Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 18, Cited by 0]

Delhi High Court

National Highway Authority Of India vs Rohtak Panipat Tollway Pvt. Ltd. on 16 February, 2023

Author: Navin Chawla

Bench: Navin Chawla

                                       Neutral Citation Number: 2023/DHC/001137



           *        IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                      Reserved on:17.01.2023
                                                                   Date of decision:16.02.2023

           +        O.M.P. (COMM) 286/2018 & I.A. 8863/2018, I.A. 2943/2019
                    NATIONAL HIGHWAY AUTHORITY OF INDIA
                                                         ..... Petitioner
                                 Through: Mr.Narender Hooda, Sr. Adv.
                                          with Mr.Arun Kumar Batta,
                                          Ms. Neha Kumari, Mr. Abdul
                                          Wahid,    Ms.   R.      Ahuja,
                                          Mr.Shaurya Lamba, Advs.

                                               versus

                    ROHTAK PANIPAT TOLLWAY PVT. LTD.
                                                                             ..... Respondent
                                               Through:       Ms.Roopali Chaturvedi and
                                                              Ms.Sadiqua Fatima, Advs.
           CORAM:
           HON'BLE MR. JUSTICE NAVIN CHAWLA

           1.       The present petition has been filed under Section 34 of the
           Arbitration and Conciliation Act, 1996 (hereinafter referred to as the
           „Act‟), challenging the Arbitral Award dated 06.10.2017 passed by the
           learned Arbitral Tribunal, as well as the order dated 20.02.2018
           passed by the learned Arbitral Tribunal on an application under
           Section 33(1)(a) and (b) of the Act.
           2.       The disputes between the parties arose out of the Agreement for
           the work of "Four Laning of Rohtak - Panipat Section of NH-71A
           from KM 0.00 (KM 63.00 OF NH 10) to KM 80.858 (KM 83.39 of
           NH-1) in the State of Haryana under the NDPH Phase III on Design,
           Build, Finance, Operate and Transfer („DBFOT‟) Basis" awarded by
           the petitioner to the respondent.

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                Page 1 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           3.       By the Impugned Award, the learned Arbitral Tribunal has
           allowed the claims of the respondent herein.
           SUBMISSIONS OF THE LEARNED SENIOR COUNSEL FOR
           THE PETITIONER:

           CLAIM NO. 1

           4.       Claim no.1 of the respondent was towards additional lead
           required for transportation of material on site. The learned senior
           counsel for the petitioner submits that the mining operation in the
           State of Haryana was lying closed since 01.03.2010. He submits that
           the Concession Agreement was signed between the parties on
           09.03.2010 and the work commenced in April 2011, that is, after the
           closure of the mining operation. He submits that, therefore, the
           respondent could not have been allowed to take the benefit of Clause
           41.1 of the Concession Agreement which provides for increase in
           costs due to change in law.
           5.       He submits that the claim for additional lead was raised by the
           respondent for the first time vide letter dated 13.05.2014, while the
           notice claiming arbitration was issued on 11.02.2016. He submits that,
           therefore, not only is the claim not maintainable in terms of the
           Concession Agreement, but is also barred by the Law of Limitation.
           6.       Placing reliance on Geo Miller and Company Private Ltd. v.
           Chairman, Rajasthan Vidyut Utpadan Nigam Limited., (2020) 14
           SCC 643 and Bharat Sanchar Nigam Limited & Another v. Nortel
           Networks India Private Ltd., (2021) 5 SCC 738, the learned senior
           counsel for the petitioner submits that as the cause of action arose on
           01.03.2010 and the notice claiming arbitration was issued only on
           11.02.2016, the claim was barred by limitation. He submits that the

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 2 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           learned Arbitral Tribunal has ignored these important facts in
           adjudicating the claim no.1 in favour of the respondent.
           7.       He further submits that as per the Government Order dated
           21.04.2012, sand mine in the Districts of Sonepat and Panipat and two
           small stone mines in the District of Mahendergarh remained
           operational even after 01.03.2010. Therefore, there was no compelling
           reason for the respondent to have allegedly chosen to procure the
           material from outside the State of Haryana. In any case, for this
           unilateral decision of the respondent, its claim for differential in prices
           was not justified and could not have been granted.
           8.       He submits that the learned Arbitral Tribunal has erroneously
           placed reliance upon the Feasibility Report, despite the fact that the
           Clause 2.13 of the RFP clearly states that the Feasibility Report is
           only a preliminary document and that nothing contained therein would
           be binding upon the Authority nor would it confer any right on the
           bidders. He submits that the Feasibility Report was only for the
           purpose of appraising the Concessionaire about the topography of the
           area and other different details mentioned in the said document, which
           are only indicative and not binding.
           9.       The learned senior counsel for the petitioner further submits
           that the learned Arbitral Tribunal has also erred in placing reliance
           upon the Letter dated 15.04.2013 from the Independent Engineer (in
           short, the „IE‟) to the petitioner, wherein, the IE allowed the additional
           carriage charges with regards to transportation of stone aggregates
           from the State of Rajasthan as change of scope of work. He submits
           that the said letter has no relevance to a claim under change in law.
           10.      He submits that even the quantification of the sum awarded
           under claim no.1 cannot be sustained. He submits that assuming, but
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 3 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           not admitting, that the Feasibility Report was binding on the
           petitioner, even in such an event, as per the Feasibility Report, the
           Granular Sub-Base Material (in short, „the GSB‟) was available at the
           maximum distance of 190 Kms, and assuming that it was brought by
           the respondent from the distance of 257 Kms, the respondent‟s claim
           could have been maintainable only for a lead distance for
           transportation of only 67 Kms. However, the learned Arbitral Tribunal
           erroneously quantified the claim with respect to additional
           transportation charges for GSB taking the lead distance of 134 Km on
           the basis of average distance of the mine mentioned in the Feasibility
           Report.
           11.      He submits that claim no.1 has been granted to the respondent
           on notional basis and without any evidence produced by the
           respondent. He submits that as the claim was of the nature of recovery
           of damages, the same could not have been allowed without proof of
           the same.
           CLAIM NO. 2
           12.      Claim no.2 pertains to the alleged loss of revenue suffered by
           the respondent due to delay in granting permission for collection of
           toll and the Provisional Completion Certificate (hereinafter referred to
           as the „PCC‟).
           13.      The learned senior counsel for the petitioner submits that as per
           Article 14 of the Concession Agreement, PCC could be issued to the
           respondent only after successful conclusion of safety tests and when
           the Project Highway could safely and reliably be put to commercial
           operations. He submits that the IE, with respect to safety, was to be
           guided by the Safety Consultant appointed by the petitioner as per the
           Article 18 of the Concession Agreement. The application made by the
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 4 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           respondent vide letter dated 24.08.2013 for issuance of PCC was not
           considered by the petitioner and the PCC could not have been issued.
           He submits that even in the letter dated 18.09.2013, which forms the
           basis for the learned Arbitral Tribunal to pass the Award in favour of
           the respondent, the works mentioned in Appendix A-1 and A-2 to the
           said letter were not complete and the respondent had to complete the
           same before the issuance of the PCC. The IE, even vide letter dated
           30.09.2013, pointed out that certain items were yet to be completed;
           the respondent was instructed to complete the pending works at the
           earliest and submit a Total Compliance Report. One of the most
           crucial items, as pointed out in the said letter, was the compliance
           regarding the metal beam crash barrier which was not completed by
           the respondent. In the light of the said letter dated 30.09.2013, the
           application made by the respondent for issuance of PCC was not
           considered by the petitioner.
           14.      He submits that the IE had communicated to the petitioner, vide
           letter dated 25.10.2013, that as on 25.10.2013, certain works were
           pending as per the Safety Audit Report attached with the said letter
           under serial no. 1, Row 5. These works were a part of the Safety Audit
           Report, and as such, it was paramount for the petitioner to complete
           the same before the issuance of PCC to the petitioner.
           15.      He submits that in view of the above, the Award passed by the
           learned Arbitral Tribunal is in violation of the fundamental policy of
           Indian Law as the learned Arbitral Tribunal has, arbitrarily and
           without any application of mind, held that none of the items said to be
           incomplete were such which may pertain to reliability and safety of
           the Project Highway, even though, the said items were brought to

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 5 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           notice for compliance by the Safety Consultant, as is evident from the
           aforementioned letter dated 30.09.2013.
           16.      He submits that the learned Arbitral Tribunal has also failed to
           consider the fact that in terms of the Clause 26.2.1 of the Concession
           Agreement, the Concessionaire (the respondent herein) had to pay to
           the petitioner, on COD date, a premium in the shape of additional
           Concession Fees for the amount of Rs. 45 Crore during that year and
           for each subsequent year of the Concession Period. He submits that
           even if the conclusion of the learned Arbitral Tribunal on Claim no.2
           is upheld, the proportionate amount of the Concession Fees of Rs. 45
           Crore should be deducted from the amount awarded by the learned
           Arbitral Tribunal. He submits that the learned Arbitral Tribunal failed
           to deduct the proportionate amount of approximately 90 days of the
           year 2013 and 8 days of the year 2014 as Concession Fees payable by
           the respondent to the petitioner in terms of Clause 26.2.1 of the
           Concession Agreement. The Concession Fees as such for the said
           period come out to be approximately Rs. 12,08,00,000/-, which is
           required to be deducted from amount awarded under the claim no.2 of
           the respondent.

           SUBMISSIONS OF THE LEARNED COUNSEL FOR THE
           RESPONDENT:

           17.      On the other hand, the learned counsel for the respondent, while
           reminding the Court of the limited jurisdiction that it exercises under
           Section 34 of the Act, submits that the Impugned Award is based on a
           proper appreciation of the contractual terms and the facts, and,
           therefore, deserves no interference from this Court.
           CLAIM NO. 1
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 6 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           18.      On Claim no.1, she submits that the request for proposal was
           issued by the petitioner on 05.06.2009; the respondent submitted its
           bid on 30.11.2009; and the Letter of Award (in short, the „LOA‟) was
           issued to the respondent by the petitioner on 04.01.2010. She submits
           that in terms of Clause 2.15.1 of the RFP, the bid could not have been
           modified, substituted, or withdrawn by the respondent after the bid
           date. She submits that in terms of Clause 3.3.6 of the RFP, the
           respondent was not entitled to seek any deviation in the Concession
           Agreement, which was to be signed between the parties after the
           acknowledgement of LOA dated 04.01.2010. She submits that,
           therefore, the binding Contract came into being between the parties on
           04.01.2010, and as the mining activity was banned vide order dated
           21.04.2012 with effect from 01.03.2010, that is, after the issuance of
           the LOA, the same falls within the ambit and scope of Clause 41.1,
           that is, „change in law‟.
           19.      On the question of limitation, she submits that in terms of
           Clause 41.1, it was only where the Concessionaire suffers an increase
           of cost as a result of change in law, the aggregate financial effect of
           which exceeds higher of Rs.1 Crore or 0.5% Realisable Fee in the
           Accounting Year, that the Concessionaire was to notify the Authority
           seeking amendment of the Agreement. She submits that the work on
           the project commenced on 18.04.2011; the respondent applied for
           Completion Certificate for the full length of the project on 13.11.2013;
           and the Provisional Certificate was issued by the petitioner on
           06.01.2014. The respondent thereafter raised a claim on 13.05.2014,
           which was rejected by the petitioner on 25.05.2015. The respondent
           thereafter invoked the Arbitration Agreement on 11.02.2016. She
           submits that therefore, the invocation was within the period of
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 7 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           limitation; there was also no delay in raising of the claim before the
           petitioner.
           20.      On the quantification of the claim, the learned counsel for the
           respondent submits that the same has been done in a reasonable
           manner and in terms of table numbers 8.5 and 8.8 of the Final
           Feasibility Report and the letter dated 15.04.2013 issued by the IE,
           which established the fact of sourcing of the materials by the
           respondent from Rajasthan and also the acceptance of carriage charges
           in accordance with the Haryana Schedule of Rates, Public Works
           Department, Haryana. She submits that no fault can be found with the
           learned Arbitral Tribunal in taking the average of the lead distance
           from the Feasibility Report.
           21.      She further submits that, in fact, the learned Arbitral Tribunal
           has rejected the respondent‟s claim for additional cost for carriage of
           sand since the sand was available in the Districts of Sonepat and
           Panipat in Haryana. The same cannot be said for the availability of
           GSB material and Aggregates.

           CLAIM NO. 2
           22.      On Claim no.2, she submits that in terms of Clause 14.3.1 and
           14.3.2, the IE was to issue the PCC on completion of atleast 75% of
           the Project Highway if the tests are successful and the Project
           Highway can be safely and reliably put to commercial operations. The
           PCC was to be issued by the IE even though certain works or things
           forming part thereof were not yet complete and were outstanding. She
           submits that the respondent applied for PCC vide letter dated
           24.08.2013 for 93.7% of the Project Highway. Various test reports as
           per the contractual provisions were submitted and the respondent also
           undertook
Signature Not Verified to complete the Punch List items. It is based on the said
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 8 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           undertaking and the completion of the works as stated in the Punch
           List-C that the IE vide letter dated 18.09.2013 informed the petitioner
           that the Project Highway can be safely and reliably put to commercial
           operation as all mandatory tests have been successfully conducted.
           Despite the fact that it was the IE who was the Competent Authority
           to issue the PCC, IE sought the approval of the petitioner in terms of
           Clause 12 of the Terms of Reference of the Independent Engineer
           Consultancy Agreement, though the same was not binding or
           applicable to the respondent. She submits that the items mentioned by
           the IE as incomplete were not essential to put the Project Highway
           safely and reliably on commercial operation. The same were just
           additional compliances sought by the Safety Consultant in its Audit
           Report. In any case, the IE vide letter dated 25.10.2013 informed the
           petitioner of completion of these works. She submits that, therefore,
           no fault can be found in the impugned Arbitral Award on the date
           when the respondent was entitled to grant of the PCC.
           23.      Without prejudice to the above submission, she submits that as
           against 75% of the Project Highway which was required to be
           completed in terms of Article 14.3 for issuance of the PCC, the
           respondent had sought the PCC for 93.7% of the Project Highway.
           Therefore, even if some works remained pending, the respondent was,
           entitled to grant of PCC.
           24.      On the claim of the petitioner for deduction of proportionate
           amount of Concession Fee for the period for which Claim no.2 has
           been granted by the Arbitral Tribunal, the learned counsel for the
           respondent submits that the same cannot be agitated at the stage of
           challenge to the Arbitral Award under Section 34 of the Act. The

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 9 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           petitioner having not raised this claim before the learned Arbitral
           Tribunal, cannot challenge the Award on basis thereof.

           ANALYSIS AND FINDINGS:
           25.      I have considered the submissions made by the learned counsels
           for the parties.
           26.      At the outset, I have to remind myself of the limited jurisdiction
           that I exercise under Section 34 of the Act. This Court cannot consider
           the award as an Appellate Court. The scope of interference/challenge
           has been explained by the Supreme Court in Ssangyong Engineering
           and Construction Company Limited v. National Highways Authority
           of India (NHAI), (2019) 15 SCC 131, wherein it has been inter alia
           held as under:
                                        "34. What is clear, therefore, is that the
                                        expression "public policy of India", whether
                                        contained in Section 34 or in Section 48,
                                        would now mean the "fundamental policy of
                                        Indian law" as explained in paras 18 and 27
                                        of Associate i.e. the fundamental policy of
                                        Indian law would be relegated to
                                        "Renusagar"       understanding      of     this
                                        expression. This would necessarily mean
                                        that Western Geco expansion has been done
                                        away with. In short, Western Geco , as
                                        explained in paras 28 and 29 of Associate
                                        Builders , would no longer obtain, as under
                                        the guise of interfering with an award on the
                                        ground that the arbitrator has not adopted a
                                        judicial approach, the Court's intervention
                                        would be on the merits of the award, which
                                        cannot be permitted post amendment.
                                        However, insofar as principles of natural
                                        justice are concerned, as contained in Sections
                                        18 and 34(2)(a)(iii) of the 1996 Act, these
                                        continue to be grounds of challenge of an
                                        award, as is contained in para 30 of Associate
                                        Builders.

                                        35. It is important to notice that the ground
                                        for interference insofar as it concerns
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                       Page 10 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        "interest of India" has since been deleted, and
                                        therefore, no longer obtains. Equally, the
                                        ground for interference on the basis that the
                                        award is in conflict with justice or morality is
                                        now to be understood as a conflict with the
                                        "most basic notions of morality or justice".
                                        This again would be in line with paras 36 to
                                        39 of Associate Builders , as it is only such
                                        arbitral awards that shock the conscience of
                                        the court that can be set aside on this ground.

                                        36. Thus, it is clear that public policy of
                                        India is now constricted to mean firstly, that a
                                        domestic award is contrary to the fundamental
                                        policy of Indian law, as understood in paras
                                        18 and 27 of Associate Builders , or secondly,
                                        that such award is against basic notions of
                                        justice or morality as understood in paras 36
                                        to 39 of Associate Builders. Explanation 2 to
                                        Section 34(2)(b)(ii) and Explanation 2 to
                                        Section 48(2)(b)(ii) was added by the
                                        Amendment Act only so that Western Geco , as
                                        understood in Associate Builders , and paras
                                        28 and 29 in particular, is now done away
                                        with.

                                        37. Insofar as domestic awards made in
                                        India are concerned, an additional ground is
                                        now available under sub-section (2-A), added
                                        by the Amendment Act, 2015, to Section 34.
                                        Here, there must be patent illegality appearing
                                        on the face of the award, which refers to such
                                        illegality as goes to the root of the matter but
                                        which does not amount to mere erroneous
                                        application of the law. In short, what is not
                                        subsumed within "the fundamental policy of
                                        Indian law", namely, the contravention of a
                                        statute not linked to public policy or public
                                        interest, cannot be brought in by the backdoor
                                        when it comes to setting aside an award on the
                                        ground of patent illegality.

                                        38. Secondly, it is also made clear that
                                        reappreciation of evidence, which is what an
                                        appellate court is permitted to do, cannot be
                                        permitted under the ground of patent illegality
                                        appearing on the face of the award.

                                        39. To elucidate, para 42.1 of Associate
Signature Not Verified
                                        Builders , namely, a mere contravention of the
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                       Page 11 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        substantive law of India, by itself, is no longer
                                        a ground available to set aside an arbitral
                                        award. Para 42.2 of Associate Builders,
                                        however, would remain, for if an arbitrator
                                        gives no reasons for an award and
                                        contravenes Section 31(3) of the 1996 Act, that
                                        would certainly amount to a patent illegality
                                        on the face of the award.

                                        40. The change made in Section 28(3) by
                                        the Amendment Act really follows what is
                                        stated in paras 42.3 to 45 in Associate
                                        Builders , namely, that the construction of the
                                        terms of a contract is primarily for an
                                        arbitrator to decide, unless the arbitrator
                                        construes the contract in a manner that no
                                        fair-minded or reasonable person would; in
                                        short, that the arbitrator's view is not even a
                                        possible view to take. Also, if the arbitrator
                                        wanders outside the contract and deals with
                                        matters not allotted to him, he commits an
                                        error of jurisdiction. This ground of challenge
                                        will now fall within the new ground added
                                        under Section 34(2-A).

                                        41. What is important to note is that a
                                        decision which is perverse, as understood in
                                        paras 31 and 32 of Associate Builders , while
                                        no longer being a ground for challenge under
                                        "public policy of India", would certainly
                                        amount to a patent illegality appearing on the
                                        face of the award. Thus, a finding based on no
                                        evidence at all or an award which ignores
                                        vital evidence in arriving at its decision would
                                        be perverse and liable to be set aside on the
                                        ground of patent illegality. Additionally, a
                                        finding based on documents taken behind the
                                        back of the parties by the arbitrator would
                                        also qualify as a decision based on no
                                        evidence inasmuch as such decision is not
                                        based on evidence led by the parties, and
                                        therefore, would also have to be characterised
                                        as perverse."

           27.      In Delhi Airport Metro Express Private Limited v. Delhi Metro
           Rail Corporation Limited, (2022) 1 SCC 131, the Supreme Court

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 12 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           reiterated the limited scope of interference permitted under Section 34
           of the Act, as under:-
                                        28. This Court has in several other judgments
                                        interpreted Section 34 of the 1996 Act to stress
                                        on the restraint to be shown by Courts while
                                        examining the validity of the arbitral awards.
                                        The limited grounds available to Courts for
                                        annulment of arbitral awards are well known
                                        to legally trained minds. However, the
                                        difficulty arises in applying the well-
                                        established principles for interference to the
                                        facts of each case that come up before the
                                        Courts. There is a disturbing tendency of
                                        Courts setting aside arbitral awards, after
                                        dissecting and reassessing factual aspects of
                                        the cases to come to a conclusion that the
                                        award needs intervention and thereafter,
                                        dubbing the award to be vitiated by either
                                        perversity or patent illegality, apart from the
                                        other grounds available for annulment of the
                                        award. This approach would lead to corrosion
                                        of the object of the 1996 Act and the
                                        endeavours made to preserve this object,
                                        which is minimal judicial interference with
                                        arbitral awards. That apart, several judicial
                                        pronouncements of this Court would become a
                                        dead letter if arbitral awards are set aside by
                                        categorising them as perverse or patently
                                        illegal without appreciating the contours of the
                                        said expressions.
                                        29. Patent illegality should be illegality which
                                        goes to the root of the matter. In other words,
                                        every error of law committed by the Arbitral
                                        Tribunal would not fall within the expression
                                        "patent illegality". Likewise, erroneous
                                        application of law cannot be categorised as
                                        patent illegality. In addition, contravention of
                                        law not linked to public policy or public
                                        interest is beyond the scope of the expression
                                        "patent illegality". What is prohibited is for
                                        Courts to reappreciate evidence to conclude
                                        that the award suffers from patent illegality
                                        appearing on the face of the award, as Courts
                                        do not sit in appeal against the arbitral award.
                                        The permissible grounds for interference with
                                        a domestic award under Section 34(2-A) on
                                        the ground of patent illegality is when the
Signature Not Verified                  arbitrator takes a view which is not even a
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                       Page 13 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        possible one, or interprets a clause in the
                                        contract in such a manner which no fair-
                                        minded or reasonable person would, or if the
                                        arbitrator commits an error of jurisdiction by
                                        wandering outside the contract and dealing
                                        with matters not allotted to them. An arbitral
                                        award stating no reasons for its findings
                                        would make itself susceptible to challenge on
                                        this account. The conclusions of the arbitrator
                                        which are based on no evidence or have been
                                        arrived at by ignoring vital evidence are
                                        perverse and can be set aside on the ground of
                                        patent illegality. Also, consideration of
                                        documents which are not supplied to the other
                                        party is a facet of perversity falling within the
                                        expression "patent illegality".
                                        30. Section 34(2)(b) refers to the other
                                        grounds on which a court can set aside an
                                        arbitral award. If a dispute which is not
                                        capable of settlement by arbitration is the
                                        subject-matter of the award or if the award is
                                        in conflict with public policy of India, the
                                        award is liable to be set aside. Explanation
                                        (1), amended by the 2015 Amendment Act,
                                        clarified the expression "public policy of
                                        India" and its connotations for the purposes of
                                        reviewing arbitral awards. It has been made
                                        clear that an award would be in conflict with
                                        public policy of India only when it is induced
                                        or affected by fraud or corruption or is in
                                        violation of Section 75 or Section 81 of the
                                        1996 Act, if it is in contravention with the
                                        fundamental policy of Indian law or if it is in
                                        conflict with the most basic notions of morality
                                        or justice.
                                                              (emphasis supplied)

           28.      Applying the above test to the facts of the present case, I shall
           consider the objections of the petitioner on merit.

           CLAIM NO. 1:
           29.      On the applicability of Clause 41.1, the learned Arbitral
           Tribunal in its Impugned Award has observed as under: -
                                        "20. Before we may deal with the controversy
                                        on merit in the context of the relevant clauses
Signature Not Verified                  as mentioned above, it would be appropriate
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 14 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        to deal with the twin objections as noted
                                        above. We have already mentioned that the
                                        Claimant was the highest bidder. His bid was
                                        accepted on 30.11.2009 or at the most when a
                                        Letter of Award was issued in his favour on
                                        4.1.2010. Highest bid given by the Claimant is
                                        an offer, it is accepted at least when Letter of
                                        Award was issued in its favour. In view of the
                                        provisions contained in Section 4 of the Indian
                                        Contract Act, 1872 the communication of an
                                        acceptance is complete as against the
                                        proposer, when it is put into a course of
                                        transmission to the person to whom it is made,
                                        so as to be out of the power of the acceptor
                                        and as against the acceptor, when it comes to
                                        the knowledge of the proposer. In view of the
                                        facts as mentioned above, when the Letter of
                                        Award was issued to the Claimants on
                                        4.1.2010 a concluded and binding contract
                                        would come into existence. The mining
                                        operations stopped in the State of Haryana on
                                        1.3.2010 i.e. after the contract had already
                                        come into being. The ground for rejection as
                                        contained in the letter of the Respondent
                                        referred to as also in the counter that the
                                        concluded contract came into being when the
                                        Concession Agreement was signed by the
                                        parties on 9.3.2010 by which time the
                                        Claimants had come to know about halting of
                                        mining operations in the State needs to be
                                        repelled. The provisions of Section 4 of the
                                        Contract Act are clear. However, we may
                                        mention that Hon'ble Supreme Court in
                                        Haridwar Singh v. Begum. Sumbruiu AIR 1972
                                        SC 1942 has held that the communication of
                                        acceptance of the highest bid is necessary for
                                        completed contract. Surely, when Letter of
                                        Award was issued by none other than the
                                        Respondent, it certainly would be an
                                        acceptance of the highest bid given by the
                                        Claimant.
                                               That apart, the RFP clearly states that
                                        no bid shall be modified, substituted or
                                        withdrawn by the bidder after the bid date and
                                        further the selected bidder shall not be able to
                                        make any deviation in the Concession
                                        Agreement after acknowledgement of the LOA.
                                        Clauses 2.15.1 and 3.3.6 read as follows:
                                               "2.15.1 The Bidder may modify,
Signature Not Verified
                                               substitute or withdraw its Bid after
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                       Page 15 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                               submission, provided that written notice
                                               of the modification, substitution or
                                               withdrawal is received by the Authority
                                               prior to Bid Due Date. No Bid shall be
                                               modified, substituted or withdrawn by
                                               the Bidder on or after the Bid Due
                                               Date."
                                               "3.3.6. After acknowledgement of the
                                               LOA as aforesaid by the Selected
                                               Bidder, it shall execute the Concession
                                               Agreement within the period prescribed
                                               in Clause 1.3. The Selected Bidder shall
                                               not be entitled to seek any deviation in
                                               the Concession Agreement."
                                               The very fact that the Claimants could
                                               not modify, substitute or withdraw their
                                               bid after the Bid Due Date i.e.
                                               30.11.2009       and     further    that
                                               Concessionaire was not entitled to seek
                                               any deviation in the Concession
                                               Agreement after acknowledgement of
                                               LOA would conclusively manifest that
                                               the contract had come into being at
                                               least when LOA was issued by the
                                               Respondent."

           30.      The above finding of the learned Arbitral Tribunal is based on
           the interpretation of various terms of the RFP. I find no infirmity in
           the above view taken by the learned Arbitral Tribunal. In terms of
           Clause 3.3.6 of the Concession Agreement, the respondent was not
           entitled to seek any deviation in the Concession Agreement after the
           acknowledgement of the LOA. Admittedly, the mining activity in the
           State of Haryana was banned vide order dated 21.04.2012 with effect
           from 01.03.2010, that is, after the issuance of the LOA on 04.01.2010.
           The same would, therefore, fall within the scope of „change in law‟.
           31.      On the question of the claim no.1 being barred by limitation, I
           again find no merit in the objection raised by the petitioner. Clause
           41.1 of the Concession Agreement is reproduced hereinunder:-
                                        "41.1 Increase in costs
                                             If as a result of Change in Law, the
Signature Not Verified                       Concessionaire suffers an increase in
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                      Page 16 of 29
                                         Neutral Citation Number: 2023/DHC/001137


                                                costs or reduction in net after tax return
                                                or     financial burden, the aggregate
                                                financial effect of which exceeds the
                                                higher of Rs. 1 crore (Rupees one crore)
                                                and 0.5% (zero point five percent) of the
                                                Realisable Fee in any Accounting Year,
                                                the Concessionaire may so notify the
                                                Authority and propose amendments to
                                                this      Agreement so as place the
                                                Concessionaire in the same financial
                                                position as it would have enjoyed had
                                                there been no such Change in Law
                                                resulting in the cost increase, reduction
                                                in return or other financial burden as
                                                aforesaid upon notice by the
                                                Concessionaire, the Parties shall meet,
                                                as soon as reasonably practicable but
                                                no later than 30 (thirty) days from the
                                                date of notice, and either agree on
                                                amendments to this Agreement or on
                                                any other mutually agreed arrangement:
                                                Provided that if no agreement is
                                                reached within 90 (ninety) days of the
                                                aforesaid notice, the Concessionaire
                                                may by notice require the Authority to
                                                pay an amount that would place the
                                                Concessionaire in the same financial
                                                position that it would have enjoyed had
                                                there been no such Change in Law, and
                                                within 15 (fifteen) days of receipt of
                                                such notice, along with particulars
                                                thereof, the Authority shall pay the
                                                amount specified therein; provided that
                                                if the Authority shall dispute such claim
                                                of the Concessionaire, the same shall be
                                                settled, in accordance with the Dispute
                                                Resolution      Procedure.     For     the
                                                avoidance of doubt, it is agreed that this
                                                Clause 41.1 shall be restricted to
                                                changes in law directly affecting the
                                                Concessionaire's costs of performing its
                                                obligations under this Agreement."

           32.      In the present case, the work commenced on 18.04.2011. The
           claim was raised by the respondent with the petitioner on 13.05.2014.
           Even in terms of the Clause 41.1, the claim for seeking amendment in
           theVerified
Signature Not   Concession             Agreement due to increase in cost resulting from
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                         Page 17 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           change of law would arise in favour of the respondent only on the end
           of the Accounting Year. Therefore, the claim was raised within the
           period of limitation by the respondent. The same was rejected by the
           petitioner only on 25.05.2015, whereafter, the respondent invoked the
           Arbitration Agreement on 11.02.2016. From the date of rejection of
           the claim, the invocation was also within the period of limitation.
           33.      In the present case, as is noted hereinabove, the „dispute‟
           between the parties can be said to arise only with the rejection of the
           claim of the respondent by the petitioner vide its letter dated
           25.05.2015. Delay in raising the claim by the respondent cannot be a
           ground to hold the same to be not maintainable.
           34.      In Geo Miller (supra), the Supreme Court has held that the
           period of limitation for commencement of arbitration runs from the
           date on which, had there been no arbitration clause, the cause of action
           would have accrued. The cause of action would also arise when
           „dispute arises between the parties.‟ It has been held that the period
           during which the parties were bona fide negotiating towards an
           amicable settlement may be excluded for the purpose of computing
           the period of limitation for reference to arbitration under the Act.
           While mere failure to pay may not give rise to a cause of action, once
           the applicant has asserted its claim and the respondent fails to respond
           to such claim, such failure will be treated as a denial of applicant‟s
           claim giving rise to a dispute and, therefore, the cause of action for
           reference to arbitration.
           35.      In Bharat Sanchar Nigam Limited (supra), the Supreme Court
           held that the period of limitation for issuing notice of arbitration
           would not get extended by mere exchange of letters, or mere
           settlement discussion, „where a final bill is rejected by making
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 18 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           deduction or otherwise.‟ It was held that the notice invoking
           arbitration must be received by the other party within a period of three
           years from the rejection of the final bill, failing which the time bar
           would prevail.
           36.      The above judgments, therefore, do not support the plea of the
           petitioner that the claim of the respondent was barred by limitation.
           37.      The learned Arbitral Tribunal has also discussed the above issue
           and has held as under:-
                                        "21. In so far as second plea pertaining to the
                                        claim being barred by time is concerned, the
                                        same has no merit either. It may be recalled
                                        that the bid was accepted on 4.1.2010 by
                                        which the Claimants were informed that the
                                        concession period is 25 years including
                                        construction period of 910 days from the
                                        Appointed Date. The construction of the
                                        project would only start after the Concession
                                        Agreement is signed by parties. The actual
                                        work was to start even as per the case set up
                                        by the Respondent in the written synopsis of
                                        arguments on 18.4.2011. It is further the case
                                        of the Respondent in synopsis that the
                                        Claimant applied for Completion Certificate
                                        for full length on 13.11.2013. Provisional
                                        Certificate was issued by the Respondent on,
                                        6.1.2014 which would only show that
                                        substantial work had already been done. The
                                        Claimants, however, state that the Provisional
                                        Certificate should have been granted 3/4
                                        months earlier. Complete computation of the
                                        extra cost incurred by the Claimants could be
                                        done only after the construction was complete.
                                        The claim was raised on 13.4.2014 and the
                                        same can by no stretch of imagination be
                                        termed as barred by time or belated.

                                               Further, for the claim to be barred by
                                        time, the Respondent places reliance on
                                        Article 41.1 which has already been
                                        reproduced hereinabove. A bare reading of the
                                        Article would show that there is no time limit
                                        to notify the Authority of the proposed
                                        amendments of the Agreement if as a result of
Signature Not Verified
                                        Change of Law, Concessionaire has suffered
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                      Page 19 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        an increase in costs and put to financial loss
                                        etc. If no time may be prescribed to file
                                        suit/application or claim, it could be said at
                                        best that the claim is belated but if the present
                                        case even this plea appears to be
                                        impermissible."

           38.      I find no infirmity with the view expressed by the learned
           Arbitral Tribunal and, consequentially, find no merit in the above
           objection of the petitioner.
           39.      On the question of quantification of the claim, I would first
           quote from the Impugned Award:-
                                        "(i) Rates for carriage of material: The
                                        carriage charges have been taken from
                                        Haryana Schedule of Rates, Public Works
                                        Department, Haryana 1988 with premium
                                        applicable with effect from 31.10.2011 as per
                                        22.11.2011. The relevant pages of the same
                                        are annexed at page nos.705, 706 and 707 of
                                        the SOC. CD -5. The Independent Engineer
                                        has computed the rates based on the same for
                                        the year 2011 and has adopted the same rates
                                        for 2012-2013. The relevant page of the same
                                        is at page no.104 of the SOC. CD-1.

                                        The Claimant has also computed the rates as
                                        per the said Schedule of Rates & Premium
                                        applicable for the year 2011 and has adopted
                                        the same rates for subsequent years without
                                        any escalation thereon. The computation of
                                        carriage charges by the Claimant is at Page
                                        704 of the SOC and the said rates of 2011
                                        have been used to compute the amount for
                                        Claim No.1 which is at Page 686 of the SOC.
                                        CD-5.

                                        Even the Independent Engineer in its letter
                                        dated 15.04.2013, Annexure C-18 annexed at
                                        page no.101 of SOC. CD-1 has observed that
                                        "the carriage charges by mechanical means
                                        and loading & unloading of materials have
                                        only been taken from Haryana Schedule of
                                        Rate, Public Works Department, Haryana
                                        1988 with premium applicable with effect from
                                        31.10.2011 as per Haryana Public Works
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 20 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        Department (B&R) Memo No.7739-56 dated
                                        31.10.2011",

                                        Thus, the Claimant has used the minimum rate
                                        for the entire period in the computation of the
                                        Claim No.1.

                                        (ii) Lead distance for transportation of raw
                                        material:

                                        For GSB: So as to rationalize the claim
                                        amount, the Lead distance for transportation
                                        of raw material, can be taken as 113 Km,
                                        which is the average of 60 km, 90 Km and 190
                                        Km, as mentioned in Table 8.5 at page 8-11 of
                                        the Final Feasibility Report got prepared by
                                        the Authority, which is also attached as page
                                        61 of the Statement of Claims (CD-1):

                                        For Aggregate: The Lead distance for
                                        transportation of raw material should be taken
                                        as 75 Km, which is the average of 60 km and
                                        90 Km mentioned in Table 8.8 at page 8-13 of
                                        the Final Feasibility Report got prepared by
                                        Authority and attached with the Statement of
                                        Claims (CD-1) at page 63.

                                        For Sand: So as to rationalize the claim
                                        amount, the compensation for Sand need not
                                        be granted and thus, we are not inclined to
                                        include the same in the awarded amount."

           40.      A reading of the above would show that the learned Arbitral
           Tribunal has taken the rates from the Haryana Schedule of Rates,
           Public Works Department. The Arbitral Tribunal has also placed
           reliance on the report of the IE dated 15.04.2013 to conclude that the
           respondent had transported stone/GSB from Rajasthan. The Arbitral
           Tribunal has awarded the claim taking the lead distance as an average
           of what was provided in the final Feasibility Report. The approach
           adopted by the learned Arbitral Tribunal can in no manner be said to
           be perverse so as to warrant interference from this Court.

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                      Page 21 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           41.      As far as the submission of the learned senior counsel for the
           petitioner that in terms of the Government Order dated 21.04.2012,
           two small stone mines in District Mahendergarh were in operation and
           that the respondent should have sourced the stone and aggregate from
           the said mine rather than from Rajasthan, the same also cannot be
           accepted as falling within the scope of the limited grounds available
           with a party to challenge the Arbitral Award. As noted hereinabove,
           the learned Arbitral Tribunal has placed reliance on the report of the
           IE, which though was for the purpose of change in scope of work,
           admitted to the respondent procuring the stone/GSB from Rajasthan.
           42.      In view of the above, challenge of the petitioner to the grant of
           Claim No. 1 in favour of the respondent by the learned Arbitral
           Tribunal, is rejected.

           CLAIM NO. 2
           43.      As far as Claim no.2 is concerned, Article 14.3 of the
           Concession Agreement is relevant to the same, and is reproduced
           hereinbelow:-
                                        "14.3 Provisional Certificate

                                        14.3.1 The Independent Engineer may, at the
                                        request of the Concessionaire, issue a
                                        provisional     certificate    of     completion
                                        substantially in the form set forth in Schedule-
                                        J (the, "Provisional Certificate") if the Tests
                                        are successful and the Project Highway can be
                                        safely and reliably placed in commercial
                                        operation though certain works or things
                                        forming part thereof are outstanding and not
                                        yet complete. In such an event, the Provisional
                                        Certificate shall have appended thereto a list
                                        of outstanding items signed jointly by the
                                        Independent Engineer and the Concessionaire
                                        (the, "Punch List"); provided that the
                                        Independent Engineer shall not withhold the
                                        Provisional Certificate for reason of any work
Signature Not Verified                  remaining incomplete if the delay in
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                       Page 22 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        completion thereof is attributable to the
                                        Authority.

                                        14.3.2 The parties hereto expressly agree that
                                        a Provisional Certificate under this Clause
                                        14.3 may, upon request of the Concessionaire
                                        to this effect, be issued for operating part of
                                        the Project Highway, if atleast 75% (seventy
                                        five percent) of the total length of the Project
                                        Highway has been completed. Upon issue of
                                        such Provisional Certificate, the provisions of
                                        Article 15 shall apply to such completed part."
                                                                      (Emphasis supplied)

           44.      A reading of the above would show that though the PCC is to
           be issued if atleast 75% of the total length of project highway has been
           completed, it is also the condition of contract that the same would be
           issued only where the project highway can be „safely and reliably
           placed in commercial operation though certain works or things
           forming part thereof are outstanding and not yet complete.‟
           45.      The learned Arbitral Tribunal has placed reliance on the letter
           dated 18.09.2013 from the IE on the grant of PCC, and has held as
           under:-
                                        "...Then there is a mention of some
                                        outstanding work but the same was not
                                        towards the' safety of the road but was such
                                        that, may be required to be done as per the
                                        punch list.
                                                              xxxxx
                                        37. What further emerges from the
                                        observations and findings of the Independent
                                        Engineer is that all tests had been successfully
                                        carried out. The request of the Concessionaire
                                        was examined for grant of Provisional
                                        Certificate and 93.70% of the total work of the
                                        project had been completed. It is specifically
                                        mentioned by the Independent Engineer that
                                        93.70% is more than 75% of the total project
                                        length which is required to grant Provisional
                                        Certificate.

                                        38. We are not at all impressed with the
Signature Not Verified                  objections raised by the Respondent that some
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 23 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        items were still left to be worked out by the
                                        Claimants and therefore, the Provisional
                                        Certificate was not issued when the
                                        Independent Engineer made recommendations
                                        for the same. None of the items said to be not
                                        complete were such which may pertain to
                                        reliability and safety. Further, it is specifically
                                        provided that Provisional Certificate shall be
                                        issued when 75% of the work has been done
                                        even when some items may have been left out
                                        and may be completed later. We are also of the
                                        view that as per provisions contained in
                                        Article 14.3.1 the Independent Engineer was
                                        himself competent to issue Provisional
                                        Certificate and it was the Independent
                                        Engineer (and not NHAI) who was required to
                                        finally satisfy itself with regard to the project
                                        highway being capable of being safely and
                                        reliably being opened to traffic for commercial
                                        operations. Our observations made above get
                                        support from the observations made in Soma
                                        Isolux Kishangarh Beawar Tollway Pvt. Ltd.
                                        {Supra} and NHAI's letter dated 05.05.2015
                                        recognizing the effect of the aforesaid
                                        judgment."
                                                                     (Emphasis Supplied)


           46.      A reading of the above observations/findings of the learned
           Arbitral Tribunal would show that the learned Arbitral Tribunal has
           concluded that the said letter dated 18.09.2013 does not indicate any
           work outstanding towards the safety of the road.
           47.      For appreciating the above findings, the letter dated 18.09.2013,
           so far as it is relevant to the present petition, is reproduced
           hereinbelow:-
                                        "We have examined the request of the
                                        Concessionaire for grant of Provisional
                                        Completion Certificate from km. 0+000 to km.
                                        75+765. Our recommendations are as under:-

                                        As per clause no. 14.3.2 (Article 14), of
                                        Concession Agreement "The Parties hereto
                                        expressly agree that a Provisional Certificate
                                        under this clause 14.3 may, upon request of
Signature Not Verified
                                        the Concessionaire to this affect be issued for
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                          Page 24 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        operating part of the Project Highway, if at
                                        least 75% (seventy five per cent) of the total
                                        length of the Project Highway has been
                                        completed. Upon issue of such Provisional
                                        Certificate, the provisions of Article
                                        15(ENTRY INTO COMMERCIAL SERVICE)
                                        shall apply to such completed part."

                                        The Concessionaire has completed the project
                                        highway in a length of 75.765 (km 04000 to
                                        75+765) out of total project length of 80.858
                                        which is 93.70% of total project length. The
                                        completed 93.70% of the project highway is
                                        more than 75% of the total project length.

                                        xxxxx

                                        All the tests as required under Article 14 of the
                                        Concession Agreement to check the
                                        compliance of the project highway to the
                                        provisions of Schedule have been conducted in
                                        the presence of the I.E.'s representatives and
                                        Concessionaire's representative's. A list
                                        showing the status of various tests is enclosed
                                        as Annexure-I.

                                        3 lists of outstanding works of the Project
                                        Highway have been prepared after Joint
                                        Inspection by the Independent Engineer and
                                        Concessionaire on 16.08.2013, 17.08.2013
                                        and 04.09.2013 which are as under:-

                                                (i)     Appendix-A1 & A2 cover the
                                                        Items of work which the
                                                        Concessionaire will complete
                                                        before issue of Provisional
                                                        Completion Certificate.
                                                (ii)    Appendix B- The Punch list
                                                        covers items which do not affect
                                                        the safe Operation of the Project
                                                        Highway and will be completed
                                                        by the Concessionaire within 90
                                                        days of the issuance of the
                                                        Provisional          Completion
                                                        Certificate as per clause no.
                                                        14.4.1 (Article 14) Vol-I of
                                                        Concession Agreement.
                                                (iii)   Appendix-C covers Items of
                                                        works, which could not be
Signature Not Verified
                                                        undertaken    due     to    Land
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 25 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                                        Acquisition Issues and        for
                                                        reasons attributed to NHAI.

                                        The Concessionaire has confirmed vide their
                                        letter no. SEL/RP/SITE/IC/1424 dt. 05.09.2013
                                        that

                                                (i)     Items of Appendix-A1 & A2 will
                                                        be completed before issue of
                                                        Provisional          Completion
                                                        Certificate.
                                                (ii)    Items of Punch List Appendix-B
                                                        will be completed within 90 days
                                                        of the issue of Provisional
                                                        Completion Certificate.
                                                (iii)   Items of Appendix-C will be
                                                        completed as and when land is
                                                        made available by NHAI.

                                        xxxxx

                                        The provision of the Article 14.3 permit the
                                        Independent Engineer to Issue Provisional
                                        Certificate at the request of Concessionaire if
                                        the tests are successful as per Schedule „I‟ of
                                        CA and the Project Highway can be safely and
                                        reliably placed to commercial operation.
                                        However, the Clause 12 of TOR of the
                                        Independent Engineer Consultancy Agreement
                                        with NHAI requires IE to take prior approval
                                        of NHAI before the issuance of the Provisional
                                        Certificate. The prior approval for issuance of
                                        Provisional Certificate is being sought vide
                                        this letter to enable the Concessionaire to
                                        commence Commercial Operation at the
                                        earliest.
                                        The draft Provisional Certificate as per
                                        Schedule „J‟ of Concession Agreement for the
                                        completed part of the Project Highway is
                                        attached herewith for your kind perusal
                                        (Annexure-II).
                                        Based on the above facts we are of the opinion
                                        that Project Highway can be safely and
                                        reliably placed in Commercial Operation."
                                                                   (Emphasis supplied)


           48.      Appendix A-1 to the said letter is titled as under:-
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                        Page 26 of 29
                                        Neutral Citation Number: 2023/DHC/001137


                                        "ITEMS REQUIRED TO BE COMPLETED
                                        BEFORE   ISSUE   OF   PROVISIONS
                                        COMPLETION CERTIFICATE"

           49.      Similarly Appendix A-2 is titled as under:-
                                        "Items required to be completed before issue
                                        of Provisional Completion Certificate - As
                                        per Safety Consultant."

           50.      Clearly, therefore, by the above letter the IE had opined that the
           respondent shall have to complete the items of work mentioned in
           Appendix A-1 and A-2 to the said letter. The work mentioned in
           Appendix A-1 was to be completed by the respondent before issuance
           of PCC. It was based on the undertaking given by the respondent that
           these items will be completed before the issuance of the PCC, that the
           IE submitted the draft Provisional Certificate for the approval of the
           petitioner. The reliance of the learned Arbitral Tribunal on the said
           letter to conclude that no issue of safety was raised by the IE or that
           the said letter amounts to an unconditional opinion of the IE to the
           grant of Provisional Certificate to the respondent is, therefore,
           completely perverse and unfounded and against the bare reading of the
           letter itself. The opinion of the IE that the "Project Highway can be
           safely and reliably placed in Commercial Operation" was based on the
           undertaking of the respondent that it shall complete the work
           mentioned in Appendix A-1 to the letter before grant of PCC. It was
           therefore, conditional in nature and could not operate unless the
           respondent completes the work mentioned in Appendix A-1 to the
           letter to the satisfaction of the IE. The learned Arbitral Tribunal has,
           however, taken the said letter as an unconditional opinion of the IE
           that the PCC can be granted to the respondent. This finding, therefore,
           cannot be sustained.
Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                                   Page 27 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           51.      In fact, the learned senior counsel for the petitioner has also
           drawn my reference to the subsequent letter dated 25.10.2013 of the
           „Team Leader‟, which in turn records the Compliance Report of Pre-
           COD Safety Audit Report, and which in turn lists out certain items for
           which the IE has reported the work to be still in progress. The learned
           Arbitral Tribunal has ignored the said letter altogether. The said letter
           shows that even as on 25.10.2013 certain work to make the Project
           Highway safely and reliably to be put in Commercial Operation were
           pending at the end of the respondent.
           52.      The learned Arbitral Tribunal while awarding Claim no.2 has
           taken 15 days from the date of the above letter as the start point for the
           loss of revenue awarded to the respondent. In view of my observation
           hereinabove, the start point for award of the claim to the respondent is
           therefore, contrary to the evidence on record and cannot be upheld.
           53.      The learned counsel for the respondent, faced with the above,
           submitted that as Clause 14.3.2 provides that the PCC can be granted
           on completion of 75% of the Project Highway, whereas the
           respondent had sought the same on completion of 93.7% of the Project
           Highway, the work that was still remaining could not come in the way
           of grant of PCC to the respondent.
           54.      In my opinion, however, as the learned Arbitral Tribunal has
           not considered the above submission nor has rendered its findings
           based thereon; the same being a factual issue, it is not for this Court to
           adjudicate thereon and to hazard a guess thereon while exercising its
           jurisdiction under Section 34 of the Act. This plea was to be
           considered by the learned Arbitral Tribunal at the first instance and
           cannot be considered by this Court in absence thereof.

Signature Not Verified
Digitally Signed By:SUNIL
Signing Date:17.02.2023
17:37:01      O.M.P. (COMM) 286/2018                                              Page 28 of 29
                                        Neutral Citation Number: 2023/DHC/001137



           55.      In view of the above, the Impugned Award on Claim no.2, even
           applying even the limited jurisdiction that this Court possesses under
           Section 34 of the Act, cannot be sustained.

           RELIEF:
           56.      In view of the above, the challenge of the petitioner to the
           impugned Arbitral Award on Claim no.1 is rejected. The Impugned
           Award, so far as it grants Claim no.2 in favour of the respondent, is,
           however, set aside.
           57.      The petition is disposed of in the above terms.
           58.      There shall be no order as to costs.


                                                                         NAVIN CHAWLA, J.

FEBRUARY 16, 2023/rv/DJ Signature Not Verified Digitally Signed By:SUNIL Signing Date:17.02.2023 17:37:01 O.M.P. (COMM) 286/2018 Page 29 of 29