Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 0]

Gauhati High Court

Jabul Ahmed vs Assam Power Distribution Co. Ltdapdcl ... on 20 December, 2022

Author: Sanjay Kumar Medhi

Bench: Sanjay Kumar Medhi

                                                                Page No.# 1/16

GAHC010039712017




                        THE GAUHATI HIGH COURT
  (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

                           Case No. : WP(C)/5635/2017

         JABUL AHMED
         PROPRIETOR, BATARASHI POWER AGENCY P.O. TILLABAZAR DIST.
         KARIMGANJ, ASSAM



         VERSUS

         ASSAM POWER DISTRIBUTION CO. LTDAPDCL and 6 ORS.
         APDCL, CAR, REP. BY ITS CHAIRMAN, BIJULI BHAWAN, PALTAN BAZAR,
         4TH FLOOR, GUWAHATI -01, ASSAM

         2:THE GENERAL MANAGER

          APDCL
          CAR
          BARAK VALLEY ZONE
          MEHERPUR
          SILCHAR
          P.O. and P.S. SILCHAR
          DIST. CACHAR
          ASSAM

         3:THE GENERAL MANAGER

          COMMERCIAL R APDCL
          BIJULI BHAWAN
          PALTAN BAZAR
          GUWAHATI-01
          ASSAM

         4:THE DEPUTY GENERAL MANAGER

          APDCL
                                                                           Page No.# 2/16

             CAR BADARPURGHAT
             BADARPUR
             P.S. BADARPUR
             DIST. KARIMGANJ
             ASSAM

            5:THE ASSTT. GENERAL MANAGER

             APDCL CAR
             KARIMGANJ ELECTRIC DIVISION
             KARIMGANJ
             P.O. and P.S. KARIMGANJ
             ASSAM

            6:THE CHIEF EXECUTIVE OFFICER

             BADARPUR ELECTRICAL CIRCLE
             APDCL
             CAR
             BADARPURGHAT.

            7:SRI SANKAR DEB

             AGM
             TMC BADARPUR ELECTRICAL CIRCLE
             APDCL
             BADARPURGHAT

Advocate for the Petitioner       : MR.P HAZARIKA

Advocate for the Respondent :


                                          BEFORE

                Hon'ble MR. JUSTICE SANJAY KUMAR MEDHI


      Advocates for the applicants :         Shri M. Dutta, Ld. Counsel
      Advocates for the respondents :        Shri KP Pathak, SC, APDCL


      Date of hearing         :       24.11.2022 & 05.12.2022
      Date of Judgment        :       20.12.2022
                                                                            Page No.# 3/16

                                 Judgment & Order

      The challenge in this writ petition pertains to an order dated 08.04.2017 by
which the prayer of the petitioner to shift the franchise of the petitioner from IBDF to
CBDF Scheme has been rejected. The petitioner is also aggrieved by the imposition of
a demand of Rs.16,11,674/- as dues to be paid to the ADPCL.

2.     Before going to the issue which has arisen for determination in this Case, it
would be convenient to state the facts of the case in brief. In fact, there is a
chequered history including earlier rounds of litigation connected to the present
dispute.

3.     The projected case of the petitioner, as would appear from the pleadings in the
writ petition is that he is an Input Based Distribution Franchise (IBDF) of the APDCL in
terms of an agreement which empowers him to draw bills on the consumers and also
to collect the dues. The petitioner alleges that some false allegations were made
against him in respect of his functioning as a franchise by one Samiti based upon
which, on 05.05.2015, the petitioner was restrained from making disconnection of the
lines of the defaulting consumers. It may be mentioned that as per the petitioner
there were default in payment of bills for which the lines were to be disconnected. The
petitioner further alleges that taking advantage of the order dated 05.05.2015, the
consumers even stopped payment of electricity bill. At the same time, the Samiti along
with 19 others had filed a Civil Suit being TS No. 176/2015 in the Court of the Munsiff
No. 2, Karimganj in which an ad interim order of temporary injunction was passed by
which both the petitioner as well as the APDCL were restrained from resorting to any
coercive measures. This led to a situation where there could not be any revenue
collection.

4.      In the meantime, the APDCL had taken a conscious decision to shift the
franchise system from IBDF to CBDF Scheme for which, the existing agreements had
to be terminated vide an order dated 02.01.2016. This compelled the petitioner to
                                                                            Page No.# 4/16

approach this Court by filing two numbers of writ petitions as he was covering 12
numbers of DTRs in two groups, which were registered as WP(C)/838/2016
(concerning 2 DTRs) and WP(C)/5875/2016 (concerning 10 DTRs). However, the
second writ petition came to be disposed of earlier vide an order dated 05.10.2016
whereby the petitioner was provided an opportunity to raise the dispute before the
DGM who would pass appropriate orders within a specified period and till such
disposal, the petitioner shall be allowed to continue in his business and further that no
recovery be effected in the said period.

5.     In terms of the aforesaid order dated 05.10.2016, the petitioner had submitted
a detail representation. However, the same was rejected vide an order dated
15.11.2016 passed by the Chief Executive Officer, Badarpur Electrical Circle. It was
held that the shifting / switch over to the credit system was valid and within seven
days, the arrears should be paid. However, the authorities vide a subsequent
communication dated 04.02.2017 while reiterating the demand for the outstanding
had observed that for six months the switching over may be deferred.

6.     So far as the first writ petition was concerned, namely, WP(C)/838/2016
wherein the termination order dated 02.01.2016 was challenged in respect of the
remaining DTRs, this Court vide order dated 15.05.2017 had passed a similar direction
giving liberty to the petitioner to submit a representation seeking appropriate order
regarding switch over which would be disposed of by the appropriate authority. The
consideration would also include the issue of arrear dues.

7.    In compliance with the aforesaid direction of the High Court, the petitioner had
submitted a representation which was disposed of vide an order dated 04.08.2017
issued by the General Manager, APDCL. By the said order, it has been held that the
prayer for exempting from switching over would not be favourably considered as the
petitioner had totally failed to fulfil the basic concept of IBDF Scheme. It has further
been held that the petitioner through his proprietorship firm had a liability of
                                                                              Page No.# 5/16

Rs.16,11,674/- the details of which was annexed in the form of a chart and it is this
order which is the subject matter of challenge.

8.     I have heard Shri M. Dutta, learned counsel for the petitioner and Shri KP
Pathak, learned Standing Counsel for the APDCL. The materials placed before this
Court have been duly examined.

9.     Shri Dutta, learned counsel for the petitioner has submitted that it is not in
dispute that it was the authorities who had passed an order dated 05.05.2015
directing the petitioner not to disconnect the electricity line. He further submits that in
TS No. 176/2015, the learned Munsiff No. 2 had passed an order of injunction on
15.06.2015. He submits that a common written statement was filed by the APDCL and
the petitioner contesting the Suit by the Samiti and 19 others. In the said written
statement, the APDCL did not put any blame on the petitioner and rather had
categorically stated that there was no fault on his part.

10.    The learned counsel for the petitioner accordingly submits that under the
aforesaid background, the factors considered in the impugned order dated 04.08.2017
are absolutely untenable in law and accordingly the order needs intervention. The
learned counsel has however submitted that the present challenge can be limited only
to the demand.

11.    In support of his submissions, Shri Dutta, learned counsel for the petitioner has
relied upon the following case laws:

            i.        AIR 1983 SC 848 [Gujarat State Financial Corporation Vs.
                 M/s. Lotus Hotels Pvt. Ltd.]

          ii.        AIRONLINE 2003 SC 700 [ABL International Ltd. Vs. Export
                 Credit Guarantee Corporation of India Ltd.]

          iii.       2022 Live Law (SC) 966 [MP Power Management Company
                 Ltd. Jabalpur Vs. M/S Sky Power Southeast Solar India Private
                                                                                Page No.# 6/16

            Limited & Ors.]

          iv.      2022 Live Law (SC) 180 [T. Takano Vs. Securities and
            Exchange Board of India & Anr.]

12.   The case of Gujarat State Financial Corporation (supra) has been cited in
support of the contention on the maintainability of a writ petition against
instrumentalities of the State. The Hon'ble Supreme Court has gone to extent that the
relief prayed need not be limited to the claim for the damages only but can also go to
the extent of specific performance of the contract. The relevant part which is in
paragraph 8 of the judgment is extracted hereinbelow:

      8....It is too late in the day to contend that the instrumentality of the State
      which would be 'other authority' under Article 12 of the Constitution can commit
      breach of a. solemn undertaking on which other side has acted and then
      contend that the party suffering by the breach of contract may sue for damages
      but cannot compel specific performance of the contract...

13.   The case of ABL International (supra) has been cited to support the view on
the availability of writ remedy under Article 226 of the Constitution of India even in
matters where there are disputed questions.

14.    In the case of T. Takano (supra), the Hon'ble Supreme Court after
considering the relevant case laws on the subject had laid down the principles which
are extracted hereinbelow:

      "39. The following principles emerge from the above discussion:

      (i) A quasi-judicial authority has a duty to disclose the material that has been
      relied upon at the stage of adjudication; and

      (ii) An ipse dixit of the authority that it has not relied on certain material would
      not exempt it of its liability to disclose such material if it is relevant to and has a
      nexus to the action that is taken by the authority. In all reasonable probability,
                                                                             Page No.# 7/16

      such material would have influenced the decision reached by the authority.

             Thus, the actual test is whether the material that is required to be
      disclosed is relevant for purpose of adjudication. If it is, then the principles of
      natural justice require its due disclosure."

15.    In the case of MP Power Management Company Ltd. (supra) , the Hon'ble
Supreme Court had explained the meaning of an arbitrary action. The relevant
paragraph is extracted hereinbelow:

      "48.    We would, therefore, sum up as to when an act is to be treated as
      arbitrary. The court must carefully attend to the facts and the circumstances of
      the case. It should find out whether the impugned decision is based on any
      principle. If not, it may unerringly point to arbitrariness. If the act betrays
      caprice or the mere exhibition of the whim of the authority it would sufficiently
      bear the insignia of arbitrariness. In this regard supporting an order with a
      rationale which in the circumstances is found to be reasonable will go a long
      way to repel a challenge to state action. No doubt the reasons need not in
      every case be part of the order as such. If there is absence of good faith and
      the action is actuated with an oblique motive, it could be characterised as being
      arbitrary. A total nonapplication of mind without due regard to the rights of the
      parties and public interest may be a clear indicator of arbitrary action. A wholly
      unreasonable decision which is little different from a perverse decision under
      the Wednesbury doctrine would qualify as an arbitrary decision under Article 14.
      Ordinary visiting a party with the consequences of its breach under a contract
      may not be an arbitrary decision."

      Further, in paragraph 54 of the judgment, the Hon'ble Supreme Court has laid
down the principles of judicial review in contractual matters by invoking the public law
remedy.

16.    Per contra, Shri KP Pathak, learned Standing Counsel, APDCL had defended the
                                                                            Page No.# 8/16

impugned action and even raised the issue of maintainability of this writ petition. He
submits that the dispute is essentially a private dispute between the petitioner and the
APDCL. Further, the said dispute is civil in nature wherein evidence will be required to
be adduced by either of the parties. He also submits that the issue arises from a
contract which is determinable in nature and under such circumstances, even
assuming there is any cause of action, the remedy would only lie in the Civil Court by
invoking, amongst others, Section 73 of the Indian Contract Act.         That apart, the
maintainability of the writ petition itself has been questioned and in this regard Clause
15 of the agreement had been referred to which contains a dispute resolution clause.

17.    Shri Pathak, learned Standing Counsel has structured his defence on certain
grounds. He submits that there is no specific challenge to the order of termination and
in absence of such challenge, the relief prayed is not maintainable. He submits that
the dispute is a purely contractual one, which cannot be adjudicated by the Public Law
Remedy under Article 226 of the Constitution of India. He also submits that a
determinable contract cannot be specifically enforced.

18.   In support of his submissions, the following case laws have been relied upon:

           i.        (1991) 1 SCC 533 [Indian Oil Corporation Ltd. Vs. Amritsar
                Gas Service & Ors.]

          ii.       (2000) 6 SCC 293 [Kerala State Electricity Board & Anr. Vs.
                Kurien E. Kalathil & Ors.]

         iii.       (2003) 1 GLR 619 [Star India Ltd. Vs. Arup Borah & Ors.]

          iv.        (2008) 12 SCC 500 [Kisan Sahkari Chini Mills & Ors. Vs.
                Vardan Linkers & Ors.]

19.    In the case of Indian Oil Corporation Ltd. (supra), it was held that Public
Law Remedy should not be normally invoked in matters concerning contractual rights.

20.   In the case of Kerala State Electricity Board (supra), the Hon'ble Supreme
                                                                              Page No.# 9/16

Court was dealing of the issue of maintainability of a writ petition on availability of the
alternative remedy. It has been held that when an alternative remedy was prescribed
in a contract, in case of dispute, the party should be relegated to other remedies.

21.      In the case of Star India Ltd. (supra), this High Court had held that in case
of a dispute involving a contract which is determinable in nature, the bar of the
Specific Relief Act would come into operation and no injunction can be granted to
enforce the same.

22.      Shri Dutta, learned counsel for the petitioner however submits that the
challenge regarding conversion / switching over may not be seriously pressed as
sufficient time has elapsed in the meantime. However, the action of recovery is liable
to be interfered with.

23.      The rival submissions made by the learned counsel for the parties have been
duly considered and the materials placed before this Court have been carefully
examined.

24.      To appreciate the issue certain factors are required to be considered. Firstly,
there is no manner of doubt that there was an order of the authorities dated
05.05.2015 directing the petitioner not to disconnect the electricity connection.
Immediately, thereafter on 15.06.2015 an order of injunction was passed by a
competent Court to the effect that the electricity connection should not be
disconnected.

25.      In the backdrop of the aforesaid preceding facts, the legality of the impugned
order is required to be examined.

26.      The Suit namely TS/176/2015 instituted by the Samiti and 19 Ors., amongst
others, had the following prayers:

   (a)        "For a declaration that consumer / members of plaintiff No. 1 Samiti
           including plaintiff Nos. 2 to 20 are the legitimate consumers of defendant
                                                                        Page No.# 10/16

      No. 1 APDCL, CAR & they are entitled to continue the enjoyment of electric
      service on payment of actual consumption bills directly to the Office of the
      defendant No. 5 & 6.



(b)      For a declaration that the bills issued by the defendant Nos. 8 & 9 in the
      name of the members of plaintiff No. 1 Samiti including plaintiff Nos. 2 to 20
      vide dated 20.04.2015 & 20.05.2015 "Bill cum Disconnection Notice" are
      illegal, arbitrary & collusive & direct violation of the letter dated 05.05.2015
      & 30.05.2015 issued by the defendant No. 6 & also in violation of tariff of
      defendant No. 1 & as such the same are liable to be declared illegal,
      collusive, baseless & cancelled & the defendant Nos. 8 & 9 have no authority
      to implement the said bills.


(c)      For a declaration that members of plaintiff No. 1 Samiti including plaintiff
      Nos. 2 to 20 are not liable to make payment of the alleged amount as shown
      in the Bill cum disconnection Notice dated 20.04.2015 & 20.05.2015 & on
      subsequent date(s) issued by the defendant Nos. 8 & 9.


(d)      For a declaration that defendant Nos. 1 to 7 are bound by law & equity to
      terminate franchise of defendant Nos. 8 & 9 for his illegal & arbitrary action
      & misuse of power (energy) & take up the consumers of plaintiff No. 1
      Samiti including the plaintiff Nos. 2 to 20 directly under the control &
      management of defendant No. 1 to 7 & its officials i.e., under the town
      feeder meter near forest office, Botorashi & Town Feeder meter near old
      custom office of Dhit Botorashi.


(e)      For a perpetual injunction restraining the defendants from giving effect to
      the bill cum disconnection notices dated 20.04.2015 & 20.05.2015 & other
                                                                           Page No.# 11/16

         bills on other dates in the name of the members of the plaintiff No. 1 Samiti
         including the plaintiff No. 2 to 20 or in any way attempt to collect the alleged
         bill amount of the said bills or in any way cause loss & suffering to the
         consumers members of plaintiff No.1 Samiti including plaintiff Nos. 2 to 20
         or deprive them from their legitimate rights & consumption charges or
         attempt to disconnect the electric service connection of the members of
         plaintiff No. 1 Samiti including plaintiff Nos. 2 to 20."


27.   As observed above, both the APDCL and the petitioner had filed a common
written statement. The petitioner and his firm were arrayed as respondent nos. 8 and
9 in the aforesaid TS/176/2015. In the said written statement, the case of the
plaintiffs was specifically opposed and it was contended that the suit be dismissed.
The averments made in the following paragraphs of the written statement which are
extracted hereinbelow are required to be taken into consideration.

      "14.   That the statements made in paragraph 7 of the plaint are not correct
      and hereby denied by the answering defendants. The answering defendant No.
      9 never issued any arbitrary bill without observing the Schedule of the tariff as
      alleged in paragraph 7 of the plaint. It is not true that the defendant No. 9
      through the defendant No. 8 failed to collect accurate / correct reading of the
      meter of its consumers. It is also a false and baseless statement that the
      defendant No. 9 through the defendant No. 8 failed to adjust subsidy as per
      schedule of tariff. The defendant No. 9 never violated the tariff. The F.P.A.
      charged in the electric energy bill as per tariff and subsequently the F.P.A.
      amount were adjusted to the consumers after change the tariff.



      15.    That the statements made in paragraph 8 of the plaint are totally false
      and baseless. It is not true that the defendant No. 9 through his franchise the
                                                                     Page No.# 12/16

defendant No. 8. Sometime collected money unauthorisely from the consumers
for providing new electric service connection under Jivan Jyoti Programme and
other project of electricity as provided by the Govt. It is also not true that the
defendant No. 9 collected consumption charges of electricity by issuing token /
slip as alleged in paragraph 8 of the plaint. The defendant No. 9 never took
money from the consumers unauthorisedly. The defendant No. 9 through his
franchise the defendant No. 8 never gave connection of electricity in the house
of some of the consumers of the plaintiff No. 1 Samity without installing meter
in their house as alleged in paragraph 8 of the plaint.

      ...

17. That the statements made in paragraph 10 of the plaint are totally false and baseless. The defendant No. 9 in the name of his franchise the defendant No. 8 issued electric energy bills to the consumers as per consumptions of electric energy by the consumers. The defendant Nos. 8 and 9 never did any illegal acts and as such there are no reasons for cancellation of franchise of the defendant Nos. 8 & 9. The consumers are not entitled to consume electric energy without payment of electric energy bills. The defaulter consumers have formed an unlawful assembly and filed the instant suit suppressing the facts to avoid payment of electric energy bills against their consumption of electric energy and to cause loss & injury to the defendants.

...

38. That the salient facts of the case are as follows:-

             i.     ...

             ii.    That the instant suit is vague, speculative and without any

cause of action. Admittedly the plaintiff Nos. 3 to 19 are defaulters in payment of electric energy bills against their consumption of electric energy. The plaintiff Nos. 3 to 19 being the consumers of Page No.# 13/16 the defendant No. 1, they have come before this Hon'ble Court with prayer for declaration that the plaintiffs are not liable to make payment of the amount of bill cum disconnection notice dated 20.04.2015 and 20.05.2015 and on the subsequent bills issued by the defendant Nos. 8 and 9. The plaintiffs stated in paragraph 25 of the plaint that the plaintiffs did not make payment of electric energy bills against their consumption of electric energy with effect from the month of January, 2015 and February, 2015. Accordingly the admitted fact is that the plaintiff Nos. 3 to 19 paid electric energy bill upto December 2014. Thereafter the plaintiff Nos. 3 to 19 continued consumption of electric energy without making payment of electric energy bills against their consumption on electric energy till today.

iii.    ...

iv.     That the defendant No. 8 under the proprietorship of the

defendant No. 9 is the franchise of the defendant No. 1 and as such all functions of the defendant Nos. 8 & 9 remains under the direct supervision of the defendant Nos. 1 to 7. The payment of electric energy bills of the consumers of the franchise, the defendant No. 8 are treated as payment to the defendant No. 1. The plaintiff Nos. 3 to 19 are not entitled to consume electric energy without payment of electric energy bills.

v. The electric energy bills are issued as per consumption of electric energy by the consumers. It is not true that the electric energy bills are issued by the defendant No. 9 through his fanchise, defendant No. 8 arbitrarily without observing the schedule of tariff. The consumers are liable to make payment of electric energy bills Page No.# 14/16 against their consumption of electric energy. In the event of detection of any genuine anomalies in the Bill the same may be adjusted as per norms and procedures. The consumers are not entitled to consume electric energy without payment of electric energy bills.

vi. There was no illegal acts and deeds of the defendant Nos. 8 & 9. The complain of the plaintiff No. 1 Samity was, however, duly entertained by the defendant/OP Nos. 3 and 6 and the defendant Nos. 8 & 9 were requested not to initiate any disconnection of the defaulting consumer until further instruction from GM Silchar Zone APDCL, Silchar. But no where it was stated that the plaintiffs are entitled to enjoy electric energy without payment of electric energy bills. The defendant No. 9 being the proprietor of defendant No. 8 Franchise is entitled to maintain the electric service connection within his franchise and issue electric energy bills to the consumers within the supervision of the defendant No. 5 & 6 to protect the interest of the consumers. The defendant Nos. 8 & 9 is under the control and supervision of the defendant Nos. 5 & 6 and as such there are no reasons for any illegality and loss of consumers.

vii. ..."

Apart from the paragraphs quoted, on a reading of the stand of the APDCL in the said Title Suit, it becomes absolutely clear that no fault was attributed upon the petitioner by the APDCL in the matter.

28. The impugned order dated 04.08.2017 has been passed by taking certain factors into consideration. It has also been stated that the petitioner's firm has been found to be regular defaulter and a police case was also lodged for making unauthorized connection along with extension of LT Line. That apart, complaints were Page No.# 15/16 made by the Samiti regarding erroneous bills.

29. A writ Court exercising jurisdiction under Article 226 of the Constitution of India can examine the decision making process. The examination can go to the extent of reaching a satisfaction as to whether the relevant factors have been taken into consideration and as to whether the conclusion reached is that of a reasonable person. This Court would also explore as to whether extraneous or irrelevant consideration had played any role in the decision making process coupled with the fact of absence of any bias. Finally, adherence to the principles of natural justice which is the hallmark of a reasonable action needs to be examined.

30. In the instant case, certain factors appear to have been taken into consideration in the impugned order dated 04.08.2012 before reaching the conclusion. Those factors, per se, do not appear to be extraneous or irrelevant. However, at the same time, one cannot ignore or overlook the stand of the APDCL in the common written statement filed in the Title Suit, the details of which have already been observed above. The APDCL being an instrumentality of the State cannot be allowed to take wavering stand in two proceedings connected to the same dispute.

31. Admittedly, there was an order dated 05.05.2015 passed by the authorities directing the petitioner not to raise any bills in respect of the consumers in question. That was followed by the order of injunction dated 15.06.2015 passed by a competent Civil Court in TS/176/2015 and as per the records, the injunction was vacated only on 21.09.2016 when the Suit was also dismissed. Therefore, the records itself would show that from 05.05.2015 to 21.09.2016, the petitioner could not raise any bills and therefore, it would be wholly unjustified to make any demand for that period.

32. At the same time, as has been laid down by the Hon'ble Supreme Court that disputed questions of facts cannot be adjudicated by a writ Court which would require adducing of evidence, cross examination etc., an attempt by this Court to enter into the merits may not be a correct step. As noted above, the issue of conversion / switch Page No.# 16/16 over has not been pressed by the petitioner.

33. In view of the above, this writ petition is disposed of by holding that so far as the challenge to the impugned demand of Rs.16,11,674/- to APDCL is concerned, the same can be the subject matter of challenge in an appropriate Suit for which liberty is granted to the petitioner. In the event, such Suit is instituted, the learned Civil Court is required to deal with the wavering stand of the APDCL as indicated above and thereafter, take a decisions on merits. Since, the present writ petition is the third round of litigation in this High Court which was continuing till date, in case a Suit is instituted by the petitioner the same be entertained and examined on merits and should not be rejected on the ground of limitation. The parties may also take recourse to Section 14 of the Limitation Act of 1963 as this present petition was being pursued bona fide.

34. The writ petition is accordingly disposed of.

35. No order, as to cost.

JUDGE Comparing Assistant