Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 2]

Supreme Court - Daily Orders

Rahul Gupta vs The Delhi Development Authority on 10 March, 2015

Bench: Jagdish Singh Khehar, S.A. Bobde

                                                               1

                                          IN THE SUPREME COURT OF INDIA

                                           CIVIL APPELLATE JURISDICTION

                            SPECIAL LEAVE PETITION (C) Nos.16385-16388 OF 2012


     RAHUL GUPTA                                                                      .......PETITIONER



                                                         VERSUS


     DELHI DEVT.AUTH.& ORS.                                                       .......RESPONDENTS



                                            O      R     D         E   R


                             We would, first of all, like to record our appreciation

     for the assistance rendered to this Court by Mr.Balwinder Kumar,

     IAS,                Vice-Chairman,    Delhi       Development         Authority,    and   Mr.Sandeep

     Mehta, Chief Engineer, holding charge of the Rohini Zone.

                             Consequent upon the factual position which was brought to

     our notice by the Vice-Chairman and the Chief Engineer, it is

     apparent, that allotment letters in respect of 10,725 plots were

     issued by the DDA before 30.11.2014, and with respect of 341 plots

     by            12.01.2015.       The    delay       in     effecting      these     allotments     with

     reference to the time frame depicted in our order dated 31.10.2014,

     is condoned.

                             Mr.Sandeep Mehta, Chief Engineer, indicated during the

     course of hearing, that in the case of the above, about 11,000
Signature Not Verified


     allotments, plots had been carved out in Sectors 28, 29, 30 and 34,
Digitally signed by
Satish Kumar Yadav
Date: 2015.03.13
10:35:14 IST
Reason:


     Rohini.                It is submitted that water, sewerage and road facilities

     have                already   been    provided       in       these    Sectors,    and    that,    the
                                             2

remaining external development (besides electrification, and storm

water     and     drain   water    infrastructure)         would       be   completed   by

10.04.2015.       It is, however, brought to our notice, that insofar as

the process of electrification is concerned, electricity poles are

being installed, and that, the process of electrification will be

completed, in the above-mentioned Sectors, by 30.06.2015. It is

affirmed, that temporary electricity connection when sought by the

above allottees, shall be provided immediately thereafter.                         It is

further assured that storm water and drain water infrastructure,

will    be   completed     in     Sectors    28,    29,    30    and    34,   Rohini,   by

30.06.2015.

             It is submitted that the external development work in

Sector 34 is also in the final stage of completion, and that, the

same will be completed by 31.03.2015.                     It is affirmed, that the

process      of   electrification      for       providing      temporary     electricity

connection to at least 3500 plot holders in Sector 34, Rohini, will

be ensured by 30.06.2015, and for the remaining approximately 3500

plot holders in Sector 34, Rohini, by 30.09.2015.

             Since the completion of the external development work, in

terms of the dates indicated hereinabove with reference to Sectors

28, 29, 30 and 34, Rohini, was communicated to us by the officers

who assisted this Court in passing of this order, we also record,

that there should not be any breach of the time frame, under any

circumstance whatsoever.

             Besides the above, approximately 11,000 plots, which have

presently been allotted, a further about 14,000 plots have to be

allotted under the same scheme (as the allotment with reference to
                                          3

11,000    allotments).       Mr.Balwinder            Kumar,       Vice-Chairman,           and

Mr.Sandeep Mehta, Chief Engineer, informed us that these allotments

would be made in Sectors 34, 35, 36 and 37,                            Rohini.           It is

submitted, that the land over which these plots will be carved out

is already available with the Delhi Development Authority.                               It is

pointed out that the external development work would have commenced

by now, but for agitation at the hands of the agriculturists of the

area.    It is also submitted, that there was a restraint order

passed by this Court, and as such, the development process could

not continue.       It is submitted, that the effect of the directions

issued by this Court came to be negated, on the withdrawal of the

petition(s)    filed    before    this    Court       on    03.02.2015.       It    is    also

affirmed, that at the present juncture, there is no agitation. In

the above view of the matter, we are informed, that there is now no

impediment     in    the    initiation         of     the     process     of        external

development.

           Mr.Sandeep Mehta, Chief Engineer, brought to our notice,

that even if the process is commenced without any further delay,

the   finalisation     of   the   tenders      would       take   approximately          three

months, and the execution of external development work, would take

a further period of about one year.                 He submitted, that it would be

appropriate to fix, an outer limit for completion of the external

development work, by 31.07.2016.

           In view of the aforesaid statement made to us, which we

hereby   accept,       we   direct       the    allotment         to    the        remaining

approximately 14,000 registered applicants be made by 31.07.2016.

Needless to mention, that as per the undertaking given to us, all
                                                  4

the external development work would be completed in Sectors 34, 35,

36 and 37, Rohini, by 31.07.2016. Insofar as the electrification

process    is      concerned,            even     though         we    are     satisfied,          that

approximately          six    months'      time       would      be    needed     to    erect      the

infrastructure for the same, we find no necessity to make any such

direction, and that, the purpose of the allottees will be served if

a   direction      is    issued     to     complete        the     electrification        process,

whereby it becomes possible to issue temporary connection in the

above-mentioned Sectors by June 30, 2016 (i.e. a month before the

completion        of      the      external           development            process).        Ordered

accordingly.            The    instant      direction         has     been     recorded       in    the

presence     of    the        learned     counsel       representing           the     Tata     Power

Distribution Limited. The same shall accordingly be brought to the

notice of the concerned officers for compliance.

           Since the completion of the external development work, in

terms of the dates indicated hereinabove, with reference to Sectors

34, 35, 36 and 37, Rohini, was communicated to us by the officers

who assisted this Court in passing this order, we also record, that

there   should      not       be   any    breach      of     the      time    frame,     under     any

circumstance whatsoever.

           It      is        apparent,      that       the    aforesaid         time     schedule,

determined        for    completing         the       development        process       will        need

unhindered        activity.         We,     therefore,             consider      it      just       and

appropriate to direct the Delhi Administration, as also, the Police

Department thereof, to take appropriate measures, preventive and

remedial, so that the above development activity, is not stalled on

account of any untoward incident(s). The Registry of this Court
                                        5

shall communicate the instant order to the Delhi Administration.

            Since the works required to be completed are extensive,

we would direct the authorities to ensure that Mr.Sandeep Mehta,

Chief Engineer, holding charge of the Rohini area, be continued in

the same capacity, or in his promoted capacity, for the Rohini

Area, at least till 31.07.2016.

            For   the    same   objective,    as   has   been    noticed   in   the

foregoing paragraph, we consider it just and appropriate to direct

that   no   Court       other   than   this   Court,     shall    entertain     any

application for grant of interim directions, with reference to the

above allotments or execution of the works. If and when an interim

direction is required, the aggrieved party who approaches a Court

of competent jurisdiction, would be relegated to this Court. The

concerned party would make such prayer, through an interlocutory

application. In such an eventuality, the party desiring an interim

direction, shall effect advance service of the application (wherein

such a prayer has been made), on the learned counsel representing

the rival parties before this Court, in the present litigation.

            Whilst disposing of these petitions with the aforesaid

directions, we consider it just and appropriate to further record,

that we have not taken into consideration any of the objections

raised by the petitioner, on any count other than, allotment of

developed plots. On all allied issues, that may arise in connection

with the above-mentioned allotment of plots, it shall be open to

the allottees to approach a competent Court having jurisdiction in

the matter.
                                6

         The special leave petitions are disposed of in the manner

indicated above.   As a sequel to disposal of the special leave

petitions, all other interlocutory applications are also disposed

of.



                                     ...........................J.
                                     (JAGDISH SINGH KHEHAR)




                                      ..........................J.
                                      (S.A.BOBDE)
NEW DELHI;
MARCH 10, 2015.
                                  7

ITEM NO.15                COURT NO.4                    SECTION XIV

                S U P R E M E C O U R T O F      I N D I A
                        RECORD OF PROCEEDINGS

Petition(s)   for    Special   Leave      to   Appeal     (C)         No(s).
16385-16388/2012

(Arising out of impugned final judgment and order dated 14/03/2012
in CM No.3312/2011 in WP No.8765/2009, WP No.7223/2007,WP No.
3590/2008 and WP No.4124/2011 passed by the High Court Of Delhi At
New Delhi)

RAHUL GUPTA                                              Petitioner(s)

                                 VERSUS

DELHI DEVT.AUTH.& ORS.                                   Respondent(s)

(With   appln.(s)   for   directions   and   permission   to   place
addl.documents on record and interim relief and office report)
(Final disposal)

Date : 10/03/2015 These petitions were called on for hearing today.

CORAM :
          HON'BLE MR. JUSTICE JAGDISH SINGH KHEHAR
          HON'BLE MR. JUSTICE S.A. BOBDE

For Petitioner(s)    Mr.Prashant Bhushan, Adv.
                     Mr. Rohit Kumar Singh, Adv.

For Respondent(s)    Mr.Mukul Rohtagi, AG
                     Mr.A.Sharan, Sr.Adv.
                     Ms.Binu Tamta, Adv.
                     Mr.Dhruv Tamta, Adv.

                     Mr.Rajiv Dutta, Sr.Adv.
                     Mr.Kumar Dushyant Singh, Adv.
                     Mr.Siddharth Dutta, Adv.
                     Mr.Daniel Goerge, Adv.
                     Mr.R.Nedumaran, Adv.

                     Mr.Ajay Bansal, Adv.
                     Mr.Praveen Swarup, Adv.
                     Mr.Gaurav Yadav, Adv.
                     Mr.Suresh Kumar, Adv.

                     Mr.Alok Gupta, Adv.

                     Mr.P.Parmeswaran, Adv.
                                  8


                    Mr.Vikas Upadhyay, Adv.
                    Mr.Alok Shankar, Adv.
                    Mr.Annanya Mishra, Adv.

                    Respondent-in-person

         Upon hearing the counsel the Court made the following
                      O R D E R

The special leave petitions are disposed of in terms of the signed order. As a sequel to disposal of the special leave petitions, all other interlocutory applications are also disposed of.




(SATISH KUMAR YADAV)                                  (RENU DIWAN)
   COURT MASTER                                       COURT MASTER

(Signed order is placed on the file)