Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0]

Madras High Court

The Tamil Nadu Water Supply vs M/S.Venkateswara Associates on 24 September, 2008

Bench: M.Chockalingam, M.Venugopal

       

  

  

 
 
 IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 24-9-2008
CORAM
THE HONOURABLE MR.JUSTICE M.CHOCKALINGAM
AND
THE HONOURABLE MR.JUSTICE M.VENUGOPAL
O.S.A.Nos.15 and 268 of 2002

The Tamil Nadu Water Supply 
 and Drainage Board,
rep. by its
Managing Director,
No.31, Kamarajar Salai,
Chennai-5.					.. Appellant in
							   OSA No.15/2002 and
							   respondent in
							   OSA No.268/2002

vs


M/s.Venkateswara Associates
a partnership firm
rep. by its
Managing Partner 
Easwaramoorthy
No.2, Saibaba Colony,
Coimbatore					.. Respondent in
							   OSA No.15/2002 and
							   appellant in
							   OSA No.268/2002

	Original side appeals preferred under Order 36 Rule 1 of O.S. Rules read with Clause 15 of the Letters Patent against the judgment and decree of this Court dated 31.1.2001 made in C.S.No.1331 of 1993.

		Appellant in							   		OSA No.15/2002 and
		respondent in							   		OSA No.268/2002		:  Mr.Sudarshana Sundar


		Respondent in
		OSA No.15/2002 and
		appellant in							   		OSA No.268/2002		:  Mr.Parthasarathy
							   Senior Counsel
							   for Mr.M.S.Sampath
COMMON JUDGMENT

(Judgment of the Court was delivered by M.CHOCKALINGAM, J.) This judgment shall govern these two appeals namely OSA Nos.15 and 268 of 2002, the former at the instance of the defendant and the latter at the instance of the plaintiff in C.S.No.1331 of 1993.

2.The respondent/plaintiff has filed C.S.No.1331 of 1993, seeking declaration and other reliefs, with the following averments:

a)The plaintiff, a partnership firm, are engineering contractors. The defendant called for tenders for the work of suction well and pump house including all pipe connections and allied civil works under the Coimbatore Drainage Scheme. The tender of the plaintiff was accepted and the work was awarded to the plaintiff and the plaintiff was issued work order, dated 12.3.1990. The plaintiff entered into an agreement dated 22.6.1990, and the plaintiff also deposited Rs.10,750/- towards earnest money deposit and also furnished the details regarding security deposit and other particulars as early as on 9.4.1990, but the defendant did not finalise the agreement, and the same was done only on 22.6.1990. The plaintiff has completed 90% of the work and on the oral instructions of the defendant's Engineers and with a view to keep up the progress of work, the plaintiff excavated the hard rock. The plaintiff was able to enter into a supplemental agreement only after a period of one and half years. The designs were also changed without any intimation to the plaintiff and this resulted in an excess of Rs.2 lakhs over the original agreement. Whenever the plaintiff demanded payment, the officials of the defendant gave false promise and the defendant at every stage, committed breach. The defendant was called upon to make necessary arrangements to dewater, but they did not do so, and it was done at the plaintiff's own expenses, and they did not make any claim for the same. The plaintiff was very co-operative and wanted to proceed with the work smoothly, but due to the attitude of the defendant, the plaintiff was put to great loss and hardship.
b)The defendant had called for tenders for construction of Anaerobic Lagoon and for providing in-let and out-let arrangement to anaerobic lagoon under Zone III of Coimbatore Drainage Scheme. The plaintiff's tender was accepted. The tender amount is Rs.16,09,339.70. The plaintiff was also issued work order, dated 28.03.1990, and he deposited a sum of Rs.32,200/- as earnest money deposit and also a security deposit of 2% of accepted contract value. The site was not handed over properly to the plaintiff by the defendant to enable the plaintiff to proceed with the work. Because of the breach committed by the defendant, the plaintiff was able to start the work only by 13.7.1990. The work could not proceed and had to be stopped because bed level for pond I and II was not fixed by the defendant and finally, the same was furnished by the defendant by letter dated 14.3.1991. As per the agreement, the bills amount are to be paid within a period of 14 days and the bill amounts to the tune of Rs.1.60 lakhs for work done have not been paid to the plaintiff. Further, since it was insisted that consolidation must be done using only sheep foot roller, the plaintiff sought for amendment of original agreement and there was no action on the part of the defendant. The work was done under the supervision and surveillance of the official of the defendant and at no point of time, the work was found fault with. Nearly 65 to 70% of the work has been completed. The plaintiff came to know that the consolidated soil was purported to have been sent for testing and the test results were not communicated to the plaintiff.
c)The earlier bills of the plaintiff (upto L S V and part bill) were paid to the plaintiff. The defendant's stand for not paying the legitimate bills of the plaintiff is unsustainable. It is not the case of the defendant that the work of the plaintiff was bad. The Superintending Engineer has also certified in the measurement book that the work is in accordance with the agreement, specification and drawings. The attitude of the Executive Engineer of the defendant is highly deplorable. A meeting of the contractors was held on 6.1.1992 and 10.4.1992 and the use of sheep foot roller was discussed, and the department officials were explained in detail in this regard. The plaintiff carried out the work according to the specifications without any protest from the defendant department upto L.S.VI and part bill. A sum of Rs.1,39,480/- is due by the defendant to the plaintiff for the work done and for which, measurements have been taken. A sum of Rs.1,70,000/- is to be paid by the defendant in respect of work done, for which measurements have to be taken, recorded and billed in Lagoon II formation of Bund.
d)The defendant has also awarded the work of laying of Sewers in Block 1-A and 2-A of Coimbatore Drainage Scheme to the plaintiff and the work order dated 2.7.90 was issued to the plaintiff. The work was done under the supervision, presence and directions of the defendant's officials. The bills were raised and certified by the official of the department before forwarding it for payment. The refilling cannot be done without conducting the funnel test and with a view to maintain a cordial relationship, the plaintiff agreed to do the said test. The defendant had committed breach at various stages of the agreement putting the plaintiff to great loss. The legitimate dues were not paid to the plaintiff and the defendant has been denying payment to the plaintiff.
e)The defendant has sent three communications informing the plaintiff that the three contracts have been terminated. The plaintiff with all difficulties did the work under the supervision of the officials of the defendant. The defendant while granting extension of three contracts, have admitted the reasons given by the plaintiff. There were occasions when the work could not be proceeded with due to rain which was beyond the control of the plaintiff. The reason given for termination of contracts is unsustainable. The plaintiff is entitled for damages for illegal termination of the contract. The plaintiff has given a memo of calculation along with the notice for the loss suffered under various heads, but the defendant did not send any reply nor made any payment. Hence the plaintiff has filed the suit for a declaration that the termination of the three contracts is illegal and for a direction to the defendant to pay Rs.2,92,750/-, Rs.5,87,680/- and Rs.9,06,580/- respectively towards damages.

3.The defendant filed a written statement, inter-alia, stating that the single tender received by the plaintiff was accepted by the Chief Engineer, T.W.A.D., Western Region, Coimbatore; that the work order was issued by the Superintending Engineer; that the period of agreement is 6 months; that the plaintiff has completed the earth work only on 2.9.1990 and 2.11.1990, i.e. 2-1/2 months after the conclusion of the agreement, but there was no delay on the part of the defendant in finalising the agreement; that with regard to bailing out water during excavation work, an agreement was entered into between the parties, and the same has to be done by the plaintiff at his cost; that it is not correct to state that designs were changed without any intimation to the plaintiff; that it is also not correct to state that till date, neither payment has been made, nor the authorised extra works and omissions had been approved; that the allegation of the plaintiff that there was delayed supply of cement is far from truth, and in fact, the plaintiff has to return the unused quantity of 30.75 M.T. of cement; that the demand towards extra cost for dewatering is in violation of the agreement condition; and that the contention of the plaintiff that dewatering done by him is not covered by the agreement is unsustainable.

4.It is further stated by the defendant that for the construction of anaerobic lagoons and providing inlet and outlet arrangement to the anaerobic lagoon at disposal work site under Coimbatore Drainage Scheme Zone III, the tender submitted by the plaintiff was accepted, and he was issued work order dated 28.03.1990; that the site was handed over to the plaintiff on 9.4.1990; that the defendant denied the allegation that the plaintiff was able to commence the work only by 13.7.1990; that at no stage, the work had been stopped for want of any levels and the plaintiff was doing the work continuously and getting payments regularly for the works executed; that certain portion of works executed by the plaintiff had been rejected by the Executive Engineer during inspection on 8.8.1991, since the same has not been done as per specifications and hence payment to the tune of Rs.1,29,502/- had been withheld. The cement required for the work had been issued to the plaintiff from 18.7.1990 onwards. If the plaintiff had done the consolidation works, as per specification, using hand roller, the question of suggesting the use of sheep foot roller would not have arisen.

5.It is further alleged in the written statement that the work done by the plaintiff for the formation of top layer of the earthen bund was found to be faulty and hence necessary samples had been tested, and the plaintiff had never sought for copy of the test report. The defendant had taken all efforts and procured necessary materials and issued the same to the plaintiff in time. With regard to the work 'providing sewers in Block 1A and 2A under Coimbatore Drainage Scheme', the site for laying of sewers in block 1A and 2A was handed over to the plaintiff on 2.7.1990, but the plaintiff commenced the work on 15.10.1990 after a delay of 3 months. On completion of preliminary works, the plaintiff had been issued departmental materials. The plaintiff had conducted funnel test only for a length of 431.40 m., leaving a balance of 3046.90 m. The plaintiff agreed to conduct funnel test for the remaining length, but he has failed to do so till the termination of the contract. The plaintiff had committed certain irregularities in the execution of the works and he had also not resumed the works and hence further payments were stopped. The plaintiff had also dug pits and trenches for laying pipelines in an unplanned manner and did not care to follow the instructions of the departmental officers in this regard, and hence for the reasons stated above, the suit has got to be dismissed.

6.On the above pleadings the trial Court framed six issues, and the parties went on trial. The plaintiff examined P.W.1 and marked 91 exhibits. The defendant examined D.W.1 and marked 7 documents. The report of the Advocate Commissioner appointed by this Court is marked as Ex.C1. The trial Court after hearing the submissions made, partly decreed in respect of the amounts to which the plaintiff is entitled and dismissed the suit in respect of damages. Aggrieved over the disallowed portion of the judgment, the plaintiff has brought forth one appeal and the defendant who was aggrieved over the decree granted in favour of the plaintiff, has brought forth the other appeal.

7.Advancing arguments on behalf of the appellant in OSA No.15 of 2002 namely defendant in the suit, the learned counsel has made the following submissions:

The judgment of the learned Single judge is contrary to law. The payment for the work done by the plaintiff under the first contract was withheld due to substandard execution of the work done by him. Similarly, the payment for the second contract was also withheld for the bad quality of work and the plaintiff has not proved his case. Further, the plaintiff did not complete the work on time as per the agreement, in spite of extension of time and hence the contract had to be terminated and given to the third parties for completion, thereby causing additional financial burden to the defendant. The amounts have been paid to the plaintiff from time to time. It is incorrect to state that the contractor was not in a position to carry out the contract because of non payment of dues by the defendant. The plaintiff is entitled to amount for the work measured and billed and therefore, that portion of the judgment of the learned Single Judge granting a decree in favour of the plaintiff has got to be set aside, by allowing the appeal filed by the defendant.

8.Contrary to the above contentions, the learned Senior Counsel for the respondent in OSA No.15 of 2002 namely the plaintiff in the suit, would submit that the judgment of the learned Single Judge in disallowing the balance claim made by the plaintiff is against the facts of the case; that the claim should have been allowed in full with regard to the Pump House contract; that having found that the plaintiff had done work which was beyond the scope of the contract, the claim should have been granted in full; that the evidence of P.W.1 should have been accepted; that payment was to be made under Ex.P.83, and no proof was filed to show that the department made payment to enable the plaintiff to proceed with the work; that there was lapse on the part of the department, and there was no fault on the part of the plaintiff; that the defendant had not measured the work done by the plaintiff at the time of termination of the contracts; that the work was done in the presence of the departmental officials; that excess work was done by the plaintiff; that the non production of M-Book is fatal and hence the appeal filed by the plaintiff has got to be allowed.

9.Admittedly, pursuant to the acceptance of the tender made by the plaintiff, three contracts were entered into by the parties with regard to three items of work namely (1) construction of pump house and suction well; (2) construction of Anaerobic Lagoon and providing inlet and outlet arrangement to anaerobic lagoon under zone III of Coimbatore Drainage Scheme and (3) laying sewers in block 1A and 2A under Coimbatore Drainage Scheme. In respect of the first work for the construction of suction well and pump house at Nunjundapuram, the work order was issued on 12.3.1990, and the value was fixed at Rs.5,35,638.18. The site was handed over on 9.4.1990 and the first measurement was recorded on 13.6.1990. An agreement in SECR No.2/90-91 was entered into on 22.6.1990. Pending the work, after exchange of communications, the said contract was terminated on 23.12.1992.

10.As far as the second item work regarding the construction of anaerobic lagoon and providing inlet and out arrangement was concerned, the work order was issued on 23.3.1990. The value was fixed at Rs.16,09,339.70. The site was handed over on 9.4.1990. An agreement in SECR/TWAD/3/90-91 was concluded on 26.6.1990. Pending the work, the same was terminated on 4.1.1993.

11.The third work order was issued on 2.7.1990 fixing the value at Rs.32,57,379/-, and the site was handed over. Pending the work, the contract was terminated on 1.12.1992.

12.In the said suit, the plaintiff has challenged the termination of all these three contracts apart from claiming compensation in that regard. The plaintiff has also claimed Rs.1.97 lakhs as amount due on the work done so far measured and billed including supplemental, additional and extra work done on item I, Rs.1,39,480/- as amount due on the work done so far measured and billed regarding item No.2, and also Rs.1.70 lakhs as per the measurement to be recorded and billed in formation of the pond, and insofar as the third item regarding block 1A and 2A, the amount due on the work done so far measured and billed Rs.1,59,430/- and for the work done, but measurement to be recorded Rs.1.30 lakhs and the work carried out on oral instructions Rs.1.26 lakhs. Insofar as the illegal termination of the three contracts, Rs.2,92,750/-, Rs.5,87,680/- and Rs.9,06,580/- respectively were claimed. On trial, granting the relief of declaration that the termination of these three contracts was illegal, the trial Court has granted a sum of Rs.50,999/- in respect of the first claim namely the amount payable by the defendant on the works done and Rs.1,39,000/- in respect of the second claim, In respect of the rest of the claim made, the suit was dismissed. Thus these two appeals have arisen. Challenging that part of the decree granting the relief in favour of the plaintiff, the defendant has brought forth the first appeal, while in respect of the disallowed portion of the claim, the plaintiff has brought forth the next appeal.

13.Perusal of all the termination orders of the contracts would indicate that they were terminated on the ground of slow progress in the work. The case of the plaintiff challenging the termination as per the averments in the plaint and also the evidence of P.W.1, was that after the work orders were issued in every case, the defendant has committed default in handing over the site; that though it was agreed that the amounts should be paid within 14 days from the date of the claim made under the bills, they were not at all paid in time; that the cement required for the work was not supplied in time; that the work could not be proceeded in view of the intervention of the unforeseen circumstances namely the water table and hard rock; that apart from that, there was a delay caused by the defendant in entering into supplemental agreement; that there was also a delay in furnishing of the invert level; that all would clearly indicate that it was the defendant who has breached the agreement by not following strictly the terms, and there was neither lapses on the part of the plaintiff, nor delay was caused by him, and under such circumstances, the termination was bad.

14.What was all contended by the defendant before the trial Court and equally here also is that as far as the first item of work was concerned, the work order was issued as early as 12.3.1990, and the site was handed over to the plaintiff on 9.4.1990; that though the preliminary work was commenced on the very next day i.e., 10.4.1990, the same was completed on 2.9.1990 and 2.11.1990 for suction well and pump house respectively; that the agreement was concluded on 22.6.1990 itself; that there was no delay in finalising the agreement; but, it was the plaintiff who completed the contract belatedly i.e., 2 = months after the conclusion of the agreement; that it was clearly agreed between the parties in Clause 3 of Schedule B of the agreement that the excavation work was to be done at the cost of the plaintiff and no extra amount would be paid by the Board, and hence the plaintiff cannot have any grievance since it was beyond the scope of the agreement; that an estimation for this work was prepared; that the agreement was also concluded on the probable quantity of the work to be executed; that according to Schedule F item 11, the quantity was to be accounted and paid to the plaintiff by drawing supplemental agreement; that pursuant to the supplemental agreement, the plaintiff was actually paid, and hence the claim on that count was baseless; that only after proper intimation there were some changes made in the design; that as per the condition (1) of page 7 of the agreement, the plaintiff would be paid as per the variations, alterations, additions, etc.,; that it is pertinent to point out that the plaintiff without any protest executed the work accordingly; that it is true that he has spent an excess amount of Rs.50,999/-; but, this amount was withheld since the work was not done according to the specifications made; that the contention put forth by the plaintiff's side that there was a delay in supply of cement was thoroughly baseless; that as per the delivery note from 13.10.1990 to 8.11.1991, 110 M.T. of cement was supplied and hence the said contention was of no basis; that as regards the further contention that there was a delayed payment and non-payment, a sum of Rs.5,86,171/- has actually been paid as per the bills claimed by the plaintiff; that insofar as the bailing and pumping water, it was clearly understood that there was no extra payment which could be made; that as far as the claim of Rs.1,97,000/- was concerned, the executed work was only to the extent of Rs.50,999/- in excess and nothing more; that the same was also withheld because of the defective execution of the work; that as far as the 2nd item was concerned, the site was handed over on 9.4.1990; but, the site was not cleaned and levelled as per the specifications till 2.6.1990; that bund lagoon was to be formed over the natural ground level available at the site only; that under the circumstances, the question of delay in handing over the site would not arise; that the work has actually commenced in the month of July 1990; that the work was to be stopped because the level for the pond I and II was not fixed by the defendant department; that after the commencement of the work the payments have been made regularly for the works executed; that five bills have been cleared as submitted by the plaintiff; that after receiving the payments regularly, the plaintiff cannot come forward to state that either there was a delay in payment or the bills to the tune of Rs.1.6 lakhs for the works done were not honoured; that the payment of Rs.1,29,502/- was withheld and not Rs.1.6 lakhs since the work was not done as per the specifications and on the basis of the rejection by the Executive Engineer of the works done during his inspection on 8.8.1991; that despite the condition in the agreement, though the plaintiff was put on notice for rectification of the work, the plaintiff did not come forward to do the same; that the re-consolidation was to be done for the top layer; but, the plaintiff did not do the same using the power roller and thus, the consolidation was found not done properly and as per the specifications; that the department has supplied cement, steel and A.C. Pipes in excess; that though they remained unused, they were not returned; that as far as the third item was concerned, though the site was handed over on 2.7.1990, the work was commenced only on 15.10.1990 after a delay of 3 months; that all the materials have been supplied in time; that immediately after the preliminary work, the plaintiff was issued departmental materials; but there was a delay; that not even 10% of the work was done actually; that the work done was also found to be defective; that under such circumstances, the department had no option than to terminate the contracts after putting the plaintiff on notice, and hence all the claims are to be rejected.

15.The Court analysed the evidence both oral and documentary adduced by both sides, and also considered the submissions made.

16.It is not in controversy that the work order for the first item for the construction of suction wall and pump house at Nunjundapuram was issued on 12.3.1990, and the agreement was entered into only on 22.6.1990. Thus, initially there was a delay caused in entering into the agreement. After the commencement of the work, at the time of excavation, there was water table and also hard rock which were to be removed for the further progress of the work. It was beyond the control of the plaintiff. In order to execute the work, the plaintiff proceeded with the work on instructions by the officials of the defendant department. D.W.1 has categorically admitted that the supplemental agreement was entered into after a period of 1 = years. It is also candidly admitted in the written statement and also by D.W.1 that changes were made in the design. The said work was carried out by the plaintiff without any murmur, but spending out of his pocket. From the averments in the written statement, it would be quite clear that these variations and additions were made by the plaintiff without any protest. This would clearly indicate that the department came with the deviation in the original design. Needless to say, that would also consume reasonable time. Having made variations and additions in the original design, the defendant cannot be permitted to say that the plaintiff was responsible for the delay since they have done it without any murmur. At this juncture, it should not be forgotten that it was done out of their pocket. The defendant has categorically admitted that the excess amount that was spent by the plaintiff with regard to the alteration and variation was to the extent of Rs.50,999/-; but, it came with a plea to state that the said amount was withheld since that work was not done as per the specifications by the department. D.W.1 has categorically admitted that the bills have got to be honoured and the amounts have got to be paid within 14 days from the date of the raising of the bill. According to P.W.1, no one bill was paid within the stipulated time of 14 days. Nowhere it is averred in the written statement that any bill was paid within the stipulated time. It would be clearly indicative of the fact that the department was not prepared to follow the procedure in making the payment within the stipulated time, but has paid later and thus, the contention put forth by the plaintiff that due to the non-payment for the bills, the amounts spent by them, were blocked, and they must do the work at their cost. All would go to show that the delay was caused at every stage from the time of handing over the site, entering the contract and making payment, by the department. Having done so, the defendant/department should not be allowed to say that the work was done by the plaintiff slowly. Even the amount of Rs.50,999/- which according to the defendant, was the value of the excess work done by the plaintiff, was not paid, but withheld stating that the plaintiff has not rectified the defects despite putting them on notice. It is pertinent to point out that the department was unable to tell anywhere or even before the Court either in the written statement or by evidence what were the defects noticed and remained to be rectified by the plaintiff. Under such circumstances, the defendant had no justification to withhold the amount. The plaintiff except the mere assertion that they have spent a sum of Rs.1,97,000/- towards the extra work done, no proof was adduced. Hence the learned Single Judge has held that the plaintiff was entitled only to a sum of Rs.50,999/- towards the claim of Rs.1,97,000/-. At this juncture, it has to be pointed out that D.W.1 the only witness examined on the side of the department, has candidly admitted that there was extra work done by the plaintiff. It is true that the removal of surplus earth was not within the scope of the agreement; but, the parties have entered into a supplemental agreement under Ex.P71. The plaintiff replied to the defendant department that Ex.P67 agreement did not contain any clause for doing any extra work; but, the same was done only on the request of the defendant's officials.

17.As pointed out above, the payments have got to be made within 14 days from the date of the certification of the Executive Engineer. Though the defendant came forward to state that the extra work was sub-standard, there was no proof available. The plaintiff not only made a claim for Rs.1.97 lakhs towards extra work done, but also in order to substantiate the same, P.W.1 was examined before the Court. There is no contra evidence by the department though examined D.W.1. At this juncture, it has to be pointed out that the M Book (measurement book) which is maintained by and in the custody of the department was not produced by the department. It is true that the plaintiff did not issue any notice to cause production of the same. In a given case where a decision could be arrived at by production of evidence on both sides, a duty is cast upon the department also for production of the documents in its custody. In the instant case, had the M Book been produced before the Court, it would have clearly indicated what was the exact work done by the plaintiff in excess of the work agreed by them since then and there measurements would have been mentioned therein and it would also contain the certificate of the Executive Engineer concerned. Hence in the considered opinion of the Court, an adverse inference has got to be drawn for the non-production of the M Book that if it was produced, it would act against the defence put forth. Hence the non-production of any documentary evidence by the plaintiff in respect of the extra work done by them, cannot be a reason to reject its claim. The evidence of P.W.1 which was not countered by D.W.1 in his evidence coupled with the fact of non-production of M Book would be suffice to sustain the entire claim of Rs.1.97 lakhs. However, the plaintiff restricted its claim in the appeal to Rs.1,28,975/-. Under the circumstances, a decree can be granted in favour of the plaintiff to that extent.

18.As far as the second contract as to the construction of the anaerobic lagoons along with inlet and outlet is concerned, it could be seen from the available evidence that though the site was handed over in the month of April 1990, it was not neither levelled nor cleaned by the department despite notice under Ex.P37. Following the plaintiff's personal meeting with the Superintending Engineer, an inspection was made on 2.6.1990, and instructions were given to do the same, and thus, the work could not be commenced till July 1991. Even thereafter, the invert level was not made known. According to D.W.1, the slope of the drainage was known as invert level, and only when the invert level was furnished, the work could be proceeded with. The plaintiff gave a letter Ex.P68 to the Superintending Engineer asking for the invert level and intimating the work done by him. D.W.1 has further stated that the plaintiff was also asking for supply of materials and due to Siruvani Main obstruction, invert level could not be finalised. Under Ex.P68 the plaintiff has also informed that the Board had to bear the extra charges if any; but, the Board did not come forward to issue any reply. Under Ex.P69, the plaintiff sought for extension of time. Under Ex.P70, the department for the reasons stated therein, granted extension of time according to D.W.1. All would clearly show that the delay was caused by the department and never by the plaintiff at all. Under such circumstances, the defendant cannot be permitted to say that there was any slow progress in the works.

19.Even for the above work also, the bills were not paid within 14 days from the date of the certificate issued by the Executive Engineer. According to the plaintiff, despite the certificate issued, a sum of Rs.1,39,408/- as claimed by the bill was not paid by the defendant. From the evidence of D.W.1, it could be seen that a sum of Rs.1.29 lakhs was retained under the head lagoon contract since the work was not completed. Under the above stated circumstances, when the bill was to be cleared within 14 days from the date of the raising of the bill and also the delay was caused by the defendant all along the period, the defendant had no justification in withholding the amount. According to the plaintiff, 65% of the work was done; but, according to the department, the work was defective since re-consolidation was not properly done. It is admitted that minutes was drawn under Ex.P83 pursuant to a meeting between the parties. Perusal of Ex.P83 would indicate that the defendant/department was liable to pay further sum to the plaintiff, and it was also decided that a part payment was to be made. Pursuant to the demand, the department decided to make 50% of the payment so that the plaintiff could proceed with the further work. Relying upon Ex.P83, it was contended on the side of the plaintiff that for the work done, which according to the department, was upto 50%, they were entitled to get. A sum of Rs.1.29 lakhs was retained under the head of lagoon. But, they have placed a bill for Rs.1.39 lakhs. According to the department, an amount of Rs.1.29 lakhs was retained since the defects which were found, were not rectified. Even here also, the Court has to comment that the M Book was not produced. That apart, the evidence of D.W.1 was not helpful to the department to counter the said claim, and hence the learned trial Judge was perfectly correct in holding that the plaintiff was entitled to the sum of Rs.1.39 lakhs under that head.

20.Insofar as the third item providing sewers in block 1A and 2A, the agreed amount was Rs.32,57,379/-. The site was entrusted on 15.10.1990. According to the plaintiff, the defendant due to the non-furnishing of invert level and materials and due to the non-payment of the bills within 14 days from the date of certification, the work was delayed. According to the defendant, not even 10% of the work was done, and even that work was not according to the specifications. According to P.W.1, the Executive Engineer directed him to close down the manholes and balance tanks and sewer lines because of the obstruction of the Siruvani Main, and hence the invert level was to be changed, and the digging of drenches, laying of pipelines and the construction of manholes were to be done again, and the plaintiff was to refill the same, and the surplus earth was to be deposited at the places shown by the defendant. He has completed the work about 5 kms, and thereafter, he could not do so since the work was terminated. According to the plaintiff, he made a claim for Rs.1,59,430/- for the work done, measured and billed. According to D.W.1, the plaintiff as per the agreement was to lay the pipeline to the length of 3478 metres; but, the plaintiff did the funnel test only to 430 metres and did not properly close the drench as per the contract, and hence loss has occurred by making retender. It is not in controversy that the work was to be completed within 9 months. But, in handing over the site, there was a delay of 2 = months. Also there was a delay of 3 = months in entering into the agreement. Though it is admitted by D.W.1 that he recorded the entire work done in the M Book maintained by the defendant, it was not produced. Insofar as this item of work, the plaintiff has done the minimum work. It was also found to be defective by the department, and the rest of the major work was to be done by calling for retender. Under such circumstances, the defendant cannot be made liable to make any payment to the plaintiff as damages.

21.As pointed out earlier, all the above three contracts awarded to the plaintiff, are terminated with a reason of slow progress in the works as narrated above. The slow progress was due to the delay caused by the defendant and not by the plaintiff. Though the bills were not honoured within 14 days from the date of the certification, the plaintiff in order to maintain a good relationship with the department, was doing the works out of its money. In such circumstances, the termination of the contracts by the defendant/department was without any justification, and hence they were to be declared as invalid. It is brought to the notice of the Court that after the termination of the contracts, the works under three contracts were completed by the department. Even then, it becomes necessary to give such a declaration in order to avoid any visitation of any consequences that would arise against the plaintiff pursuant to the termination of the contracts.

22.The learned Single Judge has rejected the claim for damages in respect of the termination of the contracts. That part of the judgment of the trial Court is not challenged by the appellant/plaintiff, and hence no relief could be granted in that regard.

23.It is an admitted fact that in respect of these three contracts, the plaintiff has made earnest money deposit namely Rs.10,750/-, Rs.32,200/- and Rs.65,150/- respectively, which the plaintiff is entitled to get back from the defendant/department.

24.For the reasons stated above, the plaintiff is entitled to a decree for a sum of Rs.1,28,975/- in respect of the first contract, apart from Rs.50,999/- awarded by the learned Single Judge. The plaintiff is also entitled to get back the earnest money deposit of Rs.10,750/-, Rs.32,200/- and Rs.65,150/- in respect of the three contracts respectively, from the defendant/department. The plaintiff is entitled to interest at the rate of 18% per annum from the date of plaint till realisation, for the said EMD amounts. In other respects, the judgment and decree of the learned Single Judge are confirmed.

25.In the result, O.S.A.No.268 of 2002 is partly allowed, and O.S.A.No.15 of 2002 is dismissed. The parties will bear their costs.

(M.C.,J.) (M.V.,J.) 24-9-2008 Index: yes Internet: yes nsv/ M.CHOCKALINGAM, J.

AND M.VENUGOPAL, J.

nsv/ OSA Nos.15 and 268/2002 Dt: 24-9-2008