[Cites 0, Cited by 0] [Section 31] [Entire Act]

Union of India - Subsection

Section 31(4) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(4)The energy charge shall be payable by every beneficiary for the total energy scheduled to be supplied to the beneficiary, excluding free energy, if any, during the calendar month, on ex power plant basis, at the computed energy charge rate. Total Energy charge payable to the generating company for a month shall be:(Energy charge rate in Rs. / kWh) x {Scheduled energy (ex-bus) for the month in kWh} x (100 - FEHS) / 100