[Cites 0, Cited by 0] [Section 15] [Entire Act]

Union of India - Subsection

Section 15(2) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(2)Where the generating company or the transmission licensee, as the case may be, makes an application for approval of its proposal for renovation and modernisation, the approval shall be granted after due consideration of reasonableness of the cost estimates, financing plan, schedule of completion, interest during construction, use of efficient technology, cost-benefit analysis, and such other factors as may be considered relevant by the Commission.