State of West Bengal - Section

Section 28 in Kolkata Municipal Corporation Building Rules, 2009

28. Completion Certificate.

(1)Within fifteen days of the receipt of notice of completion of building work, the Municipal Commissioner shall inspect the building or work and shall satisfy himself that the erection or the execution of the work has been completed in accordance with completion plan.
(2)Within ten days of inspection, the Municipal Commissioner shall, if he is satisfied that the building or work has been completed in accordance with the completion plan issue a completion certificate in the form as specified in Schedule XIII :Provided that such certificate shall not be issued in the case of building or any work for which provisional sanction was given unless the applicant produces before the Municipal Commissioner the license or permission in accordance with sub-section (3) of section 396 and documents recording compliance of the terms and conditions of such provisional sanction.
(3)After due verification, one set of the building plan as submitted under rule 27 shall be returned to the applicant with the endorsement "Approved Completion Plan", under the signature of the Municipal Commissioner.
(4)In case where the Completion Certificate is refused, the Municipal Commissioner shall communicate the reasons thereof in writing to the applicant within a reasonable time of inspection under sub rule (1) above.
(5)In case where in the opinion of the Municipal Commissioner the building or the work has not been completed in accordance with the completion plan he may take necessary action in accordance with the provisions of the Act and rules.
(6)The Municipal Commissioner shall not permit connections to be made to municipal water mains and municipal drains-from any new building in respect of which Completion Certificate has not been issued;Provided that the Municipal Commissioner may permit connections to be made in respect of a building where Partial Completion Certificate or Block wise Completion Certificate has been issued as per provision of rules 29 and 30.Provided further that the Municipal Commissioner may order disconnection of such connections if he is of the opinion that the conditions of the Partial Completion Certificate or Block wise Completion Certificate are being violated or if further erection of the building or execution of the work is proceeding contrary to the sanctioned plans.