Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 10, Cited by 0]

Bangalore District Court

M.Keshava Raju vs Government Of Karnataka on 25 October, 2019

IN THE COURT OF THE LXXXIII ADDITIONAL CITY CIVIL
  AND SESSIONS JUDGE AT BENGALURU CITY[CCH-84]

PRESENT:   Sri S.A. HIDAYATHULLA SHARIFF,
                                   B.A., LL.M.,
           LXXXIII Additional City Civil and
           Sessions Judge

      Dated this the 25th day of October 2019

                 COM.O.S.No.23/2019
           (O.S.No.10/2018 & OS 45/2017)

PLAINTIFF:            M.Keshava Raju, aged about 66
                      years, S/o late M. Narayana Raju,
                      Engineering Contractor, No.7, I.T.I
                      Layout, R.M.V. II Stage, Bangalore­
                      560094.


                      [By Sri.KMM/PHR, Advocate]

                       /v e r s u s/

DEFENDANTS:            Government of Karnataka, Public
                       Works Department.
                       Represented by its

                 1.    The Secretary,
                       Public Works Department,
                       Government of Karnataka,
                       3rd Floor, Vikasa Soudha,
                       Bangalore­560001.

                 2.    The Chief Engineer (C&B) South,
                       K.R.Circle, P.W.D,
                       Bangalore­560001.
                              2
                             CT 1390_Com.O.S.23­2019_Judgment .doc


                  3.   The Executive Engineer,
                       P.W.D. Division, Chikkaballapur,
                       Chikkaballapur District.


                       [By District Government Pleader]


Date of institution of the   :    26/02/2019(04/2/2017)
suit
Nature of the suit           :        Recovery of money
Date of commencement of      :          30/10/2017
recording of the evidence
Date    on    which    the   :           25/10/2019
Judgment               was
pronounced.
                             : Year/s Month/s           Day/s
Total duration
                                 02      08               21



                         (S.A. Hidayathulla Shariff)
                       LXXXIII ACC & SJ: Bengaluru




      Plaintiff has filed this suit against defendants for

recovery of money. This suit was originally filed before

the II Addl. Senior Civil Judge & JMFC, Chikkaballapur

and suit was numbered as OS No.45/2017. Thereafter,

the suit was transferred to I Addl. District & Sessions

Judge,   Chikkaballapur      and    numbered       as   OS      No.
                            3
                           CT 1390_Com.O.S.23­2019_Judgment .doc


10/2018.     After establishment of this court to try

commercial    disputes,    on   the    point        of     territorial

jurisdiction, the suit is transferred to this court and it

was renumbered as Commercial OS No.23/2019.

     2.    The case of the plaintiff in brief is that he is a

Class I contractor having experience in contract works.

He   submitted    tender   in   response       to        the   tender

notification issued by the Government of Karnataka for

the work of "Construction of Mini Vidhana Soudha at

Sidlaghatta, Kolar District" presently Chikkaballapur

District. He being the lowest tenderer was awarded the

above mentioned construction work vide Agreement

No.10/93­94 dated 11/8/1993.          The cost of the work

under the above mentioned tender was Rs.42,91,526/­.

The 3rd defendant­ Executive Engineer, PWD Division,

Kolar has issued work order on 24/8/1993. As per the

terms of the contract, the monthly stipulated progress

was Rs.2,14,576/­.     As per the work order the date of

commencement of the work was 19/8/1993 and the date
                            4
                           CT 1390_Com.O.S.23­2019_Judgment .doc


of completion was 15/11/1995, including monsoon

period. The contract contains schedule of quantities in

which rates for each of various individual items of work

are entered in Schedule B along with a copy of

agreement, the letter of acceptance, work order etc. with

the detailed technical specifications, with the conditions

of contract agreement.

     3. It is further case of the plaintiff that immediately

after receiving the work order, he started the work in

portion of the site made available by the Assistant

Executive Engineer.      He has mobilized the resources

including men, machinery, establishment and other

matching equipments and camped at site to execute the

work.   The site was not clear as the electric and

telephone lines were obstructing the work.            A minor

portion of the work was executed for some period as long

as clear site was available and there was stoppage of

work for a major period during the stipulated period of

performance of the contract. Immediately after the mark
                             5
                           CT 1390_Com.O.S.23­2019_Judgment .doc


out given by the sub­divisional officers, he started the

work and completed the excavation for foundation by

30/9/1993 as per the excavation plan and mark out

given by the defendant. He continued the stay at work

site with the establishment for the purpose of executing

the work in the stipulated and prolonged period upto

March 1999, but could not complete the work in all

respects due to reasons stated in the following paras.

      4. The construction of buildings of any magnitude

requires detailed approved working drawings showing the

details of foundations, basement, superstructures with

all items. The defendant failed to supply these drawings,

designs and details in time. The defendant was not in a

position to supply the working drawings at a time along

with the work order. The designs/drawings for RCC

foundations   were     supplied   only   in    the     month   of

November 1993 with a delay of 3 months for foundation.

The   drawings   for   basement     were      issued    only   on

30/10/1994 with a delay of 14 months. The drawings for
                            6
                           CT 1390_Com.O.S.23­2019_Judgment .doc


ground floor roof beams and slab were issued to him only

on 29/12/1995 with a delay of about 28 months after

commencement of the work.          Until the expiry of the

original contract period the defendant was not in a

position to issue full working drawings for all the items

even for ground floor where as the contract consists of

ground floor and first floor. Inspite of abnormal delay in

supply of work working drawings, the defendant has not

fixed any further period of performance of the contract.

He has brought all the delays to the knowledge of the

defendant at several times as and when occurred in his

several    letters   dated     16/2/1995,         27/7/1995,

30/10/1995,      5/11/1996,       16/4/1997,        4/9/1998,

5/10/1998, 14/10/1998 and 25/11/1998. The delay on

the part of defendants in supplying the full working

drawings has caused abnormal delay in executing the

work and has also resulted in huge loss to him.

     5. It is further case of the plaintiff that high tension

electric lines, telephone lines fixed were crisscrossing the
                           7
                          CT 1390_Com.O.S.23­2019_Judgment .doc


work site.   There was a Municipal Water Supply line

passing through below the ground level of the site. It was

very difficult to execute even the foundation as the

municipal underground water supply lines were not

shifted. There were major obstructions in the site due to

high tension electrical line which was crossing in the

middle of the site and posing danger to the labourers.

This fact of delays were brought to the knowledge of the

defendant    through     letters     dated      25/11/1993,

11/5/1994, 10/6/1994, 24/10/1994, 4/1/1995 and

19/10/1995. There was abnormal delay in making the

site clear by removing the high tension electric line,

telephone line and municipal water supply line. The high

tension line was shifted only during September 1994. It

was not possible to fabricate the steel for columns below

the high tension electric line. The basement work cannot

be executed without removal of the high tension electrical

line.   The delay in not shifting of the high tension

electrical line has caused stoppage of work.
                            8
                           CT 1390_Com.O.S.23­2019_Judgment .doc


     6.It is further case of the plaintiff that the essential

building materials were not available at a reasonable

distance.    He had to go in search of the building

materials since the same were not available at the

distance shown by the defendant              at the time of

tendering.   This caused further delay in executing the

work with incurring extra cost and required much more

investments by him.

     7. It is further case of the plaintiff that the interim

payments for the work done were very irregular.             The

contract agreement provided payment for the work done

in each month. There were inordinate delay in preparing

and payment of the bills.         In some occasions, the

defendant took 6 to 8 months for making one running bill

payment.     This created unbalanced working conditions

and delayed the completion of the work. Even at the time

of canceling the contract, there were substantial pending

payments. The delay in making payments was brought

to the knowledge of the defendants through letter dated
                           9
                          CT 1390_Com.O.S.23­2019_Judgment .doc


10/6/1994, 16/2/1995, 27/7/1995, 15/2/1996 and

4/9/1998.

     8. It is further case of the plaintiff that inspite of

above   mentioned    impediments,      he    continued      the

execution of the work under most trying circumstances.

He was executing the work to the possible extent and

kept ready the same establishment made at site to

execute and complete the work. In the mean time, the

defendant has illegally canceled the contract with a

threat to execute the balance work at plaintiff risk and

cost though the delays attributable to the defendant. The

defendant has not even fix further period for performance

of the contract to make the time essence of the contract

after expiry of the period of contract on 15/11/1995.

Inspite of his repeated requests for extension of time,

before expiry of original contract period, the defendant

has illegally canceled the contract without fixing period

for extension of contract.    The final bills are not yet

prepared and final account pertaining to the contract are
                           10
                          CT 1390_Com.O.S.23­2019_Judgment .doc


yet to be settled by the defendants. The defendants have

committed breach of contract.

     9. It is further case of the plaintiff that after

cancellation of the contract, he has given a consolidated

claims letter dated 5/9/2002 to the 3 rd defendant for

settlement as per clause 29 of the conditions of the

contract. As there was no reply to the above letter, he

approached the defendant by letter dated 7/11/2002 for

settlement as per the conditions of the contract.          Even

the 2nd defendant has not replied the said letter for

settlement of claims. Thereafter, he has approached the

Hon'ble   High   Court   of    Karnataka    by    filing   CMP

No.47/2003 for appointment for arbitrator as per the

conditions of the contract.     The Hon'ble High Court of

Karnataka by its order dated 11/7/2003 has rejected the

above mentioned CMP on the ground that clause 29 of

the contract is not an arbitration clause.       Aggrieved by

the order dated 11/7/2003 passed by the Hon'ble High

Court of Karnataka, he has filed WP No.40896/2003 for
                           11
                          CT 1390_Com.O.S.23­2019_Judgment .doc


appointment of arbitrator and the said writ petition was

also dismissed on 6/11/2003.       Aggrieved by the above

mentioned   order,   he   has   approached      the    Hon'ble

Supreme Court of India by filing SLP in Civil Appeal

No.1558/2004 for appointment of arbitrator. The Apex

Court of the Land by its order dated 25/10/2013 held

that clause 29 of the contract is not an arbitration clause

and has given liberty to him to recover the dues through

legal remedy. Further he has filed review petition against

the common judgment passed in SLP No.1586/2004

before the Apex Court of the Land and the said review

petition also came to be dismissed on 16/9/2014.

     10. It is further case of the plaintiff that in

connection with breach of contract dated 11/8/1993 by

the defendants, following claims have arisen to him,

which he has sought for settlement in the present suit.

     11. Claim I : to declare that the cancellation of

contract is illegal and wrongful and to desist from
                           12
                          CT 1390_Com.O.S.23­2019_Judgment .doc


applying cost and risk action of completing the

balance work and entitled for damages.

     With regard to above mentioned claim No.1, it is the

case of the plaintiff that the stipulated period of contract

expires on 15/11/1995, as per the terms of contract.

Inspite of several delays and defaults committed by the

defendant, he continued the execution of the work even

beyond the stipulated period.         The defendant also

accepted and permitted him to complete the execution of

work. Delay in completion of work is not attributable to

him. His repeated requests for grant of extension of time

were not considered by the defendants. The defendants

have not disputed the claims at the time of execution of

the work beyond statutory period of time and allowed

him to continue with the work.        All of a sudden the

defendant had taken illegal action of cancellation of the

contract.    Had the defendant made the site clear

immediately after agreement, made proper payments,

made available required drawings in time and allowed
                             13
                            CT 1390_Com.O.S.23­2019_Judgment .doc


him to continue the work, he would have completed the

work in a reasonable time. Without deciding the aspect

of the breach of contract, the cancellation of the contract

by defendants is illegal.   Hence, the cancellation of the

contract dated 11/3/1999 by the defendant is illegal and

wrongful. Hence, defendant required to refund a sum of

Rs.1,63,470/­ towards refund of EMD, FSD recovered in

bills and NSC recovered in bills and defendants are liable

to pay him a sum of Rs.3,49,825/­ as interest @ 12% per

annum on the above mentioned amount and liable to pay

him totally a sum of Rs.5,13,295/­ towards the claim

No.1.

        12. Claim 2 : Payment of damages of idle charges

of men and machinery suffered.

         With regard to the above mentioned second claim,

it is the case of the plaintiff that the execution of the

work was stopped on several occasions for want of design

details and due to obstructions at work site, lack of

payments.     The total period of stoppage was 339 days,
                               14
                              CT 1390_Com.O.S.23­2019_Judgment .doc


during     the    period    of     execution    of         work      from

commencement of work to the cancellation of contract

due to various defaults and breaches committed by the

defendant, he has suffered damages in the form of idle

charges of men and machinery, due to the default

committed by the defendant, which resulted in stoppage

of work.    The stoppage of work was intimated to the

defendant by letter dated 10/6/1994, 24/10/1994,

4/1/1995 and 16/2/1995.             He has kept separate men

and     machinery     for   the    performance        of    the      work

pertaining to contract in dispute. He has no chance to

mitigate the damages suffered during the idle period and

there    was     no   other       opportunity    to        utilize    the

establishment made at this work and was always ready

at work site for instruction of the defendant to execute

the work.        The idle charges per day works out to

Rs.3,600/­ including labours and machinery.                          The

defendant required to compensate him for the idle

charges @ Rs.3,600/­ per day for 339 days, which
                          15
                          CT 1390_Com.O.S.23­2019_Judgment .doc


amounts to Rs.12,20,400/­. Defendant required him to

pay a sum of Rs.31,60,836/­ as interest @ 12% per

annum on the above mentioned amount. With regard to

claim 2 the defendant required to pay him a total sum of

Rs.43,81,236/­ as payment of damages of idle charges of

men and machinery suffered by him.

     13. Claim 3 : Payment of equitable revised rates

for the work done beyond the stipulated period of

contract.

       With regard to above mentioned claim No.3,

plaintiff has stated that the period of performance was

prolonged beyond the stipulated date of completion due

to several defaults and breach of contract committed by

the defendants. Consequently, he was forced to execute

the work in the prolonged period beyond the stipulated

period of completion, facing the burnt of all around

increase in the market prices during the period. There is

no justice in insisting him to do the contract at tendered
                             16
                             CT 1390_Com.O.S.23­2019_Judgment .doc


rates, since the delay in completing the work was not at

all attributable to him.     He is entitled for payment of

equitable revised rates for the work done beyond the

stipulated   period     taking   into     consideration    of    the

changed market conditions and circumstances under

which the work was executed.               The defendants are

required to pay equitable revised rates for the quantities

of   work    executed    beyond     the     stipulated    date    of

completion of 15/11/1995. Plaintiff has claimed a sum

of Rs.14,84,424/­ towards equitable revised rates for the

work done beyond the stipulated period of contract and

also sought for a sum of Rs.31,76,667/­ as interest on

the above mentioned amount at 12% per annum from

11/3/1999      upto     2/2/2017,       totally   amounting       to

Rs.46,61,091/­.

     15. Claim 4 : reimbursement of expenses for

longer stay at the work site for the purpose of

executing the work.
                          17
                          CT 1390_Com.O.S.23­2019_Judgment .doc


      With regard to above claim 4, it is the case of the

plaintiff that delay in completion of the work is only

attributable to the defendants and the execution of the

work beyond the stipulated date of completion has

resulted in incurring extra expenditure on additional

monthly overhead charges by him. He had taken 10% of

the cost of work at his quoted rates via­a­viz stipulated

period of contract as the cost of overhead charges to meet

the overheads both at head office and site office which

included payment towards managerial, consultancy, legal

advise, engineering, supervision, accounts, stores and

traveling.   The overhead charges are fixed in each and

every month and will not increase or decrease in

proportion to the quantum of work executed in each

month. The establishment engaged on the works cannot

be retrenched or reduced till the completion of the work.

Hence, the expenditure on monthly overheads continued

from the date of contract period from 15/11/1995 till the

cancellation of the contract on 11/3/1999. The plaintiff
                              18
                             CT 1390_Com.O.S.23­2019_Judgment .doc


has      claimed   a   sum        of   Rs.7,22,357/­     towards

reimbursement of expenses for longer stay at the work

site and also claimed a sum of Rs.15,45,844/­ as interest

on the above mentioned amount from 11/3/1999 upto

2/2/2017       @ 12% per annum.            Plaintiff has totally

claimed a sum of Rs.22,68,201/­ towards this claim

No.4.

        16. Claim 5 : Loss of profit on the balance work.

        With regard to the above mentioned claim No.5 is

concerned, it is the case of the plaintiff that the work was

entrusted to him at his tender rate with tender cost of

Rs.42,91,526/­. Since the defendants failed in fulfilling

their contractual obligations, such as, supply of working

drawings in time, making site clear by removing the

municipal underground water lines, removing the high

tension electrical lines and telephone lines, the work was

prolonged beyond contract period and could not be

completed within time.     The defendants without fulfilling

their contractual obligations have chosen to cancel the
                                 19
                                CT 1390_Com.O.S.23­2019_Judgment .doc


contract on 11/3/1999 for no fault of the plaintiff. With

great     difficulties     he    had     achieved        progress   of

Rs.17,83,296/­           out    of     the   tender        value    of

Rs.42,91,526/­.          The balance of the cost of work was

Rs.25,08,230/­. Even in the achieved progress there was

payment due to him. The defendants reserved some of

the amounts which was payable to him due to shortage

of funds which was clearly mentioned in RA bills. The

plaintiff has claimed a sum of Rs.3,76,234/­ for loss of

profit on the balance cost of work and also claimed a sum

of Rs.8,05,140/­ as interest on the above mentioned

amount @ 12% per annum for the period between

11/3/1999 upto 2/2/2017. On claim No.5 plaintiff has

totally claimed a sum of Rs.11,81,374/­.

        17. Claim 6 : Release of reserved amount in the

RA bills.

        With regard to above mentioned claim No.6 is

concerned, it is the case of the plaintiff that the

defendants      reserved        the    amounts      to     extent   of
                          20
                          CT 1390_Com.O.S.23­2019_Judgment .doc


Rs.79,147/­ for want of funds which was clearly

mentioned in the running account bills No.8 & 9. It is

the duty of the defendants to make arrangements for the

funds for regular payments.       The cause of delay in

making irregular payments also attributable to the

defendants only. With regard to claim No.6, the plaintiff

has sought for a sum of Rs.79,147/­ towards the amount

payable to him in RA bills No.8 and 9 and also sought for

a sum of Rs.1,69,374/­ as interest @ 12% per annum for

the period between 11/3/1999 upto 2/2/2017. On claim

No.6 plaintiff has totally claimed a sum of Rs.2,48,521/­.

     18. Claim 7 : Payment of interest @ 12% on all

the claims.

     With regard to the above mentioned claim No.7, the

plaintiff has sought for interest @ 12% per annum on all

the amounts claimed in the present suit and sought for

future interest @ 18% per annum on the suit claim from

the date of the suit to the date of payment. It is further

case of the plaintiff that the claim amount quantified by
                               21
                              CT 1390_Com.O.S.23­2019_Judgment .doc


him is valid, legitimate and he is entitle for the same in

terms       of       the   agreement     conditions     and     the

correspondences from the time of awarding the contract

till its cancellation of work and thereafter. That he has

issued a legal notice to the defendants under Section 80

of CPC for settlement of claims vide letter dated

19/12/2014 and defendants have not taken any action

even after the decision of Apex Court of the Land for

settlement of the claim raised by him.           Plaintiff further

contended that this court is having territorial jurisdiction

to try the suit and the suit is filed within the period of

limitation. On these grounds, the plaintiff has sought for

recovery   of    a    sum    of    Rs.1,32,53,718/­     from    the

defendants towards the amount of claim made by him

with respect to contract No.10/93­94 dated 11/8/1993

together with costs and future interest @ 18% per annum

from the date of filing of the suit till the date of realization

of the amount.
                            22
                           CT 1390_Com.O.S.23­2019_Judgment .doc


     19.   In   response   to   the     suit     summons,    the

defendants No.1 to 3 have contested the suit by filing

their joint written statement.      The defendants in their

written statement have contended that the suit of the

plaintiff is not maintainable either in law or on facts and

same is liable to be dismissed.           Defendants further

contended that the plaintiff has filed a false, frivolous and

vexatious suit against them with a malafide intention of

harassing them. The suit of the plaintiff is speculative in

nature and misconceived one and liable to be dismissed.

Plaintiff has not properly instituted the suit as required

U/S.79(b) and Section 80(i)(c) of CPC.

     20. Defendants further contended that the suit

claim of the plaintiff is hypothetical and illogical.       The

plaintiff has caused substantial delay of 4 years in

constructing the building, as such, he could not claim

the overhead charges, labour charges, establishment and

maintenance of labourers and machinery. Due to poor

performance     in   construction     activity   and   financial
                          23
                          CT 1390_Com.O.S.23­2019_Judgment .doc


activity, the contract was terminated by them. Since the

plaintiff has failed to discharge the terms and conditions

of the agreement, he is not entitle for any relief sought

for.

       21. The defendants in the written statement have

not disputed the fact that the plaintiff was a class I

contractor and he being the lowest tenderer, he was

awarded the work       of construction of Mini Vidhana

Soudha     at   Sidlaghatta   vide    contract     agreement

No.10/93­94 dated 11/8/1993.         The defendants have

also not disputed the plaint averments with regard to

cost of the contract work, date of issuance of work order,

date of commencement of the work and date of

completion of the work stipulated in the above mentioned

contract. The defendants have denied the plaint averment

that final bill of the contract has not been prepared. The

defendants have contended that plaintiff has not come

forward to put his signature and received the same. The

defendants have denied the plaint averments that the
                            24
                           CT 1390_Com.O.S.23­2019_Judgment .doc


plaintiff has started the construction work immediately

after receiving the work order in a portion of the site

made available to him and in the portion which was

cleared without any obstruction. The defendants further

contended that the plaintiff has not started his work after

receipt of the work order and he has delayed the to

commencement of the work at site. The defendants have

also   denied   the   plaint    averments   with    regard    to

mobilization of the resources and camping of the plaintiff

at the site to execute the work and also denied the

averments that the site was not cleared as the electric

and    telephone   lines   obstructing    the   work.        The

defendants have also denied the plaint averments that

since the electric and telephone lines were not shifted,

there was stoppage of construction work for a major

period during the stipulated period of performance.

Defendants further contended that the plaintiff has not

complied the terms of the agreement dated 11/8/1993.

When the site was handed over to the plaintiff, they have
                          25
                         CT 1390_Com.O.S.23­2019_Judgment .doc


remitted a sum of Rs.9,893/­ vide cheque No.965438 dt.

14/6/1993 to shift the electric lines and poles and also

sum of Rs.8,192/­ was transferred to BSNL account vide

M.B.No.5572 shift the telephone lines and poles.         After

receipt of the said sum by the above departments, they

have shifted the poles and lines from the site. There was

no obstructions for commencement of the work by the

plaintiff and there is no latches on the part of the

defendants.

     22. The defendants in their written statement have

also denied the plaint allegations with regard to the

alleged reasons shown by the plaintiff for non completion

of the work within the stipulated period of time.         The

defendants have denied the plaint allegations that there

was delay by the defendants in supply of approved

working drawings, which resulted in non completion of

the work in the contract period.       Defendants further

contended that as per letter dated 7/4/1993 the

approved structural drawings were given to the plaintiff
                            26
                           CT 1390_Com.O.S.23­2019_Judgment .doc


and plaintiff has suppressed the same.             Defendants

further contended that as per the request of the plaintiff

made through letter dated 11/5/1994, the AEE, PWD

South Division, Chikkaballapur has caused a letter dated

26/10/1994 to the plaintiff asking him to collect the

required drawings in connection with the construction

work.   The defendants further contended that though

they have supplied the required drawings to the plaintiff,

plaintiff is trying to extract money from them through

illegal mode.   Defendants further contended that the

plaintiff received drawing for foundation on 7/4/1993

and entire drawings upto the floor, ceiling, beam, canopy

columns and beams on 26/10/1994, but he has

achieved   progress   of    only    Rs.6,25,420/­       as    on

23/3/1994 to the target progress of Rs.23,54,500/­, as

per the terms of the agreement.

     23. The defendants in the written statement have

also denied the plaint allegations with regard to non

shifting of high tension electric line, telephone line and
                                 27
                                CT 1390_Com.O.S.23­2019_Judgment .doc


Municipal water line from the site made against them as

reason for delay in construction work.                  Defendants

further     contended    that    they    have given respective

amount to the concerned department for shifting of

electric lines and telephone lines on 14/6/1993 and

inspite of it, the plaintiff has made false allegation

against them.     Defendants have further contended that

inspite of shifting of electricity lines and telephone lines,

the plaintiff had given financial implications of only

Rs.6,25,420/­      as      on        23/3/1994        instead      of

Rs.23,54,000/­,     as      per      the     tender     agreement.

Defendants further contended that the plaintiff has given

unwanted reasons to execute the work and he has

commenced the work in the month of November 1993

and there was no delay for payment. Under clause 15(c)

of the schedule form, they have never given direction to

stop the work, plaintiff has not deployed his labourers at

the site.
                                 28
                                CT 1390_Com.O.S.23­2019_Judgment .doc


        24. The defendants have also denied the plaint

allegations that non availability of essential building

material at a reasonable distance as one of the reason for

delay     in    construction     work.         Defendants    further

contended that the plaintiff being class I contractor has

to look after the supply of building materials and he

cannot depend upon the defendants for collecting the

building material to complete the tender work.                   The

defendants have also denied the plaint allegations that

they were irregular in payment for the work done by the

plaintiff. Defendants further contended that the amount

for the work done by the plaintiff has been disbursed to

him as per the allocation of funds made by the

government. There was no any inordinate delay in

preparing the bills on their side. Defendants have also

denied the plaint allegations that even at the time of

canceling the contract there was substantial pending

payment        to   the   plaintiff.     The    defendant    further

contended that as on the date of cancellation of work,
                           29
                           CT 1390_Com.O.S.23­2019_Judgment .doc


plaintiff had received a sum of Rs.17,40,149/­ on

19/2/1999. Such being the case, the question of delay

in payment to the plaintiff by them will not arise.

     25. The defendants in the written statement have

also denied the plaint allegations that inspite of severe

impediments, the plaintiff was executing the work under

most trying circumstances and defendants have illegally

canceled the contract with a threat to execute the

balance work at plaintiff's risk and cost. The defendants

have also denied the plaint allegations with regard to

breach of contract made against them.              Defendants

further contended that they have caused a notice to the

plaintiff on 22/11/2002 by objecting the illegal acts of

the plaintiff. The plaintiff on one or other way trying to

put them into trouble to gain unlawful means at their

cost. The plaintiff himself has caused delay of about 4

years in executing the work, impliedly they have allowed

the plaintiff to work till 11/3/1999.      Actually the term

fixed for completion of the work as per the agreement was
                             30
                                CT 1390_Com.O.S.23­2019_Judgment .doc


on 15/11/1995. There is no breach of contract on their

part. On the other hand the plaintiff has failed to comply

the terms and conditions of the contract and he has

failed to achieve the stipulated financial progress in

terms of the contract.

     26. The defendants in the written statement have

admitted about the receipt of notice on 5/9/2002 and on

7/11/2002 from the plaintiff and further contended that

they have suitably relied the said notice. The defendants

have also admitted the proceedings between the plaintiff

and defendants that took place before the Hon'ble High

Court of Karnataka and Hon'ble Supreme Court of India

and the orders passed in the said proceedings.

     27. The defendants in the written statement have

denied the claim No.1 of the plaintiff seeking cancellation

of contract as illegal and desisting them from applying

risk and cost action of completing the balanced work and

for payment of damages to the plaintiff. Defendants

further   contended      that     the    plaintiff   making     false
                           31
                          CT 1390_Com.O.S.23­2019_Judgment .doc


allegation against them to over come from the action to

be taken by them against him for causing loss and

inconvenience to the public at large. The plaintiff has no

right to make claim against them under the law. They

have not taken any illegal action against the plaintiff in

canceling the contract. There was no delay on their side

in clearing the site for executing the work and there is no

delay in payment.     Plaintiff himself caused inordinate

delay in executing the tendered work and caused loss to

the state. They have supplied the required drawings to

the plaintiff on time to time and they have made

payments to the plaintiff on the bills prepared and filed

by him.   Since the plaintiff has failed to complete the

work within stipulated period as per clause 3(b) & (c) of

the schedule Tender, they have canceled the contract on

cost and risk basis and have forfeited the security deposit

to the government.       Since they have canceled the

contract in terms of the contract and forfeited the

security deposit, the question of considering the claim
                                 32
                                CT 1390_Com.O.S.23­2019_Judgment .doc


made by plaintiff for a sum of Rs.1,63,470/­ together

with    interest   will   not    arise.      Defendants      further

contended that there was no contractual obligations on

their part of pay 12% interest. Once the forfeit clause is

opened by them, the question of considering the claim of

the plaintiff will not arise.

       28. With regard to the second claim of the plaintiff

pertaining to payment of idle charges of men and

machinery suffered by him, defendants have contended

that since there was no stoppage of work by them at any

stage during subsistence of contract, plaintiff cannot

make any claim for compensation as per clause 15 of the

schedule of contract form. They reserves the right to take

action against plaintiff for the delay in execution of the

work.    The plaintiff has not maintained the men and

machineries in the site during the subsistence of

contract. There is no default and breaches committed by

them.     Plaintiff unnecessarily making false allegations

against them.       The claim of plaintiff for a sum of
                            33
                               CT 1390_Com.O.S.23­2019_Judgment .doc


Rs.43,81,236 as damages for idle charges of men and

machineries is an imaginary claim. At no point of time

the plaintiff has not shown the idle of men and

machinery    at   the   site     during    the     subsistence    of

agreement. Plaintiff has not made any representation in

this regard. Plaintiff has not produced a single piece of

document to substantiate the above mentioned claim.

Plaintiff has not used any machinery for doing the work

at site.

      29. With regard to claim 3 of the plaintiff pertaining

to payment of equitable revised rates for the work done

beyond the stipulated period of contract is concerned, the

defendants have contended that there is no legal base for

the plaintiff to make said claim.                Plaintiff has not

produced any document to substantiate the said claim

and there is no provision under the contract for payment

of interest @ 12% per annum. The vouchers produced by

the plaintiff are all self serving documents. At no point of
                              34
                             CT 1390_Com.O.S.23­2019_Judgment .doc


time, the plaintiff has produced any single voucher before

them certifying the said amount.

     30. With regard to claim No.4 pertaining                   to

reimbursement of expenses for longer stay at the work

site for the purpose of executing the work claim made by

the plaintiff, the defendants have contended that the said

calculation made by the plaintiff is self serving one and

not based on any document and only on assumption the

plaintiff has calculated the amount and he is not entitle

for the said relief.     Defendants have further contended

that since the plaintiff has failed to reach the monthly

progress of the tender work prescribed under the

contract, plaintiff is not entitle for the said claim.        The

plaintiff has not engaged any man power near the

building very long time. Hence this claim of plaintiff is

liable to be rejected.

     31. With regard to claim 5 of the plaintiff pertaining

to loss of profit on the balance work is concerned, the

defendants    have     contended    that    the   plaintiff   had
                               35
                              CT 1390_Com.O.S.23­2019_Judgment .doc


achieved the financial progress of Rs.17,04,149/­ instead

of stipulated progress of Rs.42,91,526/­ in the contract.

Since the plaintiff has failed to achieve physical and

financial progress in terms of the contract is not entitle

for any claim pertaining to loss of profit on the balance

work sought for by him.

     32. With regard to claim No.6 of the plaintiff

pertaining to release of reserved amount in RA bills is

concerned, the defendants have contended that a sum of

Rs.79,147/­ was paid to the plaintiff after release of letter

of credit from the government and the bill was passed on

30/8/1997, as such, there is no dues by the defendants

to pay towards the plaintiff and hence plaintiff is not

entitle for the said claim.

     33. With regard claim No.7 of the plaintiff pertaining

to payment of interest @ 12% per annum on all the

claims is concerned, defendants have contended that

since there is no contractual obligations with regard to
                              36
                             CT 1390_Com.O.S.23­2019_Judgment .doc


the interest, plaintiff is not entitle for payment of interest

@ 12% per annum on all the claim sought for by him.

     34. Defendants in their written statement have

further contended that they are government authorities

and they are discharging their duties under the public

works department as per the statutory norms and

guidelines issued by the government, they are engaging

the civil work through out the state as and when

government called for.       Since the plaintiff has quoted

lowest rate in his tender pertaining to construction of

Mini Vidhana Soudha at Sidlaghatta, he was awarded the

above mentioned construction work in terms of contract

agreement No.10/93­94 dated 11/8/1993.               As per the

terms    of    the   above    mentioned       agreement,       the

construction     work   should     have     been    started     on

19/8/1993 and should have been completed on or before

15/11/1995 with a monthly stipulated progress of

Rs.2,14,576/­.       The contractor - plaintiff has not

completed the work as per the schedule and delayed very
                          37
                         CT 1390_Com.O.S.23­2019_Judgment .doc


badly. Consequently, the 2nd defendant - Chief Engineer

has canceled his contract as per the rules applicable by

his order dated 19/2/1999 and same was communicated

to the plaintiff by the 3rd defendant vide letter dated

22/11/2002. After termination of the contract, plaintiff

has written several letters to 3rd defendant, which were

replied suitably. The 3rd defendant gave a notice to the

plaintiff on 26/10/1994 to get the structural drawing.

On 23/6/1995 a letter was also issued to the plaintiff to

get the approved structural plan from the office of the

defendants on 4/1/1996. Another notice was issued to

the plaintiff to receive the drawing pertaining to the

construction. On 19/2/1999 approval was given by the

2nd defendant for cancellation of the tender.              On

22/11/2002, a notice was also issued to the plaintiff by

the 3rd defendant.    The notices dated 13/10/1993,

1/1/1994,     30/5/1994,       2/6/1994,        18/6/1994,

30/8/1994,     29/9/1994,      15/12/1994,        8/5/1995,

23/6/1995,    26/2/1996,      8/3/1996,     20/1/1996        &
                              38
                             CT 1390_Com.O.S.23­2019_Judgment .doc


11/3/1999 issued by the 3rd defendant to the plaintiff

clearly reflects that the plaintiff has not properly

complied the terms of the tender agreement and hence he

is liable to be penalized for the delayed work at site.

     35. Defendants further contended that there is no

cause of action for the plaintiff to file the present suit

against them.      Defendants further contended that the

court fee paid by the plaintiff is not sufficient and suit of

the plaintiff is barred by time.       On these grounds the

defendants have sought for dismissal of the suit.

     36. Based on the above pleadings of the parties and

documents produced on record, this court has framed

following :

                             ISSUES

  1) Whether the plaintiff proves that defendants have
     failed   to   perform     their    part    of   contractual
     obligations of the contract dated 11/8/1993 entered
     between him and the defendants?
                        39
                       CT 1390_Com.O.S.23­2019_Judgment .doc


2) Whether the plaintiff proves that the cancellation of
  the contract dated 11/8/1993 made by defendants
  on 11/3/1999, is illegal and wrongful?
3) Whether the plaintiff proves that defendants are not
  entitled to apply cost and risk action of completing
  the balance work of the contract against him?
4) Whether the plaintiff proves that defendants are
  liable to pay him a sum of Rs.5,13,295/­ towards
  return of EMD, FSD & NSC made by him?
5) Whether the plaintiff proves that defendants are
  liable to pay him a sum of Rs.43,81,236/­ towards
  payment of damages of idle charges of men and
  machinery suffered by him towards stoppage period
  of execution of the work in contract period?
6) Whether the plaintiff proves that defendants are
  liable to pay him a sum of Rs.46,61,091/­ towards
  payment of equitable revised rates for the work done
  beyond the stipulated period of contract?
7) Whether the plaintiff proves that defendants are
  liable to pay him a sum of Rs.22,68,201/­ towards
  reimbursement of expenses for longer stay at the
  work site for the purpose of executing the work?
8) Whether the plaintiff proves that defendants are
  liable to pay him a sum of Rs.11,81,374/­ for loss of
  profit on the balance work of contract?
                              40
                              CT 1390_Com.O.S.23­2019_Judgment .doc


  9) Whether the plaintiff proves that defendants are
     liable to pay him a sum of Rs.2,48,521/­ towards
     release of reserved amount in the RA Bills?
  10)       Whether defendants prove that suit of the
     plaintiff is not properly valued for the purpose of
     payment of court fees?
  11)       Whether defendants prove that suit of the
     plaintiff is barred by limitation?
  12)       Whether the plaintiff is entitle for the suit
     claim sought for?
  13)       Whether the plaintiff is entitle for the future
     interest @ 18% per annum as sought for?
  14)       What order or decree?



     37. Parties have entered into trial. In proof of the

case of the plaintiff, the plaintiff got himself examined as

PW.1 and tendered Ex.P.1 to P.19 documents in

evidence.   On behalf of the defendants, initially the 3 rd

defendant    -   Executive     Engineer     of   PWD     Division,

Chikkaballapur     District       was   examined      as    DW.1.

Thereafter, the learned ADGP has filed a memo to discard

the evidence of DW.1 on the ground that he was
                                     41
                                    CT 1390_Com.O.S.23­2019_Judgment .doc


transferred to some other department.                   Thereafter, on

behalf of the defendants, the present Executive Engineer,

PWD Division, Chikkaballapur was examined as DW.2

and Ex.D.1 to D.17 documents were marked in his

evidence. On the application filed by the counsel for the

plaintiff, the defendants have produced the schedule of

contract form pertaining to Ex.P.1 contract, which

contains the terms and conditions of Ex.P.1 contract and

for the purpose of convenience of the reference of the

court, the said document is marked as Ex.P.1(a).

     38. Written arguments filed on behalf of the plaintiff

and also on behalf of the defendants.

     39. Perused the materials placed on record.

     40. My findings on the above framed issues are as

follows:

     Issue   No.1   :   In   the   negative.
     Issue   No.2   :   In   the   negative.
     Issue   No.3   :   In   the   negative.
     Issue   No.4   :   In   the   negative.
     Issue   No.5   :   In   the   negative.
     Issue   No.6   :   In   the   negative.
     Issue   No.7   :   In   the   negative.
                             42
                            CT 1390_Com.O.S.23­2019_Judgment .doc


     Issue   No.8 : In the negative.
     Issue   No.9 : In the negative.
     Issue   No.10: In the negative.
     Issue   No.11: In the negative.
     Issue   No.12: In the negative.
     Issue   No.13: In the negative.
     Issue   No.14: As per final order for the following:




     41.   ISSUES No.1 & 2 : Since these two issues are

interconnected with each other, to avoid repetition of

facts and findings, both issues are taken up together for

consideration.

     42. There are certain undisputed facts pertaining to

the parties to the present suit. The fact that the plaintiff

who was a Class I Contractor has submitted tender in

response to the tender notification issued by government

of Karnataka for the work of construction of Mini

Vidhana Soudha at Sidlaghatta, Kolar District. Since the

plaintiff was the lowest tenderer, he was entrusted the

above construction work vide contract No.10/93­94

dated 11/8/1993 is not in dispute. Ex.P.1 if the contract
                                 43
                                CT 1390_Com.O.S.23­2019_Judgment .doc


dated 11/8/1993 executed between the plaintiff and

defendants. Ex.P.1(a) is the schedule of contract forms

which contains the terms of Ex.P.1 contract. Further fact

that the cost of the construction work under the contract

was Rs.42,91,526/­ is also not in dispute. Further fact

that the date of commencement of the construction work

stipulated in the contract was 19/8/1993 and the

stipulated date of completion of the work was on

15/11/1995 including the monsoon period is also not in

dispute.     Further fact that in the contract the monthly

stipulated     progress    of    construction       was    fixed    at

Rs.2,14,576/­ is also not in dispute. Further fact that on

24/8/1993, the 3rd defendant ­ Executive Engineer has

issued work order to the plaintiff is also not in dispute.

Further fact that on the allegation that the plaintiff has

failed to achieve the stipulated progress in terms of the

contract,    the   2nd    defendant     ­   Chief   Engineer       has

rescinded the contract on 19/2/1999 is also not in

dispute.     Further fact that till the rescission of the
                            44
                           CT 1390_Com.O.S.23­2019_Judgment .doc


contract, the plaintiff had achieved the approved work

progress of only Rs.17,58,071/­ is also not in dispute.

Further fact that subsequent to the communication of

rescission of the contract, plaintiff has filed CMP

No.47/2003 before the Hon'ble High Court of Karnataka,

Bangalore for appointment of an Arbitrator in terms of

the conditions of the contract and said CMP No.47/2003

was dismissed by the Hon'ble High Court of Karnataka,

Bangalore by its order dated 11/7/2003 on the ground

that Clause 29 of the contract do not contain an

arbitration clause. Thereafter, the plaintiff has filed WP

No.49896/2003     before   the   Hon'ble     High    Court    of

Karnataka,   Bangalore,    seeking     appointment       of   an

arbitrator and the said writ petition also came to be

dismissed by the Hon'ble High Court of Karnataka,

Bangalore by its order dated 6/11/2003. Thereafter, the

plaintiff has filed SLP in Civil Appeal No.1558/2004

before the Hon'ble Supreme Court of India, seeking

appointment of an Arbitrator and said SLP also came to
                          45
                         CT 1390_Com.O.S.23­2019_Judgment .doc


be dismissed on 25/10/2013.           Further, the review

petition filed by the plaintiff against the common

judgment passed in connected SLP leave petitions were

also dismissed by the Hon'ble Supreme Court of India by

its order dated 16/9/2014 is also not in dispute. Ex.P.8

is the certified copy of the judgment passed by the

Hon'ble   Supreme   Court     of   India   in   Civil   Appeal

No.1586/2004. Ex.P.9 is the certified copy of the order

dated 16/9/2014 passed by the Hon'ble Supreme Court

of India in Review Petition No.1984/2014 in Civil Appeal

No.1587/2004.

     43. The plaintiff has filed this suit for recovery of

money against the defendants, on the allegations that

they have failed to perform their part of the contractual

obligations of the contract dated 11/8/1993 entered

between him and the defendants and rescission of the

contract dated 11/8/1993 made by the defendants on

11/3/1999 is illegal and and wrongful.          Based on the

above mentioned allegations, plaintiff has sought seven
                            46
                           CT 1390_Com.O.S.23­2019_Judgment .doc


claims in the present suit.            On the other hand,

defendants have contested the suit by denying the plaint

allegations with regard to non performance of their part

of contractual obligations of contract dated 11/8/1993

and also denied the plaint allegations that the rescission

of   contract    dated   11/8/1993     made     by   them     on

19/2/1999 is illegal and wrongful. In view of the rival

contentions taken by the parties to the suit, the burden

of proof is that plaintiff to prove that defendants have

failed to perform their part of the contractual obligations

of the contract dated 11/8/1993 and also to prove that

rescission of contract dated 11/8/1993 made by the

defendants on 19/2/1999 is illegal and wrongful.

      44. A perusal of the pleadings and evidence of the

plaintiff discloses that it is the case of the plaintiff that

immediately after receiving the work order, he has started

the construction work in portion of the site made

available   to   him,    which   was    clear   without     any

obstructions. He has mobilized the resources including
                           47
                          CT 1390_Com.O.S.23­2019_Judgment .doc


men and machinery, establishment and other matching

equipments and camped at site to execute the work.

Since the site was not clear as the electric and telephone

lines were obstructing the work, he could execute a

minor portion of the work for a period of some time.

Thereafter, there was stoppage of construction for a

major period during the stipulated period of performance,

since the site was not clear from major obstructions.

      45. The plaintiff has pleaded and lead evidence

stating that due to failure on the part of the defendants

to perform their part of the contractual obligations, he

could not complete the work within the stipulated period

of time stated in the contract. A perusal of the pleadings

and evidence of the plaintiff discloses that the plaintiff

has   mainly   highlighted     the   following   alleged   four

contractual obligations, which the defendants alleged to

have failed to perform which are the alleged reasons for

the plaintiff for non completion of the construction work

within stipulated period of contract.
                               48
                              CT 1390_Com.O.S.23­2019_Judgment .doc


      (1) delay in supply of approved working drawings.

(2)   delay   in   shifting   of   high­tension    electric   line,

telephone line and Municipal water supply lines from the

site. (3) non availability of essential building materials at

a distance shown by the defendants at the time of

tendering. (4) irregular payments for the work done by

him under the contract.

      46. With regard to the first reason pertaining to the

alleged delay in supply of approved working drawings by

the defendants is concerned, it is the case of the plaintiff

that defendants have failed to supply the working

drawings, designs and details in time.           The defendants

were not in a position to supply the working drawings at

a time along with the work order. The designs, drawings

for RCC foundation were supplied only in the month of

November 1993 with a delay of 3 months. The drawings

for basement were issued only on 30/10/1994 with a

delay of 14 months. The drawings for ground floor, roof,

beam and slabs were issued to him only on 25/11/1995
                           49
                          CT 1390_Com.O.S.23­2019_Judgment .doc


with a delay of about 28 months after commencement of

the work. Until the expiry of original contract period, the

defendants were not in a position to issue full working

drawings for all the items, even for ground floor, whereas,

the contract consist of ground floor and first floor.

Inspite of abnormal delay in supply of working drawings,

the defendants have not fixed any further period for

performance of the contract.      He has brought all the

details to the knowledge of the defendants through

several letters issued by him to the defendants.

     47. To prove the alleged delay in supply of approved

working drawings by the defendants, the plaintiff has

mainly relied on Ex.P.5 which contains 18 letters dated

25/11/1993,     11/5/1994,     10/6/1994,       24/10/1994,

28/11/1994,     30/12/1994,     24/12/1994,        4/1/1995,

16/2/1995,     27/7/1995,      19/10/1995,       15/2/1996,

5/11/1996,      16/4/1997,      4/9/1998,        5/10/1998,

14/10/1998 and 25/11/1998, which were addressed by

him to the 3rd defendant - Executive Engineer. Plaintiff
                            50
                            CT 1390_Com.O.S.23­2019_Judgment .doc


has also relied on Ex.P.18 and P.19 drawings issued by

the defendant to the plaintiff.      A perusal of the above

mentioned    letters    discloses    that   in    letter   dated

25/11/1993 which was the earliest letter addressed by

the plaintiff to the 3rd defendant he has not stated

anything about the alleged delay in supply of approved

working drawings. However, in subsequent letters dated

11/5/1994, 10/6/1994, 24/10/1994, he has requested

the defendants to send the approved working drawings

and further stated that the construction work is held up

for want of drawings.     In the letter dated 28/11/1994

addressed by the plaintiff to the defendants, he has

stated   that    he     had     received     drawings       from

Chikkaballapur    Sub     Division    on    26/11/1994       and

assured that the construction work will be taken up

early. In letter dated 6/2/1995 addressed by the plaintiff

to the 3rd defendant, he had sought for supply of design

particulars and drawings from the department.              In the

letter dated 30/10/1995 addressed by the plaintiff to the
                           51
                          CT 1390_Com.O.S.23­2019_Judgment .doc


defendants, he has alleged that he had not received

approved drawings for the major items of roof, beam, roof

slab for the ground floor and first floor and also not

received roof drawings.   In the letter dated 5/11/1996

addressed by the plaintiff to the 3rd defendant, he has

alleged that the first floor drawings were not received by

him till the date of addressing the letter and sought for

supply of detailed approved drawings for all the items of

the floor. In the letter dated 16/4/1997 addressed by the

plaintiff to the 3rd defendant, he has alleged that

approved canopy drawings and first floor drawings were

not supplied to him by the department. In letters dated

4/9/1998 and 5/10/1998 addressed by the plaintiff to

the 3rd defendant, again he has alleged that the drawings

of some of the items in ground floor itself were not

received by him from the department. In the letter dated

14/10/1998 addressed by the plaintiff to the 3 rd

defendant, he has further alleged that the department

has not supplied the designs and drawings of canopy in
                           52
                          CT 1390_Com.O.S.23­2019_Judgment .doc


the ground floor and for roof, beam and roof slab in the

first floor. In the letter dated 25/11/1998 addressed by

the plaintiff to the 2nd defendant - Chief Engineer, he has

alleged that the defendants have not supplied him

designs and drawings for the first floor, inspite of his

repeated requests.

     48. On the other hand, the defendants have pleaded

and lead evidence by denying the allegations of non

supply of working drawings and designs to the plaintiff in

time and the alleged inordinate delay caused in supply of

the working drawings and designs to the plaintiff. The

defendants have pleaded and lead evidence stating that

the required drawings were already given to the plaintiff

along with the work order and the approved drawings

were given after getting the signature of the competent

authority and plaintiff had made false allegations of non

supply of working drawings and designs in time only to

overcome the inordinate delay in completion of the

construction work by him.      As per the request of the
                            53
                               CT 1390_Com.O.S.23­2019_Judgment .doc


plaintiff's letter dated         11/5/1992, issued to the

Assistant   Executive    Engineer,        PWD      Sub    Division,

Chikkaballapur, plaintiff was intimated by letter dated

26/10/1994     to    collect     the    required     drawings     in

connection with the construction work. The plaintiff had

received the drawings of foundation on 7/4/1993 and

entire drawings upto the floor cill beam, canopy column

and beams on 26/10/1994.

      49. In support of their defence, the defendants have

mainly relied on Ex.D.9 letter dated 26/10/1994.                   A

perusal of contents of Ex.D.8 letter dated 7/4/1993

issued by the 2nd defendant - Chief Engineer to the

Superintendent Engineer, PWD, Bangalore discloses that

the   structural    drawings      No.CBS/SD/MVS/S.Ghatta/

1,2,3/ 1992­93 showing the details of excavation colomn

footing were supplied to the 3rd defendant - Executive

Engineer pertaining to the construction in dispute.

Ex.D.9 letter dated 26/10/1994 issued by the 3 rd

defendant - Executive Engineer, Chikkaballapur to the
                           54
                          CT 1390_Com.O.S.23­2019_Judgment .doc


plaintiff discloses that by that letter, the plaintiff was

directed to go to the office of Assistant Executive

Engineer,   Chikkaballapur     and   to   collect   necessary

drawings in connection of the construction work.

     50. A perusal of the contents of Ex.P.1(a) schedule

of contract form discloses that clause 2(b) of the contract

provides for preparation of program of work. Clause 2(b)

of the contract provides that the time allowed for carrying

out of the work as entered in the tender shall be strictly

observed by the contractor. It shall be reckoned from the

date of handing over to the contractor not less than 75%

of the work site area comprising a contiguous block. It

provides that the work through out the stipulated period

of the contract be proceeded with all due diligence.          It

provides that to ensure good progress during the

execution of the work, the contractor shall be bound to

comply with the time schedule according to the program

of execution of the work as agreed upon and enclosed to

the contract.
                             55
                            CT 1390_Com.O.S.23­2019_Judgment .doc


     51. A perusal of the materials on record discloses

that as per clause 2(b) of the schedule of contract form,

which provides for preparation of program of work, the

contractor was required to carry out the work of tender

within the stipulated period of time and to ensure good

work progress during the execution of the work and to

comply with the time schedule contractor was required to

prepare program of execution of the work.           However, a

perusal of materials on record discloses that the plaintiff

has neither pleaded nor lead any evidence with regard to

the preparation of program of work pertaining to the time

schedule   of   supplying     working     drawings      by    the

defendants required for construction work.               In the

absence of producing any program of work agreed upon

by the plaintiff and defendants pertaining to supply of the

working drawings, the contention of the plaintiff that

defendants have failed to provide him necessary working

drawings within the stipulated period of time and there is
                          56
                         CT 1390_Com.O.S.23­2019_Judgment .doc


inordinate delay on the part of the defendants to furnish

the working drawings cannot be accepted.

     52. A perusal of the evidence on record discloses

that in letter dated 25/11/1993, which was the first

letter addressed by the plaintiff to the 3 rd defendant

marked as one of the letter in Ex.P.5 bunch of letters,

plaintiff has not whispered the fact that the working

drawings were not furnished to him by the defendants.

Only in the letter dated 11/5/1994 addressed by the

plaintiff to the 2nd defendant, which was issued almost 9

months after the commencement of the work, the plaintiff

has alleged that the construction work is held up for

want of drawings of basement and above and sought for

furnish working drawings from the defendants.

     53. A perusal of the letters dated 28/11/1994,

addressed by the plaintiff to the 2nd defendant, he had

admitted that he had received the drawings from

Chikkaballapur Sub Division on 26/11/1994.             In the

letter dated 27/7/1995 addressed by the plaintiff to the
                           57
                          CT 1390_Com.O.S.23­2019_Judgment .doc


3rd defendant, he had admitted that he had received

detailed drawings pertaining to lintels on 24/6/1995.

Further a perusal of Ex.D.8 letter dated 7/4/1993

addressed by the 2nd defendant - Chief Engineer to the

Superintendent Engineer, PWD, Bangalore, discloses that

the approved structural drawings showing the details of

excavation RC columns and footing were ready with the

department.     Considering the documentary evidence

produced on record, this court is of the opinion that the

plaintiff has failed to prove that the defendants have

failed to furnish him the necessary working drawings

which resulted in delay in construction of the work.

     54. The second ground      urged by the plaintiff for

non completion of the construction work within the

stipulated period of time by him is the alleged failure on

the part of the defendants to get the high­tension electric

lines, telephone lines and Municipal water supply lines

shifted from the construction site in time. With regard to

this alleged failure of the defendants to perform their part
                            58
                           CT 1390_Com.O.S.23­2019_Judgment .doc


of contractual obligations is concerned, plaintiff has

pleaded and lead evidence stating that since high­tension

electric lines, telephone lines and water supply lines were

passing through below the ground level of the site, it was

difficult for him to execute the work in the absence of

clearance of this obstruction in the working site. That he

had brought the fact of delay caused in clearing the

obstruction to the knowledge of the defendants through

several letters. There was abnormal delay on the part of

the defendants by making the site clear by removing the

obstruction, which resulted in stoppage of work and

abnormal delay in executing the work.           To prove the

alleged delay caused by the defendants in clearing the

obstruction in the work site, plaintiff has mainly relied on

Ex.P.5 ­ 18 letters addressed by him to the 3 rd defendant.

A perusal of the contents of Ex.P.5 letters discloses that

in these letters, plaintiff has alleged that there is delay on

the part of the defendants to get the electric, telephone
                            59
                           CT 1390_Com.O.S.23­2019_Judgment .doc


and water supply lines to be shifted from the working

site, resulted into delay in construction work.

      55. On the other hand the defendants in their

pleadings and evidence have denied the allegations of

inordinate delay on their part in shifting the electric

lines, telephone line and water supply lines from the

work site. Further the defendants have pleaded and lead

evidence stating that when they have handed over the

construction site to the plaintiff, they have remitted a

sum    of   Rs.9,893/­   vide   cheque    No.965438       dated

14/6/1993 to shift the electric lines and poles and also

transferred a sum of Rs.8,192/­ to the BSNL Account

vide MD No.5572 to shift the telephone lines and poles.

After the receipt of the said sum by the above said two

departments, the said departments have shifted the poles

and lines from the site.    There was no obstruction for

commencement of work by the plaintiff.          In support of

their defence, the defendants have relied on Ex.D.6

endorsement pertaining to payment of sum of Rs.8,192/­
                           60
                          CT 1390_Com.O.S.23­2019_Judgment .doc


to the BSNL Department to shift the telephone lines and

poles from the construction site. Further, the defendants

have also relied on the proforma bill annexed to Ex.D.6

evidencing payment of a sum of Rs.9,893/­ by the 3 rd

defendant for shifting of electric lines and poles from the

construction site. Defendants have also produced Ex.D.7

letter addressed by the Assistant Executive Engineer,

PWD Sub Division, Chikkaballapur to the KEB pertaining

to payment of Rs.9,893/­ vide receipt No.28911 dated

23/6/1993 by the defendants for shifting of electric lines

from the schedule site.        Ex.D.6 and D.7 documents

produced by the defendants supports their contention

that there was no delay on their part to get the electric

lines and poles and telephone lines and poles to be

shifted from the construction site.

     56. A perusal of the materials on record discloses

that the plaintiff who has made allegations of inordinate

delay against the defendants for shifting electric lines,

telephone lines and water supply lines has not produced
                             61
                            CT 1390_Com.O.S.23­2019_Judgment .doc


the program of work as required under clause 2(b) of the

Ex.P.1(a) schedule of contract form, wherein, the agreed

time stipulated for the defendants to get the electric lines,

telephone lines and water supply lines shifted from the

construction site and to get the site clear. In the absence

of production of program of work before the court, the

contention of the plaintiff that there was inordinate delay

on the part of the defendants to get the electric lines,

telephone lines and water supply lines shifted cannot be

accepted. Apart from that a perusal of the materials on

record   discloses   that   in   letter   dated    24/10/1994

addressed by the plaintiff to the 3rd defendant, he had

admitted that electric lines were shifted in the month of

September 1994.        In the letter dated 27/7/1995

addressed by the plaintiff to the 3rd defendant, he has

admitted that telephone lines were also shifted.

     57. By perusing the materials produced on record,

this court is of the opinion that the plaintiff has failed to

prove that there is abnormal delay on the part of the
                           62
                          CT 1390_Com.O.S.23­2019_Judgment .doc


defendants in fixing the high tension electric lines,

telephone lines and Municipal water supply lines, which

has resulted in stoppage of work, thereby, there is breach

of contractual obligations on the part of the defendants in

performing their part of the contract.

     58. The third alleged reason stated by the plaintiff

for non completion of the work within the stipulated

period of time is non availability of building materials at

the distance shown by the defendants at the time of

tendering. With regard to this reason, the plaintiff has

pleaded and lead evidence stating that the essential

building materials were not available to him at a

reasonable distance and he had to go in search of the

building materials, since same were not available at the

place shown by the defendants at the time of tendering,

which has caused further delay in executing the work

which incurred extra cost and required much more

investments by him. On the other hand the defendants

in their written statement and evidence have denied this
                           63
                          CT 1390_Com.O.S.23­2019_Judgment .doc


allegation and further contended that plaintiff being a

class­I contractor has to look after all the things, he

cannot   depend upon the defendants for             collecting

material to complete the tender work.

     59. A perusal of the evidence on record discloses

that plaintiff has not produced any document to show

that the defendants have assured him about availability

of building materials at a reasonable distance when he

has entered into contract with the defendants. Even in

Ex.P.1 tender document there is no clause stating that

defendants have assured the plaintiff about availability of

building materials at a reasonable distance from the work

site. Apart from that the plaintiff has not produced the

program of work to show that the defendants have

assured him about availability of essential building

materials at a reasonable distance at the time of

tendering.    In the absence of production of any

documentary evidence to show that the defendants have

assured the plaintiff about availability of essential
                             64
                            CT 1390_Com.O.S.23­2019_Judgment .doc


building   materials   at   a    reasonable     distance,     the

contention of the plaintiff that the essential building

materials were not available at a reasonable distance

shown by the defendants which has caused further delay

in execution of the work by him incurring extra cost and

making more investment by him cannot be accepted.

     60. The fourth reason stated by the plaintiff for non

completion of the work within stipulated period of time is

the alleged irregular interim payments made by the

defendants with regard to the construction work done by

him. With regard to this reason, the plaintiff has pleaded

and lead evidence stating that the contract provided for

payment for the work done in each month. There were in

ordinate delays in preparing and payment of bills by the

defendants. In some occasion, the defendants took 6 to 8

months for making one running bill payment.                  The

irregular payments made by the defendants has created

unbalance working condition and delayed the completion

of the work. Even at the time of cancellation of the work
                          65
                         CT 1390_Com.O.S.23­2019_Judgment .doc


there were substantial pending payments. The delay in

making payments were brought to the knowledge of the

defendants through various letters addressed by him to

the defendants.

     61. On the other hand the defendants in their

written statement and also evidence have denied the

allegations of irregular payments made by them with

regard to the work done by the plaintiff.        Defendants

further contended that the amount for the work done by

the plaintiff has been disbursed as per the allocation of

funds made by the government and there was no

inordinate delay in preparing the bills on their side.

Defendants further contended that as on the date of

cancellation of the contract, the plaintiff had already

received a sum of Rs.17,40,149/­ on 19/2/1999, which

shows that there is no delay in payment to the plaintiff

with regard to the work done by him.

     62. A perusal of the pleadings and evidence of the

plaintiff discloses that except stating the fact that the
                                 66
                                CT 1390_Com.O.S.23­2019_Judgment .doc


defendants were irregular in interim payments for the

work done by him, plaintiff has not stated the details

about the preparation of the running bills and the date of

alleged delayed payments made by the defendants

pertaining to the running bills. Admittedly, the value of

work done till cancellation of the work as per the plaint

averments is Rs.17,83,296/­.               On the other hand,

defendants contends that as on the date of cancellation

of   the     work   plaintiff     had     received    a    sum     of

Rs.17,40,149/­, which is not seriously disputed by the

plaintiff.    In the absence of production of reliable

documentary evidence the contention of the plaintiff that

there is inordinate delay on the side of defendants in

preparing and payment of running bills and the interim

payment for the work done by him were very irregular by

the defendants cannot be accepted.

      63. A perusal of the materials on record discloses

that Ex.P.1 contract was entered between the plaintiff

and defendants on 11/8/1993. Date of commencement
                             67
                            CT 1390_Com.O.S.23­2019_Judgment .doc


of the work under Ex.P.1 contract was fixed on

19/8/1993.      Date   of   work     order   was    issued     on

24/8/1993. Date of completion of the work as per Ex.P.1

contract was 15/11/1995. A period of 27 months was

fixed for performance of contract under Ex.P.1 contract.

The defendants have rescinded the contract only on

19/2/1999 i.e. after 66 months of entering into the

contract.

     64. In the present case, the plaintiff has pleaded the

alleged delay in supply of working drawings, alleged delay

on the part of the defendants to get the high­tension

electric lines, telephone lines and Municipal water supply

lines as the main reasons for non completion of the work.

However, in Ex.P.5 letters addressed by the plaintiff to

the defendants, he has admitted about the shifting of

electricity lines in the month of September 1994, shifting

of telephone lines in the year 1995 and also receipt of

working drawings in the month of November 1994. Since

the plaintiff has admitted about the shifting of electricity
                           68
                              CT 1390_Com.O.S.23­2019_Judgment .doc


lines in the month of September 1994, receiving of

working drawings in the month of November 1994 and

shifting of telephone lines in the year 1995, the alleged

reasons shown by the plaintiff for non completion of the

work within the stipulated period of time cannot be

accepted.

      65. A perusal of the pleadings and evidence of the

plaintiff discloses that plaintiff has alleged that delay on

the part of the defendants in supply of approved working

drawings, delay in shifting of high­tension electric lines,

telephone lines and Municipal water supply lines from

the   working   site,   non     availability    of   construction

materials at the distance shown by the defendants at the

time of tendering, irregular interim payments made by

the defendants for the work done by him as the reasons

for non completion of the contract work within the

stipulated period of time. However, a perusal of Ex.P.1

schedule of the contract form discloses that clause 29 of

the contract provides for settlement of dispute or
                             69
                            CT 1390_Com.O.S.23­2019_Judgment .doc


difference that arose between the 3 rd defendant -

Executive Engineer and the Contractor regarding any

dispute arose with regard to the execution of the work

during the progress of the work to be referred to the 2 nd

defendant - Chief Engineer, who has jurisdiction over the

work.    In the present case, a perusal of materials on

record   discloses   that   the   plaintiff   who   has    made

allegations of non performance of contractual obligations

by the 3rd defendant during the period of execution of the

contract has admittedly not referred the said dispute to

the 2nd defendant - Chief Engineer. The very fact that the

plaintiff has not referred the settlement of the dispute in

terms of the clause 29 of the contract is another

circumstance which goes against the case of the plaintiff

with regard to alleged failure of the defendants to perform

their part of the contractual obligations as the reason for

the plaintiff for non completion of the contractual work

within the stipulated period of time.
                           70
                          CT 1390_Com.O.S.23­2019_Judgment .doc


     66. With regard to recession of Ex.P.1 contract by

the defendants on 19/2/1999 is concerned, the plaintiff

had pleaded and lead evidence stating that inspite of non

performance of contractual obligations by the defendants

which has caused delay in execution of the work, he has

executed the work to the possible extent and trying to

complete the work.      Meantime, the defendants have

chosen to take illegal, wrongful and unwarranted action

of canceling the contract with a threat to execute the

balance work at his risk and cost, though the delay in

execution   of   the   work    were   attributable     to   the

defendants. The defendants were not even bother to fix

further period for performance to make time essence of

the contract, after original contract period expired on

15/11/1995. Inspite of repeated requests made by him

for extension of time before the expiry of the contractual

period, the defendants have not extended the period for

performance of the contract and illegally and wrongfully

canceled the contract on 11/3/1999.
                            71
                           CT 1390_Com.O.S.23­2019_Judgment .doc


      67. On the other hand, the defendants in their

written statement and their evidence have denied             the

plaintiff's allegation that the cancellation of the contract

on 19/2/1999 by them was illegal and wrongful. On the

other hand, the defendants have pleaded and lead

evidence stating that as per the terms of the Ex.P.1

contract dated 11/8/1993 the construction work should

have been started on 19/8/1993 and should have been

completed in all respects on or before 15/11/1995 with a

monthly stipulated progress of Rs.2,14,576/­.               The

contractor - plaintiff has not completed the work as per

schedule and delayed the work very badly.              Plaintiff

himself has caused delay of about 4 years in executing

the work and they have impliedly allowed the plaintiff to

work till 11/3/1999.      Plaintiff has miserably failed to

comply the terms and conditions of the tender agreement

with regard to achievement of financial progress.           The

plaintiff   has   only   achieved   financial    progress     of

Rs.17,04,149/­ instead of contractual financial progress
                           72
                           CT 1390_Com.O.S.23­2019_Judgment .doc


of RS.42,91,520/­ fixed in the Ex.P.1 contract. Due to

failure on the part of the plaintiff to achieve the financial

progress in the terms of the agreement, the Chief

Engineer C&B (S), Bangalore has canceled the contract of

the plaintiff as per rules and same was communicated to

the plaintiff by the 3rd defendant - Executive Engineer

through his letter dated 22/11/2002.

     68. A perusal of the pleadings and evidence of the

plaintiff discloses that the main grievance of the plaintiff

with regard to recession of the contract dated 11/8/1993

by the defendants on 19/2/1999 is that due to failure on

the part of the defendants to perform their part of the

contract, he could not able to perform his part of the

contract and complete the construction work within

stipulated period of time, as a result of which, he has

addressed several letters to the defendants before expiry

of the period of contract seeking extension of time to

perform his part of the contract and defendants have not

bothered to extend the time for performance of the
                             73
                            CT 1390_Com.O.S.23­2019_Judgment .doc


contract to make time essence of the contract, after

expiry of original period of contract have illegally

rescinded the contract.

      69. A perusal of the pleadings and evidence of the

plaintiff discloses that he claims that time was not the

essence of Ex.P.1 contract and the action of the

defendants   to   rescind   the    contract    without     giving

extension of time to perform his part of the contract is

illegal.

      70. At this juncture, it is relevant to consider a

decision of the Apex Court of the Land reported between

State of Maharastra & another V/s. Digambar Balwant

Kularni reported in AIR 1979 Supreme Court 1339,

wherein, the Apex Court of the Land has held that :

      "Contract Act (9 of 1872), Ss.39 and 55 - Works
contract - Time mentioned as of essence of contract - But
contract enforceable till completion of work or its
abandonment - Rescission of contract and consequent
forfeiture of security deposit held proper within terms of
                           74
                          CT 1390_Com.O.S.23­2019_Judgment .doc


contract. Appeal No.534 of 1969, dt. 11/7/1968 (Bom),
Reversed."



     71. In the above cited decision the Apex Court of the

Land has interpreted the clauses of a work contract

similar to that of Ex.P.1 contract and held that time was

essence of the contract in the limited sense that the

contract will be continued to be in force till the

completion of the work or its abandonment. In the said

decision by interpreting the clauses of the work contract

similar to that of Ex.P.1 contract, the court held that the

rescission of the contract and forfeiture of the security

deposit by the Executive Engineer on the failure of the

part of the Contractor to achieve the work progress was

valid.

     72. The aspect as to whether the time was the

essence of Ex.P.1 contract or not has to be considered by

going through clauses of Ex.P.1(a) schedule of the

contract form.
                          75
                          CT 1390_Com.O.S.23­2019_Judgment .doc


     73. A perusal of clause 2(b) of Ex.P.1(a) schedule of

contract form discloses that the same provides that the

time allowed for carrying out the work as entered in the

tendering shall be strictly observed by the Contractor. It

further provides that the work shall through out the

stipulated period of the contract be proceeded with all

dues diligence (time being deemed to be the essence of

the contract on the part of the contractor).           It also

provides that to ensure good progress during the

execution of the work, the contractor shall be bound to

comply with the time schedule according to the program

of execution of work as agreed upon enclosed to the

contract.

     74. A perusal of clause 2(d) of the contract which

provides for penalty for delay discloses that it provides

that in respect of shortfall in progress assessed due to

the delay on the part of the contractor as per clause 2(b)

& (c), the contractor shall be liable to pay as penalty an

amount equal to 1% of the estimated cost of the balance
                             76
                            CT 1390_Com.O.S.23­2019_Judgment .doc


work assessed according to the program for every day

that the due quantity of work remains incomplete.

Further clause 3 of the contract provides that in any case

in which under any clause or clauses of the contract, the

Contractor shall have rendered himself liable to pay

compensation or penalty amounting to the whole of his

security deposit including the amount deducted in

installments from his bills as further security deposit, the

Executive   Engineer   on    behalf    of   the   Governor     of

Karnataka shall have power to adopt the recourses, such

as, forfeiture of security deposit, recession of the

contract. Clause 3(e) of the contract provides that in the

event of the Executive Engineer taking recourses with

regard to forfeiture of security deposit of the contract and

for recession of the contract, the Contractor shall have no

claim to compensation for any loss sustained by him.

     75. A perusal of the above mentioned provisions of

Ex.P.1 contract stated in Ex.P.1(a) schedule of the

contract form, if read together and interpreted with
                             77
                            CT 1390_Com.O.S.23­2019_Judgment .doc


reference to each other provision and read as single

whole closely goes to show that the contract was to

continue to be in force till the completion of the work or

its rescission. The time was the essence of the contract

only for the limited sense that if the plaintiff completed it

within the original contractual period, he would not be

liable to pay any compensation, but in case of non­

completion of the contract within the contractual period,

plaintiff has to compensate the defendants for non

completion of the work and right of recession of the

contract   would   accrue    to   the   defendants      on   non

completion of the work by the plaintiff.            Hence, the

contention of the plaintiff that under Ex.P.1 contract

dated 11/8/1993 the time was not the essence of the

contract and the act of the defendants to rescind contract

without extending period of time for performance of the

contract is illegal cannot be accepted.

     76. With regard to the grievance of the plaintiff

pertaining to non extension of time to perform contract
                            78
                           CT 1390_Com.O.S.23­2019_Judgment .doc


by the defendants is concerned, a perusal of clause 5 of

the schedule of contract discloses that the same deals

with grant of extension of time.         Clause 5(a) of the

contract provides that :

     " If the contractor shall desire an extension of the
time for completion of the work on the ground of his
having been unavoidably hindered in its execution or on
any other ground, he shall apply in writing to the
Executive Engineer before the expiration of the period
stipulated in the tender or before the expiration of 30
days from the date on which he was hindered as
aforesaid or on which the cause for asking for extension
occurred, whichever is earlier and the Executive Engineer
or other competent authority may, if in his opinion, there
are reasonable grounds for granting an extension, grant
such extension as he thinks necessary or proper.            The
decision of such competent authority in this matter shall
be final."


     77. A perusal of the clause 5(a) of the schedule of

contract form discloses that the aspect of extension of

time with regard to performance of the contract was in
                           79
                           CT 1390_Com.O.S.23­2019_Judgment .doc


the discretionary of the 3rd defendant - Executive

Engineer. The decision of the 3rd defendant - Executive

Engineer in the extension of time is final. In the light of

the clause 5(a) of the contract, a perusal of the materials

on record discloses that on the letters addressed by the

plaintiff to the defendants seeking extension of time to

perform his part of the contract, the defendants though

have not extended the time for performance of contract in

writing, but have impliedly granted extension of time till

recession of the contract.     However, the 2 nd defendant

considering the fact that the plaintiff has failed to achieve

the required work progress has issued Ex.D.10 to D.16

notices to the plaintiff on various dates calling upon him

to make up the shortfall of the work progress and on

failure of the part of the plaintiff to make up the shortfall

of the stipulated work progress has issued Ex.D.7 final

notice dated 27/2/1996, calling upon the plaintiff to

make up the shortfall in the work progress and on the

failure of the plaintiff to reach the stipulated work
                           80
                          CT 1390_Com.O.S.23­2019_Judgment .doc


progress has rescinded the contract through Ex.D.5 letter

dated 19/2/1999 addressed by the 2nd defendant to the

3rd defendant permitting to rescind Ex.P.1 contract of the

plaintiff on cost and risk basis in terms of clause 3 of the

contract.

     78. On the aspect of recession of Ex.P.1 contract is

concerned, a perusal of the contents of Ex.P.1(a)

schedule of the contract form discloses that clause 2(d) of

the contract deals with penalty for delay in respect of

shortfall in progress assessed due to the delay on the

part of the Contractor in completing the work.         Clause

2(d) of the contract provides for payment of penalty by

the Contractor in case of shortfall in progress an amount

equal to 1% of the estimated cost of the balance work

assessed according to the program for every day that the

due quantity of work remains incomplete.

     79. A perusal of clause 3 of the contract discloses

that it provides that in any case in which under any

clause of the contract, the Contractor shall have rendered
                                 81
                                 CT 1390_Com.O.S.23­2019_Judgment .doc


himself liable to pay compensation / penalty, the

Executive Engineer under clause 3(a) of the contract have

right to rescind the contract by issuing a written notice to

the Contractor.

       80. In light     of the above mentioned provision of

clause 2 and 3 of the Ex.P.1 schedule of contract form a

perusal of the materials on record discloses that the

Assistant    Executive          Engineer,     PWD       Department,

Chikkaballapura has issued Ex.D.10, D.12, D.13, D.14,

D.15    &   D.16      notices    dated     2/6/1994,      1/1/1994,

18/6/1994, 30/8/1994, 30/9/1994 & 15/12/1994,

calling upon the plaintiff to make good the shortfall in the

progress of the work and to achieve the work progress in

terms of the contract. A perusal of contents of Ex.D.17

final notice dated 27/2/1996 issued by the 3 rd defendant

- Executive Engineer to the plaintiff discloses that in the

said notice it is alleged that inspite of repeated notices

issued to the plaintiff, he had failed to achieve the

necessary work progress in terms of the contract and as
                           82
                          CT 1390_Com.O.S.23­2019_Judgment .doc


on 15/11/1995 there was shortfall of work progress

amounting to Rs.34,25,092/­ and plaintiff had stopped

the construction work in the month of December 1995

and had not commenced the work since then.                  It is

further alleged that since the plaintiff has failed to

achieve the required work progress, the defendants have

decided to impose penalty on the plaintiff for the shortfall

of the work and called upon the plaintiff to start the

remaining construction work within 15 days, failing

which his contract will be rescinded on cost and risk

action.   Thereafter, ExP.1 contract was rescinded on

19/2/1999      under   Ex.D.5   letter    dated     19/2/1999

addressed by the 2nd defendant to the 3rd defendant.

      81. A perusal of the materials on record discloses

that the fact that under Ex.P.1 contract dated 11/8/1993

the   agreed   monthly   stipulated      progress   fixed   was

Rs.2,14,576/­ is not in dispute. Further fact that even

after completion of the stipulated period of contract on

15/11/1995 and upto recession of the contract on
                           83
                          CT 1390_Com.O.S.23­2019_Judgment .doc


19/2/1999, plaintiff could only achieve approved work

progress of Rs.17,58,071/­ instead of the required work

progress of Rs.42,91,526/­ is also not in dispute. Plaintiff

who has alleged that the alleged defaults on the part of

the defendants in performing their part of the contractual

obligation as reasons for non completion of the work

within the stipulated period of time has failed to prove

the same.    On the other hand, the defendants on the

ground that the plaintiff has failed to achieve the

required stipulated progress of work have issued Ex.D.17

final notice dated 27/2/1996 stating that they have

decided to impose penalty in terms of the Ex.P.1 contract

for the shortfall in the work progress have decided to

rescinded the contract in terms of Ex.P.1 contract on

failure of the plaintiff to reach the stipulated work

progress and to commence the work which had stopped

by him.     Thereafter, the defendants have rescinded

Ex.P.1 contract through Ex.D.5 letter dated 19/2/1999

on the ground that plaintiff has failed to make up the
                           84
                           CT 1390_Com.O.S.23­2019_Judgment .doc


shortfall of the stipulated work progress in terms of

Ex.P.1 contract. Since the defendants have rescinded the

contract in terms of Ex.P.1 contract for failure on the

part of the plaintiff to achieve the required progress of the

work, the contention of the plaintiff that the recession of

the contract dated 11/8/1993 by the defendants on

19/2/1999 is illegal and arbitrary, cannot be accepted.

     82. The learned counsel for the plaintiff in his

written arguments and further written arguments filed

before the court has mainly relied on Section 52 to 55 of

the Indian Contract Act and argued that since the

defendants have failed to fulfill their promise in terms of

the Ex.P.1 contract, the plaintiff could not able to

complete the construction work within stipulated period

of time. It is further argued that inspite of failure on the

part of the defendants to perform their part of the

contract, the plaintiff was executing the work under most

trying circumstances.     Inspite of it, defendants have

chosen to take illegal, wrongful and unwarranted action
                           85
                          CT 1390_Com.O.S.23­2019_Judgment .doc


of cancellation of the contract with a threat to execute

balance work at his risk and cost, though the delays and

defaults were attributable to the defendants. It is further

argued that the defendants were not even bothered to fix

further period of performance to make time essence of

the contract after expiry of original contract period. It is

further argued that in view of the breach of contractual

obligations by the defendants, plaintiff is entitle for the

damages which the plaintiff has sought for as suit claims

in the present suit.

     83. On issues No.1 and 2 are concerned, the

learned counsel for the plaintiff in his written arguments

and additional written arguments has relied on following

citations, which will be considered one by one.

     (1) In Hind Construction Contractors V/s. State of

Maharastra reported in AIR 1979 page 720, wherein, the

Apex Court of the Land has stated about the tests for

deciding if the time was essence of the contract when

Contractor   has   not   completed   the contract       within
                            86
                           CT 1390_Com.O.S.23­2019_Judgment .doc


stipulated period of time and when no term in contract

making the time essence of contract.

     84. I have perused the ratio of the above cited

decision. However, unlike cited decisions in the present

case in hand in clause 2(b) of Ex.P.1 schedule of contract

form, it was specifically stated that time being deemed to

be the essence of the contract on the part of the

Contractor. Hence, the ratio of the above cited decision

is not helpful for the plaintiff to prove that time is not the

essence of the contract under Ex.P.1 agreement.

     85. The learned counsel for the plaintiff has also

relied on a decision reported between State of Karnataka

V/s. Sree Rameshwara Rice Mill, Theerthahalli, reported

in 1987 AIR 1359, wherein, the Apex Court of the Land

has held that in case of breach of agreement amount of

assessment of damages is to be made by the independent

body and not by parties to the contract.

     86. I have perused the ratio of the above cited

decision also.    However, unlike cited decision, plaintiff
                             87
                            CT 1390_Com.O.S.23­2019_Judgment .doc


has failed to prove that defendants have committed

breach of condition of agreement and he is entitle for

damages. Hence the ratio of the above cited decision is

also not helpful for the plaintiff.

     87. The plaintiff's counsel has also relied another

decision reported between J.J.Engineers Private Limited

V/s. Union of India and another reported in 2011(2)

ARB.LR.84(SC), wherein the Apex Court of the Land held

that the question whether the other party committed

breach cannot be decided by the party alleging breach. A

Contractor cannot provide that one party will be the

Arbitrator to decide whether he committed breach or the

other party committed breach, the question can only be

decided by an adjudicatory firm i.e. a Court or an Arbitral

Tribunal.

     88. I have perused the ratio of the above cited

decision.   However, considering the fact that the Ex.P.1

contract do not provide for arbitration clause for decide

breach of contract by the defendants themselves who are
                             88
                            CT 1390_Com.O.S.23­2019_Judgment .doc


the parties for the contract, the ratio of the above cited

decision is also not helpful for the plaintiff.

     89. The learned counsel for the plaintiff has also

relied   on   another   decision    reported      in   Municipal

Corporation of Delhi V/s. Jagannath Ashok Kumar

reported in Arbitrators Law Reporter 1987(2) page 344,

wherein, the Apex Court of the Land has held that if the

contract has a provision for extension of time or

compensation then it cannot be said that time was

essence of the contract.

     90. I have perused the ratio of the above cited

decision. Unlike cited decision in Ex.P.1(a) schedule of

contract form it was specifically stated that time was the

essence of the contract.     The provision for extension of

time for performance of contract was given at the

discretion of the defendants. Considering the fact that in

Ex.P.1 contract it was specifically stated that time was

the essence of the contract and work of plaintiff was

required to perform his part of the contract strictly within
                             89
                            CT 1390_Com.O.S.23­2019_Judgment .doc


the specific period of time, the ratio of the above cited

decision is also not helpful for the plaintiff.

       91. By perusing the oral and documentary evidence

produced on record and over all assessment of the same,

I hold that plaintiff has failed to prove that defendants

have    failed   to   perform    their   part   of   contractual

obligations of the contract dated 11/8/1993 entered

between him and the defendants. Plaintiff has also failed

to prove that cancellation of contract dated 11/8/1993

made by defendants on 19/2/1999 is illegal and

wrongful. With these observations, I answer issues No.1

and 2 in the negative.

       92. ISSUE NO.3 : With regard to issue No.3 is

concerned, the plaintiff has pleaded and lead evidence

stating that the stipulated period of contract expired on

15/11/1995.       Inspite of several delays and defaults

committed by the defendants, he continued the execution

of the work even beyond he stipulated period.                The

defendants have also implied and permitted him to
                           90
                          CT 1390_Com.O.S.23­2019_Judgment .doc


complete the execution of the work. His repeated request

for grant of extension of time to perform part of the

contract was kept in silent by the defendants and made

him to continue the work. All of a sudden the defendants

have taken illegal action of canceling the contract by

applying cost and risk action of completing the balance

work.

      93. On the other hand, the defendants have pleaded

and     lead evidence stating   that   since the      plaintiff

contractor has failed to complete the work within

stipulated period, they have canceled the tender of the

plaintiff on cost and risk basis as per clause 3(b) & (c) of

the schedule of the contract.

      94. In the present case in hand, the plaintiff has

failed to prove that cancellation of the contract dated

11/8/1993 made by the defendants on 19/2/1999 is

illegal and wrongful.    On the other hand, perusal of

evidence on record discloses that admittedly the plaintiff

has failed to achieve monthly stipulated progress of the
                           91
                          CT 1390_Com.O.S.23­2019_Judgment .doc


work in terms of the contract.            On the date of

cancellation of the contract, the plaintiff was required to

achieve the work progress of Rs.42,91,526/­, against

which, he had reached the approved work progress of

only Rs.17,58,071/­.     A perusal of clause 2(d) of the

contract discloses that it provides for payment of penalty

by the contractor in respect of shortfall in progress due to

delay on the part of the contractor as per clause 2(b) & (c)

of the contract. Clause 3 of the contract provides that in

cases in which under any clause of the contract, the

Contractor shall have rendered himself liable to pay

penalty, the Executive Engineer have power to rescind

the work under clause 3(a) of the contract and cancel the

contract on risk and cost basis as per clause 3(c) of the

contract.

     95. A perusal of the materials on record discloses

that since the plaintiff - Contractor has failed to reach

the stipulated work progress and the shortfall in work

progress was assessed due to delay on the part of
                           92
                          CT 1390_Com.O.S.23­2019_Judgment .doc


contractor, defendants rescinded the contract of the

plaintiff on cost and risk basis as per clause 3(b) & (c) of

the schedule tender. Since Ex.P.1(a) schedule of contract

form provides for recession of the contract on cost and

risk basis and since the defendants have rescinded the

contract on cost and risk basis in terms of the Ex.P.1(a)

schedule of contract form, the contention of the plaintiff

that the defendants cannot apply the cost and risk action

for completing the balance work against him in case of

recession of contract cannot be accepted.         With these

observations, I answer issue No.3 in the negative.

     96. ISSUE NO.4 : With regard to issue No.4 is

concerned, the plaintiff has pleaded and lead evidence

stating that due to several delays and defaults committed

by the defendants, he was unable to complete the

construction work within stipulated period of time. The

defendants instead of granting extension of time to him

to complete the construction work have wrongfully

rescinded the contract. That the defendants are liable to
                              93
                             CT 1390_Com.O.S.23­2019_Judgment .doc


refund EMD of Rs.40,000/­, FSD recovered under bills

amounting to Rs.1,10,770/­ and NSC recovered in bill

amounting     to    Rs.12,700/­,      totally   amounting       to

Rs.1,63,470/­. Plaintiff has claimed interest @ 12% per

annum on the above mentioned sum of Rs.1,63,470/­

amounting to Rs.3,49,825/­.          Plaintiff has sought for

total claim of Rs.5,13,295/­ on the above mentioned

amounts.

      97. On the other hand, the defendants have pleaded

and lead evidence stating that since the plaintiff has

failed to complete the work within stipulated period of

time, they have canceled the contract on cost and risk

basis as per clause 3(b) & (c) of the schedule of contract

and   security     deposit   has    been     forfeited    to   the

government.      Hence, the question of considering the

claim made by the plaintiff for a sum of Rs.1,63,470/­

and interest of Rs.3,49,825/­ will not arise.            Once the

forfeiture clause is opened by them, the question of

considering the above claim of the plaintiff will not arise.
                          94
                          CT 1390_Com.O.S.23­2019_Judgment .doc


     98. In the present case in hand, the plaintiff has

failed to prove that recession of the contract dated

11/8/1993 on 19/2/1999 by the defendants is illegal

and wrongful. On the other hand, since the plaintiff has

failed to reach the stipulated work progress in terms of

the contract, the defendants by invoking clause 3(a) of

the contract have rescinded the contract and forfeited the

security deposit of the plaintiff - Contractor. Since the

defendants have forfeited the amount deposited by the

plaintiff in term of clause 3(a) of the contract, the

contention of the plaintiff that defendants are liable to

pay him claim of Rs.5,13,295/­ on the forfeited security

deposits cannot be accepted. With these observations, I

answer issue No.4 in the negative.

     99. ISSUE NO.5 : As claim No.2 plaintiff has sought

for payment of damages of Rs.43,81,236/­ from the

defendants towards payment of damages of idle charges

for men and machinery suffered by him towards stoppage

period of execution of the work in contract period. With
                            95
                           CT 1390_Com.O.S.23­2019_Judgment .doc


regard to this claim is concerned, the plaintiff has

pleaded and lead evidence stating that the execution of

the work was stopped on several occasions for want of

design details and due to obstruction on work site and

lack of payment. The total period of stoppage was 339

days during the period of execution of the work from

commencement of the work to the cancellation of the

contract due to various defaults and breach committed

by the defendants, as a result of which, he has suffered

damages in the form of idle charges for men and

machinery.    He had written various letters to the

defendants by intimating the stoppage of the work before

the expiry of the contract period. He has kept separate

men and machinery for this work. He has no chance to

mitigate the damage suffered during the idle period and

there   are   no   other    opportunity      to   utilize    the

establishment made by this aspect and he was always

ready at work site waiting for instructions of defendants

to execute the work. The idle charges per day works out
                           96
                           CT 1390_Com.O.S.23­2019_Judgment .doc


to Rs.3,600/­ including labourers machinery.                The

defendants are required to compensate him for idle

charges at the rate of Rs.3,600/­ per day for the period of

339 days.    The idle charges were calculated for the

construction period when the stoppage was occurred. On

this claim, the plaintiff has sought for payment of

damages     of     Rs.12,29,400/­       plus     interest     of

Rs.30,60,836/­ @ 12% per annum, totally amounting to

Rs.43,81,236/­.

     100. With regard to the above mentioned alleged

claim No.2 of the plaintiff is concerned, the defendants

have pleaded and lead evidence stating that the payment

of damages by them for the idle charges of men and

machinery alleged to have been suffered by the plaintiff

do not arise, since there was no stoppage of work ordered

by them at any stage during the subsistence of the

contract.   The Contractor cannot made any claim for

compensation as per clause 15 of the schedule of

contract form.    They reserved their right to take action
                          97
                          CT 1390_Com.O.S.23­2019_Judgment .doc


against the plaintiff for the delay in execution of the

work.    Plaintiff has not maintained the men and

machinery in the site during the subsistence of the

contract. There is no default and breach committed by

them.   Plaintiff unnecessarily making false allegations

against them and has sought for imaginary amount of

compensation on this claim. At no point of time, plaintiff

has shown the idle of men and machinery at the site

during the subsistence of agreement and plaintiff          has

not made any representation in this regard.

     101. In support of this claim of damage for idle

charges of men and machinery alleged to have been

suffered by him, plaintiff has mainly relied on Ex.P.16 -

56 vouchers pertaining to some payments made by

plaintiff to one D. Kuppuswamy on various dates towards

4 skilled and 15 unskilled workers.       Except producing

Ex.P.16 vouchers before the court, plaintiff has not

proved the contents of the said vouchers by examining

the above mentioned D. Kuppuswamy to prove that he
                           98
                          CT 1390_Com.O.S.23­2019_Judgment .doc


had made any payments to him with regard to the

labourers as alleged in the said vouchers. Hence mere

production of Ex.P.16 vouchers are not helpful for the

plaintiff to claim any compensation towards idle charges

of men and machinery, alleged to have been suffered by

him.

       102. A perusal of the evidence on record discloses

that the plaintiff has failed to prove that the stoppage of

work of construction was ordered by the defendants at

any point of time. No documentary evidence produced on

record by the plaintiff to show that the total period of

stoppage of the work was 339 days.         Plaintiff has not

produced any documentary evidence to show that he has

kept separate men and machinery for this work and as a

result of the alleged stoppage of the work he has suffered

any damages.       Plaintiff has also not produced any

documentary evidence to show that he had incurred

expenses of Rs.3,600/­ per day as idle charges for

stoppage of the work. On the other hand, a perusal of
                           99
                          CT 1390_Com.O.S.23­2019_Judgment .doc


the evidence on record discloses that admittedly, plaintiff

has failed to reach the stipulated work progress in terms

of the contract. Inspite of issuance of repeated notices by

the defendants to the plaintiff, he has failed to make up

the shortfall of the work, as a result of which, defendants

have rescinded the contract of the plaintiff in terms of the

contract.   A perusal of Ex.P.1(a) schedule of contract

form discloses that clause 3 (d) of the contract provides

that if the contractor does not maintain the rate of

progress as required under clause 2 of the contract and

failed to maintain the rate of progress even after taking

action under clause 2(c) & (d) by the Executive Engineer,

then the contractor will have no claim for compensation

for any loss sustained by him owing to such actions.

     103. Since the plaintiff has failed to prove that due

to various defaults and breaches committed by the

defendants, he has suffered damages in the form of idle

charges for men and machinery and since clause 3 (b) of

the contract provides that the plaintiff will have no claim
                           100
                           CT 1390_Com.O.S.23­2019_Judgment .doc


for compensation for any loss sustained by him due to

failure on his part to maintain the rate of progress as

required under the contract, plaintiff is not entitle for

payment of damages of idle charges for men and

machinery alleged to have been suffered by him.            With

these observations, I answered issue No.5 in the negative.

     104. ISSUE No.6 : With regard to issue No.6

pertaining to claim No.3 sought for by the plaintiff is

concerned, the plaintiff claimed a sum of Rs.46,61,091/­

as payment of equitable revised rates for the work done

by him beyond the stipulated period of time.

     105. With regard to this claim is concerned, the

plaintiff has pleaded and lead evidence stating that the

period of performance of the contract was prolonged

beyond the stipulated date of completion, due to several

defaults and breach of contract committed by the

defendants.     Due to the defaults committed by the

defendants he was forced to execute the work in the

prolonged     period   beyond   the   stipulated    period    of
                          101
                          CT 1390_Com.O.S.23­2019_Judgment .doc


completion facing the burnt of all round increase in the

market price during that period. There was no justice in

insisting him to do the work at tender rates, since the

delay in completing the work was not at all attributable

to him, he is entitle for payment of equitable revised rates

for the work done beyond the stipulated period taking

into consideration of the changed market conditions and

circumstances under which the work was executed. He

has requested the defendants to pay the equitable revised

rates for the quantity of work executed beyond the

stipulated period of completion of 15/11/1995, but the

defendant has kept silent and not made payment at

equitable revised rates for the work done by him beyond

the statutory period of contract. On this claim, plaintiff

has sought for a sum of Rs.14,84,424/­ and interest of

Rs.31,76,667/­ from 11/3/1999 upto 2/2/2017, totally

amounting to Rs.46,61,091/­.

     106. On this alleged claim of the plaintiff, the

defendants have pleaded and lead evidence stating that
                            102
                            CT 1390_Com.O.S.23­2019_Judgment .doc


the alleged payment of equitable revised rates for the

work done beyond the stipulated period of contract does

not fall under the schedule of contract form. The plaintiff

by making false allegations has claimed huge amount

from them according to his whims and fancies and the

claim of the plaintiff is hypothetical and illogical.

     107. In the present case in hand, the plaintiff has

failed to prove that the period of completion of work was

prolonged beyond the stipulated date of contract due to

several   defaults   and    breaches     committed      by    the

defendants. On the other hand, a perusal of the evidence

on record discloses that admittedly it is the plaintiff who

has failed to reach the stipulated work progress in terms

of the contract and inspite of issuance of number of

notices by the defendants, the plaintiff has failed to make

up the shortfall of the stipulated work resulting into

recession of the contract by the defendants. Further, a

perusal of the Ex.P.1(a) schedule of contract form

discloses that there is no provision for payment of
                          103
                          CT 1390_Com.O.S.23­2019_Judgment .doc


equitable revised rates for the work done beyond the

stipulated period of contract as claimed by the plaintiff

particularly when the plaintiff has failed to prove that the

period of performance of the contract was prolonged

beyond the stipulated date of completion due to default

and breach of contract committed by the defendants.

Since the plaintiff has failed to prove that the period of

performance was prolonged beyond the stipulated date of

completion due to defaults and breach of contract

committed by the defendants, plaintiff is not entitle for

any payment for equitable revised rates for the work done

beyond the stipulated period of contract.         With these

observations, I answer issue No.6 in the negative.

     108. ISSUE No.7 : With regard to issue No.7

pertaining to claim No.4 of the plaintiff is concerned, the

plaintiff has sought for a sum of Rs.22,68,201/­ as

reimbursement of expenses for longer stay at the work

site for the purpose of executing the work. With regard to

this claim is concerned, the plaintiff has pleaded and lead
                           104
                           CT 1390_Com.O.S.23­2019_Judgment .doc


evidence stating that as a result of defaults and breach of

contract committed by the defendants, the execution of

the work prolonged beyond the stipulated date of

completion due to which he was made to incur extra

expenses and additional monthly overhead charges. He

had taken 10% of the cost of work at quoted rates vis­a­

vis stipulated period of contract as the cost of over head

charges to meet the overhead both at head office and site

office, which included payment towards managerial

consultancy,   legal   advise,   Engineering,     Supervision,

Account stores and traveling overhead charges are fixed

in each and every month and will not increase or

decrease in proportion to quantum of work executed in

each month.    The establishment engaged on the works

cannot be retrenched or reduced till the completion of the

work.    Hence the expenses on monthly overhead

continued from the date of contract period dated

15/11/1995 till the cancellation of the contract on

11/3/1999.     On this claim, plaintiff has sought for a
                           105
                           CT 1390_Com.O.S.23­2019_Judgment .doc


reimbursement of Rs.7,22,357/­ along with interest of

Rs.15,45,844/­, totally amounting to Rs.22,68,201/­ as

reimbursement      expenses     from      11/3/1999        upto

2/2/2007 for longer stay at the work site for the purpose

of executing the work.

     109. With regard to this claim is concerned, the

defendants have pleaded and lead evidence stating that

there is no base for the plaintiff to claim a sum of

Rs.22,68,201/­ as reimbursement expenses for the

longer stay at the work site for the purpose of executing

the work.   The plaintiff on assumptions has calculated

the amount.     Since the plaintiff has not reached the

monthly tender work, which prescribed under the

agreement, the plaintiff is not entitle for the said claim.

     110. A perusal of the evidence on record discloses

that the plaintiff has failed to prove that the construction

work prolonged beyond the stipulated date of completion

due to defaults and breach committed by the defendants.

The alleged breach of contract and the alleged defaults
                           106
                           CT 1390_Com.O.S.23­2019_Judgment .doc


committed by the defendants resulting into delay in

performance of the contract work is base for the plaintiff

to make this claim. In the absence of proving the alleged

default and breach of the contract by the defendants

resulting into longer stay of the plaintiff at work site,

plaintiff is not entitle for this claim. Apart from that

except his interested oral evidence, plaintiff has not

produced any documentary evidence to show that he had

incurred any expenses for longer stay at the work site for

the purpose of executing the work.          In the absence of

production of any reliable evidence with regard to the

alleged expenses incurred by the plaintiff for longer stay

at the work site for the purpose of executing the work,

plaintiff is not entitle for this compensation also.

     111. With regard to issue No.7 is concerned, the

learned counsel for the plaintiff has relied on a decision

reported   between     Government      of    Karnataka      V/s

Sudhakar Reddy reported in ILR 1992 Karnataka 3276,

wherein, with regard to the tender agreement it was held
                            107
                            CT 1390_Com.O.S.23­2019_Judgment .doc


that whatever be the quantity of work that remains over,

the Contractor should have been in readiness to complete

the work and for that purpose he should keep his entire

establishment and machinery idle for the entire period. In

that view of the matter, it cannot be said that overhead

charges should have been calculated only on the quantity

of work that remains over beyond the period in question.

     112. I have perused the ratio of the above cited

decision.   Unlike cited decision, in the present case in

hand the plaintiff has failed to prove that the defendants

have ordered for stoppage of the construction work. On

the other hand, due to the inability of the plaintiff -

Contractor to reach the stipulated work progress the

contract was rescinded by the defendants.            Hence the

question of defendants paying overhead charges with

respect to the balance of the construction work will not

arise. Hence the ratio of the above mentioned decision is

not helpful for the plaintiff.
                           108
                          CT 1390_Com.O.S.23­2019_Judgment .doc


     113. Plaintiff's counsel has relied on another

decision between Mcdermott International Inc. V/s burn

standard co. Ltd. & others reported in 2006(2) Arb.Lr 498

(SC), wherein the Apex Court of the Land has held that in

case of challenge of the arbitration award, the scope of

intervention   of   the   court   is   envisaged      in    few

circumstances only like in case of fraud or bias by

arbitrators, violation of natural justice­ where arbitrator

has gone contrary to or beyond expressed law of contract

or granted relief in matter not in dispute would come

within purview of Section 34. When Arbitrator quantified

claim by taking recourse to Emden formula which is

widely accepted one. Arbitrator cannot be committed an

error warranting interference by court.

     114. I have perused the ratio        of the above cited

decision. Since the plaintiff has failed to prove that the

recession of the contract by the defendants is illegal, the

question of defendants paying any compensation to the

plaintiff towards reimbursement of expenses for longer
                            109
                             CT 1390_Com.O.S.23­2019_Judgment .doc


stay at work site will not arise. Hence, even the ratio of

this decision is also not helpful for the plaintiff.

      115. Plaintiff has also relied on another decision

reported between M/s. National Highways Authority of

India Vs. M/s. Tantia­TBL (JV) rendered in OMP 482 of

2009 dated 16/2/2012, wherein the Hon'ble High Court

of Delhi has upheld the finding of the arbitral tribunal

that when the contractor issued early warning notices to

the   National    Highways    Authority     of   India    seeking

extension of time and when National Highways Authority

of India had notified with compensation event, the

contractor has not committed breach of contract.              The

Delhi High Court has also upheld the finding of the

Tribunal that when the construction work undertaken by

the contractor prolonged because of indecisiveness on the

part of the NHAI it had resulted in loss and damage to

the contractor.

      116. I have perused the ratio of the above cited

decision.    Unlike cited decision, in the present case in
                          110
                          CT 1390_Com.O.S.23­2019_Judgment .doc


hand the plaintiff has failed to prove that the contract

work was prolonged because of        indecisiveness on the

part of the defendants. On the other hand, the contract

was rescinded due to failure on the part of the plaintiff to

reach the stipulated work progress. Hence, the ratio of

the above cited decision is also not helpful for the

plaintiff.

      117. The learned counsel for the plaintiff has relied

on another decision between M/s. National Highways

Authority of India V/s. M/s. Elsamex­TWS­SNC­JV

rendered in OMP 789 of 2012, wherein, the Hon'ble High

Court of Delhi has rejected the petition filed by the

National Highways Authority of India challenging the

award passed by the Arbitral Tribunal by awarding

compensation to the Contractor on the breach of the

contract.

      118. I have perused the ratio of the above cited

decision.    Unlike cited decision in the present case in

hand, the plaintiff has failed to prove that the delay in
                          111
                          CT 1390_Com.O.S.23­2019_Judgment .doc


execution of the work was not due to the reasons

attributable to him. On the other hand, the contract was

rescinded by the defendants for failure on the part of the

plaintiff to reach the stipulated work progress.       Hence,

the ratio of this decision is also not helpful for the

plaintiff.

      119. The plaintiff's counsel has relied on another

decision reported between U.P.State Electricity Board

V/s. Om Metals and Minerals (Pvt) Ltd, reported in

Arbitration Law Reporter 1994(2), wherein Allahabad

High Court has upheld the finding of the arbitral

Tribunal granting compensation to the contractor where

delay of construction work was resulted due to obstacle

created by the U.P.State Electricity Board in providing

suitable site.

      120. I have perused the ratio of the above cited

decision.    Unlike cited decision in the present case in

hand, the plaintiff has failed to prove that due to

obstacles created by the defendants, he could not able to
                              112
                             CT 1390_Com.O.S.23­2019_Judgment .doc


complete the construction work within stipulated period

of time.     Hence, the ratio of this decision is also not

helpful for the plaintiff.

      121. The learned counsel for the plaintiff has also

relied on another decision reported between Government

of Karnataka     V/s. K. Sudhakar Reddy reported in ILR

1992 Karnataka 3276, wherein, while interpreting the

clause of tender agreement it was held that over head

charges not confined only to balance of quantity of work,

entire establishment and machinery kept idle by the

plaintiff.

      122. I have perused the ratio of the above cited

decision. However, unlike cited decision in the present

case the plaintiff has failed to prove that due to default

on the part of the defendants to perform their part of the

contract, he has failed to complete the construction work

within stipulated period of time. Hence the question of

payment of over head charges by the defendants to the
                            113
                            CT 1390_Com.O.S.23­2019_Judgment .doc


plaintiff will not arise. Hence the ratio of this decision is

also not helpful for the plaintiff.

      123. The learned counsel for the plaintiff in his

arguments has also relied on a decision reported between

Rail India Technical and Economic Services Limited, New

Delhi V/s. Ravi Constructions, Bangalore and another

reported in 2001 (Suppl) Arb. LR 436 Karnataka (DB),

wherein, the Division Bench of Hon'ble High Court of

Karnataka has held that parties are bound to strictly

abide by the appointment procedure pertaining to the

Arbitral Tribunal.

      124. I have perused the ratio of the said decision.

The ratio of the said decision is not helpful for the

plaintiff.

      125. By perusing the materials produced on record,

I hold that the plaintiff has failed to prove that the

defendants are liable to pay him a sum of Rs.22,68,201/­

towards reimbursement of expenses for longer stay at the
                              114
                             CT 1390_Com.O.S.23­2019_Judgment .doc


work site for the purpose of executing the work. With

these observations, I answer issue No.7 in the negative.

       126. ISSUE No.8 : Issue No.8 of the present suit

relates to claim No.5 of the plaintiff, claiming loss of

profit on the balance work amounting to Rs.11,81,374/­.

With regard to this claim is concerned, the plaintiff has

pleaded and lead evidence stating that the work was

entrusted to him at his tender rate with the tender cost of

Rs.42,91,526/­ by the defendants. Inspite of failure on

the part of the defendants to fulfill their contractual

obligations he continued with the construction work and

with great difficulty he had achieved his progress of

Rs.17,83,296/­       out     of     the     tender        value   of

Rs.42,91,526/­. The defendants though failed to perform

their part of the contract have illegally canceled the

contract. The defendants are liable to make payment of

loss   of   profit   on    the    balance   cost     of    work   of

Rs.25,08,230/­ @ 15% interest per annum, totally

amounting to Rs.3,76,234/­, the defendants are required
                           115
                           CT 1390_Com.O.S.23­2019_Judgment .doc


to pay him interest of Rs.8,05,140/­ @ 12% per annum

on the sum of Rs.3,76,234/­. Plaintiff has sought total

sum of Rs.11,81,374/­ towards loss of profit on the

balance work.

     127. With regard to issue No.8 is concerned, the

defendants pleaded and lead evidence stating that since

the plaintiff had achieved financial progress of only

Rs.17,04,149/­ instead of the financial progress of

Rs.42,91,526/­ in terms of the contract, the plaintiff is

not entitle for any compensation for loss of profit on the

balance work.

     128. A perusal of the evidence on record discloses

that the plaintiff has failed to prove that the defendants

have failed to perform their contractual obligations and

failed to prove that the recession of the contract dated

19/2/1999 was illegal.          On the other hand, the

defendants have rescinded the contract of the plaintiff in

terms of the contract for failure on the part of the plaintiff

to reach the stipulated work progress in terms of the
                           116
                           CT 1390_Com.O.S.23­2019_Judgment .doc


contract.   Further, a perusal of the clause 3(d) of the

schedule of contract form discloses that it provides that

when the contractor does not maintain the rate of

progress as required under clause 2 of the contract and if

the Executive Engineer take action against the contractor

under clause 3(b) or (c) pertaining to failure on the part of

the Contractor to make up the shortfall of the work, the

Contractor will have no claim for any compensation for

any loss sustained by him owing to such actions.

     129. It is pertinent to note that the defendants have

rescinded the contract of the plaintiff, since he has failed

to reach the stipulated work progress in terms of the

contract.   In view of the provision of clause 3(b) of the

schedule of the contract form, plaintiff is not entitle for

any compensation pertaining to loss of profit on the

balance work as claimed by him.

     130. With regard to issue No.8 is concerned, the

learned counsel for the plaintiff has relied on two

decisions reported between M/s. A.T.Brij Paul Singh and
                              117
                             CT 1390_Com.O.S.23­2019_Judgment .doc


Bros V/s. State of Gujarath reported in AIR 1984

Supreme Court 1703 and between Dwaraka Das V/s.

State of Madhya Pradesh and another rendered in Civil

Appeal No.1209/1992, wherein, the Apex Court of the

Land has held that wherein the work contract, the party

entrusting the work commits breach of contract, the

Contractor would be entitle for claim damages for loss of

profit, which he expected the earn by undertaking the

works of contract. The measure of the damages depends

on facts of each case.

     131. I have perused the ratio of the above cited

decisions. Unlike cited decisions in the present suit,

plaintiff - Contractor has failed to prove that the

defendants who have entrusted the contract work to him

have committed breach of contract. On the other hand,

the contract of the plaintiff was rescinded for failure on

the part of the plaintiff to reach his stipulated work

progress. Hence, ratio of the above cited decisions is not

helpful for the plaintiff.
                          118
                          CT 1390_Com.O.S.23­2019_Judgment .doc


     132. By perusing the materials produced on record,

I hold that the plaintiff has failed to prove that the

defendants are liable to pay him a sum of Rs.11,81,374/­

for loss of profit on the balance work of contract. With

these observations, I answer issue No.8 in the negative.

     133. ISSUE No.9 : Issue No.9 pertains to claim No.6

sought for by the plaintiff, by which, he has sought for

payment of a sum of Rs.2,48,521/­ as the release of

reserved amount in RA Bills. With regard to issue No.9 is

concerned, the plaintiff has pleaded and lead evidence

stating that the defendants have reserved the amounts to

an extent of Rs.79,147/­ for want of funds, which was

clearly mentioned in running account bills on 8 th and 9th.

It is the duty of the defendants to make arrangement for

the funds for regular payment to him. The cause of delay

in making regular payments also attributable to the

defendants only. The defendants are required to release

the reserved amount of Rs.79,147/­ with respect to 8 th

and 9th RA bills. The defendants are required to pay him
                             119
                            CT 1390_Com.O.S.23­2019_Judgment .doc


interest of Rs.1,69,374/­ @ 12% per annum on the

reserved amount of Rs.79,147/­, totally amounting to

Rs.2,48,521/­.

     134. With regard to issue No.9 is concerned, the

defendants have pleaded and lead evidence stating that

the alleged reserved amount of Rs.79,147/­ was made

after release of letter of credit from the government and

the bill was passed vide SBR No.72 dated 30/8/1997, as

such, they are not due any amount to the plaintiff

towards the release of reserved amount in RA bills

claimed by the plaintiff.

     135. A perusal of the materials on record discloses

that except his oral evidence, plaintiff has not produced

any documentary evidence to prove that the defendants

are due a sum of Rs.79,147/­ towards the release of

reserved amount in RA bills No.8 and 9. On the other

hand, the defendants have taken a specific contention

that the alleged amount due was released to the plaintiff

on 30/8/1997 vide SBR No.72. Plaintiff has not filed any
                           120
                           CT 1390_Com.O.S.23­2019_Judgment .doc


rejoinder to the written statement of the defendants by

denying the release of this amount of Rs.79,147/­

towards RA bill No.8 and 9. Apart from that a perusal of

Ex.P.6 and P.7, the claim statement of the plaintiff made

to the 2nd defendant prior to filing of suit discloses that in

this claim statement, the plaintiff has not stated that the

defendants were due any amount to him towards release

of reserved amount in RA Bills No.8 and 9. If the

defendants were due any amount to the plaintiff towards

release of reserved amount as alleged by him, certainly

defendants would have stated the same in Ex.P.6 and P.7

claim statement. The very fact that the plaintiff in Ex.P.6

and P.7 claim statements has not claimed the alleged

amount due by the defendants towards release of

reserved amount in RA bills supports the contention of

the defendants that they were not due any amount to the

plaintiff towards release of reserved amount in RA bills.

     136. By perusing the materials produced on record,

I hold that the plaintiff has failed to prove that the
                           121
                           CT 1390_Com.O.S.23­2019_Judgment .doc


defendants are due a sum of Rs.2,48,521/­ to him

towards release of reserved amount in RA bills.            With

these observations, I answer issue No.9 in the negative.

     137. ISSUE No.10 : The defendants in the written

statement have taken a defence that the court fee paid by

the plaintiff is insufficient.   However, a perusal of the

evidence on record discloses that the defendants have not

lead any specific evidence to prove that the plaintiff has

not properly valued the suit for the purpose of payment

of court fee and court fee paid by him is insufficient. On

the other hand, a perusal of the materials on record

discloses that on the suit claim of Rs.1,32,53,718/­, the

plaintiff has paid a court fee of Rs.2,73,394/­ as per

clause 79 and schedule (1) Article (1) of the Karnataka

Court Fees & Suits Valuation Act, 1958. By considering

the materials produced on record, I hold that defendants

have failed to prove that the suit of the plaintiff is not

properly valued for the purpose of payment of court fees.
                           122
                           CT 1390_Com.O.S.23­2019_Judgment .doc


With these observations, I answer issue No.10 in the

negative.

     138. ISSUE No.11 : The defendants in the written

statement have taken another legal defence that the suit

of the plaintiff is barred by limitation.         However, a

perusal of the pleadings and evidence of the defendants

discloses that they have not lead any specific evidence to

prove that the suit of the plaintiff is barred by limitation.

Further no arguments were addressed on the aspect of

limitation by the counsel for defendants. In the absence

of specific pleadings and evidence to prove that the suit

of the plaintiff is barred by limitation, a stray sentence in

the written statement of the defendant is not sufficient to

come to the conclusion that the suit of the plaintiff is

barred by limitation.   By perusing the materials placed

on record, I hold that the defendants have failed to prove

that suit of the plaintiff is barred by limitation.        With

these observation, I answer issue No.11 in the negative.
                           123
                           CT 1390_Com.O.S.23­2019_Judgment .doc


     139. ISSUE No.12 : Since plaintiff has failed to

prove that the defendants have failed to perform their

part of the contractual obligations of contract dated

11/8/1993 entered between him and the defendants as

the reasons for non completion of the contract work

within the stipulated period of time and also failed to

prove that rescission of the contract dated 11/8/1993

made by the defendants on 19/2/1999 is illegal and

wrongful, plaintiff is not entitle for the suit claims sought

for. With these observations, I answer issue No.12 in the

negative.

     140. ISSUE No.13 : In the present suit, plaintiff has

sought for future interest @ 18% per annum.                 The

learned counsel for the plaintiff on the aspect of payment

of future interest has relied on number of decisions in his

written arguments.      However, since the plaintiff has

failed to prove that he is entitle for suit claims sought for,

the question for awarding future interest on the suit
                           124
                            CT 1390_Com.O.S.23­2019_Judgment .doc


claims sought for by the plaintiff do not arise. Hence, I

answer issue No.13 in the negative.

     141. ISSUE No.14 : In view of my findings on issues

No.1 to 13 and the reasons assigned thereon, I proceed

to pass the following:

                      ORDER

Suit of the plaintiff is dismissed.

Parties are directed to bear their costs.

Draw decree accordingly.

[Dictated to the Judgment Writer; transcript thereof corrected, initialed and then pronounced by me, in the Open Court on this the 25th day of October 2019] [S.A.Hidayathulla Shariff] LXXXIII Additional City Civil Judge.

BENGALURU.

1. List of witnesses examined on behalf of the Plaintiff/s:

PW.1 Sri. M. Keshava Raju

2. List of witnesses examined on behalf of the Defendant/s:

DW.1 : Sri. H.P.Ajith (discarded) DW 2 : Manjunatha L.N 125 CT 1390_Com.O.S.23­2019_Judgment .doc

3. List of documents marked on behalf of the Plaintiff/s:

     Ex.P 1         Agreement.
                    .




     Ex.P.1(a)      Schedule of contract form.
     Ex.P 2         Schedule B - 18 sheets.

     Ex.P 3         Note

     Ex.P 4         Note of schedule A.

     Ex.P.5         Correspondence - 28 sheets.

     Ex.P.6         Claim statement of plaintiff.

     Ex.P.7         Claim   appeal     before       the   2nd
                    defendant.

     Ex.P.8         Certified copy of order on civil Apeal
                    No.1586/2004.

     Ex.P.9         Notice dt. 19/12/2014 - 10 sheets

     Ex.P.10     to Postal Receipts.
     12
     Ex.P.13     to Postal Acknowledgements.
     15
     Ex.P.16     to Payment voucher, Certificate, Two
     19             drawings.

4. List of the documents marked for the defendant/s:

Ex.D.1 Letter of correspondence by the defendant for taking measurement. .
Ex.D.2 Postal Acknowledgement dt.
13/7/2018.
Ex.D.3 Copy of the Mahazar dt. 18/7/1998 126 CT 1390_Com.O.S.23­2019_Judgment .doc Ex.D.4 Contract certificate dt. 22/10/1998.
Ex.D.5 Rescind Order dt. 19/2/1996.
Ex.D.6 Letter addressed by defendant to BSNL.
Ex.D.7 Letter executed by defendant to KEB.
Ex.D.8 Letter dt. 7/4/1993 addressed to Superintendent Engineer, PWD.
Ex.D.9 Letter addressed to the plaintiff by AEE, PWD to collect drawings.
Ex.D.10 Notice dt. 2/6/1994 addressed to the plaintiff.
Ex.D.11 RPAD Acknowledgement.
Ex.D.12 Notice dt. 1/1/1994 addressed to the plaintiff.
Ex.D.13 Notice dt. 18/6/1994 addressed to the plaintiff.
Ex.D.14 Letter dt. 13/8/1994 addressed to the plaintiff.
Ex.D.15 Notice dt. 13/9/1994 addressed to the plaintiff.
Ex.D.16 Notice dt. 15/12/1994 addressed to the plaintiff.
Ex.D.17 Final notice dt. 22/2/1996 addressed to the plaintiff.
[S.A.Hidayathulla Shariff] LXXXIII Additional City Civil Judge.
BENGALURU.
127 CT 1390_Com.O.S.23­2019_Judgment .doc 1 CT 1390_Com.O.S.23­2019_Judgment .doc 3 .
1 CT 1390_Com.O.S.23­2019_Judgment .doc 3 .