Union of India - Subsection

Section 27(4) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(4)After completion of the renovation and modernisation (R&M), the generating company or the transmission licensee, as the case may be, shall file a petition for determination of tariff. Expenditure incurred or projected to be incurred and admitted by the Commission after prudence check, and after deducting the accumulated depreciation already recovered from the admitted project cost, shall form the basis for determination of tariff.