Section 2(44) in Joint Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2019
| (a) Wind energy power project | 25 years |
| (b) Biomass power project with Rankine cycletechnology | 20 years |
| (c) Small Hydro Plant | 35 years |
| (d) Municipal Solid Waste (MSW)/ and RefuseDerived Fuel (RDF) based power project | 20 years |
| (e) Solar PV/Solar thermal power project With orwithout Energy Storage | 25 years |
| (f) Hybrid Wind and Solar | 25 years |
| (g) Biomass Gasifier based power project | 20 years |
| (h) Biogas based power project | 20 years; |