Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 0]

Orissa High Court

Executive Engineer vs Grievance Redressal Forum on 29 September, 2014

Author: B.K. Patel

Bench: B.K. Patel

                    HIGH COURT OF ORISSA : CUTTACK.
                                W.P.(C) NO.28024 of 2013

     In the matter of an application under Articles 226 and 227 of the
     Constitution of India.

                                           -------
     Executive Engineer,
     Rourkela Electrical Division, WESCO,
     Rourkela, Dist. Sundargarh                             ......     Petitioner

                            -    Versus-


     Grievance Redressal Forum,
     Rourkela, Plot No.UU/9 Civil Township,
     Rourkela, Dist. Sundargarh and another                 ...... Opposite Parties

                  For Petitioner      :      M/s. B.K. Nayak-1 and
                                                  D.K. Mohanty
                  For Opp. Parties    :      M/s. Sreejit Mohanty,
                                                  Debraj Mohanty and
                                                  A.K. Nath (O.P.2)

     PRESENT:

                    THE HONOURABLE SHRI JUSTICE B.K. PATEL
          Date of Hearing: 01.07.2014 :: Date of Judgment - 29.09.2014


B.K. PATEL,J.     In this writ petition, the petitioner representing distribution

    licensee WESCO, has assailed the legality of order dated 11.11.2013 passed

    by Grievance Redressal Forum, Rourkela (for short 'the GRF') in Case No.57

    of 2013 in which it was held that claim of the petitioner of reliability

    surcharge in the energy bills for the months of May and June, 2013 from

    opposite party no.2 was unjust and the petitioner was directed to revise the

    energy bills of opposite party no.2 for the months of May and June, 2013

    waiving out the reliability surcharge from the bills.
                                          2
2.           Opposite party no. 2, situated at Kalunga Industrial Estate, is

a mini steel plant, having contract demand of 2600 KVA, availing power

supply from the industrial feeder which emanates from 132/33 KV grid

substation on the strength of agreement dated 20.6.2012 at Annexure-1

entered into with WESCO.          Clauses-6 and 7 of the agreement at

Annexure-1 read as follows:

             "(6)   Charges to be paid by the Consumer:              The
             Consumer shall pay to the Engineer for power demanded
             and electrical energy supplied under this agreement
             minimum monthly charges, 'demand charges', 'energy
             charges' and 'other charges' in accordance with the
             provisions of OERC Distribution (Conditions of Supply)
             Code, 2004 and as notified in the Tariff Notifications from
             time to time:
                     In Large Industry category.
                     Provided that annual sum payable by any individual
             consumer under the provision to Section 45 of the Indian
             Electricity Act, 2003, shall not be deemed to be part of the
             minimum monthly charges or demand charges, if any,
             payable by the consumer or the particular class of
             consumers under Regulations 84 and 85 of the OERC
             Distribution (Conditions of Supply) Code, 2004.
                     Provided further that the consumer shall pay
             electricity duty or such other levy, tax or duty as may be
             prescribed under any other law in addition to the charges,
             fuel surcharge and transformer loss payable under the
             OERC Distribution (Conditions of Supply) Code, 2004.

             (7)    The tariff and conditions of supply mentioned in
             this Agreement shall be subject to any revision that may
             be made by the Licensee from time to time."

 Thus, Clause-6 of the agreement specifically provides that opposite party

 no.2 is liable to pay, apart from minimum monthly charges, demand

 charges and energy charges, 'other charges' in accordance with provisions

 of the Orissa Electricity Regulatory Commission Distribution (Conditions

 of Supply) Code, 2004 (for short 'the OERC Code) and as notified in the

 Tariff Notifications from time to time in Large Industry category. Orissa

 Electricity Regulatory Commission (for short 'the OERC) Tariff Orders or
                                             3
Notifications did not provide for 'reliability surcharge' earlier. However,

reliability surcharge was made leviable on high end consumers under

certain conditions as provided under paragraph 196 in the OERC Tariff

Order for the financial year 2013-14 (for short 'the Tariff Order') which

came into effect from 1.4.2013. Paragraph 196 of the Tariff Order read as

follows:

               "196. Reliability Surcharge
                       Many concerns, basically HT/ EHT Industries
               brought to the notice of the Commission regarding
               uninterrupted quality power supply to their units. Many
               process industries particularly connected with the
               dedicated feeders from the Grid of OPTCL and Primary
               sub-station of DISCOMs objected to the restrictions being
               imposed on their units by the DISCOMs in case of exigency
               with or without the express intimation of SLDC. While
               there is a need to supply uninterrupted power to high end
               HT/EHT consumers this has to be viewed in the overall
               perspective of a situation of system unavailability / power
               deficit where a large number of ordinary consumers suffer
               power cut during peak hours and also sometimes during
               the summer months. The Commission is, therefore, of the
               view that for getting uninterrupted power supply in this
               adverse scenario the high end consumer must compensate
               the DISCOMs who may otherwise would have imposed
               power cuts on those consumers. Therefore, we introduce a
               concept of reliability surcharge in this tariff order for FY
               2013-14. The reliability surcharge shall be payable to
               start with such HT and EHT consumers who get power
               supply through dedicated feeders from OPTCL Grid sub-
               station or from the primary 33/11 KV sub-station of
               DISCOMs. The reliability surcharge shall be 20 paise per
               unit for all the units consumed by such HT and EHT
               consumers in the billing month. This surcharge is leviable
               over and above the bill amount based on normal tariff for
               that category of consumers after the rebate and penalty if
               any. The reliability surcharge is leviable provided following
               two conditions are satisfied.
           (a)         If Reliability Index formula which is given below is at
               or more than 99 % in a month.
                       Reliability Index for dedicated feeder for the month
                       [1      SAIDI for the dedicated Feeder ] x 100
                               24 x 60 x nos. of days in the month
                                              and
           (b)         The voltage variation at the consumer premises is as
               per Section 2.1 (Schedule 1) of OERC (Standard of
               Performance) Regulation, 2004. (underline supplied)
                                          4
            DISCOMs shall also attach the reliability index calculation
            and voltage variation report with the bill in case of levy of
            reliability surcharge. They are not required to pay any
            charges for this report to be attached with the bill. We also
            direct M/s. OPTCL to co-operate for ensuring
            uninterrupted power supply without restriction to such
            consumers." (underline supplied)

3.          In purported exercise of authority to impose reliability

surcharge under paragraph 196 of the Tariff Order, WESCO levied

reliability surcharge on opposite party no.2 in its energy bills for the

months of May and June, 2013.          Opposite party no.2 filed complaint

bearing Case No.57 of 2013 challenging imposition of reliability surcharge

on the ground that pre-conditions for levy of reliability surcharge as

provided at paragraph 196 of the Tariff Order do not exist inasmuch as

opposite party no.2 does not get power supply through dedicated feeder

from OPTCL grid sub-station or from the primary 33/11 KV sub-station of

the WESCO.        WESCO filed objection against the complaint. On

consideration of rival contentions and materials on record the GRF passed

the order impugned in this writ petition on the basis of following findings:

                    "Tariff order of OERC for the FY 2013-14 at Para-
            196 speaks about reliability surcharge for HT and EHT
            consumer.        Para-196 speculates that, the reliability
            surcharge shall be payable to start with such HT and EHT
            consumer who get power supply through dedicated feeder
            from OPTCL Grid substation or from the primary 33/11
            KV substation of DISCOMs. The reliability surcharge shall
            be 20 paisa per unit for all the units consumed by such HT
            and EHT consumers in the billing month. This such as is
            leviable or all above the bill amount based on normal tariff
            for that category of consumers after the rebate and penalty
            if any.
                    From the above tariff order this forum
            understands that, getting power supply through
            dedicated feeder is a prerequisite for the purpose of
            claiming reliability surcharge. In the instant case the
            petitioner is getting power supply from 33 KV, Kalunga
            feeder emanating from 132/33 KV Grid substation,
            Rourkela which is not a dedicated feeder from OPTCL Grid
            to the petitioner's industry. Around 15 Large Industries
                                         5
            consumers are also getting power supply from the said
            feeder as per the documents submitted by the Distribution
            Licensee."


Thus, the GRF recorded the finding that opposite party no.2 is getting

power supply from 33 KV, Kalunga feeder emanating from 132/33 KV grid

substation which is not a dedicated feeder from OPTCL grid to the

petitioner's industry inasmuch as around 15 Large Industries consumers

are also getting power supply from the said feeder as per the documents

submitted by the WESCO. In such circumstances, opposite party no.2

does not satisfy the first prerequisite under paragraph 196 of the Tariff

Order for getting power supply through dedicated feeder so as to be liable

for payment of reliability surcharge.

4.          It is not disputed that opposite party no.2 is getting power

supply through feeder emanating from 132/33 KV grid substation,

Rourkela through which feeder other Large Industries consumers are also

getting power supply. Opposite party no.2 does not dispute that reliability

index was more than 99 per cent and voltage variation was as per Section

2.1 (Schedule I) of the OERC (Standard of Performance) Regulation, 2004

(for short 'the OERC Regulation') during the months of May and June,

2013.


5.          It was contended by the learned counsel for the petitioner

that the GRF has committed illegality in holding that opposite party no.2

does not get power supply through dedicated feeder. Placing reliance on

the decision of the Madhya Pradesh High Court in K.S. Oils Ltd. -vrs.-

Madhya Pradesh Kschetra Vidut Vitran Company Ltd., Bhopal &

others: AIR 2013 Madhya Pradesh 167 it was argued that a dedicated
                                         6
feeder does not mean that it can be used only by a single consumer to run

its unit. It was further argued that in the present case power supply has

been given through the same feeder to the opposite party no.2 and other

similar industrial units only. No supply of power is given through the

feeder to any general consumer. There being no dispute that power supply

to opposite party no.2 industry fulfills the criteria of reliability index as

well as the standard of voltage variation as provided under sub-

paragraphs (a) and (b) of paragraph 196 of the Tariff Order, reliability

surcharge was rightly levied.

6.          Per contra, it was contended by the learned counsel for

opposite party no.2 that the first and foremost prerequisite for levy of

reliability surcharge is supply of power through a dedicated feeder as is

evident from paragraph 196 of the Tariff Order. The provision for levy of

tariff is essentially a fiscal provision for which it is to be construed

strictly. Paragraph 196 of the Tariff Order presupposes fulfillment of three

conditions for levy of reliability surcharge. The very first condition is that

reliability surcharge shall be payable by such HT and EHT consumers

who get power supply through dedicated feeder from OPTCL grid

substation or from the primary 33/11 KV substation of DISCOMs.

Secondly, the reliability index must be more than 99 per cent. Third

condition is that the voltage variation on the consumers' premises must

be as per Section 2.1 (Schedule I) of the OERC Regulation. Distribution

licensee cannot levy reliability surcharge in the absence of any of the

three conditions. It was submitted that the term 'dedicated feeder' has

not been defined either in the Electricity Act, 2003, or any of the Rules,
                                        7
Regulations or Code applicable to Odisha including the OERC Code. In

the Tariff Order also the term 'dedicated feeder' has not been defined. In

ordinary parlance 'dedicated feeder' means a feeder which is connected to

a single consumer. Even the OERC Code envisages supply of electricity

through a feeder to a single consumer. Regulation 27 of the OERC Code

provides for arrangement agreed to in writing for providing service line for

exclusive use of a consumer.       Admittedly, the feeder through which

opposite party no.2 gets electricity supply has not been agreed upon to be

used exclusively by opposite party no.2. It was further submitted that

Regulation 2(f) of the Andhra Pradesh Electricity Regulatory Commission

provides that 'dedicated feeder' means feeder emanating from substation

where transformation to the required voltage takes place and feeds power

to a single consumer having contracted capacity of minimum fifty percent

of line capacity or more. Similarly, Regulation 5.3 of the Meghalaya State

Electricity Regulatory Commission provides that the licensee shall not

extend electric supply to any other consumer from the dedicated feeder.

Clause 24 of Kerala Electricity Supply Code, 2014 provides that the

service line and other equipment of a consumer with a dedicated feeder

shall not be used to supply power to another consumer. Referring to

paragraphs-6 and 11 of the judgment of the Appellate Tribunal For

Electricity, New Delhi passed in Appeal No.109 of 2011 in the case of

Maharashtra     State    Electricity   Distribution     Co.   Ltd.    -vrs.-

Maharashtra Electricity Regulatory Commission and R.L. Steels Ltd.

(MANU/ET/0132/2011)       it was argued that dedicated feeder has been

specifically referred to by the Appellate Tribunal for Electricity to be a
                                         8
feeder where only one consumer is connected. It was further argued that

all licensees under the Electricity Act are obliged to ensure uninterrupted

quality power supply without voltage fluctuation or variation to the

consumers. The consumer is not liable to pay any surcharge for availing

services which licensees are obliged to provide.    Reliability surcharge is

envisaged by the OERC to be levied only on such HT and EHT consumers

who get such quality supply through dedicated feeders. It cannot be levied

on a consumer whenever in a particular month reliability index and

voltage variation are in accordance with the standard prescribed in sub-

paragraphs (a) and (b) of paragraph 196 of the Tariff Order, irrespective of

the manner of use of the feeder.

7.          From the admitted facts as well as averments and rival

contentions made by the parties, it is evident that the petitioner

distribution licensee also does not dispute that supply of electricity

through a dedicated feeder is an essential prerequisite for levy of

reliability surcharge. However, in spite of the fact that as many as about

fifteen other Large Industries consumers are getting power supply

through the same feeder, learned counsel for the petitioner contended

that such feeder is a dedicated feeder. On the other hand, case of opposite

party no.2 is that electricity supply is not given through a dedicated

feeder. Therefore, the only issue which requires to be decided in this case

is as to whether the feeder through which opposite party no.2 is getting

electricity supply is a dedicated feeder or not.


8.          None of the statutory provisions or Rules and Regulations

applicable to the State of Odisha including the OERC Code provide for the
                                         9
definition of the term 'dedicated feeder'. As has been stated at paragraph

196 of the Tariff Order, the fiscal concept of levy of reliability surcharge

was introduced to start with such HT/EHT consumers who get power

supply through dedicated feeders from OPTCL grid substation or from the

primary 33/11 KV substation of DISCOMs. Learned counsel for the

petitioner vehemently argued that the term 'dedicated feeder' has to be

assigned the meaning as assigned by the Madhya Pradesh High Court in

K.S. Oils Ltd. -vrs.- Madhya Pradesh Kschetra Vidut Vitran Company

Ltd., Bhopal & others (supra) in which the sole question before the Court

was as to whether distribution licensee can be allowed to provide power

supply to any other consumer from the dedicated feeder provided to the

appellant at appellant's cost. Upon reference to Clause 5.3 and placing

reliance upon clause 4.9 of the M.P. Electricity Supply Code, 2004 (for

short 'the M.P. Code'), the question was answered in the affirmative.

Clause 5.3 of the M.P. Code reads as follows:

            "5.3 Consumers desirous of getting power supply from
            dedicated feeders may request for such facility to the
            licensee. The dedicated feeder shall be extended from the
            Power Sub-station to the consumer's point of supply. In
            such cases the consumers shall be liable to pay the cost of
            Bay and all protection Switchgears and its accessories
            provided at the power sub-station for this feeder in
            addition to the cost of the feeder. On receipt of such
            request, the licensee will check the feasibility based on
            merits of providing a dedicated feeder to the consumer's
            premises. It found feasible, the consumer will be provided
            with a dedicated feeder and the consumer will be liable to
            pay additional charges as indicated in the Schedule of
            Miscellaneous Charges."

Thus, it is evident that Clause 5.3 of the M.P. Code simply provides for

modalities for providing dedicated feeder to a consumer. It is not a fiscal

provision. Clause 4.9 of the M.P. Code reads as follows:
                                          10
            "4.9 The service connection/extension of distribution
            mains, notwithstanding that it has been paid for by the
            consumer, shall be the property of the licensee. The
            licensee shall maintain it at its cost and shall also have the
            right to use the same service connection/ extension for
            supply of energy to any other person but such extension or
            service connection should not adversely affect the supply
            to the consumer who paid for the extension of the
            distribution supply network."

Thus, Clause 4.9 of the M.P. Code explicitly provides that service

connection/ extension, cost of which has been paid by the consumer, can

be permitted by the licensee to be used for supply of energy to any other

person. In such circumstances, it was held that the licensee may provide

connection to any other consumer from the feeder installed in accordance

with Clause 5.3 of the M.P. Code.

9.           In absence of any definition, the term 'dedicated feeder',

understood in ordinary parlance, means a feeder provided for the

exclusive use of a consumer. In the present case, admittedly, the feeder

through which opposite party no.2 is getting power supply is used for

power supply to other industries also. Provision for levy of reliability

surcharge introduced for the first time during the financial year 2013-14

is a fiscal provision intended to levy the surcharge as one of the 'other

charges' in terms of Clauses 6 and 7 of the agreement dated 20.6.2012 at

Annexure-1 entered into between the parties.               Therefore, the term

'dedicated feeder' has to be given a strict interpretation.


10.          Learned counsel for opposite party no.2 has brought to the

notice of the Court definition of the term 'dedicated feeder' assigned by the

Electricity Regulatory Commissions of some other States.
                                          11
11.         Regulation 2(f) of the Andhra Pradesh Electricity Regulatory

Commission provides as follows:

            "(f) "Dedicated Feeder" means feeder emanating from
            substation where transformation to the required voltage
            takes place and feeds power to a single consumer having
            contracted capacity of minimum fifty percent of line
            capacity or more. The Consumer shall bear the full line
            cost, including take off arrangements at Substation end of
            the Licensee. In such cases the billing meter shall be
            provided at the Licensee's sub-station." ( underline
            supplied)

12.         Regulation 5.3 of the Meghalaya State Electricity Regulatory

Commission provides as follows:

            "5.3    Dedicated Feeder
                    Consumers other than 3 MVA & above including
            steel and other similar industries desirous of getting power
            supply from dedicated feeder may make a request for such
            facility to the licensee. The dedicated feeder shall be
            extended from the power substation to the consumer's
            point of supply. In such cases the consumers shall be
            liable to pay the cost of Bay and all protection switchgears
            and its accessories provided at the power substation for
            this feeder in addition to the cost of the feeder. On receipt
            of such request, the licensee will check the feasibility,
            based on merit, of providing a dedicated feeder to the
            consumer's premises. If found feasible, the consumer will
            be provided with a dedicated feeder and the consumer will
            be liable to pay additional charges such as supervision
            charges, etc. as approved by the Commission from time to
            time. The Licensee shall not extend electric supply to any
            other consumer from the dedicated feeder." (underline
            supplied)

13.         Similarly, Clause 24 of the Kerala Electricity Supply Code,

2014 provides as follows:

            "24. The service line, meter and associated equipment
            deemed to be the property of the licensee.- (1) The
            whole of service line, meter and other associated
            equipment shall be deemed to be the property of the
            licensee and shall remain under his control so long as they
            are connected to the distribution system of the licensee.
            (2)     The licensee may use the service line and other
            apparatus to give supply to other consumers, if the supply
            to the consumer who has paid for such line and apparatus
            is not affected adversely:
                                          12
                   Provided that the service line and other equipment
            of a consumer with a dedicated feeder shall not be used to
            supply power to another consumer.
            (3) Even if the supply to the consumer who has paid for
            the line or equipment is disconnected, for whatsoever
            reason, the consumer shall permit the licensee, continued
            access to the service line and other equipment if they are
            required to give supply to other consumers, until alternate
            arrangements are made by the licensee:
                   Provided that no payment shall be due to the
            consumer for such access or facility.
            (4)    The licensee shall make all possible efforts to
            provide alternate arrangement or mutually acceptable
            arrangement for continuation of the installation at the
            existing place, as early as possible." (underline supplied)


14.         Appellate Tribunal for Electricity, New Delhi, constituted

under Section 110 of the Electricity Act, 2003 at paragraphs 6 and 11 of

the order passed in     Maharashtra State Electricity Distribution Co.

Ltd. -vrs.- Maharashtra Electricity Regulatory Commission and R.L.

Steels Ltd. (supra) has observed as follows:

            "6.     On 13.11.2009, the Appellant submitted a petition
            being Case No.71 of 2009 before State Commission praying
            for allowing the Appellant to levy of low voltage surcharge to
            consumers connected on non-express feeders (more than
            one connection on the said feeder) at voltages lower than
            that specified in Standard of Performance Regulations. The
            Appellant also prayed that in case of dedicated feeders
            (where only one consumer is connected), the Appellant may
            be allowed to charge on the basis of consumption recorded
            by meters installed at sending end and receiving end
            whichever is higher.
            Xx           xx            xx            xx            xx
            Xx           xx            xx            xx            xx

            11.    The State Commission disposed of this petition in
            Case No.52 of 2010 through a Clarificatory order dated
            9.11.2010

. In this order, the State Commission clarified that under its Order dated 5.3.2010 the levy of 2 % extra units cannot be made if the power supplied was connected on dedicated feeder (only one connection on the said feeder). Levy of 2 % extra units was applicable only if consumer is connected on non-dedicated feeder (more than one connection on the said feeder)." (underline supplied) 13 Thus, the Appellate Tribunal For Electricity has clearly assigned the meaning of 'dedicated feeder' to be a feeder to which only one consumer is connected.

15. It is not disputed that the feeder through which opposite party no.2 gets power supply has never been agreed upon by the parties either in the agreement at Annexure-1 or in any subsequent instrument to be used exclusively by opposite party no.2. That goes to indicate that it was never meant to be a dedicated feeder. A close reading of paragraph 196 of the Tariff Order would reveal that the concept of reliability surcharge was introduced in view of objection raised by industries particularly connected with "dedicated feeders" from the Grid of OPTCL substation and primary substation of DISCOMs. Considering objections and the scenario of the system of availability/power deficit the OERC introduced the concept of levy of reliability surcharge to be payable, to start with, such HT and EHT consumers who get power supply through dedicated feeders. Thus, reliability surcharge was levied on the basis of objections raised by a class of consumers availing power supply through dedicated feeders to be payable by such HT and EHT consumers who get power supply through dedicated feeders. The expression "dedicated feeders" occurs twice in paragraph 196 of the Tariff Order. In the absence of any definition of the expression "dedicated feeder" provided under the Statues, Rules, Regulations or the OERC Code, the OERC ought to have provided for a precise definition or meaning of the term "dedicated feeder"

in the Tariff Order itself. That having not been done, no fault can be found with the meaning of the expression "dedicated feeder' assigned by 14 the GRF in the impugned order, such meaning being in consonance with the meaning and definition of "dedicated feeder" assigned by Electricity Regulation Commissions of other States as well as the Appellate Tribunal for Electricity which are essentially expert technical bodies. The meaning sought to be assigned by the petitioner to the term "dedicated feeders"

would render the use of expression "dedicated feeders" by the OERC in paragraph 196 of the Tariff Order redundant. In the facts and circumstances of the case, the GRF has rightly held that the petitioner is not entitled to claim reliability surcharge from the opposite party no.2.

16. In view of the above, there is no merit in the writ petition. Accordingly, the writ petition is dismissed.

.......................

B.K. Patel, J.

Orissa High Court, Cuttack, Dated 29th September, 2014/B. Jhankar