Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 13, Cited by 0]

National Green Tribunal

Asgar Ahmad Najar vs Ministry Of Environment Forest And ... on 18 November, 2024

Item No. 11                                                            Court No. 2

                  BEFORE NATIONAL GREEN TRIBUNAL
                    PRINCIPAL BENCH, NEW DELHI


                      Original Application No. 706/2022
                              ( IA NO 260/2022 )



ASGAR AHMAD NAJAR                                                      Applicant

                                   Versus


Ministry of Environment Forest
and Climate Change                                              Respondent(s)



Date of hearing: 18.11.2024


CORAM:        HON'BLE MR. JUSTICE SUDHIR AGARWAL JUDICIAL MEMBER
              HON'BLE DR. AFROZ AHMAD, EXPERT MEMBER


Applicant:     Mr. Rahul Proxy Counsel for Mr. Amit Jain, Counsel for Applicant
              (through VC)

Respondents: Mr. Debarshi Bhadra, Advocate for Respondent No. 7
             Mr. Vijay Nair and Mr. Karan Rajpurohit, Advocates for Respondent No. 8
             Mr. Ghansham Singh, Member Secretary JKPCC (through VC)




                                      ORDER

1. The applicants have filed present application under Section 18 of National Green Tribunal Act, 2010 read with Rule 8 of National Green Tribunal (Practice and Procedure) Rules, 2011 with the prayer inter alia for directing respondent no. 2 to cancel NOC granted to respondent 8 and directing respondents 7 and 8 to immediately stop discharging of waste material over the land of applicant and Pathway, School and install proper water disposal mechanism.

2. The applicant has submitted that respondent 8, under the aegis of respondent 7, has installed a Benching Plant (Cement concrete USBRL 1 Project T-77 D, Tunnel) in the mid of residential area at Village Channar, Bankoot, District Ramban, Jammu and Kashmir. The respondent 8 is continuously emitting highly toxic chemicals, which is causing huge damage to the flora and fauna including agricultural land and fruit bearing trees in the adjoining area. Respondent 7 is continuously discharging waste material over the land of applicants, pathways, streets which makes the land unfit for cultivation and causes blockage to the public way and routes of Alam Shah Convent School, Adnam Academy Banihal and the Anganwadi Centre. Due to tunnel work and explosions conducted by respondents 7 and 8, the houses of the applicants and other inhabitants got cracks in their walls because of dangerous vibrations.

3. Tribunal issued notices to respondents 2, 4, 7 and 8 requiring them to file their responses vide order dated 28.09.2022. It also constituted a Joint Committee to verify factual position and submit report. Joint Committee report dated 15.12.2022 was filed giving factual position as under:-

"2.1. Verification and Factual Report of the Joint Committee:
The matter was examined by the Joint Committee from Environmental angle and as directed by Hon'ble National Creen Tribunal, point-wise factual report prepared based on the physical verification and record made available to the Joint Committee, is submitted as follows:
S. Grievance of the Applicant Verification and Factual Report of No. as filed in the OA No. 706 of the Joint Committee as on 2022, by the applicant. l6/11/2022 along with suggested remedial measures.
1. The benching plant installed by The settling tank for settling the solid the respondent No. 7 and 8 has inorganic waste has been provided, for no water disposal mechanism primary treatment of in place and all the waste waste water generating from the material generated from the batching plant as on 16/11/2022.

Unit is being discharged over However, the examination of record the land of the applicant.

provided by Divisional Office of JKPCC, 2 indicates that the facility for primary treatment of the waste water generated have been inadequate in the past upto 16/8/2022 (Letter No.PCC/DO/Rbn/2022/66 dated 21/7/2022 attached as Annexure-3 and Letter No, PCC/RD-J/2022/1288/2830-32 dated 16/8/2022 attached asAnnexure-4), thereby confirming that the pre-

treatment/sedimentation tank of batching plant was of inadequate size and also project proponent was non-complaint before 16/8/2022 and the tunnel waste water without any proper treatment, was being discharged into the nearby drain (concrete lined except pathways/ /crossing points), leading lo agriculture land. The physical condition of the land as verified by the Joint Committee also indicated the same (Photograph-1 of Annexure-6).

J&K PCC is required to take action for non- compliance of the terms & conditions of the Consent to Operate (CTO) and the directions given to the project proponent.

2. The waste water also flows During visit to the site, this point was through the pathways streets verified by the Joint Committee make it difficult for the public to (Photograph 2 & 3 of Annexure-6) walk on the streets as wells as and to avoid this problem, either ramps also makes hindrance for the or closed pipes are required to transport the waste water at the points where school going children.

waste water is crossing the pathways/crossing points.

3. The respondent No. 7 and 8 It was observed by the Joint Committee have not made any proper way that the to handle the chemicals and steel 3 fibre, slash etc and the water water accumulated in the tunnel under from the tunnel (de- reference is muddy/slushy due to the construction activities winterization).

and movement of vehicles engaged in the construction activities in the main tunnel, and is pumped outside through tunnel T-77A and discharged on down slope natural drainage passing through one side of the village into the Bishleri Nallah.

In this regard, the record shared by the concerned Divisional Office of JKPCC indicates that this site was previously visited by JKPCC team and it was found that the water from de-watering of the tunnel and is discharged into the small nallah/ drain which passes through the nearby village (Letter No. PCC/DO/Rbnl2022/66 dated 21/7/2022 attached asAnnexure-3).

Subsequently, a letter was also issued by JKPCC to the project proponent asking them to construct settling tanks of adequate sizes outside the face of the tunnel and at the batching plant so that slush etc is settled and removed at regular intervals (Letter No, PCC/RD-J 12022/ 128812830-32 dated 16/8/2022 attached as Annexure-4).

During the verification of the factual position by the Joint Committee, it was observed that while the project proponent has provided the settling tank for the batching plant (Photograph- 4 of Annexure-6), no arrangement/ settling tanks have been provided for the muddy water coming out of the tunnel as on 16/112022 and the muddy water is still going in the nearby nallah/drain and also on the pathways/crossing points being used by villagers (Photograph-5 of Annexure-6), leading 4 to the village pathways and the land in the village Chanar Bankoot Village, Tehsil Banihal, District Ramba (Photogruph-6of Annerure-6). Therefore, it may be concluded that the project proponent is yet to comply with the directions/advice of J&KPCC to prevent damage to the public health and soil environment.

J&K PCC is required to take action for non- compliance of the directions issued to Project Proponent so that the tunnel work is performed with the compliance of prescribed norms/directions of J&K PCC.

4. The illegal activities of It was observed by the Joint Committee Respondent No.7 &8 have that the resulted in creation of a huge village Chanar Bankoot, tunnel T-77 A dumping ground which can fall and batching plant are at lower anytime and may cause elevation than the existing Tatnihal- damage Banihal road maintained by IRCON International Ltd. The project proponent to the whole village.

has constructed an approach road in the acquired land towards batching plant and tunnel T-77Aby dumping the muck at the junction for the purpose of widening it so that the construction vehicles can easily reach the site.

However, al the same time, as apprehended by the applicant, it is true that if it slides due to any reason, this may cause damage on down slopes since proper retaining wall is not provided by the project proponent so for (Photograph-7 of Annexure-6.

Therefore, a retaining structure such as gabions/crate wall to retain the muck dumped for construction of approach rood on upper side of the village is needed badly to avoid any untoward 5 incident, leading lo loss of property or life.

"

4. Joint Committee report also made some observations in respect of other aspects, as under:-

"2.2. Other Observations made by the Joint Committee:
1. lt was informed by the representative of the Project Proponent that the Project Proponent namely M/s ABCI Infrastructure Ltd is at present executing the construction of balance work for Tunnel T-77D (Km 146.60 to 148.36 approx.) awarded by IRCON INTERNATIONAL Ltd. on Katra-Banihal section of Udhampur-

Srinagar-Baramula Rail Link (USBRL) project. Due to the change in alignment of the railway tunnel/route, the already constructed tunnel (T-77 A) near village Bankoot is to be plugged permanently after completion of the realigned tunnel work which is nearing its completion stage and may take about 06 months more for its completion. The tunnel (T-77A) near the village Chanar, Bankoot is used for transportation of men and material by the project proponent and another construction company namely M/s Beigh Construction Company which has also been awarded work (in 373 ml length) inside main tunnel upto kapran bridge towards katra.

2. As per condition of CTO granted by JKPCC to the batching plant, the Project Proponent is required to apply for renewal of consent 60 days in advance before expiry of the consent order. However, the examination of the records indicates that it remained operational without valid consent to operate for 35 days.

3. The project proponent is required to collect and store the empty cement bags properly and dispose off the same through supplier or vendor, to avoid contributing towards particulate emissions.

4. With regard to the use of toxic chemicals, it was observed that project proponent is using only commonly used concrete additives to improve the setting time of the concrete."

5. Joint Committee also has referred to reports obtained from some other departments like District Mineral Officer, Chief Animal Husbandry Officer, District Sheep Husbandry Officer, Sheep Development Officer, Chief Horticulture Officer, Sub- Divisional Magistrate and Chief 6 Agriculture Officer and factual reports by these Departments reads as under:-

"2.3.1. Feedback from District Mineral Officer, Ramban (Annexure-7):
The dumped material in the form of Tunnel muck/road cutting muck has been found on the site as il has been noticed that the said material has been dumped by M/s. ABCL Infrastructure Pvt. Ltd to widen the sharp curve at the junction of link road leading to batching plant of ABCL and Old aligned Railway Tunnel T-77A for the smooth and easy movement of vehicles on the sharp curve as there is no huge dumping found on the ground as reported by the complainant at site. The crate stone wall and the old aligned Railway tunnel T-77A also found at the base of site in question as protection.
The report of the Mineral Officer was examined by the Joint Committee and it was observed that no feedback with regard to the adequacy of the protection provided to the muck dumped by the proponent and the additional measures required, lo avoid any untoward incident leading to loss of proper and life, have been provided.
Therefore, a revisit to the report is required by the Mining Officer in the interest of public properly and precious life of inhabitants.
2.3.2. Feedback from Chief Animal Husbandry Officer, Ramban (Annexure-8):
No livestock farmer of the area has reported death of any animal (Bovine) in the area due to pollution of drinking water since last two years. Also, no such incident has been seen by the field staff of Animal Husbandry Department, Ramban, during field inspections and visits since long.
2.3.3. Feedback from District Sheep Husbandry Officer, Ramban (Annexure-9):
No resident/breeder of the area has reported death of any animal (Sheep/Goat) in the area due to pollution of drinking water of animals since last two years. Also, no such incident has been seen by the field staff of Sheep Husbandry Department, Ramban, during field inspections and visits since long.
2,3.4. Feedback from Sheep Development Officer, Ramban (Annexure-10):
Neither anybody (Breeder/Resident) of the said area reported to this office regarding death of Sheep and Goat in large numbers due to 7 drinking of Cement-mix water nor this office has observed it during our routine field inspections.
2.3.5. Feedback from Chief Horticulture Officer, Ramban (Annexure-11):
The catchment area at Chanar Bankoot, Banihal has been visited along with HDO Banihal and observed that there is no considerable affect damage to the horticulture plantations.
It was observed by the Joint Committee that report of the Chief Horticulture Officer does not speak anything about the land under reference, which was found to be occupied/Jilled with silt/mud and therefore nothing could be concluded from the report of the Chief Horticulture Officer, A revisit to the report with relevant data of the yield of horticulture crops before and after installation of batching plant is required, to conclude the matter.
2.3.6. Feedback from Sub Divisional Magistrate, Banihal (Annexure-12):
The applicant namely Asgar Ahmed Najar is having land measuring 9 Marlas falling under Khasra No. 111 & 112 in Village Bankoot and recorded in the name of his father Ghulam Mohd as per revenue records. Regarding emitting of toxic chemicals, it was observed that muddy water found coming from one abandoned tunnel of Northern Railway located at said location. This muddy water flows through one pucca drain leading to the agriculture land of local inhabitants and finally into Bichleri River.
During spot visit, some cracks were found in the walls of applicant's house and other inhabitants residing in locality. Cause of these cracks needs lo be ascertained that whether these cracks are result of blasting or due to some construction fault.
Pucca Pathway of mound 25-30 m was found in dilapidated condition leading to nearby locality. Further, one pucca drainage found reportedly constructed by concessionaire of IRCON. Muddy water emanating from abandoned tunnel flowing through the drainage found entering in land of applicant and other inhabitants near the tail end of this pucca drainage.
The said dumping is protected by Gabion Structures but there is apprehension that this dumping may slide down as it is done on the downhill side.
The above facts reported by the SDM, Banihal is similar to what has been reported by the Joint Committee. It may be noted that SDM, Banihal was part of the Joint Committee during the sile visit as a representative of the Deputy Commissioner, Ramban.
8
2.3.7. Feedback from Chief Agriculture Officer, Ramban (Annexure-13):
A team of Agriculture Officers of Zone Banihal visited the spot on 08- 12-2022 and reported vide letter no. AEO/B/2022-23/78 Dated: 08- 12-2022 that an area of I -1 .5 acre of Paddy land has been damaged due to the effluents coming from the construction site of Railway Tunnel by ABCI.
The above Factual Report is being filed in compliance to the directions of Hon'ble National Green Tribunal."

6. Reply dated 03.12.2022 has been filed vide email dated 05.12.2022 by respondent 8 i.e. M/s ABCI Infrastructure Private Limited and stand taken by it reads as under:-

i. The Answering Respondent is a private limited Company engaged in construction and development works, which includes works of National and State Highways, Major & Minor Bridges of all kinds, Tunnels, Power Houses, Industrial Complexes, Buildings, etc. The Respondent No. 7, i.e., IRCON International Limited is a wholly owned subsidiary of the Indian Railways, Ministry of Railways, Government of India ('IRCON') and is also the principal employer of the Answering Respondent in the context of the project in question.
ii. On 05.07.2019, IRCON floated e-tender for construction of balance work for Tunnel T-77D on the western side of Bichelri River on Katra Banihal Section of Udhampur- Srinagar-Baramulla Railway Line Project ("USBRL Project"). The Answering Respondent was the successful bidder and was therefore, awarded the tender for the USBRL Project. In regard to the above, IRCON issued a letter of acceptance dated 18.12.2019 in favour of the Answering Respondent. Copy of Letter of Acceptance dated 18.12.2019 is annexed hereto and marked as Annexure R-8/2.
iii. It is submitted that the Northern Railways and IRCON have taken up the Project of USBRL since, the year 2000 for linking of Udhampur Srinagar Baramulla Railway Line for connecting the Union Territory of Jammu & Kashmir with the rest of country. In this regard, lands were acquired by the Northern Railways and from the year 2000, several projects had been accomplished in this line of USBRL. All the necessary acquisitions, NOC's, Environmental Monitoring, Geological Surveys, Construction Consultation with DDC, 9 Compensation for the land acquisition and damages, if any, recorded thereof had been taken care of properly.
iv. Moreover, before initiating the work at the Project site, the Answering Respondent during the year 2020-2021 obtained all necessary approvals, permissions, sanctions from the government authorities, local bodies including local residents of the areas nearby the USBRL Project site, including the Applicant. It is submitted that in addition to the NoC's of various authorities, the Answering Respondent also applied and received permissions/ sanctions from the 'Jammu Kashmir Pollution Control Board', i.e., the Respondent No. 2. It is submitted that vide letter dated 08.02.2021, the Respondent No. 2 granted permission, i.e., Consent to Establish the 'Batching Plant' (Cement Concrete).

Furthermore, the Consent to Operate was also renewed timely on 26.03.2021 and 18.04.2022. Copy of Letter granting Consent to Establish dated 08.02.2021, and Consent to Operate dated 26.03.2021 and 18.04.2022 are annexed hereto and marked as Annexure R-8/3 (Colly.).

v. That only upon getting all necessary permissions, sanctions and approvals, the Answering Respondent installed the Batching Plant on the land acquired by the Northern Railways for the purpose of execution of Tunnel T-77D, i.e., Udhampur-Srinagar-Baramulla Railway Line Project, which is of national importance. Copy of the Maps and the land details are annexed hereto and marked as Annexure R-8/4.

vi. It is pertinent to mention that the Applicant and his brothers have been causing regular nuisance at the project site. The Answering Respondent had also filed a police complaint on 26.02.2021 to the SHO, Banihal Police Station, District Ramban, Jammu & Kashmir in this regard. In fact, even on the date of filing of the police complaint, the Applicant and his brothers entered the project site and stopped work at South Portal Office near the Batching Plat area. Copy of Police Complaint dated 26.02.2021 is annexed hereto and marked as Annexure R-8/5 vii. It is pertinent to mention that the USBRL Project has benefitted locals at large, as most of the workers including contractors and sub-contractors are employed from the nearby areas of the project site. It is pertinent to mention that even the Applicant herein was employed at the said Project, who supplied vehicle on a monthly hire-charges basis and also executed some miscellaneous works in the capacity of sub-contractor of the Answering Respondent. It is submitted 10 that vide work order dated 15.11.2021, the Answering Respondent awarded work to the Applicant for construction of cement store sheds at south portal chanar at T77D Bankoot-Banihal and other miscellaneous works Copies of the work order issued by the Answering Respondent and the Account Statement of the Applicant in the books of the Answering Respondent are annexed hereto and marked as Annexure R-8/6 (Colly.).

viii. In addition to the above, three brothers of the Applicant were also employed with the Answering Respondent. The details are mentioned below;

S.         Name                Designation     Date      of End date of
No.                                            Appointment Service

1          Aijaz Ahmed NajarBatching           01-05-2021      02-09-2022
                            Plant
                            Attendant
2          Manzoor    Ahmed Driver             16-11-2020      15-03-2022
           Najar
3          Javeed     Ahmed Driver HMV         05-04-2021      02-07-2022
           Najar


Copy of joining report and wages register are annexed hereto and marked as Annexure R-8/7 (Colly.).

ix. While being in contractual employment with the Answering Respondent, the Applicant and his brothers on various occasions caused hinderances in the execution of the Project work by forcibly closing batching plant and dewatering at South Portal. Moreover, the Applicant and his brothers had not just stopped the work at the Project site, but also made unnecessary demands and blackmailed the officials of the Answering Respondent. Being aggrieved by the illegal acts and actions of the Applicant and his brothers, the Answering Respondent also approached the principal employer i.e., IRCON vide letter dated 27.06.2022. Copy of Letter dated 27.06.2022 addressed to 'IRCON' is annexed hereto and marked as Annexure R-8/8.

x. That when the Applicant and his brothers continued harassing the officials of the Answering Respondent and caused nuisance at the Project site, the Answering Respondent being left with no other option approached the 'Munsif Court' at Banihal on 29.06.2022 and filed a Civil Suit for permanent prohibitory injunction alongwith an application under Order XXXIX Rule 1 & 2 CPC, against the Applicant. It is pertinent to mention that the 'Munsif Court' at Banihal while considering the application of the Answering Respondent, vide order dated 23.07.2022 directed the non- applicants i.e., the Applicant herein and his brothers to 11 refrain themselves from interfering, trespassing in the construction of Railway Tunnel at T-77D, Bankoot Tehsil, Banihal District, Ramban. Copy of order dated 23.07.2022 passed by 'Munsif Court' along with its true typed copy is annexed hereto and marked as Annexure R-8/9 (Colly.).

xi. It is apposite to mention that on 08.07.2022, the Applicant along with his brothers once again trespassed the project site and forcibly closed the batching plant and stopped dewatering, which caused considerable damage to the ongoing tunnelling work. Therefore, the Answering Respondent once again sought intervention of its principal employer i.e. IRCON, vide letter dated 08.07.2022 and requested for their assistance for smoothly carrying out the work at T-77 D Tunnel. Copy of Letter dated 08.07.2022 addressed to IRCON is annexed hereto and marked as Annexure R-8/10.

xii. In the aforesaid background, the Answering Respondent is placing reliance on the 'No Objection' letter dated 06.07.2021, signed by the local residents of Village Chanar Bankoot including their Sarpanch for Operating Temporary Batching Plant. It is pertinent to note here that Applicant is signatory to the said 'No Objection' letter dated 06.07.2021. It is submitted that not just the local residents of the area situated near the Project site, but also various other local bodies, authorities such as i.) Block Medial Office, Banihal, ii.) Block Development Officer, Banihal, iii.) Office of Chief Education Officer, Ramban, iv.) Chief Medical Officer, Ramban, v.) Office of Range Officer, Forest Range, Banihal, vi.) Office of Zonal Education Officer, Banihal; etc. have granted the NoC's for temporary establishment and operation of Batching Plant at the Project site. Copy of NoC's are annexed hereto and marked as Annexure R-8/11 (Colly.).

xiii. That the principal employer of the Answering Respondent, i.e., IRCON also wrote letters dated 18.05.2022 and 28.06.2022 to the office of the Superintendent of Police, District Police Office, Ramban Dist., Ramban for taking action against the Applicant and his brothers for causing regular hinderance in execution of work at Project site. Copy of Letter dated 28.06.2022 addressed by IRCON to Superintendent of Police, Banihal is annexed herewith and marked as Annexure R-8/12 (Colly.)."

12

7. Allegations made by complainant have been denied by respondent 5.

Tribunal considered report on 10.02.2023 and observed that area in Himalaya falls in fragile ecology and therefore compliance and action taken report should be submitted by Joint Committee.

8. Respondent 8 filed objection to Joint Committee report dated 15.12.2022 vide objections dated 08.02.2023. We may refer to these objections at a later stage.

9. District Magistrate, Ramban, pursuant to order dated 10.02.2023 has submitted action taken report dated 13.04.2023, in the form of a chart, which reads as under:-

 S.    Recommendation of                       Action Taken
 No.   Committee
 1     The report of the Mineral Officer       The District Mineral Officer,
       was examined by the Joint               Ramban, has revisited the site
       Committee and it was observed           and reported vide his office
       that no feedback with regard to         letter No. R/NGT/2023-24/04.
       the adequacy of the protection          DMO- dated 04.04.2023, which
       provided to the muck dumped by          reveals that the retaining
       the proponent and the additional        wall/Crate wall provided at the
       measures required, to avoid any         base of Muck Dump above old
       untoward incident leading to loss       aligned Railway tunnel is
       of property and life, have been         sufficient to hold the dump
       provided. Therefore, a revisit to       muck at site (copy is enclosed
       the report is required by the           as Annexure-"I") for kind
       Mining Officer in the interest of       perusal.
       public property and precious life
       of inhabitants.
 2     It was observed by the Joint            The Chief Horticulture Officer,
       Committee that report of the            Ramban, has submitted a
       Chief Horticulture Officer does         clarification report vide his
       not speak anything about the            office        letter        No.
       land under reference, which was         CHO/Rbn/Dev/36,           dated
       found to be occupied/filled with        11.04.2023, which reveals that
       silt/mud and therefore nothing          no damage, has been caused to
       could be concluded from the             the horticulture plantations to
       report of the Chief Horticulture        the land in question (copy is

Officer. A revisit to the report with enclosed as Annexure-"II") for relevant data of the yield of kind perusal. horticulture crops before and after installation of hatching plant is required, to conclude the matter.

13

3 During spot visit, some cracks The matter was taken up with were found in the walls of the Chief General Manager, applicant's house and other IRCON INTERNATIONAL Ltd, inhabitants residing in locality. Banihal, in response, he has Cause of these cracks needs to be reported that the geo-tagging of ascertained that whether these the structures falling along the cracks are result of blasting or alignment of T-77D was carried due to some construction fault. out in the year 2020 and none of the structures in the Channar area fall within the ambit of 125mts and do not qualify for damage compensation as agreed upon by Northern Railway on the demands. projected by the locals of the area which has also been shared with this office vide No. DCE/C/BAHL/IRCON/T- 77D, dated 07.09.2017 (copies are enclosed as Annexure-"III") kind perusal.

4 A team of Agriculture Officers of The Chief Agriculture Officer, Zone Banihal visited the spot on Ramban, has assessed the 08-12-2022 and reported vide compensation to the tune of Rs. letter No. AEO/B/2022-23/78, 69084/- on account of damage dated 08-12-2022, that an area to the crops (copy enclosed as of 1-1.5 acre of Paddy land has Annexure-"IV"). Accordingly, been damaged due to the this office vide communication effluents coming from the No. DCR/ARA/2023-24/10, construction site of Railway dated 12.04.2023, issued Tunnel by ABCI. directions to the Project Manager, ABCI Infrastructure Pvt. Ltd. to deposit the aforesaid amount in the office of Sub-Divisional Magistrate, Banihal, for further course of action (copy is enclosed as Annexure- "V") for kind perusal.

10. Further action taken report has been filed by Jammu Kashmir Pollution Control Committee, Jammu, (hereinafter referred to as 'JKPCC') vide letter dated 17.04.2023. It says as under:-

2) Action Taken by Jammu and Kashmir Pollution Control Committee w.r.t the findings/suggestions of the Joint Committee :-
a) The Regional Director, Pollution Control Committee, Jammu has submitted a detailed report w.r.t the Action Taken by J&K Pollution Control Committee, whereby the project proponent M/s ABCI Infrastructure Ltd. has been made to 14 comply to the remedial. measures suggested by the Joint Committee as under:-
i) The Project proponent has provided a three chambered sedimentation tank existing / provided near the batching plant for primary treatment of the waste water generated by washing of the plant.
ii) Empty cement bags are stored in separate closed shed.
iii) Pucca drain on down slope drainage passing through one side of the village stands provided which was not there in place earlier.
iv) A Gabion wall has also been provided now to retain the muck along the bottom of the dump in the railway acquired land, photograph enclosed as Annexure-1.
b) Consent to Operate (Renewal) granted in favour of the batching plant stands expired in the month of February, 2023 and renewal application of same is under process, which shall be considered by the J&K Pollution Control Committee only on the outcome of this present Ο.Α."

11. The Joint Committee has submitted its point wise factual position to recommendations made by Joint Committee vide letter dated 17.04.2023 and the same reads as under:-

S.No. Grievance of the Recommendations of the Factual Position as Applicant as filed in Joint Committee in its on 31.03.2023, as OA No. 706 of 2022, report dated 15.12.2022 verified by the Joint by the applicant. Committee.
1 The benching plant The settling tank for settling Non-Compliant with installed by the the solid inorganic waste has regard to tunnel respondent No. 7 and been provided, for primary waste water 8 has no water treatment of waste water discharge.

disposal mechanism generating from the batching in place and all the plant as on 16llll2022. A sedimentation tank waste material However, the examination of comprising of 03 generated from the record provided by Divisional chambers for the Unit is being Office of JKPCC, indicates treatment of muddy discharged over the that the facility for primary water coming out of land of the applicant. treatment of the waste water the tunnel T-77A, was generated have been found constructed inadequate in the past upto near the northern 161812022 (Letter No. face of the tunnel but PCC/DO/Rbnl2l22l66 dated without any 2l/712022 attached as arrangement for Annexure-3 and Letter No, settling/removal of PC C/RD-J/2022 I | 288 I the mud/slush. The 283 0 -32 dated 161812022 unsettled tunnel attached as Annexure-4), muddy water was still thereby confirming that the being discharged into pretreatment/sedimentation drain on down slope tank of batching plant was of passing through one inadequate size and also side of the village, 15 project proponent was non- through a pipe complaint before l6/8/2022 connected at the and the tunnel waste water bottom of without any Proper Sedimentation tank.

treatment, was being (Photograph I 2 & 3 of discharged into the nearby Annexure-I) drain (concrete lined except pathways/crossing points), It was also leading to agriculture land. recommended earlier The physical condition of the by the Joint land as verified by the Joint Committee that "J&K Committee also indicated the PCC is required to some (Photograph-I of take action for non- Annexure-6). J&K PCC is compliance of the required to take action for terms & conditions of non-compliance of the terms the Consent to & conditions of the Consent Operate (CTO and the to Operate (CTO) and the directions given to the directions given to the project project proponent"

proponent As per DO, PCC Ramban, the consent to operate (renewal) under Green Category issued to the batching plant by J&K PCC was already valid upto February, 2023(Annexure-2) when the Joint Committee earlier visited the site on 16.11.2023 and the project proponent has also applied for its further renewal and the case is under process.
                                                            According     to   the
                                                            member representing
                                                            J&K PCC, a separate
                                                            "Action Taken report"
                                                            is being filed by J&K
                                                            PCC to Hon'ble NGT,
                                                            in this regard.
2   The waste water also     During visit to the site, this Complied with.
    flows through the        point was verified by the
    pathways       streets   Joint              Committee It was verified by the
    make it difficult for    (Photograph2&3              of Joint Committee that
    the public to walk on    Annexure-6) and to avoid the project proponent
    the streets as wells     this problem, either ramps or has provided pucca
    as     also    makes     closed pipes are required to drain (on down slope
    hindrance for the        transport the waste water at natural         drainage
    school          going    the points where waste water passing through one
    children.                is        crossing         the side of the village).
                             pathways/crossing points.      Further, the concrete
                                                            rumps      over    the
                                                            pathways/crossing
                                                            points over drain have
                                                            also              been



                                                                                   16
                                                                 provided(Photograph
                                                                4 & 5 of Annexure-3)
3   The respondent No. 7     It was observed by the Joint       Non-Compliant with
    and 8 have not made      Committee that the water           regard    to  tunnel
    any proper way to        accumulated in the tunnel          waste          water
    handle the chemicals     under         reference       is   discharge.
and steel fibre, slash muddy/slushy due to the etc and the water construction activities and (the non- compliance from the tunnel (de movement of vehicles as already mentioned winterization). engaged in the construction at S.No. I above) activities in the main tunnel, and is pumped outside A sedimentation tank through tunnel T-77 A and comprising of 03 discharged on down slope chambers for the natural drainage passing treatment of muddy through one side of the water coming out of village into the Bishleri the tunnel T-774, was Nallah. found constructed In this regard, the record near the northern shared by the concerned face of the tunnel but Divisional Office of JKPCC without any indicates that I this site was arrangement for previously visited I I UV settling/removal of JKPCC team and it was I I the mud/slush. The found that the water from unsettled tunnel dewatering of the tunnel and muddy water was still is discharged into the small being discharged into nallah/ drain which passes drain on down slope through the nearby village passing through one (Letter No. side of the village, PCC/DO/Rbn/2022/66 through a Pipe dated 211712022 attached connected at the as Annexure-3). bottom of Subsequently, a Letter was Sedimentation tank. also issued by JKPCC to the (Photograph I 2 & 3 of project proponent asking Annexure-l) them to construct settling According to the tanks of adequate sizes member representing outside the face of the tunnel J&K PCC, a separate and at the batching plant so "Action Taken report"

that slush etc is settled and is being filed by J&K removed at regular intervals ( PCC to Hon'ble NGT, Letter No, with regard to non-

PCC/RDI/2022/128812830- compliance of the 32 dated 16/8/2022 directions issued by attached as Annexure-4). J&K PCC in this During the verification of the regard.

                             factual position by the Joint
                             Committee, it was observed
                             that     while    the   project
                             proponent has provided the
                             settling tank for the batching
                             plant     (Photograph-4      of
                             Annexure-6 ). arrangement/
                             settling tanks have been
                             provided for the muddy water
                             coming out of the tunnel as
                             on 16/11/2022 and the
                             muddy water is still going in
                             the nearby nallah/drain and
                             also            on          the
                             pathways/crossing        points

                                                                                      17
                               being used by villagers
                              (Photograph-Sof Annexure-
                              6), leading to the village
                              pathways and the land in the
                              village       ChanarBankoot
                              Village,   Tehsil     Banihal.
                              District Ramba (Photograph-
                              6of Annexure-6). Therefore, it
                              may be concluded that the
                              project proponent is yet 10
                              comply         with       the
                              directions/advice of J&KPCC
                              to prevent damage to the
                              public    health    and soil
                              environment. J&K PCC is
                              required to take action for
                              non-compliance       of   the
                              directions issued to Project
                              Proponent so that the tunnel
                              work is performed with the
                              compliance of prescribed
                              norms/directions of J&K
                              PCC.


4   The illegal activities    It was observed by the Joint       Complied with, but
    of                        Committee that the village         further      action
    RespondentNo.T&8          Chanar Bankoot, tunnel T-          required.
    have    resulted    in    77 A and batching plant are
    creation of a huge        at lower elevation than the        It was verified by the
    dumping        ground     existing    Tatnihal-Banihal       Joint Committee that
    which      can     fall   road maintained by IRCON           A gabion wall has
    anytime and may           International Ltd. The Project     provided to retain the
    cause damage to the       proponent has constructed          muck     along     the
    whole village             an approach road in the            bottom of the dump in
                              acquired     land      towards     the railway acquired
                              batching plant and tunnel T-       land (Photograph 6 of
                              77A by dumping the muck at         Annexure-4).
                              the junction for the purpose
                              of widening it so that the         However,      it    was
                              construction vehicles can          observed that a small
                              easily reach the site.             portion of the soil has
                                                                 started sliding down
                              However, at the same time,         just below the gabion
                              as apprehended by the              wall provided by the
                              applicant, it is true that if it   Proponent          near
                              slides due to any reason, this     Northern     face     of
                              may cause damage on down           tunnel (Photograph 7
                              slopes since proper retaining      of Annexure-4). It is
                              wall is not provided by the        recommended         that
                              project proponent so far (P ho     slop     stability     is
                              to graph- 7 of Annexure - 6.       ensured      by      the
                                                                 proponent,        before
                              Therefore,    a    retaining       leaving the site.
                              structure      such        as
                              gabions/crate wall to retain
                              the    muck   dumped      for
                              construction of approach
                              rood on upper side of the
                              village is needed badly to
                              avoid any untoward incident,



                                                                                       18
                           leading to loss of property or
                          life.




12. Above report recommends that apart from providing compensation for loss of crop, remediation of agricultural land damaged as verified by Agriculture Officer is to be restored to its original condition by Proponent under the supervision of concerned Agriculture Officer. This report has also been objected by Respondent 8 vide objection dated 13.05.2023.

13. By order dated 17.05.2023, Tribunal required District Magistrate, Ramban and Member Secretary, JKPCC to take remedial measures in accordance with Joint Committee Report. District Magistrate thus submitted action taken report vide email dated 12.08.2023, stating as under:-

S.No. Recommendation of Committee Action Taken 1 The report of the Mineral Officer On the directions of the Hon'ble Court was examined by the Joint District Mineral Officer, Ramban, Committee and it was observed revisited the site and submitted a that nо feedback with regard to report vide his office letter No. DMO-

the adequacy of the protection R/NGT/2023-24/04, dated provided to the muck dumped by 04.04.2023, which reveals that the the proponent and the additional retaining /crate wall constructed at the measures required, to avoid any base of Muck Dump above old aligned untoward incident leading to loss Railway Tunnel is sufficient to hold the of property and life, have been dumped muck at the site for kind provided. Therefore, a revisit to perusal. The undersigned, along with the report is required by the concerned stakeholder officers, visited Mining Officer in the interest the site and found that the protection public property and precious life wall is strong enough to hold back the of inhabitants. muck at the site. In order to further protection, a concrete wall outside the abandoned Tunnel T-77S has also been constructed. The undersigned, during his spot visit, also witnessed the newly constructed drain which shall safeguard the residential houses from torrential rains/ downpours. The undersigned also met the complainant, who expressed his satisfaction over the measures taken by the District Administration Ramban on the directions of the Hon'ble NGT. The undersigned also issued directions to IRCON International Ltd & the Project Proponent to clear the debris outside the portal of the abandoned Tunnel T-

19

77, to safeguard the interests of the residents living down below, The Project Proponent has already carried out the instructions issued in the matter.

2 It was observed by the Joint The Chief Horticulture Officer, Committee that report the Chief Ramban, has submitted a clarification Horticulture Officer does anything report vide his office letter No. land under which was found be CHO/Rbn/Dev/36, dated 11.04.2023, occupied/filled with silt/mud and which reveals that no damage, has therefore of not speak about the been caused to the horticulture reference, to nothing could be plantations to the land in question. concluded from the report of the Chief Horticulture Officer. A revisit to the report with relevant data of the yield of horticulture crops before and after installation of hatching plant is required, to conclude the matter.

3 During spot visit, some cracks The matter was taken up with the Chief were found in the walls of General Manager, IRCON International applicant's and other inhabitants Ltd, Banihal. In response, he has residing in locality. Cause of these reported that the geo-tagging of the cracks needs to be ascertained structures falling along the alignment that whether these cracks are of T-77D was carried out in the year result of blasting or due to some 2020 and none of the structures in construction fault. Channar area fall within the ambit of 125mts and do not qualify for damage compensation as agreed upon by Northern Railway on the demands projected by the locals of the area which has also been shared with this office vide No. DCE/C/BAHL/IRCON/T-77D, dated 07.09.2017.

4 A team of Agriculture Officers of Chief Agriculture Officer, Ramban, has Zone Banihal visited the spot on assessed the compensation to the tune 08.12.2022 and reported vide of Rs. 69084/- on account of damage letter No. AEOQ/B/2022-23/78, to the crops. Accordingly, this office dated 08-12-2022, that an area of vide communication No. 1-1.5 acre of Paddy land has been DCR/ARA/2023-24/10, dated damaged due to the effluents 12.04.2023, issued directions to coming from the construction site Project Manager, ABCI Infrastructure of Railway Tunnel by ABCI. Pvt. Ltd. to deposit the aforesaid amount in the office of Sub Divisional Magistrate, Banihal, for further course of action. Pursuant upon above, ABCI Infrastructure Pvt Ltd deposited an amount of Rs.69,084 with SDM Banihal as crop compensation.

However, SDM Banihal vide communication No.SDMB/2023- 24/390, dated 24.07.2023, has communicated that the land for which Rs.69,0874 has been deposited with him by the Project Proponent is State land and cannot be disbursed in favour of the complainant. He has sought further instructions from the office of the undersigned. Consequent upon above, the matter has been taken up with the office of worthy Divisional 20 Commissioner, Jammu, for instructions/ advice on the issue. As and when the instructions are issued, further action shall be taken in the matter and Hon'ble Court informed accordingly. Further, following the site visit on 11.08.2023, Chief Agriculture Officer, Ramban, made spot visit of the aforementioned land pocket. He has vide his communication No.CC/CAO/Rbn/2023-24/2111-12, dated 12.08.2023, submitted an estimate to the tune of Rs,2,93,394/-

for taking up works for restoration of aforesaid land to its original form.

Following the receipt of the estimate, ABCI Infrastructure Pvt Limited was vide No.DCR/ARA/2023-24/243-45, dated 12.08.2023, to deposit the said amount for restoration of land to its original form. In deference to the directions received, ABCI Infrastructure Pvt Ltd, vide No.ABCI/IRCON/J&K/NGT/2023- 24/389, dated 12.08.2023, has deposited an amount of Rs.2,93,394/-

with the office of Sub Divisional Magistrate, Banihal.

14. Member Secretary, JKPCC had also submitted action taken report referring to Joint Committee Report stating as under:-

"2. Report of the Joint Committee:
In compliance to the directions of Hon'ble NGT, the joint committee comprising of Shri Zaheer Abbas, Sub Divisional Magistrate (SDM), Banihal (representative of Deputy Magistrate, Ramban), Dr. Narender Sharma, Additional Director, CPCB Chandigarh (Representative of CPCB, New Delhi) and Shri Sanjay Rathore, Divisional Officer, PCC Ramban (Representative of J&KPCC) visited the site on 20.07.2023, the date fixed for conducting joint visit by Deputy Commissioner, Ramban vide his office communication no. DCR/ARA/2023-24/202-09 dated 14.07.2023. The applicant accompanied by other inhabitants of village Chanar, Bankoot and the representatives of the project proponent were associated and were also present during the visit of site.

The point-wise factual position regarding the compliance to the recommendations made in the earlier reports of the joint committee by the respondent no. 8-project proponent vis-à-vis to 21 the objections filed by the project proponent is submitted as follows in Table 1 Table 1: point-wise factual position regarding the compliance to the recommendations made in the earlier report of the joint committee by the respondent no. 8-project proponent vis-à-vis to the objections filed as on 20.07.2023.


S.No Verification       and     Point-wise response Verification   and factual
     factual Report of          cum objection and Report of Joint Committee as
     Joint Committee            clarification of the on 20.07.2023
     as on 31.03.2023,          Project Proponent
     observations and
     recommendations
     thereof
1    Non-Compliant with         a. Observation of the       It was earlier reported by the
     regard to tunnel           joint Committee to the      Joint Committee in its report
     waste Discharge. A         extent that there is        dated 17.4.2023 as follows:
     sedimentation tank         'non-compliance' with
     comprising of 03           regard      to     tunnel   A       sedimentation          tank
     chambers for the           waste water discharge       comprising of 03 chambers for
     treatment of muddy         is completely flawed,       the treatment of muddy water
     water coming out of        miscalculated,              coming out of the tunnel T- 77A,
     the tunnel T-77A,          erroneous            and    was found constructed near the
     was              found     inaccurate foe the          northern face of the tunnel but
     constructed        near    following reasons; i) It    without               arrangement
     the northern face of       is not in dispute, that     settling/removal of any for the
     the     tunnel      but    the Project Proponent       mud/slush.        The     unsettled
     without             any    has     made       proper   tunnel muddy water was still
     arrangement          for   arrangements           by   being discharged into drain on
     settling/removal of        constructing            a   down slope passing through one
     the mud/slush. The         Sedimentation Tank          side of the village. through pipe
     unsettled       tunnel     having 03 chambers,         connected at the bottom of
     muddy water was            as         per        the   sedimentation Tank The Joint
     still             being    recommendations of          Committee revisited all the geo-
     discharged         into    the earlier factual         tagged photographs taken from
     drain on down slope        report of the Joint         various      directions,     during
     passing       through      Committee, However          earlier visit to re-verify the facts
     one side of the            it is wrongly alleged       w.r.t. objections raised by the
     village,      through      that the unsettled          project proponent. The Joint
     pipe connected at          tunnel muddy water          Committee         with       utmost
     the      bottom       of   is being discharged         responsibility submits that this
     sedimentation Tank         into the drain through      is an attempt by the Project
                                a pipe connected at         Proponent to misrepresent and
                                the       bottom       of   mislead      the    investigations.
                                sedimentation tank.         There only and only one pipe
                                ii) It is clarified that    and that too connected at the
                                there is no case of         bottom of the settling tank
                                'non-compliance' as         leading to the discharge of waste
                                the Joint Committee         water containing silt onto the
                                has wrongly observed        agriculture land without any
                                or misconducted that        treatment of waste water. Geo-
                                the flush pipe was          tagged Photographs of the
                                main flow pipe which        settling tank showing pipe
                                is at the top of the        connected at the bottom of
                                tank. ln fact, the pipe     sedimentation tank taken by the
                                connected        at   the   Joint Committee on 31.03.2023
                                bottom         of     the   are enclosed as Annexure-I,
                                Sedimentation Tank          which clearly indicate the
                                is meant for the            factual position and nullifies the

                                                                                            22
 purpose of flushing       objections raised by the project
the slush at the          proponent, in this regard
designated area on        Further, the evidence in this
the acquired land of      regard was also provided by the
the northern railways     Applicant during the visit on
and the pipeline at       20/7/2023, in the form of i)
the top of the tank is    photographs showing bursting
used to discharge the     of tank when the settling tank
water             after   was first put into . operation
completion of the         with overflow pipe as Annexure-

Sedimentation 2. ii) Letter written by the process. iiD It is applicant to the District further clarified that authority, with regard to the photograph filled bursting of the tank and safety by the joint of the inhabitants (Annexure-3). Committee with its This further confirms that the report and enclosed settling tank was never operated as Annexure- ! At by the proponent and waste running page 147 has water containing silt/mud was been clicked from discharged into the village another angle which throughout the implementation shows both the flush of the project.

and     flow     pipes
separately which were     Current status:
present even at the       During the recent visit, it was
time       of       the   observed that the Tunnel
construction. Hence,      waste/seepage water from the
there Is no case of       main tunnel has been diverted
'non-compliance'.         towards the Jammu end by
Colored photographs       laying the drain inside the main
showing           clear   tunnel T-77D and nothing was
placement of flush        diverted through the abandoned
and flow pipes are        tunnel T-77A.
annexed       herewith    An intimation letter in this
and     marked       as   regard          vide         No.
Annexure R{46(Copy).      IRCON/1014/J&K/14/1014/T-
iv) Even otherwise,       77D dated 6.04.2023 from
the tunneling work is     IRCON International Ltd also
progressing towards       stands    submitted     to   Dy.
completion and the        Commissioner Ramban. (Copy
flow of water is          Enclosed Annexure-4).
already moved to the
opening of the tunnel
i.e. towards Jammu
end and water line of
Tunnel T 77D is
permanently plugged,
whilst ensuring that
no de-watering is
done towards village
i.e. Chanar side. In
this regard, proper
intimation has been
given to IRCON i.e.
Respondent      No.07.
Copy of Letter dated
06.04.2023 issued to
IRCON is annexed
herewith and marked
as Annexure R- 8/37.
v.)       Furthermore
IRCON vide letter

                                                       23
                            dated       06.04.2023
                           informed
                           Dy.Commissioner,
                           Ramban       that    the
                           Project Proponent has
                           permanently
                           channelized the water
                           flow    towards      the
                           Jammu       end     and
                           temporary water line
                           of Tunnel T-77D is
                           permanently plugged,
                           whilst ensuring that
                           no dewatering will be
                           done towards Chanar
                           end. Copy of Lefter
                           dated       06.04.2023
                           issued by IRCON to
                           Dy.      Commissioner
                           Ramban is annexed
                           herewith and marked
                           as Annexure R-8/38.
2   Non-Complaint with     Observation of the Same as above.
    regard to tunnel       Joint committee to
    waste    water.    A   the extent that there
    sedimentation tank     is    'non-compliance'
    comprising of 03       with regard to tunnel
    chambers for the       waste water discharge
    treatment of waste     is completely flawed,
    water was found,       miscalculated,
    but without any        erroneous           and
    arrangements     for   inaccurate for the
    still         being    following reasons. In
    discharges      into   response              to
    drain.                 Objections at S.No 3
                           of the table, the
                           response/ objections
                           mentioned at S.No. 1
                           of this table may be
                           read as part and
                           parcel in response to
                           the              present
                           paragraph, contents
                           thereof      are     not
                           repeated for the sake
                           of brevity.
3   It was observed that                            During the recent inspection, it
    a small portion of                              was has been observed that the
    the soil has. started                           proponent has constructed a
    sliding down just                               PCC retaining wall near the
    below the gabion                                Northern face of the tunnel in
    wall provided by the                            about 20M length and 3.0 M
    proponent        near                           above ground in height.
    Northern face of
    tunnel                                         (Photograph         Annexure-5)
    (Photographs 7 of                              enclosed as
    the Annexure-4 of
    previous       report
    enclosed           as
    Annexure-III).
4   It is recommended First and foremost, it       The Joint Committee reconfirms
    that apart from is clarified that the          that the amount Rs 69,084/- so

                                                                                24
 providing           the    compensation               deposited is only compensation
compensation         for   assessed by the Chief      assessed for the damaged crop
the loss of crop, the      Agriculture     officer,   which does not include the cost
remediation of the         Ramban      i.e.      an   for     remediation      of     the
agriculture       land     amount       of       Rs   agriculture land to restore to its
damaged as verified        69084/- (Rs sixty          original        condition        as
by the Agriculture         nine thousand and          recommended by the Joint
Officer, is to restore     eighty four only) is       Committee. This is again an
to     its    original     qua remediation of         attempt      by     the     Project
condition by the           the land only and the      Proponent to mislead the
Proponent       under      said    amount      has    investigation       by       wrong
the supervision of         already           been     interpretation                 and
concerned                  deposited    by      the   misrepresentation of the fact.
Agriculture Officer        project proponent. It      This fact can be validated
of the area.               is submitted that the      Annexure-IV) Project Proponent
                           said land is acquired      to Chief Agriculture Officer,
                           by Government as per       Ramban             vide          nо
                           revenue       records.     ABCI/IRCON/J&K/CA/2023-
                           Copy     of   revenue      24/588       dated     15.06.2023
                           records showing the        (Annexure-6)      requesting     to
                           ownership of the said      advice     that    whether      the
                           agriculture        land    restoration of the agriculture
                           annexed      herewith      land be carried out by project
                           and      marked       as   proponent or the amount of
                           Annexure        R-8/41     restoration be deposited in the
                           (enclosed             as   office of CAO/or any other office
                           Annexure-IV)               as advised with the sum of
                                                      amount to be deposited. Current
                                                      Status: As per the letter of ABCI
                                                      International Pvt Ltd vide Ref.
                                                      nо.
                                                      ABCI/IRCON/J&K/CA/2023-
                                                      24/380 dated 21.07.2023, an
                                                      amount of Rs 69,084/- has been
                                                      deposited vide RTGS- Reference:
                                                      FBBT232027470731/Sub
                                                      Divisional Magistrate in the
                                                      Account No. CD-621 (copy
                                                      enclosed as Annexure-7).
                                                      The assessment of the cost of
                                                      damage and work on the
                                                      remediation       of     damaged
                                                      agriculture land were yet to be
                                                      done, when the Joint Committee
                                                      visited site on 20/7/2023.
                                                      However, as informed by the
                                                      Nodal Officer representing J&K
                                                      PCC on 12/8/2023: The cost of
                                                      restoration of the agriculture
                                                      land, damaged due to discharge
                                                      of untreated waste water has
                                                      now been assessed by the
                                                      District Agriculture (Annexure-
                                                      8), Officer Rs. as 293394/- and
                                                      the project proponent has
                                                      deposited this amount, as well
                                                      on        12.8.2023(Annexure-9),
                                                      under the directions of Deputy
                                                      Commissioner. As far as the
                                                      issue of title of the land is
                                                      concerned, the report of same is



                                                                                     25
                                                 being filed by the       District
                                                Magistrate separately.


15. It further states that Joint Committee during its recent visit verified compliance of recommendations by respondent 8 as follows:-

1. Construction of the pucca drain passing through one side of the village (natural drainage on down slope).
2. Laying of concrete ramps over the pathways/crossing points over the drain.
3. Construction of settling tank for the muddy water coming out of the abandoned Tunnel T-77A but the same was not made into use when the joint Committee visited the site on 31.3.2023.

However, the settling tank was found dismantled and the tunnel seepage water is now permanently diverted through the main tunnel T-77D since 6.4.2023 and no water found diverted through the abandoned tunnel and village drain.

4. A gabion wall provided to retain the muck dumped along the bottom of the dump in the railway acquired land.

5. Store for empty cement bags provided.

6. Construction of PCC retaining wall for slope stability outside face of the abandoned tunnel T-77A where a small portion of the soil was found sliding down in previous visit on 31.3.2023 just below the gabion wall provided by the project proponent in a length of about 20 M and 3 M in height above ground.

7. Deposited an amount of Rs 69,084/- as annual damages assessed by the Chief Agriculture Officer. Ramban for the crops Rabi & Kharif in office of the Sub Divisional Magistrate, Banihal.

8. The cost of restoration of the agriculture land, damaged due to discharge of untreated waste water has now been assessed by the District Agriculture Officer, as Rs. 293394/-= and the project proponent has deposited this amount, as well, under the directions of Deputy Commissioner

9. The remediation work utilizing the amount deposited by the project proponent to the District Administration is yet to be started."

26

16. Matter was considered by Tribunal on 10.11.2023 and a further action taken report taking remedial measures was required to be submitted.

17. Pursuant thereto, Member Secretary, JKPCC has submitted its report dated 12.01.2024 stating as under:-

S.No Recommendations of the Status of the compliances done by Joint Committee during the Project Proponent to the visits to the site. recommendations of Joint Committee.
1 Visit dated 16.11 .2022 As already reported, pucca/concrete Ramps or closed pipes are drain passing through one side of the required to transport the waste village (natural drainage on down water at the points where slope) has been constructed by the waste water is crossing the project proponent and concrete ramps pathways/crossing points. have been laid over the pathways/crossings points of the village over the drain as per the recommendations of the Joint Committee. (Photograph of drain is annexed as Annexure-I) 2 Visit dated 16.I 1.2022 The main tunnel T- 77D (now To construct settling tank of renamed as T-55) seepage water (clean adequate size outside the face water as the construction activities of the tunnel so that the slush inside the main tunnel are completed) etc is settled and removed at has been permanently diverted regular intervals. towards the Jammu end through concrete deep drain laid inside the main tunnel and nothing is diverted through the abandoned tunnel T77 A/Village drain. Moreover, the work on the main tunnel has been completed and the trial runs of the train also done through it between Banihal and Khari stations.
3 Visit dated 16.11 .2022 As already reported, a gabion wall to A retaining structure such as retain the muck dumped for the gabions/crate wall to retain the construction of approach road muck dumped for construction towards tunnel T-77A has been of approach road on upper side provided by the project proponent of the village is needed badly to along the bottom of the dump in the avoid any untoward incident, railway acquired land as per the leading to loss of property or recommendations of the Joint life. Committee and was found intact (Photograph is annexed as Annexure-

Il) 4 The project proponent is Store for empty cement bags already required to collect and store provided. It was observed that the the empty cement bags operation of the batching plant has properly and dispose off the been stopped and the dismantling of same through supplier or same has been started. The vendor, to avoid contributing underground sedimentation tank of towards particulate emissions the batching plant has been closed and filled with debris/muck due to 27 completion of the project work.(Photographs is annexed as Annexure- III) 5 Visit dated 31.3.2023 As already reported, a PCC retaining It was observed that a small wall in about 20 M length and 3.0 M portion of the soil has started above ground in height has been sliding down just below the constructed to avoid sliding of the soil gabion wall provided by the near the Northern face of the proponent near Northern face abandoned tunnel T-77 A by the of tunnel T77A. It was project proponent as per the recommended that slope recommendations of the Joint stability is ensured by the Committee. (Photograph is annexed as proponent before leaving the Annexure IV A) site.

6 It was recommended that apart The project proponent has already from providing the deposited an amount Rs 69,084/- as compensation for the loss of annual damages assessed by the Chief crop, the remediation of the Agriculture Officer, Ramban for the agriculture land damaged as crops Rabi &Kharif and has also verified by the Agriculture deposited an amount of Rs 2,93,3941- Officer, to restore to its original as the cost of restoration of the condition by the Proponent agriculture land, damaged due to under the supervision of discharge of untreated waste water as concerned Agriculture Officer assessed by the Chief Agriculture of the area. Officer, Ramban with the office of Sub Divisional Magistrate, Banihal as per the directions of District Magistrate, Ramban. The remediation work utilizing the amount is yet to be started.

7 On spot verbal instructions The project proponent has removed were issued by the District the construction debris lying in front Magistrate, Ramban during his of the tunnel T-77A and has also visit to the site on l1 .8.2023 to submitted latest photograph of the remove debris in front of the ongoing construction work of the abandoned tunnel T77A and retaining wall in front of the tunnel as construct a retaining wall in per the instructions. (Photograph is front of the tunnel. annexed as Annexture-IVB)

18. Replying to various reports of various authorities and District Authorities, Applicant has filed rejoinder dated 26.08.2024 stating as under:-

"1. That the report submitted by the joint committee dated 15/12/2022 page 06 stated "As per condition of consent to operate (CTO) granted by JKPCC to the batching plant, the Project Proponent is required to apply for renewal of consent 60 days in advance before expiry of the consent order. However, the examination of the records indicates that it remained operational without valid consent to operate for 35 days." (Annexure 1/1).
This fact was further corroborated by the report submitted by the Jammu Kashmir Pollution Control Committee (JKPCC) in its action 28 taken report (ATR) dated 17/04/23 page no. 336 (b) before the Honourable Tribunal which states that the "Consent to Operate (Renewal) granted in favour of the batching plant stands expired in the month of February, 2023 and renewal application of same is under process, which shall be considered by the J&K Pollution Control Committee only on the outcome of this present O.A."

(Annexure A½) That this ATR submitted by the JKPCC clearly depicts that the project proponent was operating the plant in collusion with JKPCC without obtaining the consent to operate (CTO) from the JKPCC which is illegal, unreasonable and in gross violation of law and how the renewal application shall be considered by the JKPCC on the outcome of the disposal of this O.A filed before the Honourable Tribunal is unreasonable, illegal and in violation of environmental laws. That the project proponent had not stated an iota of word regarding consent to operate (CTO) in its objection filed dated 13/05/23 before the Honourable Tribunal. It is noteworthy that after the expiry of consent to operate, any activity by the batching plant Private Company, without renewal is an offence under the Environmental Protection Act, punishable under section 15, and 16 of the Environmental Protection Act, 1986. The Project Proponent is liable to be proceeded against and prosecuted accordingly.

2. That the Joint Committee had in its factual inspection report page no. 08 dated 15/12/2022 had stated that some cracks were found in the walls of applicant's house and other inhabitants residing therein. The true reason for such cracks was due to the high level of blast beyond permissible limit conducted illegally by the project proponent at the benching plant. That the applicant had filed a complaint dated 06/07/21 bearing no. THE/BNL/NS/2032-22/245-46 pertaining to high Level blast conducted by the project proponent to the Deputy Commissioner Ramban, SDM Banihal and Tehsildar Banihal wherein an inspection was done by the Tehsildar in the presence of applicant and other inhabitants along with manager of project proponent where it was found by the Tehsildar that about 40 houses were damaged due to such highlevel blasts. That the total valuation of loss to the said houses would amount to Rs. 5000000/- (fifty lakhs).

3. That the project proponent in its objection submitted dated 13/05/2023 page no. 358 (iv) had stated that as regard to damage caused to paddy land, The Chief Agriculturel Officer (CAO) Ramban assessed the compensation to the tune of rupees 69,084/-. which was deposited by the project proponent in the office of the SDM Banihal. That the Joint Committee in its report dated 15/12/22 had stated the feedback from Chief Agriculture Officer Ramban (Annexure 13) wherein it was stated that "A team of Agriculture Officers of Zone Banihal visited the spot on 08/12/2022 and reported vide letter no.AEO/B/2022-23/78 29 dated 08/12/2022 that an area of 1-1.5 acre of paddy land has been damaged due to effluents coming from the construction site of project proponent." That it is not stated how the Chief Agriculture Officer calculated such a meager amount of Rs. 69084/- for the damage caused to the paddy land of an area approx 1.5 acre. That the valuation of one acre land amounts to 8 canal and the value of 1 canal land is about Rs.16,89,000 (Sixteen lakh eighty nine thousand rupees). That the total valuation of paddy land damaged by the project proponent amounts to 1689000*12=Rs. 20268000/- (two crore two lakh sixty eight thousand Rs.). That the applicants paddy land since 2020 due to discharge of effluents had become barren and cannot be used for paddy cultivation. That the valuation of paddy land damage conducted by Chief Agricultural Officer is false and far from the truth and the correct value of damage to Paddy land is about approximate Rs. 2,02,68,000/- (two crore two lakhs sixty eight thousand Rs.). That the applicant had received not a single penny from the project proponent for the huge loss caused to the paddy land of the applicant thereby violating Fundamental Right enshrined under Article 21 of the constitution ie Right to Life includes Right to livelihood

4. That the SDM Banihal had submitted false feedback to the Joint Committee that the applicant is having land measuring 09 marlas falling under khasra No. 111 and 112 in village Bankoot and recorded in the name of his father Ghulam Mohammad as per revenue records. That the factual position is that khasra no.111 belongs to Mr. Ghulam Rasool, Md. Afzal S/o Lasoo Giri and khasra no. 112 belongs to Nisar Ahmed. Annexures attached here with and revenue records page no. 83. That the applicant's land falls under khasra no. 210 and 211 which was paddy land totally damaged since 2020 by the effluent discharged by the project proponent. That there is a contradiction between the reports submitted by the Patwari Banihal and Tehsildar Banihal and the SDM Banihal endorses the report submitted by the Tehsildar Banihal. That the Patwari Banihal states that the State land comes under khasra no.582 and whereas the report of the Tehsildar Banihal states that the State land falls under khasara no. 882 so there is a contradiction between the two reports submitted by Tahsildar and Patwari. That the Tehsildar and Patwari are misleading and submitting false reports before the Honorable Tribunal. That the SDM Ramban had filed false report that Khasra number 110 and 111 belongs to the present applicant whereas the revenue record shows that kasra no. 210 and 211 belongs to applicant and his family members. It is noteworthy that the SDM in collusion and conspiracy with the Batching Plant Private Company, have framed a record, knowing that the record is incorrect relating to khasra numbers and the ownership of government over the concerned residential 30 properties, and then making a report maliciously and corruptly in judicial proceedings of this specialized Judicial Body knowing that the report is incorrect and false, tantamounting to offences under sections, 218 and219 of the Indian Penal Code, and are liable to proceeded and prosecuted according under IPC. (Annextures attached herewith report dated 07/12/22)

5. That the Jammu Kashmir Pollution Control Committee (JKPCC) had concealed the fact that the three chambered sedimentation tank constructed on 06/04/23 by the project proponent for primary treatment of the wastewater generated by washing of the plant busted on the very same day. That an application was filed by the applicant dated 06/04/23 to Deputy Commissioner Ramban and SDM informing about the burst of said sedimentation tank. (Annexures of application and Pictures of burst sedimentation tank are attached here with.)

6. That the project proponent coerced and threatened the applicant to withdraw his Original Application and in failing to do so a false case shall be registered against the applicant. That when the applicant refused to withdrew his case pending before the Honourable Tribunal a false FIR case 104/2023 was registered against the applicant/farmer in year 2023.

7. That the contention of the project proponent that the photographs taken by the joint committee during factual inspection was taken from certain angle is far from truth. That even for the sake of the argument if it is taken from certain angle that does not change the factual position of the said premises which can be clearly seen from the photographs uploaded by the joint committee. That there is a presumption u/s 114 (e) of the Evidence Act that all judicial and official acts have been regularly performed.

8. That the contention of the project proponent that when the joint committee visited for verification of factual position there was heavy rainfall is not corroborated by the project proponent and is false.

9. That the project proponent had filed a false affidavit before the Honourable Tribunal and had not fully complied with the recommendations made by the joint committee to the project proponent.

10. That the Honourable NGT may initiate appropriate proceedings against the SDM, who in collusion with the Private Company Batching Plant/project proponent, is liable for prosecution for committing offences under section 1208, 218 and 219 of IPC for framing incorrect record and for making incorrect report corruptly and maliciously in Judicial proceedings of NGT, in writing wrong Khasra numbers in its report and in corruptly writing private property as Government Property. That initiation of appropriate 31 action is necessary so that the trial may be conducted in the appropriate trial court.

11. That Hon'ble NGT may order for the initiation of proceedings against Batching plant Company, for offences under section 15 and 16 of the Environmental Protection Act. 1986, for continuing their activities without renewal, causing pollution and damage to the residential buildings."

19. In order to show compliance on the part of respondent 8, it has filed certain additional documents by way of an affidavit dated 16.09.2024 and facts disclosed therein are as under:-

3. As regards the above directions, it is submitted that as per the requirements of law, the Project Proponent timely applied for renewal of the CTOs, whenever required and the JKPCC duly issued the same in favour of the Project Proponent. The trial of CTOs obtained from JKPCC clearly establishes, that at all times the Project Proponent operated the Batching Plant with valid permissions. The details of CTO's are mentioned herein below:
S. Document Details Date of Date of Valid upto No. application issuance 1 Consent to Establish the 04.02.2021 08.02.21 Feb. 22 batching plant (Cement Concrete) was received from JKPCC 2 Consent to Operate the 26.03.21 Feb. 22 batching plant (Cement Concrete) was received from JKPCC 3 Consent to Operate the 08.02.2022 18.04.22 Feb. 23 batching plant (Cement Concrete) was received from JKPCC 4 Consent to Operate the 26.12.2022 31.07.23 Feb. 24 batching plant (Cement Concrete) was received from JKPCC Copy of applications submitted to JKPCC for issuance / renewal of CTO along with the copy of the CTO's issued by JKPCC are annexed hereto and marked as Annexure-1 (Colly.).
4. Since the scope of the work of the Project Proponent got reduced and no further scope was there to operate the Batching Plant, a letter dated

20.09.2023 was issued by the Project Proponent to JKPCC for handing over the CTO's. Thereafter, vide letter dated 11.10.2023, the Project Proponent informed Divisional Officer, JKPCC that the Batching Plants of T-77D, North & South portals have been dismantled and another 32 Batching Plant of T-74R shall also be dismantled. Accordingly, the Project Proponent requested JKPCC for handing over of the CTOs. Copy of Letters dated 20.09.2023 and 11.10.2023 issued by Project Proponent to Divisional Commissioner, JKPCC are annexed hereto and marked as Annexure-2 (Colly.).

5. During the hearing conducted on 27.08.2024, this Hon'ble Tribunal raised queries to the Project Proponent, as regards the status of the Project and the date of completion. It is submitted that IRCON International Ltd. i.e. Respondent No. 7 awarded the work for construction of balance work for Tunnel T-77D, Banihal Section of USBRL Project, J&K to the Project Proponent on 18.12.2019 and the Project Proponent completed and handed over the project site to IRCON on 03.12.2023. Besides this, IRCON after verifying and certifying the works done by the Project Proponent issued a letter of satisfaction cum certificate dated 19.08.2024 to the Project Proponent which contains details of Commencement, Completion and the date of handing over the Project. Copy of letter of satisfaction cum certificate dated 19.08.2024 issued by IRCON to the Project Proponent is annexed hereto and marked as Annexure-3.

6. Notwithstanding the above, it is submitted that on the specific request of the Project Proponent, the counsel for the Applicant supplied the copy of the Rejoinder on 27.08.2024. The allegations made in the Rejoinder of the Applicant are summarily dealt by the Project Proponent in the tabular chart below:-

Sr. Summary of the Brief response cum clarification of No. allegations/contention raised by the Project Proponent the Applicant in his rejoinder 1 OPERATION OF BATCHING PLANT a. Before starting operation of the WITHOUT VALID CTO Batching Plant, the Project Proponent took 'no objection' a. Project Proponent operated from the local residents of village the batching plant without Chanar Bankoot and from valid Consent to operate various Government (CTO) for a period of 35 departments which is enclosed days. as Annexure R-8/11 (Colly.) b. To support the above @Pg. 148-158 of Reply dated contention, Applicant relied 03.12.2022 filed by the Project on the 1st Joint Committee Proponent.

Report dated 15.12.2022 b. At Para-2.2.2 [Page-240] of the @page-192, wherein it is objections dated 15.12.2022 observed by the Joint filed in response to 1st Joint Committee that Project Committee Report, the Project Proponent was required to Proponent has mentioned the apply for renewal of CTO 60 details of the CTO's. days in advance before c. Copy of the Consent Orders expiry of the consent order, (CTO's) were filed along with however the plant remained reply dated 03.12.2022 filed by in operation for 35 days the Project Proponent and without any valid CTO. marked as Annexure R-

        c. The applicant further relied    8/3(Colly.) @Page 110115 of the
           on JKPCC's report dated         reply.
           17.04.2024       @page-336, d. In view of the above, it is
           which records that the CTO      submitted that the Project
           granted for the batching        Proponent always had valid
           plant stands expired in the     permission and CTO's for

                                                                            33
           month of Feb. 2023 and                  operating the batching plant
          renewal was kept on hold by             and for the brief period of 35
          JKPCC awaiting outcome of               days in and around the plant
          the present proceedings.                month of February 2022, the
       d. On the strength of above                batching     plant    was     not
          submissions, the Applicant              operational due to injunction
          has stated that the Project             order passed by the Munsif
          Proponent     has       illegally       Court, Banihal in a frivolous
          operated batching plant in              injunction suit filed by the
          collusion     with       JKPCC          Applicant.
          without a valid CTO and             e. It is further submitted that the
          therefore it is violation of            Injunction Suit, as was filed by
          Section-15 & 16 of the                  the Applicant was dismissed
          Environmental Protection                vide order dated 15.07.2022 by
          Act 1986.                               the Court of Ld. Munsiff,
       e. It is argued by the Applicant           Banihal. Copy of order dated
          that the Project Proponent              15.07.2022 passed by Court of
          has not stated an iota of               Ld. Munsif, Banihal is enclosed
          word regarding CTO in its               as Annexure-8/15 @Page 172-
          objections        filed        on       183 along with Reply dated
          13.05.2023.                             03.12.2022
2   DAMAGE        CAUSED        TO      40       a. The Project Proponent seeks
    HOUSES DUE TO BLASTING                           to clarify that the damages
    ACTIVITY RESULTING TO A LOSS                     caused to the house of
    OF INR. 50 LACS. (approx.)                       Applicant      and      nearby
       a. Applicant while referring to               residents is not on account of
          Joint Committee report                     blasting but may be on
          dated 15.12.2022 @Page-                    account of inferior quality of
          194 has argued that Joint                  construction and ageing of
          Committee has observed                     the walls of the houses of on
          some cracks in walls of the                account of poor construction
          Applicant's house and other                quality.
          inhabitants residing nearby.           b. . Attention of the Hon'ble
       b. In regard to the above, the                Tribunal is invited to Page-
          Applicant further submitted                194 of the Joint Committee
          that the walls were cracked                Report dated 15.12.2022,
          due to blasting activity                   where it is captured that the
          carried out by the Project                 Joint Committee/ SDM has
          Proponent.     It     is     also          not been able to ascertain the
          allegedly that 40 houses                   cause of cracks in wall,
          were damaged due to the                    whether it was on account of
          blasting causing a total loss              blasting or on account of
          of approx. Rs. 50 lakhs.                   faulty construction.
                                                 c. At Page-329 a letter dated
                                                     12.04.2023 is enclosed which
                                                     is issued by IRCON to DC,
                                                     Ramban clarifying that the
                                                     Channar area does not qualify
                                                     for compensation, as the
                                                     structures in Channar village
                                                     are beyond 125 mtrs distance
                                                     from center line of alignment
                                                     of tunnels.
                                                 d. . Furthermore, at column-3
                                                     @page 392 of Action Taken
                                                     Report dated 12.08.2023 filed
                                                     by DC Ramban, it is recorded
                                                     that IRCON / R-7 has carried
                                                     out    geo-tagging    of   the
                                                     structures falling in the
                                                     alignment of Tunnel T-77D in
                                                     the year 2020, and none of

                                                                                 34
                                              the structures in Channar
                                             area fall within the ambit of
                                             125 mtrs. and do not qualify
                                             for         any           damage
                                             compensation, as agreed by
                                             Northern Railway on the
                                             demands projected by the
                                             locals of the area.
                                          e. In view of the above, the
                                             Applicant is not entitled to
                                             claim any compensation on
                                             account of alleged damage, if
                                             any caused to his house,
                                             more particularly the Project
                                             Proponent cannot be made
                                             liable to pay compensation to
                                             the Applicant.
3   CROP DAMAGE COMPENSATION              a. Joint Committee in its report
      a. The applicant has argued            dated 15.12.2022 has filed
         that he is not compensated          various records including a
         for the damage caused to            letter dated 08.12.2022 which
         the crops cultivated by him         is a report issued by the Office
         on account of discharge of          of Chief Hoticulture Officer,
         effluents by the Project            Ramban (enclosed at Page
         Proponent in the paddy              215), indicating that there is
         fields.                             no considerable damage to
      b. The compensation accessed           the Hoticulture plantations in
         by the Agricultural Officer to      the area on account of the
         the tune of Rs. 69,084/- is         activities carried out by the
         meager as against the total         Project Proponent.
         damage caused to the land        b. . Furthermore, the Action
         in question.                        Taken         Report        dated
      c. SDM Banihal has submitted           13.04.2023 filed by DM,
         false feedback to the Joint         Ramban also captures the
         Committee as regards the            relevant      facts     regarding
         ownership of the land,              assessment of compensation
         therefore compensation is           payable      by     the    Project
         not     released    to    the       Proponent i.e. INR 69,084/-
         Applicant.                          column-4 @Page no. 325
                                             towards the crop damages.
                                          c. . Further, at page-392 of the
                                             Action taken report filed by
                                             DC,        Ramban           dated
                                             12.08.2024,           particularly
                                             column-4, it is recorded that
                                             the Project Proponent has
                                             earlier paid an amount of INR
                                             69,084/-        on       21.07.23
                                             towards crop compensation
                                             and     INR     2,93,394/      on
                                             12.08.23 on account of
                                             additional compensation for
                                             crop damage, which amount
                                             is lying with SDM, Banihal.
                                          d. . As regards the payment of
                                             the compensation for crop
                                             damage and restoration of the
                                             agricultural land, Project
                                             Proponent                     has
                                             alreadydeposited              the
                                             aforesaid amounts. Now, as
                                             regards the question, whether

                                                                             35
                                            the Applicant is entitled to
                                           claim        the        aforesaid
                                           compensation             amount
                                           deposited by the Project
                                           Proponent, thus issue needs
                                           to be answered by the Official
                                           Respondents,                 more
                                           particularly DM & SDM,
                                           Ramban and by this Hon'ble
                                           Tribunal.
                                        e. During the hearing of the case
                                           on 27.08.2024, the DC,
                                           Ramban clarified that the
                                           land in question where the
                                           Applicant had cultivated the
                                           crops earlier belongs to
                                           government as per revenue
                                           records and the local villages
                                           including the Applicant has
                                           done illegal cultivation of the
                                           said land. Therefore, the
                                           Applicant is not entitled to
                                           any compensation on account
                                           of alleged damage caused to
                                           the Crops.
                                        f. In the above context, it is
                                           clarified that the Project
                                           Proponent has filed revenue
                                           records      alongwith        with
                                           objections dated 13.05.2023
                                           filed in response to 2nd Joint
                                           Committee       Report       dated
                                           17.04.2023, wherein at Page
                                           no. 380 387 [Annexure R-
                                           8/41]      enclosed      revenue
                                           records which confirms that
                                           the land in question where
                                           the Applicant had cultivated
                                           crops in past, belongs to
                                           government.
4   THREE-CHAMBERED                     a. The clarification to this
    SEDIMENTATION        TANK    GOT       submission       is    that the
    BURSTED ON DAY IT WAS                  sedimentation tank structure
    COMMISSIONED i.e. 06.04.2023           was dismantled by the Project
      a. As per applicant, JKPCC           Proponent on the directions of
         has concealed that the three      IRCON, as the same was no
         chambered sedimentation           longer        required,         as

tank busted on 06.04.2023. dewatering was permanently b. . Applicant gave information plugged from T-77A.

to SDM and DC, Ramban b. In this regard, the Project vide letter dated Proponent has given an 06.04.2023. undertaking affidavit to JKPCC, which is enclosed @Page 389 along with objections filed by the Project Proponent to the 2nd joint committee report.

c. In view of the above clarification, it is submitted that there is no strength to the allegation of the Applicant that the Sedimentation tank 36 got busted on the day it got commissioned.

7. The Applicant has belatedly filed the rejoinder making frivolous allegations against the Project Proponent and the other Respondents. There is no merit in any of the allegations levelled by the Applicant and the same are false and denied. It is falsely alleged by the Applicant in the Rejoinder that the Project Proponent has coerced and threatened the Applicant to withdraw the captioned Original Application and is filing cases. However, it is submitted that on account of regular nuisance and hindrances caused by the Applicant and his family at the Project site, the Project Proponent faced many challenges in completing the Project of such magnitude in the scheduled time considering the national importance of the Project.

8. In the above context, it is relevant to mention that the Project Proponent was compelled to report the illegal acts and actions of the Applicant and his family to the concerned local police and the administration. The following documents are sufficient to demonstrate the conduct of the Applicant and his family;

i.) Complaint was filed by the Project Proponent against the Applicant with P.S. Banihal on 26.02.2021 (enclosed at Page-121- Annexure R-8/5];

ii.) Letter dated 27.06.2022 written by Project Proponent to IRCON complaining about the hinderance caused by the Applicant in the Project [enclosed at Page-140-Annexure R- 8/8];

iii.) an injunction order dated 23.07.2024 was passed against the Applicant and his family by Ld. Munsiff Court, Banihal restraining them from illegally trespassing in the Project [enclosed at Page-141 -146-Annexure R-8/91; iv.) Letter dated 08.07.2022 written by Project Proponent to IRCON complaining about forceful closure of Batching Plant by Applicant and his family [enclosed at Page 147-Annexure R-8/10];

v.) Letters dated 28.06.2022 & 18.05.2022 issued by IRCON to Superintendent of Police as regards the hindrances caused by the Applicant and their family in working of the Project [enclosed at Page 159 & 160-Annexure R-8/12 (Colly.)]:

vi.) Letter dated 30.04.2023 was issued by Project Proponent to SHO, Banihal after some local and the Applicant attacked the Project site to stop the work, and request was made to register FIR against them [enclosed at Page 375-376- Annexure R-8/39].
vii.) Letter dated 02.05.2023 issued by DM, Ramban to SDM, Banihal for providing assistance to the Project Proponent. In this letter it was also informed that FIR No. 104/2023 has 37 been registered against the Applicant and others [enclosed at Page 379 Annexure R-8/40]."
20. On the question of payment of compensation, Deputy Commissioner, Ramban stated that land in question is a State land and therefore compensation is not payable to complainant, whereupon Tribunal directed Deputy Commissioner to place on record relevant documents in support of the stand.
21. Consequently, Deputy Commissioner, Ramban has submitted compliance report dated 27.09.2024 stating as under:-
The Sub Divisional Magistrate, Banihal vide his communication No. SDMB/2024- 25/402 dated 14.09.2024 submitted his report, which reveals that:- 1. As per Khasra Girdawari- Rabi (Year: 1955);
• Land bearing Khasra No. 638/582 measuring 01M is recorded in the ownership of State (Malkiyati Sarkaar) but in possession of Khazir, Habib etc. who are recorded as Gair Maroosi. The land type is recorded as: GM Gharhat. • Land bearing Khasra No. 649/582 measuring 01K-18M is recorded in the ownership of State (Malkiyati Sarkaar) but in possession of Khazir, Habib etc. who are recorded as Gair Maroosi The land type is recorded as: Abi Doem. • Land bearing Khasra No. 647/582 measuring 17M is recorded in the ownership of State (Malkiyati Sarkaar) but in possession of Khazir, Habib etc. who are recorded as Gair Maroosi. The land type is recorded as: Abi Doem (for 8M) and GM Nalla (for 09M).
2. As per Khasra Girdawari - (Year: 1956-1966);

• All of the aforementioned Khasra Nos were in the possession of same persons viz., Khazir, Habib etc. for the period 1956-1966. • Further, the land continued to be recorded in the ownership of State.

3. As per Khasra Girdawari- Rabi (Year: 1967); • Except Khasra No. 638/582 measuring 01M, the recorded entries of the aforementioned persons (as cultivators/possessors) were not reflected in the remaining Khasra Nos in the revenue record. • However, the land continued to be recorded in the ownership of State.

4. As per Khasra Girdawari - (Year: 1967-1989); • The same entries were continued for the period 1967-1989 (Rabi).

38

5. As per Khasra Girdawari- Kharief (Year, 1989):

• Land bearing Khasra No. 648/582 measuring 10K was recorded in the ownership of State but in the possession of new persons viz, Ahmed, Ghulam, Ramzan, etc. Ss/o Khazir, Habib, etc. • Land bearing Khasra No. 638/582 measuring 01M continued to be recorded in the ownership of State but in the possession of Khazir, Habib, etc.

6. As per Khasra Girdawati (Year, 1989-2019); • The same entries were continued for the period 1989-2019 (Rabi)

7. As per Khasra Girdawari Kharief (Year: 2019); • The recorded entries of the aforementioned persons (as cultivators/possessors) were expunged from the Khasra No. 648/582 and Khasra No. 638/582. The said entries were expunged in compliance with the directions issued by the Hon'ble High Court of Jammu & Kashmir in WP PIL No. 19/2011 and MP No. 10/2016 case titled SK Bhalla V/s State & Ors. • Subsequently, the land was recorded in the ownership and possession of State, which continues till date.

It is pertinent to mention that u/s 133 sub section (2-A) (a) (ii) of the Land Revenue Act 1996 B.K any encroachment on the State Land including in the form of cultivation can be removed without paying any compensation for crops. The relevant excerpt is produced below. 133 (2-A) Penalty for denial of or obstruction in the exercise of right or for encroachment; (a) Where any person is denied, or obstructed in, the lawful exercise of his right of user as provided in sub-section (1), or where any person has taken possession of or brought under cultivation or otherwise encroached upon any common land as described above, or when any person, without due authority, has taken possession of land belonging to the Government, a Revenue Officer may, on his own motion or on the application of any person interested and after such enquiry as may be deemed necessary,-

(ii) eject the person who has taken possession of or brought under cultivation or otherwise encroached upon such common land and take possession of such land without paying any compensation for crops or improvements, and may also, by order duly proclaimed, forbid repetition of the encroachment;

In the light of above facts, it is submitted that the petitioners are not entitled for the crop compensation in the instant case."

22. The matter was heard by Tribunal on 22.10.2024 when applicant with reference to document on record on page 445 showed that he is owner 39 of land in question. In reply thereto no appropriate document could be shown by State Authority. Thus Tribunal required Deputy Commissioner to remain present on next date to explain as to why compensation is not payable to applicant in view of documents relied by him which is at page 445 of paper book.

23. Today when the matter was taken up, neither Deputy Commissioner, Ramban is present nor any counsel has appeared on his behalf and in fact on behalf of State Authorities no one has represented.

24. In these facts and circumstances, we have no option but to issue bailable warrant to Deputy Commissioner, Ramban of the sum of Rs.

25,000/- to the satisfaction of the arresting officer, in exercise of our powers and in terms of provisions of Section 19(4) (a) of National Green Tribunal Act, 2010 read with order XVI Rule 10(3) and Section 15 of Code of Civil Procedure, 1908 for securing presence before Tribunal on the next date i.e. 09.12.2024.

25. List the matter on 09.12.2024.

26. A copy of this order be forwarded to Deputy Commissioner, Ramban by email for compliance.

Sudhir Agarwal, JM Dr. Afroz Ahmad, EM November 18, 2024 Original Application No. 706/2022 ( IA NO 260/2022 ) AB 40