling charges as determined by the Commission.