Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 11, Cited by 0]

Karnataka High Court

Mantri Developers Pvt Ltd vs Gokulam Shelters Private Limited on 16 December, 2025

                            -1-
                                      WP No. 36101 of 2024



     IN THE HIGH COURT OF KARNATAKA AT BENGALURU

       DATED THIS THE 16TH DAY OF DECEMBER, 2025

                        PRESENT
        THE HON'BLE MR. JUSTICE JAYANT BANERJI
                            AND
        THE HON'BLE MR. JUSTICE UMESH M ADIGA
       WRIT PETITION NO. 36101 OF 2024 (GM-RES)
BETWEEN:

MANTRI DEVELOPERS PVT LTD,
A COMPANY INCORPORATED UNDER
THE COMPANIES ACT, 1956, HAVING ITS
REGISTERED OFFICE AT, C-5, RICH HOMES,
NO.5/1, RICHMOND ROAD, BANGALORE -560 025,
REP. BY ITS DIRECTOR, MR.MOHAN KUMAR S.J
                                         ...PETITIONER
(BY SRI.BASAVARAJ S., SENIOR COUNSEL FOR
    SMT.JAITHRA J NARAYAN, ADVOCATE)

AND:

1.    GOKULAM SHELTERS PRIVATE LIMITED,
      A COMPANY EXISTING UNDER
      THE COMPANIES ACT, 2013,

2.    KRISHNA LILA PARK FOUNDATION,
      A REGISTERED TRUST,

3.    ISKCON CHARITIES,
      A REGISTERED TRUST,

4.    INDIAN HERITAGE FOUNDATION,
      A REGISTERED TRUST,
                            -2-
                                   WP No. 36101 of 2024



     RESPONDENT Nos.1 TO 4 HAVING OFFICE AT 8TH
     MILE,DODDAKALLASANDRA POST, KANAKAPURA
     MAIN ROAD, BENGALURU-560 062.
     REP. BY ITS AUTHORISED REPRESENTATIVE,
     SRI.SHAMA SUNDER MUDUKUTHORE.

5.   M/S CASTLES VISTA PVT. LTD,
     A COMPANY EXISTING UNDER
     THE COMPANIES ACT, 2013 AND
     HAVING ITS OFFICE AT C-5,
     RICH HOMES, NO.5/1, RICHMOND ROAD,
     BENGALURU-560 025,
     REP. BY ITS MANAGING DIRECTOR.
                                          ...RESPONDENTS
(BY SRI.K.G.RAGHAVAN, SENIOR COUNSEL FOR
    SRI.PRADEEP NAIK, AVOCATE FOR R1 TO R4;
    SRI.DHANANJAY JOSHI, SENIOR COUNSEL FOR
    SRI.ANISH ACHARYA, ADVOCATE FOR R5)


     THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA PRAING TO (A)
ISSUE A WRIT ORDER OF DIRECTION SETTING ASIDE THE
ORDER DATED 28/11/2024 PASSED BY THE ARBITRAL
TRIBUNAL IN THE MATTER BETWEEN GOKULAM SHELTERS
PVT. LTD., AND OTHERS VS. CASTLES VISTA PVT. LTD.,
WHEREIN THE ARBITRAL TRIBUNAL BY MAJORITY HAS
ALLOWED THE IA NO.V PRODUCED AS ANNEXURE-A, (B)
GRANT SUCH OTHER AND FURTHER ORDERS.


     THIS WRIT PETITION HAVING BEEN HEARD AND
RESERVED FOR ORDERS ON 09.09.2025, COMING ON FOR
'PRONOUNCEMENT OF ORDER' THIS DAY, THE COURT MADE
THE FOLLOWING:


CORAM:    HON'BLE MR. JUSTICE JAYANT BANERJI
          AND
          HON'BLE MR. JUSTICE UMESH M ADIGA
                                      -3-
                                               WP No. 36101 of 2024



                               CAV ORDER
                (PER: HON'BLE MR. JUSTICE JAYANT BANERJI)


     1.        The array of parties in this petition is as under:


                                                RANK OF THE PARTIES
                                           ARBITRATION     HIGH COURT
     MANTRI DEVELOPERS PVT LTD,1
     A COMPANY INCORPORATED UNDER          RESPONDENT       PETITIONER
     THE COMPANIES ACT, 1956, HAVING          NO.2
     ITS REGISTERED OFFICE AT, C-5, RICH
     HOMES, NO.5/1, RICHMOND ROAD,
     BANGALORE-560025, REPRESENTED BY
     ITS DIRECTOR, MR.MOHAN KUMAR S.J.


                      AND:


1.   GOKULAM SHELTERS2
     PRIVATE LIMITED,                       CLAIMANT      RESPONDENT
     A COMPANY EXISTING UNDER THE             NO.1           NO.1
     COMPANIES ACT, 2013

2.   KRISHNA LILA PARK FOUNDATION3,         CLAIMANT      RESPONDENT
     A REGISTERED TRUST                       NO.2           NO.2

3.   ISKCON CHARITIES4                      CLAIMANT      RESPONDENT
     A REGISTERED TRUST                       NO.3           NO.3

4.   INDIAN HERITAGE FOUNDATION5            CLAIMANT      RESPONDENT
     A REGISTERED TRUST                       NO.4           NO.4

     GSPL TO 4 HAVING OFFICE AT
     8TH MILE, DODDAKALLASANDRA POST,
     KANAKAPURA MAIN ROAD,
     BENGALURU-560 062,


     REPRESENTED BY ITS AUTHORISED
     REPRESENTATIVE
     SRI.SHAMA SUNDER MUDUKUTHORE




1
  Mantri Developers
2
  Gokulam Shelters
3
  Krishna Lila
4
  ISKCON Charities
5
  IHF
                                    -4-
                                              WP No. 36101 of 2024



5.    M/S. CASTLES VISTA PVT. LTD.,6      RESPONDENT   RESPONDENT NO.5
     A COMPANY EXISTING UNDER THE            NO.1
     COMPANIES ACT, 2013 AND HAVING ITS
     OFFICE AT C-5, RICH HOMES, NO.5/1,
     RICHMOND ROAD, BENGALURU-560 025
     AND REPRESENTED BY ITS MANAGING
     DIRECTOR.




       2. The instant petition has been filed seeking to set aside

of an order dated 28.11.2024 passed by the Arbitral Tribunal

whereby the Arbitral Tribunal by majority has allowed an

application bearing IA No.5 filed by the claimants.


       3. By the IA No.5 the claimants had sought impleadment

of Mantri Developers under Section 2(1)(h) read with Section 7

of the Arbitration and Conciliation Act, 19967. By the impugned

order of 28.11.2024, the Arbitral Tribunal by majority, allowed

the application aforesaid, directing impleadment of Mantri

Developers on the ground that even though it is non-signatory

to the arbitration agreement, it has by its action and conduct

consented to be bound by the arbitration agreement.               For

coming up this conclusion, the Arbitral Tribunal, by majority

relied upon the judgment of the Supreme Court in M/s. ONGC

Limited Vs. Discovery Enterprises Pvt. Ltd.8, which was

approved in the judgment of the Supreme Court in Cox and


6
  Castles Vista
7
  Act 1996
8
  (2022) 8 SCC 42
                                      -5-
                                                 WP No. 36101 of 2024



Kings Ltd. Vs. SAP India Pvt. Ltd.9, Consequential directions

were also issued.


         4.    The case set out in the petition is that, Mantri

Developers          being   a   Company       incorporated   under     the

Companies Act, 1956 is a pioneer developer in real estate

sector around Bengaluru and other cities which has undertaken

various development activities both residential and commercial.

It has also received prestigious awards in the field of real estate

development.           Gokulam Shelters (Respondent No.1) is a

company incorporated under the Companies Act, which is

majorly involved in achieving the aims and goals of the

Respondent Nos. 2 to 4, that is, Krishna Lila, ISKCON Charities,

IHF, who are the Claimant Nos. 1 to 4 in the arbitration

proceedings. Castles Vista is the respondent in the arbitration

proceedings.


         5. ISKCON Charities and IHF, being the land owners of

certain plots of land, approached Mantri Developers to develop

the     lands.       Pursuant   to   which,   the   petitioner   and   the

Respondent Nos.3 and 4 entered into an agreement dated

26.06.2010 with regard to the development and purchase of

the portion of lands belonging to the Respondent Nos.3 and 4.
9
    (2024) 4SCC 1
                                     -6-
                                                  WP No. 36101 of 2024



Thereafter, they entered into a supplementary agreement

dated 29.07.2010 incorporating certain changes in the terms

and        conditions, which agreement        was    in   the   nature    of

addendum/amendment to the first agreement of 26.06.2010.


           6. Thereafter a second supplementary agreement10 dated

29.09.2010 was entered into by them, wherein the rights and

obligations under the framework agreement were assigned by

the Respondent Nos.3 and 4 to the Respondent No.1- Gokulam

Shelters. Mantri Developers assigned its rights to Castles Vista.

It is stated that the assignment of rights under the SSA

transferred all responsibilities from the petitioner to Castles

Vista.


           7.   It is stated that, this effectively severed and

terminated all prior legal relationships between the petitioner

and the Respondent Nos.3 and 4 leaving Castles Vista as the

sole party responsible for the obligations under the separate

Joint Development Agreement11 dated 29.09.2010. It is stated

that the petitioner had exited from the entire transaction

including       the   performance   of    their   obligations/rights     and


10
     SSA
11
     JDA
                                        -7-
                                                WP No. 36101 of 2024



liabilities under the prior agreements. The JDA was registered

in the Office of the Sub-Registrar, J.P.Nagar, Bengaluru, which

was entered into between the Gokulam Shelters, as 'Land

Owner', ISKCON Charities and IHF, as Confirming Parties, and

the Respondent No.5-Castles Vista as 'Developer'.


           8. That Gokulam Shelters also executed an irrevocable

General Power of Attorney12 dated 29.09.2010 authorizing

Castles Vista to do all such acts and deeds in relation to the

development and construction on the JDA property. Pursuant

to the execution of JDA, several amendments to the agreement

took       place    on   08.12.2010,     24.07.2012,   19.01.2015   and

05.06.2018, either to rectify the drafting errors or capturing the

subsequent events or to amend the terms of the JDA.


           9. Thereafter, Castles Vista commenced its construction

activities     by    obtaining   necessary    approvals   from   various

authorities to construct multi-storied residential apartments in

phased manner. In order to finance the construction, Castles

Vista availed financial assistance from Piramal Capital and

Housing Finance Limited and executed a loan agreement dated

30.04.2018 by mortgaging JDA properties after consent from


12
     GPA
                                 -8-
                                          WP No. 36101 of 2024



Gokulam Shelters Pvt. Ltd., The petitioner-Mantri Developers

stood guarantor to the said loan transaction. To secure the

term loan, various documents were executed between the

parties viz.,-


        i)    Deed of Hypothecation dated 30.04.2018

       ii)    Deed of Pledge dated 30.04.2018

       iii)   Memorandum of Deposit of Title Deeds dated
              05.06.2018

      iv)     Security Trustee Agreement dated 05.06.2018


Thereafter, certain disputes arose between Castles Vista and

Gokulam Shelters which were very specific to the JDA, due to

which, GSPL along with IHF and ISCKON Charities, invoked

arbitration clause in JDA and accordingly, the Arbitral Tribunal

was constituted.


      10.     Respondent Nos.1 to 4 filed their claim petition and

Castles Vista filed its statement of objections and counterclaim.

An application numbered as I.A. No.5 was filed on behalf of

respondent Nos.1 to 4 seeking to implead the petitioner -

Mantri Developers to the arbitration proceedings on the basis of

'Group of Companies Doctrine'. Objections were filed both by

Mantri Developers and Castles Vista.
                                 -9-
                                            WP No. 36101 of 2024



     11.      After hearing both the parties, the impugned order

was passed.


      12.     The contention is that respondents Nos.1 to 4 in

their application have not made out any direct contractual

relationship between the petitioner - Mantri Developers and

execution of JDA. The dispute is strictly between Gokulam

Shelters and the Castles Vista with the relief sought by the

Gokulam Shelters and other claimants being exclusively against

Castle Vista.    The Mantri Developers having no role in the

execution or performance of the JDA cannot be made a party to

the arbitral proceedings.     There is lack of mutual intent on

behalf of Mantri Developers to uphold the rights or obligations

under the primary agreement and supplementary agreement.

Instead, there exists clear intent to sever such ties leading to

inovation and execution of an unambiguous JDA.                 Mantri

Developers has not participated in any activities related to the

execution or performance of the JDA.               Limited secretarial

practices,    such   as   facilitating   certain     correspondences

unrelated to JDA execution or providing conditional guarantees

for funding     or having common employees cannot establish

mutual intent to bind the Mantri Developers to the JDA.           The

submission is that the mutual intent of the parties must be
                                     - 10 -
                                                   WP No. 36101 of 2024



assessed     specifically   concerning       the    JDA   and   not   other

independent transactions unconnected to its execution or

performance.


       13. Secondly, it is urged that concerning the relationship

of non-signatory to a party to the agreement, pertains to the

Group of Companies Doctrine but does not, by itself, satisfy the

criteria.


       14.   Thirdly, commonality of the subject matter must

relate to the execution or performance of the JDA.                         The

petitioner-Mantri Developers has no such commonality with the

parties to the JDA in the activities of the parties to the JDA and

the Castles Vista.


       15. Fourthly, the composite nature of the transaction

pertains to the JDA's execution and the performance, which

clearly does not involve the petitioner herein in any capacity.

Mantri Developer role as a guarantor to Piramal Finance to

imply direct obligations under the JDA is misplaced because its

role   as    mentioned      under      the    loan    agreement       as     a

Guarantor/obligor is restricted to that extent and cannot be

interlinked with the rights and obligations arising out of JDA

which is exclusively between respondent Nos.1 to 4 and Castles
                                    - 11 -
                                               WP No. 36101 of 2024



Vista. The corporate guarantee furnished by Mantri Developers

has an independent arbitration clause with the specific triggers

like Castle Vista's loan default, which has not occurred, and

therefore, reliance on the same is premature. The Tribunal has

gone beyond the scope of reference by assuming jurisdiction

even under the independent Corporate Guarantee. It is stated

that the Tribunal has erred in considering that loan documents,

corporate      guarantee     and    JDA     constitute   a   composite

transaction.


     16.       Lastly, it is urged that the performance of the

contract is confined with the relationship between the signatory

parties and Mantri Developers has no role in its execution. It is

submitted that the SSA dated 29.09.2010 transferred Mantri

Developers'     obligation   to    Castle    Vista,   severing   Mantri

Developer's     contractual ties with Gokulam Shelters regarding

the JDA.


   17.      The learned counsel has referred to the various terms

in the first supplementary agreement and SSA in this regard.

The agreements with Piramal Finance               are stated to be

independent of the JDA and were structured solely to finance

Castle Vista construction activities. Mantri Developers role was
                                - 12 -
                                          WP No. 36101 of 2024



limited to provide financial security as a guarantor with no

obligations. These agreements, distinct in purpose and terms,

were acknowledged by respondent Nos.1 to 4 in the Fourth

Amendment to the JDA as separate arrangements. It is stated

that the Respondent Nos.1 to 4 having filed a commercial suit,

have impliedly admitted that the loan transactions and the JDA

transactions are distinct and independent of each other.



      18.   On behalf of the Respondent No.1, a statement of

objections to the writ petition was filed in which maintainability

of the petition has been questioned on the ground of non-

disclosure, inter alia, that the Respondent No.5 is a wholly

owned subsidiary of the petitioner. Further it has been stated

that under Section 16 of the Act, 1996, the Arbitral Tribunal

possesses exclusive powers to decide its jurisdiction and is the

proper forum to determine whether the petitioner is a party to

the arbitration agreement. It is further stated that, this Court

ought not to interfere in the impugned order passed in exercise

of jurisdiction under Section 16 of the Act, 1996 while

exercising powers under Article 227 of the Constitution,

inasmuch as the scheme of the Arbitration Act contemplates

minimal judicial interference in Arbitration Proceedings. No
                                        - 13 -
                                                  WP No. 36101 of 2024



exceptional circumstances or perversity on the face of the

impugned order has been demonstrated by the petitioner

warranting interference by this Court.                  In this regard, a

reference has been made to the judgment of the Apex Court in

SBP & Co. Vs. Patel Engineering Ltd.13 and the judgment of

the Supreme Court in Deep Industries Ltd. Vs. ONGC14.


        19. It is stated that the Act of 1996 is a complete Code

and it provides sufficient safeguards to the parties to an

arbitration leaving little to no scope to avoid the statutory

scheme         and   seek        interference   under    the   supervisory

jurisdiction of this Court. It is only the Arbitral Tribunal which

would decide if a non-signatory is a party to an arbitration

agreement and, consequently to implead.                 In this regard, the

learned counsel has referred to the judgments of the Supreme

Court     in    Bhavan          Constructions    Vs.    Sardar    Sarovar

Narmada Nigam Ltd.15 and the judgment in Cox and Kings

Ltd. Vs. SAP India (P) Ltd.16


        20. It is stated that the Arbitral Tribunal has carefully

assessed the complex factual matrix in the present case, the


13
   (2005) 8 SCC 618 (Para-46)
14
   (2020) 15 SCC 706
15
   (2022) 1 SCC 75.
16
   (2024) 4 SCC 1
                                   - 14 -
                                             WP No. 36101 of 2024



various contractual clauses, representations and warranties of

the parties as well as commercial role of the parties in dispute

while passing the impugned order.            It is stated that the

impugned order is well-reasoned which considers in detail the

relevant five-factors test mandated in ONGC Vs. Discovery

Enterprises Pvt. Ltd.17. The judgment of the Supreme Court

in Ajay Madhusudan Patel Vs. Jyotrindra S. Patel18 has

also been referred to.       It is stated that a party aggrieved by

any order of the Arbitral Tribunal has a right of appeal under

Section 37 of the Act, 1996, and has to await passing of the

award by the Arbitral Tribunal.


          21.    It is stated that, Castle Vista is held by the

petitioner-Mantri Developers as a subsidiary Company, which

holds 99.9% of the share-holding in Castle Vista.                The

remaining 0.1% is also owned by Mr. Sushil Mantri and Ms.

Snehal Mantri, who are the Directors of the Company.


          22.    It is stated that on the basis of the representation

of the petitioner to the respondent-Gokulam Shelters and

ISCKON Charities that it had the means and expertise to

develop the property into a residential complex and a cultural


17
     (2022) 8 SCC 42
18
     (2025) 2 SCC 147
                                    - 15 -
                                                      WP No. 36101 of 2024



theme park, ISCKON Charities and IHF executed an agreement

with the petitioner on 26.06.2010 agreeing to execute the JDA,

wherein the petitioner agreed to develop the property.                     That

agreement stipulates that the parties to it will execute the JDA

and that the petitioner-Mantri Developers would be entitled to

70% of the super built-up area and undivided interest in the

property.     As consideration for the 2010 agreement, the

petitioner-Mantri Developers paid a sum of Rs.15.00 Crores in

favour of ISCKON Charities, which amount is to be adjusted

against the final sale consideration /refundable security deposit

to be paid in respect of the Item No.1 and/or Item No.2

mentioned     in    the   agreement.             On    29.07.2010,    a    First

Supplementary        Agreement       was         executed     between       the

petitioner-Mantri Developers and, ISCKON Charities and IHF,

under which agreement, the petitioner-Mantri Developers paid

another sum of Rs.5.00 Crores.               The respondents Gokulam

Shelters, ISCKON Charities and IHF were led to believe in the

commitment         and    involvement       of    the    petitioner   in    the

development of the properties, in view of its significant

investment.


     23.    On       29.09.2010,      the         Second     Supplementary

Agreement (SSA) was executed between the petitioner-Mantri
                               - 16 -
                                        WP No. 36101 of 2024



Developers and the Respondents Gokulam Shelters, ISCKON

Charities and IHF as well as Castle Vista, whereunder, the

ISCKON Charities and IHF assigned their rights and obligations

under the first agreement to Gokulam Shelters. The petitioner-

Mantri Developers nominated Castle Vista (then known as Land

Masters Realtors Pvt. Ltd.) to take on the rights, duties and

obligations of the petitioner-Mantri Developers under the 2010

agreement.    The SSA also records that the respondents and

Castle Vista will execute the proposed JDA.


     24. On 29.09.2010 itself, Gokulam Shelters and Castles

Vista executed the JDA for the development of the property

through the construction of a residential project.   It is stated

that the JDA was executed subsequent to negotiations and

discussions between the petitioner-Mantri Developers and the

Respondents Gokulam Shelters, ISCKON Charities and IHF.



     25.     It is stated that under clauses 6, 7 and 9 of the

JDA, Castles Vista is required to develop the project on the

property entirely at their cost and expense. In consideration of

Gokulam Shelters granting the exclusive right to Castles Vista

to develop the property by constructing a residential complex,

Gokulam Shelters along with ISCKON Charities and IHF were
                                - 17 -
                                           WP No. 36101 of 2024



entitled to 30% of the sale proceeds in the defined in the JDA

of various units in the project. In terms of clause 16 of the JDA,

Castles Vista was entitled to take loans and financial assistance

from banks, financial institutions or any third-party credit

agencies for persons for development of the project against the

security of the areas demarcated to its share alone. Castles

Vista was solely responsible for the repayment of any loans and

the discharge of any mortgage/charge created. Under clause 23

of the JDA, there was also a specific stipulation that the name

'Mantri' and the logo of the petitioner-Mantri Developers will

always remain in the project. It is stated that accordingly, as

on date, the project continues to be called the "Mantri Serenity"

project.


      26.   It is stated that Mantri Developers and its personnel

were involved in liaising with the claimants for the construction

of the Project. From the execution of the JDA in 2010, it has

always been the petitioner-Mantri Developers that has been

coordinating   with   Gokulam       Shelters,   and   through   its

representatives including its Managing Director and its General

Manager, were providing various updates regarding the status

of the project, inventory, cash flow, statements etc. and was

involved in the day-to-day performance of the JDA. It is also
                                    - 18 -
                                                WP No. 36101 of 2024



stated that a few months after the registration of the JDA, the

petitioner-Mantri   Developers        also    wrote    a   letter   to    the

homeowners in the project explaining that it has been brought

in to develop the project. The letter further explains that it will

also be taking bookings for the units in the project. Reference

has been made to a letter issued by the petitioner to the

homeowners on 25.10.2010. It is also stated that the petitioner

also released several advertisements for the project under its

name and logo. Various other emails emanating from the

domains belonging to Mantri Developers, agreement, loan

agreement, corporate guarantee are referred to endeavour to

demonstrate the intention of the petitioner-Mantri Developers

to be bound by the JDA. The negotiations leading to the

sanction of Rs.650 crores by Piramal Group are stated to have

been carried out by Mantri Developers and Castles Vista

without the knowledge of the claimants, though they pertained

to creation of charge over the claimants' share. Mantri

Developers had active obligations under the loan agreement.


      27.    We now proceed to discuss the case of Deep

Industries    which   is   cited      by     learned   counsel      for   the

respondents as regards the issue of maintainability of this

petition. The Supreme Court in the case of Deep Industries
                                  - 19 -
                                              WP No. 36101 of 2024



was considering a case where, after termination of the contract,

on the very next day the vendor code of the appellant was

blocked, and a show cause notice was issued to the vendor as

to why it should not be blacklisted for a period of two years.

The appellant therein invoked the arbitration clause contained

in the contract and a sole arbitrator was appointed. About two

weeks after the claim petition was filed, the appellant was

blacklisted for two years by an order. Application under section

17 of the Act, 1996 was filed before the learned arbitrator.

Applications to amend the petition and a Section 17 application

were moved by the appellant, which were allowed.


       27.1. Meanwhile a Section 16 application was moved

before the learned arbitrator basically on the ground that since

the arbitration notice was confined only to termination of the

agreement, blacklisting would be outside the                   arbitrator's

jurisdiction. This application was dismissed by the arbitrator.

On that very day the Section 17 application was disposed of by

the learned arbitrator by an order in which the operation of the

order of blacklisting was stayed on the condition that the two-

year   ban/blacklisting   will   only     operate   if   the    Appellant

ultimately loses in the final arbitration proceedings.
                                - 20 -
                                          WP No. 36101 of 2024



      27.2.       An appeal against the stay order granted by

the arbitrator was filed before the City Civil Court which upheld

the order of the learned arbitrator and dismissed the appeal

filed under Section 37. At this stage a petition under article 227

of the Constitution was filed before the High Court challenging

the order of the City Civil Court. The High Court without

answering the question as to whether the petition filed under

article 227 should be dismissed at the threshold, as it did not

raise any jurisdictional issue, went on to state that the

blacklisting order had been passed not under a clause of the

agreement but under a General Contract Manual, as a result of

which a serious dispute arose as to the jurisdiction of the

arbitrator to deal with the same. The High Court finally held

that no stay could possibly have been granted under Section 17

with regard to the blacklisting order as an injunction could not

be granted in cases where party can be compensated later in

damages. The petition was allowed and the civil courts order

was set aside.


      27.3.       After noticing the time limit introduced under

section 29-A by the Amendment Act, 2016 of 12 months within

which the arbitral award must be made from the date the

arbitral tribunal enters upon the reference, it was noticed that
                                        - 21 -
                                                    WP No. 36101 of 2024



even so far as section 34 applications are concerned, section 34

(6)   added      by    the     same    amendment,        states      that   these

applications are to be disposed of expeditiously and in any

event within a period of one year from the date on which the

notice referred to in sub-section (5) is served upon the other

parties.


      27.4.            The non-obstante clause contained in section

5 was noticed. It was also observed that section 37 grants a

constricted right of first appeal against certain judgments and

orders and no others. A second appeal cannot be filed. It was

observed      that     that    being   the      case,   there   is    no    doubt

whatsoever that if petitions were to be filed under Articles

226/227 of the Constitution against orders passed in appeals

under section 37, the entire arbitral process would be derailed

and will not come to fruition for many years. It was also

observed that at the same time, it cannot be forgotten that

Article    227    is   a      constitutional     provision   which      remains

untouched by the non-obstante clause of section 5 of the Act,

1996. Though petitions can be filed under Article 227 against

judgments allowing or dismissing first appeals under section 37

of the Act, 1996, yet the High Court would be extremely

circumspect in interfering with the same, taking into account to
                                       - 22 -
                                                    WP No. 36101 of 2024



the statutory policy so that interference is restricted to orders

that are      passed        which are       patently     lacking   in inherent

jurisdiction.


      27.5.          After noticing its various judgments, the

Supreme Court referred to the case of SBP & Co. and quoted

its extract as under: -


      "19. In SBP & Co. [SBP & Co. v. Patel Engg. Ltd., (2005) 8
   SCC 618] , this Court while considering interference with an order
   passed by an Arbitral Tribunal under Articles 226/227 of the
   Constitution laid down as follows: (SCC p. 663, paras 45-46)


          "45. It is seen that some High Courts have proceeded
      on the basis that any order passed by an Arbitral Tribunal
      during arbitration, would be capable of being challenged
      under Article 226 or 227 of the Constitution. We see no
      warrant for such an approach. Section 37 makes certain
      orders of the Arbitral Tribunal appealable. Under Section
      34, the aggrieved party has an avenue for ventilating its
      grievances against the award including any in-between
      orders that might have been passed by the Arbitral
      Tribunal acting under Section 16 of the Act. The party
      aggrieved by any order of the Arbitral Tribunal, unless has
      a right of appeal under Section 37 of the Act, has to wait
      until the award is passed by the Tribunal. This appears to
      be the scheme of the Act. The Arbitral Tribunal is, after all,
      a   creature     of    a   contract      between   the   parties,   the
      arbitration agreement, even though, if the occasion arises,
      the Chief Justice may constitute it based on the contract
                                  - 23 -
                                              WP No. 36101 of 2024



     between the parties. But that would not alter the status of
     the Arbitral Tribunal. It will still be a forum chosen by the
     parties by agreement. We, therefore, disapprove of the
     stand adopted by some of the High Courts that any order
     passed by the Arbitral Tribunal is capable of being
     corrected by the High Court under Article 226 or 227 of
     the Constitution. Such an intervention by the High Courts
     is not permissible.


        46. The object of minimising judicial intervention while
     the matter is in the process of being arbitrated upon, will
     certainly   be   defeated   if   the   High   Court   could   be
     approached under Article 227 or under Article 226 of the
     Constitution against every order made by the Arbitral
     Tribunal. Therefore, it is necessary to indicate that once
     the arbitration has commenced in the Arbitral Tribunal,
     parties have to wait until the award is pronounced unless,
     of course, a right of appeal is available to them under
     Section 37 of the Act even at an earlier stage.""


     27.6.        It was observed that this statement of law (in

SBP & Co.) does not apply directly on the facts of the case, yet

it is important to notice that the 7 Judge bench in SBP & Co.

has referred to the object of the Act, 1996 being that of

minimising judicial intervention and that this important object

should always be kept in mind in the forefront when an Article

227 petition is being disposed of against proceedings that are

decided under the Act, 1996. It was further noted that in the

case of Punjab Agro industries Corpn. Ltd. v. Kewal Singh
                                         - 24 -
                                                    WP No. 36101 of 2024



Dhillon19, this Supreme Court distinguished SBP & Co. stating

that it will not apply to a case of non-appointment of an

arbitrator. The observations of the Supreme Court in Punjab

Agro industries were for the reason that no provision for appeal

had been given by statute against the orders passed under

section      11,    which    is   why     the    High   Court's   supervisory

jurisdiction first be invoked before going to the Supreme Court

under Article 136. The Supreme Court observed that the facts

of the case in Deep Industries was distinguishable for the

reason that Article 227 jurisdiction was exercised by High Court

only after a first appeal was dismissed U/s 37 of the Act, 1996.

Even otherwise it was found that whether or not an injunction

ought to have been issued, is a mere error of law and not an

error of jurisdiction, much less an error of inherent jurisdiction

going to the root of the matter.


          27.7.          The Supreme Court held that the legislative

policy is that no revision lies under section 115 CPC if an

alternative remedy of appeal is available. Moreover, even when

a revision does lie, it lies only against a final disposal of the

entire matter and not against interlocutory orders. Therefore

the general revisional jurisdiction that is contained by the
19
     (2008) 10 SCC 128
                                 - 25 -
                                           WP No. 36101 of 2024



amendments made to Section 115 CPC should be kept in mind

when the High Courts dispose of petitions filed under Article

227.


         28.   The aforesaid judgment in Deep Industries was

followed in yet another three Judge Bench of the Supreme

Court in the case of Bhaven Construction. After observing its

mandate in the case of Nivedita Sharma Vs. Cellular

Operators Association of India20, the Court in Bhaven

Construction observed that it is prudent for a Judge to not

exercise discretion to allow judicial interference beyond the

procedure established under the enactment. This power needs

to be exercised in exceptional rarity, wherein one party is left

remediless under the statute or a clear "bad faith" shown by

one of the parties. The Court observed that this high standard

set by the Supreme Court is in terms of the legislative intention

to make the arbitration fair and efficient.


         29.   We may now discuss the facts of the present case.


         29.1. The petitioner-Mantri Developers entered into an

agreement dated 26.06.2010 with ISKCON Charities and IHT.

In the said agreement, the Mantri Developers represented that

20
     [(2011) 14 SCC 337]
                               - 26 -
                                         WP No. 36101 of 2024



it is carrying on the business of property development and is

interested in purchasing absolutely from ISKCON Charities

and IHT (Land Owners), the Item No.1 land of the Schedule to

the agreement and that it had also means and expertise to

develop the Item No. 2 land of the Schedule property; that

Mantri Developers being desirous of purchasing the Item No.1

of the Schedule Property and developing Item No.2 land of the

Schedule Property on a Joint Development basis is entering into

the agreement based on certain representations of the Land

Owners. All disclosures were made by the land owner regarding

encumbrances, the legal proceedings, etc., and on the basis of

the representations and the facts given by the land owners, the

land owners offered to sell the Item No.1 land of the schedule

property and to convey the same absolutely in favour of the

Mantri Developers, and also agreed to irrevocably empower and

authorize Mantri Developers to develop Item No.2 land of the

Schedule property on joint Development basis and Mantri

Developers agreed to accept the said offer on compliance by

the land owners of the terms set-out in the agreement.


     29.2. Under that agreement, Mantri Developers was

entitled to publish a public notice in the Newspapers calling for

claims with respect to the Schedule property, which claims the
                                - 27 -
                                           WP No. 36101 of 2024



land owners were responsible for clearing entirely at their own

cost, failing which Mantri Developers at its sole discretion is

entitled to clear the same at the cost of the land owners. As

consideration    for   executing   that   agreement,   the   Mantri

Developers paid an amount of Rs.15.00 crores.


     29.3.         With regard to the joint development of Item

No.2 Schedule land, in consideration of Mantri Developers

agreeing to develop and hand over to the land owners 30% of

the super built-up area in Item-2, the land owners agreed to

transfer 70% of the undivided interest in Item No.2 along with

70% of the super built-up area developed on Item -2 to Mantri

Developers.     The parties agreed to execute a JDA subject to

fulfillment of other terms in the agreement to consummate the

joint development of Item-2. It was provided that the parties

may agree to a revenue share model at the time of execution

of JDA. Simultaneous with the execution of the JDA, the land

owners were required to execute an irrevocable power of

attorney in favour of the Mantri Developers to enable transfer

and development of land. The Land Owners were to appoint

Mantri Developers as their exclusive marketing agent to market

their entitlement under the JDA.
                              - 28 -
                                        WP No. 36101 of 2024



     29.4.   It was agreed that Mantri Developers shall pay an

amount of Rs.40.00 Crores on execution and registration of the

JDA and handing over vacant possession of the Schedule

property for development and execution of GPA as refundable

deposit to the land owners for the Item No.2 land in the

schedule under the JDA in the manner specified.


     29.5.    On completion of the obligation set out in the

agreement, the Land Owners were required to execute a sale

deed with regard to Item No.1-land and a JDA with respect to

Item No.2 land of the Schedule property in favour of Mantri

Developers and/or any of its nominees. It was provided in the

agreement that in case the land owners are unable to

satisfy/get clear and marketable title of the schedule property

and/or are unable to satisfy all claims that may have been

raised in response to the public notice to the satisfaction of

Mantri Developers, Mantri Developers shall be entitled to

terminate the agreement.


     29.6.       Upto the date of execution of the sale deed

and JDA and handing over vacant possession of the schedule

property to Mantri Developers, the land owners were required
                                - 29 -
                                           WP No. 36101 of 2024



to obtain khata of the property from BBMP and pay all taxes,

levies and cess in respect of the schedule property.


      29.7.       It   was   disclosed   that   Mantri   Developers

proposes to develop residential buildings on Item no.2 land of

the schedule property.       It was also disclosed that Mantri

Developers intends to construct on part of Item No.1 land of

the schedule property a commercial and/or residential building.

It was further provided that in the rear portion of the Item no.2

land of the schedule property, Mantri Developers would provide

a road of width 24.5 meters and the land owners shall be

entitled to a right of way through the said road for access to its

other developments being the Krishna Leela Theme Park.

However, Mantri Developers would have absolute right over the

same (road). The land owners were permitted to put a

Gopuram at the entry on the beginning of the said road.         An

exclusive access road of 18.3 meters width was to be reserved

for use of Mantri Developers for developments at the schedule

property.


      29.8.    The land owners agreed and undertook that on

the adjacent property measuring approximately 6.445 acres

(area retained by the land owners) it shall not develop
                                  - 30 -
                                             WP No. 36101 of 2024



commercial and/or residential buildings which will become

competition to Mantri Developers developments.


     29.9          The     terms      regarding     arbitration     and

assignment mentioned in the agreement are as under:-


          "All disputes, claims and questions whatsoever in
    relation to or arising out of   this Agreement between the
    Parties either during the continuance of the Agreement or
    afterwards, if not settled by mutual discussion, shall be
    referred to binding arbitration with three arbitrators in
    accordance with the provisions of the Arbitration and
    Conciliation Act, 1996 or any statutory modification or re-
    enactment thereof. Each party shall be entitled to appoint
    one Arbitrator and the two Arbitrators in turn will appoint a
    third Arbitrator.    The arbitration shall be conducted in
    Bangalore and in English language.       The decision of the
    Arbitrator shall be final and binding on the parties."

    .....

"IC and IHT shall not be entitled to assign any of their rights in this agreement without the prior written approval of MDPL. MDPL shall be permitted to assign this Agreement to any of its affiliates, associates, SPVs or group companies, or companies in which MDPL has an interest." 29.10. It is pertinent to mention here that the description of Mantri Developers given towards the beginning of this agreement dated 26.06.2010 is as follows:-

- 31 -
WP No. 36101 of 2024
"Mantri Developers Private Ltd., a company incorporated under the Companies Act, 1956, having its Registered Office at No.41, Vittal Mallya Road, Bangalore 560 001, hereinafter referred to as the "MDPL", (which expression shall, wherever the context so required or admits, mean & include its successors in interest, nominees and assigns)"

29.11. This agreement is signed, on behalf of Mantri Developers, by its Director/Authorised Signatory, Girish Gupta H.S.. Among its witnesses is Sushil Mantri, who is the Director of Mantri Developers.

30. Just three days after the aforesaid agreement, a First Supplementary Agreement was executed on 29.07.2010. The parties to it are ISKCON Charities and IHT of one part ('Land Owners'), and, Mantri Developers, of the other part. This agreement provided, inter alia, that in addition to the advance paid under the agreement of 26.7.2010, at the request of the Land Owners, Mantri Developers have agreed to pay additional advance amount of Rs. 5 crores which shall be adjusted towards the sale consideration for the item No. 1 property. Additionally, Mantri Developers agreed to bear and pay all actual interest amounts only for a limited period of 90 days on several loan amounts totaling Rs. 120.00 crores availed by the

- 32 -

WP No. 36101 of 2024

land owners. Further, a clause was inserted in the agreement which provided that without prejudice to its right to terminate the agreement and the supplemental agreement, Mantri Developers shall be entitled to transfer/assign its rights under the agreement and the supplemental agreement (on terms and conditions it may deem fit) to a mutually acceptable third party. In the event of such transfer/assignment, Mantri Developers shall have the first right to be paid all amounts mentioned in clause 7.3.1 therein, expended by it.

30.1. It further provided that the land owners shall appoint Mantri Developers their exclusive marketing agent to market their entitlement in the built-up area as per clause 5.1. In consideration of Mantri Developers selling and marketing the land owners entitlement, Mantri Developers shall be entitled to 2.5% of the sale price of such built-up area service charges. On behalf of Mantri Developers, this supplementary agreement was also signed by the aforesaid Girish Gupta H.S. as authorized signatory.

31. On 29.9.2010, the SSA was executed between ISKCON Charities and IHT of the First part, and, Land Master Realtors Private Limited, of the Second part, and, Gokulam

- 33 -

WP No. 36101 of 2024

Shelters, of the Third part, and, Mantri Developers of the Fourth part. Land Master Realtors Private Limited21 was one of the previous names of Castles Vista, the Respondent no.5.

31.1. Inter alia, the SSA provided that Mantri Developers has now nominated LMRPL to take on the rights, duties, obligations and liabilities of Mantri Developers under the Agreement and First Supplementary Agreement. The SSA states that parties have entered into the SSA which shall along with the Agreement dated 26.06.2010, and the First Supplementary Agreement dated 29.07.2010 (together referred to as the 'Framework Agreements') specify comprehensively the rights, duties, obligations and liabilities of the parties including the payment and receipt of the consideration for the sales to be made.

31.2. It is mentioned in the SSA that Gokulam Shelters has also represented that it shall honour the obligations undertaken by the Land Owners under the Agreement and the First Supplementary Agreement wherein the Land Owners have undertaken to sell the item No.1 property to LMRPL and to 21 LMRPL

- 34 -

WP No. 36101 of 2024

enter into a JDA with Mantri Developers with respect to Item No.2 property of Agreement.

31.3. The LMRPL consented to assignment of the land owner's rights in the Agreement and the First Supplementary Agreement with respect to schedule property in favour of Gokulam Shelters. Gokulam Shelters as the assignee of the Land Owners agreed to sell Item No.1 property to LMRPL and further to execute a JDA in favour of LMRPL in terms of the Framework Agreements. Both LMRPL and Gokulam Shelters consented to enter into a JDA on the terms agreed under the Framework Agreements and assented to develop Item No.2 property on the same terms as laid down under the Framework Agreements. The SSA recognized that Mantri Developers has made payment of Rs.23,90,00,000/- under the agreement and First Supplementary Agreement and the same shall be treated as an advance consideration paid by LMRPL to Gokulam Shelters for sale of Item -1 property and to that extent LMRPL shall be discharged of its obligation to make payment of the sale consideration for Item-1 property.

31.4 In the SSA, sale of Item No.3 property admeasuring approximately 6.32 acres of land was also agreed to be

- 35 -

WP No. 36101 of 2024

transferred. Gokulam Shelters agreed to pay total consideration of Rs.57,53,97,500/- for the Larger Extent Property and an undivided interest in the land measuring 7 acres 18 guntas reduced by 7 acres 5.13 guntas in the Gokulam Property to the Land Owners jointly. It was provided that in the light of the recitals, the parties are desirous of amending and adding certain provisions of the agreement. Pursuant to the same, the parties decided to execute the SSA.

31.5 After the aforesaid recitals the SSA stated that the Land Owners shall sell the Larger Extent Property in favour of Gokulam Shelters and assign their rights in the agreement and First Supplementary Agreement in favour of Gokulam Shelters in consideration for receiving a portion of the Entitled Receivables and receiving the advance and non-refundable deposit. The encumbrance was to be discharged by LMRPL under the terms of the Framework Agreement in order to facilitate the proposed sale of Item No.1 property to LMRPL and the proposed JDA between LMRPL and Gokulam Shelters in respect of Item No.2 property. The Land Owners agreed to execute a GPA in favour of LMRPL to enable LMRPL to obtain such approval as are incidental to the purpose of the

- 36 -

WP No. 36101 of 2024

agreement. Simultaneous with the execution of the sale deed with respect to a larger extent property a similar GPA was to be granted by Gokulam Shelters in favour of LMRPL.

31.6 With regard to the Item No.1 property sale by Gokulam Shelters in favour of LMRPL, Gokulam Shelters confirmed and agreed to sell Item No.1 property in favour of LMRPL. It was mentioned that Mantri Developers, pursuant to the terms of the agreement, had published a public notice in the newspapers after the execution of the agreement with the Land Owners calling for claims with respect to Item No.1 and Item No.2 property and objections were received by the Mantri Developers regarding the same. The Land Owners and Gokulam Shelters undertook that they alone shall be responsible for clearing all such claims, failing which, LMRPL at its sole discretion would be entitled to clear the same at the cost and expense of Gokulam Shelters and for the Land Owners.

31.7 As regards joint development of Item No.2 property, the Land Owners confirmed and agreed to irrevocably empower and exclusively authorize Gokulam Shelters to develop Item No.2 property by entering into a JDA with LMRPL.

- 37 -

WP No. 36101 of 2024

Under the JDA the revenues from the proceeds of sale were to be shared in the ratio of 30:70, that is 30% will fall into the share of Gokulam Shelters and 70% to the share of LMRPL. Other terms and conditions between the Land Owners, Gokulam Shelters and LMRPL were also specified.

31.8 Thereafter the terms were specified pertaining to execution of sale deed and JDA. Under this, the Land Owners were required to execute a sale deed with respect to larger extent property in favour of Gokulam Shelters. It also contemplated execution of sale deed by Gokulam Shelters in respect to the Item No.1 property in favour of LMRPL. The JDA between LMRPL and Gokulam Shelters was to be simultaneous with the execution of the sale deed and the Land Owners, Gokulam Shelters and LMRPL were to jointly execute the JDA in respect of Item No.2 property.

31.9 Certain Clauses of the SSA are quoted below.

"4.4. This Second Supplementary Agreement does not amount to a waiver of the rights, conditions, accuracy of representations or any other term of the Agreement dated 26th June 2010 and the representations made in the First Supplementary Agreement dated 29th July 2010 thereto by any of
- 38 -
WP No. 36101 of 2024
the Parties except what is specifically amended or added in this Second Supplementary Agreement.
4.5. This Second Supplementary Agreement, together with the Agreement and First Supplementary Agreement, constitute and represent the entire agreement and understanding amongst the Parties with respect to the subject matter hereof.
4.6 This Second Supplementary Agreement shall modify the relevant portions of the Agreement and First Supplementary Agreement (even where specific clauses are not referred to) and the Parties shall construe the Agreement, the First Supplementary Agreement and this agreement harmoniously. Except as expressly modified or added by this Second Supplementary agreement, the terms and conditions of the Agreement and First Supplementary Agreement shall continue in force and constitute legal and binding obligations of the Parties. Any amendment or addition to the same shall be reduced in writing."

31.10. It is pertinent to mention here that on behalf of Mantri Developers as well as LMRPL, the same Director/Authorised signatory has signed namely, Sri. Girish Gupta. It is further pertinent to mention here that only in the recital section of the SSA was it mentioned that 'whereas Mantri Developers has now nominated LMRPL to take on the

- 39 -

WP No. 36101 of 2024

rights, duties, obligations and liabilities of Mantri Developers under the agreement and the First Supplementary Agreement to which the Land Owners hereby consent'.

32. On the same day as the execution of the SSA, the JDA was executed between Gokulam Shelters, LMRPL (which is described in the JDA as "Developer" or "Second Party"), ISKCON Charities and IHT. In the recital to the JDA, it was mentioned that ISKCON Charities and IHT on the one hand and Mantri Developers on the other hand entered into a registered agreement on 26.06.2010 in respect of the schedule property and Developer Adjacent Property and certain other properties forming part of the Larger Extent of Property, wherein ISKCON Charities, inter alia, agreed to sell the Developer Adjacent Property ( referred to as the Item-1 property) in favour of Mantri Developers and develop the schedule property. Subsequently, the First Supplementary Agreement dated 29.07.2010 was executed between those parties whereby certain terms of the Agreement were amended. Mantri Developer had nominated the Developer to take on the rights, duties, obligations and liabilities of Mantri Developers under the Agreement and the First Supplementary Agreement. On 29.09.2010, the ISKCON Charities, IHT, Gokulam Shelters

- 40 -

WP No. 36101 of 2024

(Owner) and the Developer executed a further amendment to the Agreement and First Supplementary Agreement by way of SSA. Pursuant to the SSA, the Owner acquired the schedule property (consisting of undeveloped land) and is also executing the JDA in favour of the Developer.

32.1 The Agreement, First Supplementary Agreement and the SSA were collectively referred in the JDA as "Framework Agreements". The various terms in the agreement between the parties were specified in the JDA. The terms and conditions in the JDA consisted of those terms mentioned in the agreement of 26.06.2010, the First Supplementary Agreement and the SSA. As far as the name of the project was concerned, it was specified in the JDA, that the project name shall bear the word "Mantri" as part of its name always along with its Logo. The Developer (LMRPL) represented that they have the right to use the name "Mantri" and the Logo.

32.2 As far as Dispute Resolution is concerned, it was provided as follows:-

"30. DISPUTE RESOLUTION 30.1 The Parties agree to negotiate in good faith to resolve any dispute between them regarding
- 41 -
WP No. 36101 of 2024
this Agreement. If the negotiations do not resolve the dispute to the reasonable satisfaction of the Parties, then each disputing party shall nominate a person with respectable professional standing and unimpeachable conduct as its representative. These representatives shall, within 30 (thirty) days of a written request by any Party to call such a meeting, meet in person and shall attempt in good faith to resolve the dispute.
30.2. Upon the Parties being unable to appoint the representatives as aforesaid, or if the disputes cannot be resolved by such persons in such meeting as aforesaid, the disputes or differences shall be submitted to final and binding arbitration of 3 (three) arbitrators at the request of any of the Parties upon written notice to that effect to the other. In the event of such arbitration;
30.2.1. The arbitration shall be in accordance with the Indian Arbitration and Conciliation Act, 1996, in force at the relevant time (which is deemed to be incorporated into this Agreement by reference).
30.2.2. All proceedings of such arbitration shall be in the English language. The venue of arbitration shall be Bangalore, India;
30.2.3. The arbitration panel shall consist of 3 (three) arbitrators, 1 (one) arbitrator to be
- 42 -
WP No. 36101 of 2024

appointed by the Owner and 1 (one) arbitrator to be appointed by the Developer, and the, third arbitrator to be appointed jointly by the 2 (two) arbitrators so appointed;

30.2.4. Arbitration awards rendered shall be final, binding and shall not be subject to any form of appeal. The loosing party (ies), as determined by arbitrators, shall pay all reasonable out-of-pocket expenses (including, without limitation, reasonable advocates' fees) incurred by the prevailing Party (ies), as determined by the arbitrators, in connection with any dispute unless the arbitrators direct otherwise;

30.2.5. Nothing shall preclude a Party from seeking interim or permanent equitable or injunctive relief, or both, from any Court having jurisdiction to grant the same. The pursuit of equitable or injunctive relief shall not be a waiver of the duty of the Parties to pursue any remedy for monetary losses through the arbitration described in this Clause 30.

32.3 It is pertinent to mention here that the JDA was signed by the Director/Authorised Signatory of LMRPL namely, Mr. Girish Gupta.

33. After the execution of the JDA, a letter was issued on 25.10.2010 jointly by Snehal Mantri, Director Marketing,

- 43 -

WP No. 36101 of 2024

Mantri Developers, and by ISKCON Charities to Gokulam Homeowners informing them about the integrated township called Hare Krishna City and for setting up of ISKCON's dream project - Krishna Lila Park on the adjacent land. It is stated in the letter that with more than a decade of history and expertise as one of India's leading developers of world class homes, IT Parks, and educational institutions, Mantri Developers are committed to creating a legacy of excellence for all its customers; that handing over the development to Mantri Developers frees ISKCON missionaries to focus on the Krishna Lila Park. Mantri Developers have committed to transfer substantial benefits of development to support the setting up of the Krishna Lila Park. It is stated that with this strong endorsement from the Mantri Brand, Homeowners at Gokulam can be assured of distinctive homes to boost of world class quality with superior amenities and facilities. The Mantri brand name also brings with it, value appreciation for your investment. It is further stated as follows:-

"However, there are certain minimum quality standards a brand like Mantri abides by. As the threshold of these standards is much higher for Mantri Developers, naturally it adds on to capital expense. We are proud to say that, we have ensured that only a minimalistic
- 44 -
WP No. 36101 of 2024
percentage of this capital expense is borne by you, who has trusted in ISKCON Charities and booked these apartments well in advance.
Therefore, the cost of this additional value add on and quality enhancement for you will be an addition of 10% of the price committed by Iskcon Charities. For others the project is launched at Rs.3190/ sqft by Mantri Developers for fresh bookings.
In case if you would like to withdraw the booking, Iskcon Charities will refund the booking amount. However on choosing to continue, your advance booking amount will be taken into account by Mantri Developers.
We look forward for you to be Mantri Family member and welcome you in advance."

34. Mantri Developers has also issued an advertisement for Mantri Serenity in which the Logo of Mantri was used in respect of the aforesaid project. There are numerous e-mails on record that have been exchanged between the officers of Mantri Developers and the representatives of the claimants from November 2010 till the year 2025 admittedly pertaining to the aforesaid project which is the subject matter of the JDA.

35. On record is a loan agreement dated 30.04.2018 between Mantri Castles Private Limited (formerly, LMRPL, which name later was changed to Castles Vista) referred as the "Borrower" of the First Part, Piramal Finance Limited referred as

- 45 -

WP No. 36101 of 2024

"Lender" of the Second Part, and Mantri Developers as well as Mr. Sushil Mantri of the Third Part. The signatures of the aforesaid persons appear on each page of the said loan agreement. The loan agreement was in respect of extending financial assistance to the extent of up to Rs.650.00 Crores. To secure the aforesaid corporate loan, inter alia, there was execution of power of attorney by the Borrower in favour of the Security Trustee; Demand Promissory Note; Issuance of Personal Guarantee; Issuance of Corporate Guarantee, etc.

36. Thereafter, an Escrow Agreement was executed between (i)Mantri Castles Private Limited, (ii) Piramal Trusteeship Services Private Limited, (iii) Mantri Developers,

(iv) HDFC Bank Limited, (v) Gokulam Shelters, (vi) Krishna Lila, (vii) Hamara Shelters Private Limited (acting through the aforesaid Mr. Girish Gupta), and (viii) Abhishek Propbuild Private Limited (acting through the aforesaid Mr. Girish Gupta). This Escrow Agreement was to secure and facilitate the term loan secured obligations of Mantri Castles Private Limited under the loan agreement. The word "Project" was defined to mean the residential housing project being constructed/developed by the borrower by the name and style of "Mantri Serenity". This agreement too was signed by the aforesaid Sri. Girish Gupta

- 46 -

WP No. 36101 of 2024

H.S. as authorized signatory for Mantri Castles Private Limited, Mantri Developers, Hamara Shelters Private Limited and Abhishek Propbuild Private Limited.

37. A letter dated 01.06.2018 is on record which is addressed to Gokulam Shelters by Sri. Sushil Mantri for Mantri Developers, which is a letter of undertaking from Mantri Developers with regard to the obligations of Mantri Castles Private Limited under certain Clauses of a Memorandum of Understanding dated 02.06.2018. Pursuant thereto, Mantri Developers irrevocably agreed and undertook to ensure payment of the dues of Gokulam Shelters upto an extent of Rs.35.00 Crores to Gokulam Shelters and Krishna Lila. It was provided inter alia that in the event Mantri Castles Private Limited fails to make any payment due to Gokulam Shelters and/or Krishna Lila under the "Serenity Documents", Mantri Developers ( as the original intended developer of the Project) undertakes to pay the same to Gokulam Shelters and/or Krishna Lila ( as the case may be). It also appears that the said letter was sent by e-mail by Mantri Developers as an attachment using its domain name on 02.06.2018.

- 47 -

WP No. 36101 of 2024

38. Additionally, a Deed of Hypothecation dated 05.06.2018, Memorandum of Deposit of Title Deed dated 31.08.2020, an unconditional and irrevocable corporate guarantee dated 30.09.2020 are on record, all executed by Mantri Developers and others.

39. The aforesaid facts, thus reveal that Mantri Developers is closely involved in various stages of the project which was being developed along with the claimants despite execution of the SSA and the JDA. It has an abiding and deep- rooted interest in the success of the project as envisaged in the agreement dated 26.06.2010 as well as in the subsequent agreements. The admitted case of Mantri Developers is that it has assigned its rights under the aforesaid agreement of 26.06.2010 and the First Supplementary Agreement to LMRPL. The name of LMRPL was changed to Mantri Castles Private Limited and then again changed to Castles Vista. It is not disputed by the petitioner-Mantri Developers that it owns its subsidiary company, Castles Vista. In the agreement dated 26.06.2010, Mantri Developers agreed that reference to it shall mean and include its successors in interest, nominees and assigns, and the said agreement has an arbitration clause. The intention of Mantri Developers is clearly to be bound by the

- 48 -

WP No. 36101 of 2024

agreements entered into between the claimants on one hand, and LMRPL, Mantri Castles Private Limited and Castles Vista on the other hand. Mantri Developers is intimately connected with Castles Vista for ensuring revenue for the project to the extent of 650.00 crores by executing loan agreement, Escrow agreement, hypothecation agreement and offering security for the amount of loan by executing Corporate Guarantee Agreement as well as personal guarantee of its Director to secure the loan advanced by Piramal Finance.

[ 40. Starting from the first agreement on 26.06.2010, the subsequent agreements leading up to the JDA and even later agreements reflect common participation by Mantri Developers and Castles Vista with the claimants for the purpose of achieving a common purpose, which is the success of the Project of the claimants which is reflective of the mutual intent to be bound by the agreement to arbitrate. Mantri Developers has actively assumed obligations and performance under the agreements upon itself. Even otherwise, Mantri Developers has an enormous financial exposure in the Project of the claimants. There is thus a clear legal relationship between the petitioner- Mantri Developers and the claimants/respondents. Mantri developers has veritably consented to be bound by the JDA

- 49 -

WP No. 36101 of 2024

despite it not being a signatory to the agreement. After the execution of the JDA, the joint letter issued on 25.10.2010 by Mantri Developers, and by ISKCON Charities to Gokulam Homeowners reflects that the claimants were under the legitimate belief that the non-signatory Mantri Developers was a veritable party to the JDA. Therefore, it is mentioned in the joint letter of 25.10.2010 that handing over the development to Mantri Developers frees ISKCON missionaries to focus on the Krishna Lila Park and that Mantri Developers have committed to transfer substantial benefits of development to support the setting up of the Krishna Lila Park. It was stated in the joint letter that with the strong endorsement from the Mantri Brand, Homeowners at Gokulam can be assured of distinctive homes to boost of world class quality with superior amenities and facilities. In that joint letter, Mantri Developers projected that Mantri brand name also brings with it value appreciation for the investment of the home buyers.

41. Therefore, the reliance on and affirmation of the cumulative factors that the Courts and tribunals should consider in deciding whether a company within a group of companies is bound by the arbitration agreement, as laid down in the judgment in Discovery Enterprises, in the landmark

- 50 -

WP No. 36101 of 2024

judgment of the Supreme Court in Cox & Kings Ltd., are mandatorily required to be followed. The same is extracted below:-

"115. In Discovery Enterprises, this Court refined and clarified the cumulative factors that the Courts and tribunals should consider in deciding whether a company within a group of companies is bound by the arbitration agreement:
"40. In deciding whether a company within a group of companies which is not a signatory to arbitration agreement would nonetheless be bound by it, the law considers the following factors;
              (i)       The mutual intent of parties;

              (ii)      The relationship of a non-signatory to a party
                        which is a signatory to the agreement;

              (iii)     The commonality of the subject-matter;

              (iv)      The composite nature of the transactions; and

              (v)       The performance of the contract.""



42. We find from perusal of the impugned majority order of the Arbitral Tribunal that all the relevant factors prescribed in Cox & Kings Ltd. relating to impleadment of the non-signatory party, Mantri Developers, were duly considered by it. The Arbitral Tribunal is empowered to decide on its jurisdiction. The provisions of Section 2 (1) (h) of the Act, 1996
- 51 -
WP No. 36101 of 2024
read with Section 16 thereof leave no room for doubt with regard to the authority of the Arbitrator to decide on its jurisdiction which is precisely what has been done by the Arbitral Tribunal by majority in the impugned order. So there is neither patent lack of jurisdiction nor inherent lack of jurisdiction of the Arbitral Tribunal in impleading the petitioner- Mantri Developers which is a non-signatory party to the JDA.
43. Thus we find no reason to interfere in the impugned majority order of the Arbitral Tribunal in exercise of our jurisdiction under Article 226/227 of the Constitution.
44. This petition is therefore, dismissed. Pending IAs., if any, stand disposed of.
Sd/-
(JAYANT BANERJI) JUDGE Sd/-
(UMESH M ADIGA) JUDGE KGR