Jharkhand High Court
Ms Zoom Developers P Ltd Through Its ... vs The Jharkhand State Electricity Board ... on 7 January, 2016
Author: D.N. Patel
Bench: D.N. Patel
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Arb. Application No.16 of 2014
M/s. Zoom Developers (P) Ltd., a Company incorporated under the
Indian Companies Act, 1956, having its registered Office at 7th
Floor, Chetak Centre, 12/2, R.N.T. Marg, P.O. GPO, P.S.: South
Tukogunj, Town: Indore 452001, Dist: Indore, Madhya Pradesh
through its Assistant General Manager Rupendra S Patwardhan, S/o
Shri S R Patwardhan, aged about 51 years, R/o 'SMRUTI' 1st Floor,
Ram Maruti Road, PO & PS Naupada, Thane (West) 400 602,
Maharashtra.
... ... ... Appellant
Versus
1. The Jharkhand State Electricity Board through its Chairman
2. The Managing Director, M/s Jharkhand Urja Sancharan Nigam
Limited, Dhurwa, Ranchi
3. The Chief Engineer (Transmission), Jharkhand State Electricity
Board, Dhurwa, Ranchi
4. The General Manager (Special Projects), Jharkhand State
Electricity Board, Dhurwa, Ranchi
... ... ... ... ... ... Respondents
CORAM: HON'BLE MR. JUSTICE D. N. PATEL
For the Petitioner: Mr. Manish Mishra
For the Respondents: J.C. to A.A.G.
05/Dated: 07th January, 2016
Per D.N. Patel, J.
1) This application has been preferred under Subsection (6) of Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an Arbitrator in pursuance of Clause 3.8 of the Agreement, arrived at between the parties, which is at Annexure 1 to the Memo of this Arbitration Application.
2) Having heard learned counsels for both sides and looking to the facts and circumstances of the case, it appears that the dispute 2 arose between the applicantContractor and the respondents and there being an arbitration clause, notice has already been given by the applicant, which is Annexure 18 to the Memo of this Arbitration Application. The said notice is dated 20th June, 2014 and despite this notice, no Arbitrator has been appointed by the respondents and, hence, I hereby appoint Hon'ble Mr. Justice Amareshwar Sahay (Former Judge of this High Court) as an Arbitrator to resolve the dispute between the parties.
3) Learned Arbitrator is requested to resolve the dispute between the parties as early as possible, preferably within a period of six months from the date of commencement of the arbitration proceedings.
4) Both the parties have agreed that they shall cooperate in the hearing before the learned Arbitrator and they shall not ask for any unnecessary adjournments.
5) This Arbitration Application is allowed and disposed of.
Manoj/ (D. N. Patel, J)