Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 14, Cited by 0]

Calcutta High Court (Appellete Side)

Steel Authority Of India Limited vs M/S Sms India Private Limited on 24 September, 2025

Author: Arijit Banerjee

Bench: Arijit Banerjee

                    IN THE HIGH COURT AT CALCUTTA
                     CIVIL APPELLATE JURISDICTION
                         COMMERCIAL DIVISION
                            APPELLATE SIDE
Present:
The Hon'ble Justice Arijit Banerjee
AND
The Hon'ble Justice Rai Chattopadhyay


                     FMAT (ARBAWARD) No. 7 of 2024
                                With
                     FMAT (ARBAWARD) No. 8 of 2024

                     Steel Authority of India Limited
                                   Vs.
                     M/s SMS India Private Limited

For the Appellant                     : Mr. Sarathi Dasgupta
                                      : Mr. Arijit Basu



For the Respondent                  : Mr. A. Tripathi, ld. Sr. Adv.
                                      : Ms. Sneha Nath
                                      : Ms. Suprava Jana
                                      : Mr. Ayanava Acharya



Heard on                              : 03.09.2025

Judgment on                           : 24.09.2025

Rai Chattopadhyay, J. :-

1. Two identical judgments and orders of the Commercial Court at Asansol
  dated December 21, 2023 in proceedings under section 34 of the
  Arbitration and Conciliation Act 1996 being Misc Arbitration Case No.
  10 of 2022 and Misc Arbitration Case No. 11 of 2022, are assailed in
  the instant appeals, which are filed by the award debtor/Steel Authority
                                                                     Page 2 of 27


   of India Limited [in short „SAIL‟] under section 37 of the said Act of
   1996. The appeals have been heard together and are being disposed of
   by dint of the following common judgment.


2. The issue involved and required to be decided here is with regard to
   construction of terms of a contract, entered into between the parties on
   May 23, 2008. This Court may not enter into the enormous details of
   the background facts. Suffice to state for the time being that, being
   aggrieved with the deductions made by the appellant in disbursement of
   bills, the respondent sought to bring the dispute before the arbitral
   tribunal. The tribunal decided the act of the appellant as above to be
   improper and illegal and directed for refund of the deducted sum of
   money to the respondent, in its award dated June 28, 2022 [in
   Arbitration Case No. 25594/HTG]. The present appellant being
   aggrieved with the said award of the tribunal, dated June 28, 2022,
   filed its cases under section 34 of the Arbitration and Conciliation Act
   1996, before the Commercial Court at Asansol [being Misc Arbitration
   Cases No. 10 & 11 of 2022], which have ultimately culminated into the
   judgments dated December 21, 2023. Those judgments are identical in
   nature and have been assailed in the instant appeals, filed by the
   appellant /SAIL, under section 37 of the Arbitration and Conciliation
   Act 1996.


3. Details of the two contract agreements are as follows:

  (a) Contract Agreement for Basic Oxygen Furnace ("Contract 1"), dated
  19 March 2008 signed by the Parties, SMS Demag AG and Bridge and
  Roof (I) Ltd. This Contract is the subject matter of Arbitration Case No.
  25594/HTG.

  (b) Contract Agreement for Secondary Refining Unit ("Contract 2"), dated
  23 May 2008, signed by the Parties, SMS Mevak UK Ltd., and Shriram
                                                                            Page 3 of 27


  EPC Ltd. This Contract is the subject matter of Arbitration Case No.
  25595/HTG arises out of this Contract.

  It may be mentioned at the outset that the provisions of the two
  Contracts are similar. In fact, those provisions which are relevant for
  determining the controversy/disputes that have arisen in these
  proceedings are identical. It is also pointed out at this stage itself that
  all the concerned clauses of the Special Conditions of the Contract
  (SCC) and General Conditions of the Contract (GCC) in both the
  Contract 1 and Contract 2 are also identical.



4. The respondent/claimant‟s case in a nutshell is as follows:
   Pursuant to the award of work and in terms of the agreement entered
   between the parties, the contractor‟s obligation covered design &
   engineering; supply of technological steel structures; manufacture
   (including associated purchases and/or sub-contracting) & supply of
   plant & equipment and commissioning spares; customs & port
   clearances (excluding all taxes, duties, levies, cess, etc. as may be
   applicable in India other than withholding tax on design & engineering,
   supervision and training services as may be applicable in India for
   which prices are quoted in Foreign currency); inland transportation;
   marine    and    inland     transit   insurance,    erection,   testing,      pre-
   commissioning, start-up & commissioning and demonstration &
   establishment    of   performance      guarantees    of   the   Facilities,     in
   accordance with the plans, specifications, drawings, codes and any
   other documents as specified in the Contract Technical Specifications.
   For providing these services a lump sum price was fixed. However, in
   the Price Schedule appended with the contract, this amount was
   further categorized into following elements: (a) Basic price, (b) Excise
   Duty (ED), (c) Central Sales Tax (CST), (d) Value Added Tax (VAT) and
   (e) Service Tax (ST) etc.
                                                                            Page 4 of 27


5. Upon completion of works on 19 May 2019, the appellant issued a
   Performance     Guarantee      Certificate   dated   06.07.2019   to   all   the
   consortium members including the respondent/claimant certifying that
   the works had been successfully completed. Accordingly, in terms of the
   contract, the claimant on 29 July 2019 submitted invoices towards 5%
   payments upon issuance of Performance Guarantee Certificate. Out of
   the   said   invoices,   the   appellant     withheld   an   amount    of    INR
   23,98,07,285. On 24 December 2019 the appellant informed that the
   said payment had been kept on hold on account of shortfall in the
   amount of guaranteed CENVAT Credit, which had not been passed on
   to the appellant by the respondent/claimant. The claimant protested
   against the said withholding through letters dated 2 January 2020 and
   24 January 2020 wherein it was explained that such withholding was
   not in terms of the contract. However, the appellant, vide its letter dated
   4 March 2020, reiterated its stand and justified the withholding of the
   amount.


6. In terms of Article 10 of the Contract read with Clause 6 of the GCC,
   the respondent issued a notice of Conciliation to resolve the disputes
   vide letters dated 19 March 2020 (in respect to 25594/HTG) and 19
   March 2020 (in respect to 25595/HTG). In the said letter, the
   respondent stated: "Failure on your part to release the payment within
   15 days shall be deemed to have exhausted all attempts towards
   amicable settlement of the dispute and we shall be constrained to take
   appropriate actions as may be advised and permissible under our
   contract and law to enforce our rights". The appellant did not respond
   to the above letters and hence, the respondent invoked the arbitration
   clause and filed its Request for Arbitration (RFA) before the ICC on 24
   August 2020.


7. The contra-case of the appellant is also stated below:
                                                                      Page 5 of 27


  The appellant say that arbitration invoked by the respondent is time
  barred, non-maintainable and de-hors the contractual agreements and
  law. Contracts were awarded by the appellant to a Consortium of three
  members entities of which the respondent is one of the members. The
  Arbitration Agreement contained in the contracts provide for arbitration
  only between the consortium (collectively composed of three parties)
  and the appellant. In the RFA, the appropriate law governing this
  arbitration proceeding has been agreed to be held under the aegis of the
  Indian Laws and the settled Indian Law prohibits arbitration proceeding
  being filed by individual member of consortium. Accordingly, where the
  parties to an arbitration agreement in their wisdom have agreed to enter
  into the agreement only as a consortium, clearly the obligation to
  arbitrate is between the consortium as a whole with the appellant on
  the other side. The respondent‟s attempt to individually invoke the
  arbitration proceedings is, thus, highly flawed and is in contravention
  to the terms and conditions of the Contract.


8. The respondent was awarded the contract by the appellant after
  evaluating all Bids received (including that of the respondent) net of
  taxes as all the Bidders including the respondent had, while quoting
  price under their respective Bids, specified "minimum guaranteed
  CENVAT Credit". The Bidders were to indicate Minimum Guaranteed
  CENVAT Credit that can be availed by the appellant against materials
  supplies for subject work and, in case of any shortfall in CENVAT Credit
  from that guaranteed by the Bidder, the said shortfall shall be deducted
  by the appellant from the contract. In this case, the respondent failed to
  discharge its obligation to pass on the specified amount of CENVAT
  Credit to the appellant. Not only has the respondent failed to perform
  its contractual obligation, but also it has unilaterally amended the
  contract Price by nullifying the guaranteed tax credit which has
  resulted into loss to the appellant and Public Exchequer. Further, in
  terms of the minimum guaranteed assurance given by respondent
                                                                       Page 6 of 27


    under the contract, to provide a specific value of tax credits, which is
    unconditional, the shortfall from such assured sum is recoverable by
    appellant from the respondent as per contract. Therefore, the appellant
    acting within the four corners of the terms and conditions of the
    awarded contract, has made payments to the respondents against the
    invoices received and has recovered the shortfall that it has incurred
    from the assured sum of guaranteed credit. Since the shortfall in the
    tax credits have not been disputed by the respondent, the appellant is
    entitled to deduct the same from payments due to the respondent. The
    respondent is interested in denying the right of the appellant to recover
    the said guaranteed sum under the contractual agreement.


 9. The appellant seeks the relief by stating that the respondent does not
    have any cause of action against the appellant, nor does the alleged
    claim of the respondent disclose any cause of action. It is submitted
    that no ground has been made justifying any of the claims and the
    reliefs sought by the respondent. Accordingly, the same should be
    dismissed. The appellant, therefore, seeks relief in the form of
    declaration that it is entitled to withhold such payments from the
    monies due to the respondent under the terms of the contract.
    Consequently, the appellant is also entitled to an award of the
    guaranteed sum less adjustments already made thereunder.


10. Before the arbitration tribunal, the respondent/claimant has sought for
    the following relief:


                       CASE NO. 25594/HTG (Contract 1)
     Sl                      Particulars                  Amount in INR
    No.
     A.      Outstanding payment due towards               23,98,07,285
             Invoice   No.    Prof/18-19/48   dated
             29.07.2019 of supply issued against
                                                                          Page 7 of 27


               Performance Guarantee certificate.
      B.       Interest     @18%           on    the          To be Quantified
               aforementioned claim from the date
               the same became due till the date of
               realization of the payment.
      C.       Costs on actual                                To be determined
                   Total Outstanding Amount                    23,98,07,285




                      CASE NO. c-25595/HTG (Contract 2)


  Sl                        Particulars                       Amount in INR
  No.
      A.       Outstanding payment due towards                  4,19,63,769
               Invoices dated 23.07.2018 issued
               against Commissioning certificate.
      B.       Interest     @18%           on    the          To be Quantified
               aforementioned claim from the date
               the same became due till the date of
               realization of the payment.
      C.       Costs on actual                                To be determined
                   Total Outstanding Amount                     4,19,63,769




11.          Summary of the tribunal‟s award is as follows:




"M1        BOF Contract (Case No. 25594/HTG)
 Claim                       Particulars                         Tribunal's
  No.                                                             Decision
       A.        Outstanding   payment   of  INR          Awarded INR
                 23,98,07,285 due towards Invoice         23,98,07,285 in
                                                                                    Page 8 of 27


             No.        Prof/18-19/48        dated               favour of the
             29.07.2019      of    supply   issued               Claimant
             against Performance Guarantee
             certificate.
      B.     Interest       @18%       on      the               Awarded simple
             aforementioned claim from the date                  interest @ 7% per
             the same became due till the date                   annum (refer
             of realization of the payment.                      paragraph L6.3
                                                                 above)


 M2   BOF Contract (Case No. c-25595/HTG)
 Claim                      Particulars                                Tribunal's
  No.                                                                   Decision
      A.     Outstanding       payment    of INR                 Awarded INR
             4,19,63,769 due towards Invoices                    4,19,63,769 in
             dated 23.07.2018 issued against                     favour of the
             Commissioning certificate.                          Claimant
      B.     Interest       @18%       on     the                Awarded simple
             aforementioned claim from the date                  interest @ 7% per
             the same became due till the date                   annum (refer
             of realization of the payment.                      paragraph L6.3
                                                                 above)


 181. In addition, the tribunal awards combined cost of US$ 285,000 plus
 INR 2,100,000 in Case No. 25594/HTG and Case No. c-25595/HTG in
 favour of the Claimant."


12.        The operative part of the tribunal‟s award is quoted bellow:

                      "OPERATIVE PART

                      In summation, various findings of the Tribunal on different issues
                      and claims are recapitulated below:

                      (a) The Additional Parties are not necessary for adjudication of
                      disputes raised in the present proceedings.

                      (b) The arbitration initiated by the Claimant is not premature.
                                                                                     Page 9 of 27


                       (c) The Tribunal has the jurisdiction over the Respondent pursuant
                       to the Arbitration Agreement to adjudicate upon the disputes.

                       For all the reasons set out above, the Tribunal has concluded and
                       declares that SMS INDIA PVT. LTD. is held entitled to the following
                       reliefs:

                       (a) STEEL AUTHORITY OF INDIA LIMITED shall pay SMS INDIA PVT.
                       LTD. the outstanding payment of INR 23,98,07,285 due towards
                       Invoice no. Prof/18-19/48 dated 29.07.2019 of supply issued against
                       Performance Guarantee certificate and outstanding payment of INR
                       4,19,63,769 due towards Invoices dated 23.07.2018 issued against
                       the commissioning certificate from Respondent;

                       (b) STEEL AUTHORITY OF INDIA LIMITED shall pay SMS INDIA PVT.
                       LTD. simple interest @ 7% per annum on the aforesaid amount of
                       INR 23,98,07,285 and INR 4,19,63,769 from the date of invocation of
                       the arbitration, i.e., from 24 August 2020 until full payment by
                       Respondent;

                       (c) STEEL AUTHORITY OF INDIA LIMITED shall pay SMS INDIA PVT.
                       LTD. costs of INR 2,10,000 being the legal costs incurred by
                       Claimant, and US$ 285,000 being the costs of the arbitration; and

                       (d) All other requests and claims are rejected.

                       Wherever necessary, relevant portions of the Contract Agreement,
                       judgments, laws, etc. are reproduced in the Award. Despite all care
                       having been taken, it may be possible that some typographical
                       and/or clerical errors in the quoted portions may have crept in. It is
                       observed that such errors would be treated as corrected and
                       substituted by the original text of the concerned documents and/or
                       evidence."




13. The Commercial Court, Asansol in its judgments dated December 21,
    2023, has held inter-alia that, the arbitral award does not suffer from
    any perversity and that the interpretation of the contract made therein
    is reasonable; that individual facts of the case have been duly
    considered with reference to the relevant clauses of the contract, and
    the award cannot be said to be based on any conjecture or surmises.
    Hence, it has declined to interfere with the arbitral award and the
    proceedings initiated before it by the present appellant/SAIL, under
    section 34 of the Arbitration and Conciliation Act 1996 were dismissed.
                                                                                 Page 10 of 27




14. Mr. Dasgupta, learned counsel, has represented the appellant/SAIL. He
    has submitted that the parties are bound by the terms of the concluded
    contract entered into by and between them. He says that the contract
    dated May 23, 2008 is such a concluded and binding contract between
    the parties. That the terms thereof cannot be varied while performing
    the same and if so, can only be done pursuant to a specific stipulation
    to that effect, made in the contract itself. Otherwise, that will attract the
    consequential penal or compensatory provisions as enumerated in the
    contract itself. He submits that according to the terms of the said
    contract         entered      into      between      the      parties,           the
    contractor/claimant/present respondent would be obliged to fulfil
    requirement of raising demand for tax reimbursement to the tune of
    optimum ceiling limit as prescribed in the said contract. This condition
    of contract being prescribed in the contract itself, has been well known
    to the respective parties from the day of entering into such contract. He
    elaborates further that reimbursement of tax to the optimum ceiling
    limit as prescribed under the contract, by the appellant/SAIL, would
    fetch the appellant credits, with regard to its own contractual outflow
    and the taxes payable by it. He elaborates further that the instant
    provision in the contract is the safeguard so that the appellant/SAIL is
    not twice vexed with the liability to pay the tax. He says that according
    to the terms of the contract, any lesser credit obtained by the
    appellant/SAIL               and          attributable             to            the
    claimant/contractor/respondent, would be recoverable by the SAIL, as
    per the contractual terms. He submits that the contractor would be
    obliged to arrange his affairs in such a manner, that a minimum
    guaranteed credit be available to the SAIL. He has ventilated the
    grievance    of    the     appellant   that   in   the   instant        cases,   the
    respondent/contractor has not fulfilled its obligations under the
    contract    to    secure     the   minimum     guaranteed    credit        for   the
    appellant/SAIL, resulting in non-receipt of or receipt of lesser amount
                                                                          Page 11 of 27


    of credit by the SAIL against its own contractual outflow. According to
    the appellant, this amounts to deviation in performance of contract by
    the respondent/contractor, in terms thereof, rendering it to be liable for
    the process of recovery of the deficit credit amount, than the optimum
    ceiling limit thereof. Hence, according to the appellant, withholding of
    the shortfall from the milestone payments to be made to the respondent
    /claimant is maintainable as per the terms of the contract. Hence that
    there would not be any infirmity or illegality as alleged and held, as
    regards deductions made by the appellant/SAIL, from the milestone
    payments to be disbursed to the respondent/claimant. It is the
    contention of the appellant/SAIL that in such view of the matter, both
    the decisions of the arbitral tribunal as well as the Commercial Court at
    Asansol are erroneous and unreasonable. The judgments of the
    Commercial court at Asansol, challenged in the instant proceeding
    under section 37 of Arbitration and Conciliation Act 1996 are thus
    liable to be set aside.


15. Per contra, Mr. A. Tripathi, learned Senior counsel appearing for the
    respondent/claimant/contractor,       has   vehemently   objected    to   the
    contentions and prayer made by the appellant in the instant appeals.
    He has vehemently objected to the contention of the appellant/SAIL
    that the amount of CENVAT credit in favour of the appellant would only
    be static and guaranteed amount, in terms of the contract entered into
    between the parties. He has argued that the credit allowable to the
    appellant is dependent on and subject to the amount of tax reimbursed
    by the appellant towards the respondent/contractor, while disbursing
    its   bills.   The        tax   reimbursement   sought     for      by    the
    respondent/contractor has diminished over time, from the date of
    entering into the contract, pursuant to reduction in the rate of taxes
    over the period of time. Mr. Tripathi has stated that the Excise Duty
    payable by the contractor which was 12 percent and odd at the time of
    entering into the contract, subsequently reduced to 10 per cent and
                                                                       Page 12 of 27


    thereafter to 8 percent. Hence, the contractor, having remitted tax at a
    reduced rate, would not ever raise a bill for reimbursement thereof, at a
    rate or for an amount greater than what the contractor has actually
    remitted. More so, when his demand should be supported by
    appropriate and relevant documents. That, with reduction of rate of tax,
    the contractor had to pay less on account of tax and therefore sought
    for reimbursement at a rate and for an amount which was actually paid
    by the same as tax. Mr. Tripathi submits that the contractor would not
    have any control over the change in the rate of taxes over the period of
    time. He says that in accordance with the contractual terms, cent
    percent tax liability of the contractor is reimbursable by the SAIL, that
    in turn fetches it the adequate credit. It is submitted that there cannot
    be any minimum unchangeable guaranteed amount for which the
    contractor would be liable to raise bill, irrespective of whatever actual
    amount of tax paid by the contractor, as the rate of tax is always
    subject to change in pursuance of the policies of the government in this
    regard.




16. Mr. A. Tripathi, learned Senior Counsel has submitted further that in
    absence of any patent error, illegality or perversity being traced in the
    impugned judgments of the Ld. Commercial Court or in the award of
    the arbitral tribunal, this Court while deciding the appellant‟s case
    under section 37 of the Arbitration and Conciliation Act 1996, may not
    venture to re appreciate the evidence, as it is the dictum of the law as
    settled on date. He has stated that after due consideration of the
    materials on record and the evidence, a proper and reasoned decision
    has been arrived at by the arbitral tribunal, which has not been
    unsettled or varied or interfered into by the Ld. Commercial Court,
    Asansol, in any manner whatsoever. That, the Appeal Court exercises
    only limited supervisory role as to any patent illegality or perversity of
    the said decision. He says that this principle applies both in cases of
                                                                   Page 13 of 27


Court exercising power under section 34 of the said Act and this Court
which exercises power under section 37 thereof. Rather it is more
narrow in case of this Court, he says. The appellate power of section 37
of the Act is said to be limited within the domain of section 34 of the
Act; that it is exercisable only to find out if the Court exercising power
under section 34 of the Act, has acted within its limits as prescribed
under the law or has exceeded or failed to exercise the power so
conferred. With reference to one judgment of the Supreme Court in
Punjab State Civil Supplies Corporation Limited vs Salman Rice
Mills, reported at 2024 SCC Online SC 2632, Mr. Tripathi has stated
that the Appellate Court shall have no authority of law to consider the
matter in dispute before the arbitral tribunal on merits, so as to find
out as to whether the decision of the arbitral tribunal is right or wrong,
upon reappraisal of evidence, as if it is sitting in an ordinary Court of
Appeal. To buttress his argument and on the proposition of law as
mentioned above, he has relied on some other judgments also, as stated
below:


    (I)     AC Chokshi Share Broker Private Limited Vs. Jatin
            Pratap Desai And Another reported at (2025) 5 SCC 321


    (II)    UHL Power Company Limited Vs. State of Himachal
            Pradesh reported at (2022) 4 SCC 116


    (III)   MMTC Limited Vs. Vedanta Limited reported at (2019) 4
            SCC 163


    (IV)    Associate Builders Vs. Delhi Development Authority
            reported at (2015) 3 SCC 49


    (V)     Executive Engineer Vs. S. Bose reported at 2025 SCC
            OnLine Cal 567
                                                                       Page 14 of 27




         (VI)   National Highways Authority of India Vs. Manta Kumar
                Saha and Others reported at 2024 SCC OnLine Cal 7587


         (VII) South City Projects (Kolkata) Limited and Another Vs.
                Kolkata Metropolitan Development Authority reported at
                2023 SCC Online Cal 2050


17.   Mr. A. Tripathi, learned Senior counsel has further submitted that in
      these appeals, the appellant makes endeavour to prompt the Court to
      appreciate materials and evidence one again, which is however, not
      permissible under the law. He submits that the award of the arbitral
      tribunal would not be proper to be interfered with, since the same has
      not been challenged on the ground of any illegality or perversity. He
      submits further that in this case the Court exercising power under
      section 34 of the said Act has neither acted beyond its power as
      prescribed nor has exceeded or failed to exercise the power conferred
      by law, on the same. Therefore, he submits further, that this Court
      while exercising power conferred under section 37 of the said Act is
      not authorised to see if the decision of the arbitral tribunal or the
      Commercial Court was right or not, upon re-appraisal of the evidence
      and the case on merits. The respondent has stated that within the
      narrow scope and purview of section 37 of the Arbitration and
      Conciliation   Act   1996,   and   while   exercising   the   power   of
      superintendence as vested in it by law, this Court may not enter into
      the questions of the impugned orders or the arbitral award being right
      or wrong, as sought for by the appellant. Instead the said impugned
      orders being not patently erroneous, illegal or perverse, may not be
      interfered into by this Court. Mr. Tripathi, learned Senior Counsel for
      the respondent seeks that the appeals as above may be dismissed.
                                                                                Page 15 of 27


18. Before proceeding further with the discussions, relevant terms of the
    contract may be extracted as herein below, for benefit of the discussion:



                  "The Summary Price Schedule reads as follows:

                    S.N               Description                 Total Price at base date
                                                                  In INR (INR Million)
                                                                  at base date for SMS
                                                                       (I) Pvt. Ltd.
                     A                   B
                    14.         Total Contract Price                     1857.643
                    15.          CENVAT Credit                            125.643
                    16.     VAT Credit (Input Tax Credit)
                    17.     VAT on Works Contract Credit
                    18.      Total Package Price-net of                  1732.00
                           CENVAT, VAT & Vat On Works
                                      Contract



                   2.1 Contract Price (Reference GCC Clause 11)

                   The employer hereby agrees to pay to the Contractor the Contract Price
                   in consideration of the performance by the Contractor of its obligations
                   hereunder. The Contract Price shall be the aggregate of : GBP 4000,000/-
                   (GBP four million only), and Indian Rupees 1944913000/- (Rupees one
                   billion nine hundred forty four million nine hundred thirteen thousand
                   only) or such other sums as may be determined in accordance with the
                   terms and conditions of the Contract. The guaranteed amount of
                   CENVAT and VAT Credit to be passed on to the Employer in Indian
                   Rupees 134,913,000 Million (Rupees One Hundred Thirty Four Million
                   Nine Hundred Thirteen Thousand Only).

                   "GCC Clause 11.2, Price Basis

                   11.2.1 The Contract Price indicated in Indian Rupees shall comprise
                   Basic price, Excise Duty, Central Sales Tax/VAT (including sales
                   tax/VAT/Works Contract Tax for the erection portion of the contract
                   only) Octroi, Service Tax, Education Cess and any other duties, taxes and
                   levies, as may be applicable and prevailing on base date of the Contract.
                   While the basic price will constitute the consideration under the
                   Contract, the payment of duties, taxes, levies, etc., will be reimbursed
                   (on actual)/ paid against documentary evidence to be produced by the
                   Contractor, subject to a ceiling indicated in Price Schedule given in
                   Appendix 1. In no case the reimbursement towards duties and taxes, etc.,
                                                            Page 16 of 27


shall exceed the amount indicated in Appendix 1 towards duties, taxes,
levies, etc., except as indicated in Sub-clause 14.06.1, hereof.

Service Tax and Excise Duty shall mean to cover applicable Education
Cess, Secondary and Higher Education Cess or any other surcharge
thereon as applicable.

"GCC Clause 14. Taxes and Duties

14.1 Except as otherwise specifically provided in the Contract, the
Contractor shall bear and pay all taxes, duties, levies and charges
assessed on the Contractor, its Sub-Contractors or their employees by
Municipal, State or Central Government Authorities.

However, subject to stipulations of the Contract, the payment of
duties, taxes, levies, cess etc., will be reimbursed / paid (on actual)
against documentary evidence to be produced by the Contractor,
subject to a ceiling indicated in price schedule (s) of the Contract. In
no case the reimbursement / payment towards duties, taxes, levies, cess
etc., shall exceed the amount indicated in price schedule(s) of the
Contract towards duties, taxes, levies, cess etc., except on account of
statutory variation in Taxes & Duties and / or imposition of new taxes
and duties. All taxes and duties payable outside India in respect of
performance of the Contract, shall be borne & paid by the Contractor.

"GCC Clause 14.5 CENVAT, VAT, VAT ON WCT

14.5.1 Contractor shall furnish the Employer along with the billing
schedule the list of goods for which CENVAT Credit can be availed
indicating the Tariff headings to enable the Employer to declare the same
to Appropriate Authority.

14.5.3 Excise Invoices for all indigenous plant, equipment and materials
shall be made consigned to "Steel Authority of India Limited-IISCO
Steel Plant" for availing CENVAT Credit under relevant Rules and shall
be furnished by the Contractor to the Employer for availing CENVAT
Credit.

14.5.5 The Contractor shall also submit any other Document required by
the Employer to avail the CENVAT Credit. In case, the Contractor fails
to submit the required document for availing the CENVAT credit by the
Employer in respect of supplies, the amount of Excise Duty on such
indigenous plant & equipment and countervailing duty on imported plant
& equipment for which the prices are in Indian Rupees shall not be paid
by the Employer to the Contractor.

14.5.6 Contractors has indicated Minimum Guaranteed CENVAT Credit
that can be availed by the Employer against material supplies for subject
work for which price quoted is in Indian Rupees. In case of any shortfall
                                                                               Page 17 of 27


                  in CENVAT credit from the value guaranteed by the Contractor, the
                  shortfall shall not be reimbursed to the Contractor.

                  In case, Employer is not able to avail CENVAT credit for reasons,
                  attributable to the Contractor and the ED amount for such cenvat credit
                  has already been paid to the contractor as per the approved billing
                  schedule, the same shall be recovered by the Employer from the
                  Contractor. CENVAT credit in excess of the guaranteed amount will be
                  shared in proportion of 50: 50 between the Employer and the contractor.
                  Sharing of CENVAT Credit as detailed above shall not include in
                  CENVAT credit amount on account of statutory variation.

                  14.5.8 For direct supply of the indigenous brought-out plant & equipment
                  by the Sub-contractor to the Employer, the contractors will draw their
                  invoices as per relevant trade notice to enable the Employer to avail the
                  CENVAT Credit.




                  "GCC Clause 14.6 Variations in Taxes & Duties"

                  14.6.1 For the purposes of the Contract, it is agreed that the 'Contract
                  Price' specified in Article 2 ("Contract" & "Terms of Payment") of the
                  Contract Agreement is based on the taxes, duties, levies etc., and
                  charges prevailing on Base Rate (hereinafter called "Tax" in this Sub-
                  Clause 14.6 hereof). If any rate of tax is increased or decreased, a new
                  tax is introduced, an existing tax is abolished, or any change in
                  interpretation or application of any tax occurs in the course of the
                  performance of Contract, which was or will be assessed on the
                  Contractor, Sub-Contractors or their employees in connection with
                  performance of the Contract, an adjustment of the Contract Price or
                  indigenous portion for which prices are indicated in Indian Rupees
                  shall be made as per Sub-Clause 14.6.2 & 14.6.3 hereof, by addition to
                  the Contract Price or deduction therefrom, as the case may be.




                  14.6.2 The adjustment in the Contract Price towards variation in the taxes
                  shall be made by the Employer on production of the documentary
                  evidence by the Contractor."




19. On a careful reading of the provisions under sections 34 and 37 of the
    Arbitration and Conciliation Act 1996 and the verdicts of the Court in
                                                                      Page 18 of 27


    interpretation thereof, the law as it stands on the date emerges to be
    that the Court in exercise of power under the said provisions of statute
    shall only have a limited supervisory power, as enshrined in the said
    provisions of law. The Court cannot intervene beyond the specific
    grounds, enumerated in the statute and cannot correct errors in the
    arbitral   award.   The   Court   cannot   undertake   an   independent
    assessment of the merits of the award by appreciating evidence or
    interfering with a reasonable interpretation of contractual terms by the
    arbitral tribunal. The law has been narrated by the Supreme Court
    that a Court under section 37 must only determine whether the
    section 34 Court has exercised its jurisdiction properly and rightly,
    without exceeding its scope as enumerated in the statute itself.
    Otherwise, the Court‟s verdict would be marred with erroneous
    exercise of jurisdiction as per law. In the case of Jatin Pratap Desai
    (supra), the Supreme Court has dwelled on these principles.


20. The law is now settled that the scope of intervention of the Court in
    arbitral matters is virtually prohibited. The interference if any, is
    confined only to the extent envisaged under the said statutory
    provisions, including that the appellate power of section 37 of the Act
    is limited within the domain of section 34 of the Act. That it is
    excisable only to find out if the Court exercising power under section
    34 of the Act, has acted within its limits as prescribed under the law or
    has exceeded or failed to exercise the power so conferred. That the
    Appellate Court has no authority of law to consider the matter in
    dispute before the arbitral tribunal on merits so as to find out as to
    whether the decision of the arbitral tribunal is right or wrong, upon
    appraisal of evidence. As it has been held by the Supreme Court in the
    case of Sanman Rice Mills (supra), that it is only where the Court
    exercising power under section 34 has failed to exercise its jurisdiction
    vested in it under section 34 or has travelled beyond its jurisdiction,
    the Appellate Court can step in and set aside the order passed under
                                                                                   Page 19 of 27


     section 34 of the Act. The Supreme Court says that the power of the
     Appellate Court is more akin to that of superintendence, as is vested in
     civil Courts while exercising revisionary power.


 21. Pertinent is to note what the Supreme Court has laid down while
     discussing the scope and extent of 2015 amendments to section 34 of
     the Arbitration and Conciliation Act 1996, in the case of Vedanta
     Limited (supra), which is in the following words:


                       "13. It is relevant to note that after the 2015 Amendment to Section 34,
                       the above position stands somewhat modified. Pursuant to the insertion
                       of Explanation 1 to Section 34(2), the scope of contravention of Indian
                       public policy has been modified to the extent that it now means fraud or
                       corruption in the making of the award, violation of Section 75 or Section
                       81 of the Act, contravention of the fundamental policy of Indian law, and
                       conflict with the most basic notions of justice or morality. Additionally,
                       sub-section (2-A) has been inserted in Section 34, which provides that in
                       case of domestic arbitrations, violation of Indian public policy also
                       includes patent illegality appearing on the face of the award. The
                       proviso to the same states that an award shall not be set aside merely
                       on the ground of an erroneous application of the law or by
                       reappreciation of evidence."




22. The scope of the provision under section 37 has been discussed therein
    in the following manner:


                       "14. As far as interference with an order made under Section 34, as
                       per Section 37, is concerned, it cannot be disputed that such
                       interference under Section 37 cannot travel beyond the restrictions
                       laid down under Section 34. In other words, the court cannot
                       undertake an independent assessment of the merits of the award,
                       and must only ascertain that the exercise of power by the court
                       under Section 34 has not exceeded the scope of the provision. Thus,
                       it is evident that in case an arbitral award has been confirmed by
                       the court under Section 34 and by the court in an appeal under
                       Section 37, this Court must be extremely cautious and slow to
                       disturb such concurrent findings."
                                                                                        Page 20 of 27


23. Similarly, in the other judgments of the Supreme Court and this Court,
      as relied on by the respondent in this appeal, the law as mentioned,
      have been elaborately discussed. Findings of this Court in South City
      Projects (supra), may also be apt and beneficial to be mentioned in this
      regard, which is as follows:
                   "41. From the above decisions the following principles may be culled out. An
                   award may be interfered with only if:--
                   a) It is perverse i.e. the conclusions are not based on the evidence on record
                   and/or based on extraneous considerations and/or material.
                   b) No reasonable man can arrive at the conclusion arrived at by the Arbitral
                   Tribunal.
                   c) The findings of the Tribunal are such that would shock the conscience of a
                   reasonable person.
                   d) The award is patently illegal or irrational.
                   e) The award is against the basic and/or fundamental and/or public policy of
                   India or Indian Law.
                   f) Any of the parties have been denied a reasonable opportunity to put forth
                   their case or an equal opportunity is not given to the parties and there is denial
                   of the principles of natural justice and the procedure followed is dehors a judicial
                   approach.
                   g) If the award is against the specific term of the contract and against the
                   substantive law if India."




24.    Within the limited power vested under the law this Court would only
       be justified to assess whether the Commercial Court at Asansol, while
       exercising its power under section 34 of the Arbitration and
       Conciliation Act 1996, has travelled beyond scope of that vested in it
       by the law or has committed any patent illegality or been patently
       irrational or that if it has failed to consider whether the arbitral award
       was against the terms of contract or any substantive law or public
       policy of the of the country.


25.    Going back to the case as made out by the appellant in this Court, we
       find that the appellant‟s case is basically with regard to the alleged
                                                                                     Page 21 of 27


      invalidity of the arbitral award due to the reason of it not being in
      terms of the contractual terms. The terms of contract as relied on by
      the appellant are elaborately referred to above. It is the case of the
      appellant herein that they were entitled to deduct the shortfall in
      CENVAT credit from the bills of the respondent and that arbitral
      tribunal misinterpreted Clause 14.5.6 of the GCC and erroneously
      came to the conclusion that the appellant has no power or right to
      deduct or withhold the amount of shortfall in the CENVAT credit.
      According   to   the   respondent,       the     contract      does     not    permit
      withholding/deducting amount of shortfall in the CENVAT credit from
      bills of the respondent.



26. It would be pertinent to mention the finding of the tribunal, as follows:

                        "128. To sum up, the "guaranteed amount of CENVAT Credit" records
                        minimum assured amount of CENVAT Credit in the Contract on the basis
                        of quotations given by the Contractor in the bid. The Employer keeps in
                        mind that it will be able to avail the stated figure of CENVAT Credit.
                        However, even when the Contractor fulfils its assurance and enables the
                        Employer to avail the figure of minimum CENVAT Credit mentioned in
                        the Contract, the Employer does not gain anything therefrom. On the
                        one hand, the Employer avails the CENVAT Credit and on the other hand,
                        it pays this very amount to the Contractor in the form of
                        "reimbursement" of the taxes paid by the Contractor. The position
                        remains the same even when the CENVAT Credit availed of by the
                        Employer is lesser than the minimum guaranteed amount thereof as
                        mentioned in the Contract....."

                        "136. Clause 14.5.6 of GCC in no uncertain terms states that "in case of
                        any shortfall in CENVAT Credit from the value guaranteed by the
                        contractor, the shortfall shall not be reimbursed to the contractor". As
                        noted above, this shortfall can be for the reason that proper and valid
                        documents are not given by the Claimant to the Respondent to enable
                        the Respondent to avail full credit. It may also be for the reason that
                        excise duty paid was lesser than which was guaranteed. This clause
                        takes care of both the situations resulting in shortfall of CENVAT Credit.
                        The stipulation that "the shortfall shall not be reimbursed to the
                        contractor" applies to both the eventualities. Apart from this, there is no
                        provision in the Contract which entitles the Employer/Respondent to
                        "withhold" or "deduct" the said shortfall from the amounts that are
                        payable to the Contractor/Claimant under the Contract. In the absence
                        of such a provision in Clause 14.5.6 of GCC or anywhere in the Contract,
                                                                                   Page 22 of 27


                      it can safely be inferred that the Respondent has no right to deduct or
                      withhold the amount of shortfall in the CENVAT Credit. Clause 14.5.6 of
                      GCC, thus, provides the complete answer."

                      "141 To sum up, the Contract provides for Contract Price (Article 2.1 of
                      the Contract) and also gives the basis of this price (Clause 11.2.1 of GCC)
                      by bifurcating it into the basic price (which is the consideration for the
                      performance and its obligation under the Contract by the Contractor)
                      and the duties, taxes, etc. No doubt, the Contract also mentions the
                      minimum guaranteed CENVAT Credit that is assured by the Contractor to
                      the Employer. However, in case of shortfall, the consequence thereof is
                      also provided in the Contract itself (Clause 14.5.6 of the GCC). To repeat,
                      the only consequence is that the Contractor shall not be reimbursed for
                      the amount of taxes, etc. which it has not paid. This clause nowhere
                      provides for "deduction" or "withholding" of such a shortfall from the
                      basic price which is the consideration payable by the Respondent to the
                      Claimant under the Contract."




27. The reasoning given by the tribunal was further endorsed by the
    Commercial Court at Asansol with the following words:

                      "23. Having examined the various contentions of the Learned
                     Advocate for the petitioner on the touchstone of the parameter of
                     interference as laid down by the Hon'ble Apex Court in several
                     judgments referred to above I am of the view that the impugned
                     award does not suffer from any infirmity. The Learned Arbitral
                     Tribunal has deliberated on all issues under reference and has duly
                     explained the reasons for arriving at its decision. There is nothing to
                     indicate that the award is in conflict with the basic notion of justice
                     and fair play and fundamental of policy of Indian Law or is in
                     contravention of the terms of the contract or lacks reasoning. The
                     impugned award therefore does not call for any interference.

                     Hence,
                     It is,                                 ORDERED
                     That Misc. Arbitration case being Misc. Arbitration Case No.10 of
                     2022 is rejected on contest.
                     The impugned award is upheld."
                                                                       Page 23 of 27


28. The basic contract price (Net Package Price) as specified in the contract is a
    lump-sum price, which the appellant agreed to pay to the respondent.
    Thus, the lump sum price payable to the respondent was Rs. 1732 million
    (Item 18). If, as per the Summary Price Schedule, the respondent had
    submitted CENVAT documents of Rs. 125.643 Million (Item 15), they would
    have been paid Rs. 1857.643 Million (Item 14) by the appellant (Rs. 1732
    Million + Rs. 125.643 Million = Rs. 1857.643 Million). In the present case,
    the respondent submitted documents (on which appellant received CENVAT
    credit) of Rs. 58.323 Million. Thus, as per contract, the respondent is
    entitled to Rs. 1790.323 Million (Rs. 1732 Million + Rs. 58.323 Million). If
    somehow no tax had been paid (assuming indirect taxation was abolished),
    the respondent would have been entitled only to the sum of Rs. 1732
    Million. From the above, it is evident that the amounts mentioned in the
    contract can change on the basis of a host of factors, including market
    dynamics, change in rates of taxes etc. The shortfall in the documentation
    pertaining to ED, ST, Education cess etc. is due to a number of factors,
    including (a) change in rates of taxation (b) change in rates of items (c)
    changes in quantity of materials to be supplied. The respondent could not
    have paid more taxes than demanded by the Government. Moreover, there
    was no reason for the respondent to hide the taxes paid since they were, in
    any case, to be reimbursed by the appellant for the taxes paid by them.
    Merely because the words "guaranteed" and "minimum" have been used in
    the contract does not make the said figure a constant figure. A conjoint
    reading of Article 2.1 of the agreement and GCC Clause 14.5.6 would make
    the intention of the terms "Minimum" and "Guaranteed" clear and
    unequivocal. Thus, the averment of the appellant that the contract price as
    set out in the contract is not changeable, is unacceptable. The Gross
    Contract Price depends upon a number of variables, including changes in
    rates of taxes, price variation etc. and hence, it cannot ever be stated that
    the Contract Price is a fixed amount. Accordingly, Article 2.1 of the
    agreement read with clause 14.5.6 and 14.6 envisages that the Contract
                                                                          Page 24 of 27


       Price as well as CENVAT amount is subject to changes (upwards or
       downwards). They cannot remain constant as stated by the appellant.




29.   A perusal of the paragraphs of the award quoted above would show that
      the appellant has no power under the contract to make any deduction
      and that the amount of minimum guaranteed CENVAT credit is not a
      sum due to the appellant but depends upon factors, which are
      changeable in nature. Hence, the insistence of the appellant on the
      amount of shortfall is beyond the provisions of the contract and was
      correctly held as such by the learned arbitral tribunal. The contention of
      the appellant that the shortfall in the CENVAT amount had any impact
      on their financial planning has also been dealt with in the Award and
      endorsed in the judgment of the Commercial Court at Asansol.




  30. This court finds the tribunal's award to be based on a careful examination
       of the contract, contemporaneous records, evidence of parties, and
       consistent application of law. Under Section 34 of the Act, such findings are
       not liable to be interfered with, even if an alternative view is possible. The
       Hon'ble Supreme Court in Ssangyong Engineering & Construction Co.
       Ltd. v. NHAI reported at (2019) 15 SCC 131 has held that unless the
       award is perverse or patently illegal, no interference is permissible. None of
       the conclusions in the present award satisfy that threshold.




  31. The challenge that the tribunal exceeded its mandate under Section
       34(2)(a)(iv) is wholly unfounded. The tribunal adjudicated the dispute
       framed in the Terms of Reference, namely, whether the appellant was
       contractually entitled to withhold ₹23.98 crores under Clause 14.5.6. The
       award does not travel beyond this issue. No extraneous relief was granted.
       The findings remain strictly confined to the scope of submission. In fact,
                                                                                   Page 25 of 27


      the tribunal repeatedly emphasized its interpretive limits and derived all
      conclusions from specific clauses, notably Clause 14.5.6 and Article 13.




 32. The    appellant    alleges   patent   illegality,    but   this     challenge    is   an
      impermissible     attempt    to   reargue     the   merits.   As     per   Ssangyong
      Engineering (supra) to show a patent illegality, challenge must be held as
      to a contravention of law on the face of the award. Here, the tribunal's
      analysis of Clause 14.5.6 is cogent, reasoned, and entirely consistent with
      commercial logic. The award was never improbable but only a plausible
      outcome, considering that the deduction was made unilaterally against a
      certified invoice. No error of law or fact is manifest on the face of the record.
      The appellant did not demonstrate any claim under Clause 14.5.6.
      Moreover, no contemporaneous amendment under Article 13 existed
      permitting any such deduction. The tribunal therefore rightly held that the
      deduction was baseless.




33.   The Commercial Court, in its judgment dated 21st December 2023, while
      rejecting the Section 34 petition, has categorically upheld the arbitral
      award as being reasoned, legally sound, and consistent with both the
      contractual terms and settled legal principles. The judgment reinforces
      several key conclusions of the arbitral tribunal and highlights the absence
      of any grounds for interference under Section 34 of the Arbitration and
      Conciliation Act, 1996. The Court reaffirmed that the arbitral tribunal had
      interpreted clause 14.5.6 of the General Conditions of Contract (GCC)
      correctly by holding that the said clause does not authorize unilateral
      deductions    from   certified    invoices.    Instead,    the     only    consequence
      contemplated by the clause is the non-reimbursement of excess duty
      amounts in the event of a shortfall of CENVAT credit. At Paragraphs 135-
      141 of the judgment, the Commercial Court observed that "there is no
      provision in the Contract which entitles the Employer to „withhold‟ or
                                                                         Page 26 of 27


      „deduct‟ the said shortfall from the amounts that are payable," thereby
      endorsing the tribunal‟s core finding.




 34. The Court has further held that the invocation of arbitration by the
      respondent was entirely valid and permissible. Interpreting clause 1 of the
      GCC and the structure of the consortium, the Court found that each
      member, including the respondent herein, was independently treated as a
      "Contractor" under the terms of the agreement. The Court also recorded
      that the other consortium members neither raised claims nor objected to
      exclusion from arbitration, and thus their non-participation did not vitiate
      the proceedings. The Court specifically cited the tribunal's holistic
      interpretation of Articles 1.3, 10.1, 12.1.1, and the Terms of Payment,
      concluding that the contract was divisible and permitted independent
      invocation of arbitration by any consortium member. The Court has also
      emphasized the well-established limitations on judicial review of arbitral
      awards. It relied on precedents including Associate Builders (supra,)
      Ssangyong Engineering (supra) to reiterate that re-appreciation of
      evidence   or   alternate   interpretations   of   contractual   clauses   are
      impermissible unless the award suffers from patent illegality or is contrary
      to the fundamental policy of Indian law. The Court observed that the
      arbitral award was well-reasoned, based on documentary evidence, and not
      rendered in violation of any procedural mandate, thereby precluding any
      interference. Lastly, the Court upheld the tribunal's award of interest and
      costs under Sections 31(7) and 31A of the Act. It noted that the simple
      interest at 7% per annum was neither excessive nor arbitrary, and the
      costs awarded reflected the prevailing norms and the conduct of the
      parties.




35.   These judicial observations lend further credence to the Award and
      demonstrate that the tribunal's reasoning has passed judicial scrutiny on
                                                                           Page 27 of 27


        all relevant parameters, jurisdiction, contractual interpretation, procedural
        confirmation, significantly diminishing any scope for further challenge.




36.     The present appeal essentially seeks reappraisal of facts and interpretation
        of contractual clauses,, impermissible under settled arbitration law. The
        tribunal's award as well as the order by the Commercial Court at Asansol in
        regard to the application filed by the appellant under Section 34 of the
        Arbitration and Conciliation Act, 1996 is well-reasoned and contractually
        consistent, withstands all grounds of challenge presented by the appellant.



37.     Hence, on the basis of the entire discussion as above, this Court finds
        no merits in the instant appeals.


38.     The appeals being FMAT (ARBAWARD) No. 7 of 2024 and FMAT
        (ARBAWARD) No. 8 of 2024 are dismissed. There will be no order as to
        costs.


39.     Urgent certified copy of this judgment, if applied for, be supplied to the
        parties upon compliance with all requisite formalities.




        I agree.


      Arijit Banerjee, J.                               Rai Chattopadhyay, J.