Section 8(2)(d) in Andhra Pradesh Electricity Regulatory Commission (Standards of Performance) Regulations, 2000
(d)Connection shall be provided within the estimated time, as intimated, after deposit of estimated charges, submission of Test Report by consumers, inspection by Supplier's Engineer/Electrical Inspector and Agreement, if required. The licensee shall, however, not be held responsible for delay, if any, for providing connection, if the same is on account of statutory clearances, rights of way, acquisition of land over which licensee has no reasonable control.