Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 6, Cited by 1]

Delhi High Court

Delhi Jal Board Contractors Welfare ... vs Delhi Jal Board & Ors. on 30 May, 2011

Author: Dipak Misra

Bench: Chief Justice, Sanjiv Khanna

*IN THE HIGH COURT OF DELHI AT NEW DELHI

+      LETTERS PATENT APPEAL NO. 509/2011

                                                   Date of order: 30th May, 2011

DELHI JAL BOARD CONTRACTORS
WELFARE ASSOCIATION                   ...... Appellant
                      Through, Mr. Chetan Sharma, Sr.
                      Advocate with Mr. Peeyoosh Kalra,
                      Advocate.

                       versus

       DELHI JAL BOARD & ORS.                                 ..... Respondents
                     Through

        CORAM:
        HON'BLE THE CHIEF JUSTICE
        HON'BLE MR. JUSTICE SANJIV KHANNA

1. Whether Reporters of local papers may be allowed to see the judgment?       Yes
2. To be referred to the Reporter or not?                                      Yes
3. Whether the judgment should be reported in the Digest?                      Yes

DIPAK MISRA, CJ.:

C.M.No.10875/2011

       This is an application for condonation of 72 days delay in

preferring the appeal. We have heard Mr. Chetan Sharma, learned

senior counsel along with Mr. Peeyoosh Kalra, learned counsel for the

petitioner on the question of condonation of delay.

2.     Before issuing notice on the question of condonation of delay,

we think it appropriate to address whether there is justification, warrant

or merit in the appeal to issue notice. Thus, we proceed to deal with the

appeal on merits.
LPA No.509/2011                                                        Page 1 of 13
 3.     Questioning the legal substantiality of the order dated 16 th

December, 2010 passed by the learned single Judge in W.P.(C)

No.8052/2010, the present intra-Court appeal has been preferred. The

appellant, namely, Delhi Jal Board Contractors Welfare Association

(Regd.), members of which are class-I contractors, preferred the writ

petition under Article 226 of the Constitution of India assailing the

empanelment and enlistment of fifth respondent, namely, M/s Vishal

Nimriti Pvt. Ltd. as a contractor under Delhi Jal Board (for short,

„DJB‟) on the ground that it did not meet the eligibility criteria under

Rule 11.1 and 14.0 of Rules for Enlistment of Contractors in DJB (for

brevity, „Rules‟). It was contended before the learned single Judge that

the said company was a new contractor, which did not have the

requisite experience since it had not executed necessary number and

magnitude of works as fixed under the eligibility criteria for

registration as a class-I contractor.

4.     The said stand and stance was controverted by the fifth

respondent on the ground that a scheme of amalgamation has been

approved by the Bombay High Court under Sections 391 and 392 of

the Indian Companies Act, 1956 and as per which all contracts,

agreements, arrangements of whatsoever nature to which M/s

Permanent Prestress Pvt. Ltd. was a party or had benefit of, stood

transferred to the new entity and, therefore, there was no error in its

LPA No.509/2011                                           Page 2 of 13
 empanelment. To bolster the said submission, reliance was placed on

the decision in New Horizons Ltd. Vs. Union of India (1995) 1 SCC

478, where the issue of past experience was the subject matter of lis

before the Apex Court. That apart, inspiration was drawn from the

decision in the case of Ganpati RV-Talleres Alegria Track Pvt. Ltd.

Vs. Union of India (2009) 1 SCC 589. On behalf of the present

appellant, an effort was made to distinguish the said decision before

the learned single Judge, but he has placed reliance on New Horizons

Ltd. (supra) and expressed the view that the writ petition was without

any substance and the nature of litigation was against the spirit of

Indian Competition Act, 2002. Being of this view, he dismissed the

writ petition.

5.     Mr. Chetan Sharma, learned senior counsel appearing for the

appellant-association has raised the following contentions:-

(i)    The Rule 11.1 has been erroneously interpreted by the learned

single Judge inasmuch as the experience that is envisaged under the

said Rule has to be satisfied by the contractor, but not by the

amalgamated entity.

(ii)   The single Judge has totally lost sight of Rule 14.0, which

clearly lays a postulate that there cannot be a change in constitution of

a firm without prior approval of DJB. In the present case, such a thing



LPA No.509/2011                                            Page 3 of 13
 has happened thereby disentitling the fifth respondent from being

enlisted.

(iii)   The reliance placed on New Horizons Ltd. (supra) by the

learned single Judge is totally incorrect, for in the said decision their

Lordships have fairly stated that in the absence of experience by all the

constituents, experience of a newly emerged entity cannot be taken into

consideration.

(iv)    DJB in pursuance of an application preferred by the petitioner

under the Right to Information Act, 2005 had clearly stated that the

respondent No.5 was not eligible for entitlement, but thereafter

reviewed the same in a laconic manner, which defies the basic

ingredients of administrative law inasmuch as it is incumbent on any

authority reviewing an order to ascribe reasons.

6.      To appreciate the aforesaid submissions raised by the learned

senior counsel for the appellant, it is imperative to note that the fifth

respondent, namely, M/s Vishal Nimriti Pvt. Ltd., got a scheme of

amalgamation accepted by the Bombay High Court under the

Companies Act, 1956. As is perceptible, a stand was taken before the

learned single Judge that all contracts, agreements, arrangements,

which were granted in favour of M/s Permanent Prestress Pvt. Ltd.

would stand transferred to the new contractor i.e. the new amalgamated

entity. The said stand of the fifth respondent has not been negatived on

LPA No.509/2011                                           Page 4 of 13
 facts. Thus, the question, which arises, is whether in view of this fact,

Rule 11.1 and Rule 14.0 would defeat the benefit of empanelment.

7.     First we shall proceed to deal with the applicability of Rule 14.0

to the facts of the present case.       Rule 14.0 deals with change in

constitution of a firm after it is registered. As Mr. Sharma, learned

senior counsel has laid enormous emphasis on the said clause, we think

it seemly to reproduce the same;

             "Change in Constitution of Firm- The
             contractor/firm shall not modify the existing
             partnership or enter into any fresh partnership or
             change the name of firm without the prior
             approval of the enlistment authority. Such
             proposal, if any, shall be submitted in advance
             giving full details of the intended partnership/sole
             proprietorship along with the draft partnership
             deed/affidavit and documents as per Annexure-VI.
             Any change in status of the contractor as an
             „individual‟ or in constitution of the firm or
             change in the name of firm without prior approval
             of the enlistment authority will render the
             contractor/firm liable to be removed from the
             approved list of contractors."


       On a perusal of Rule 14.0, we have no iota of doubt that the

same really gets applicable once a firm or company is registered.

Unless there is registration or empanelment, the said Rule is not

attracted.

8.     Rule 11.1 of the Rules reads as under:-

             "The criteria for experience, in case of enlistment,
             shall be the completion of requisite number of

LPA No.509/2011                                              Page 5 of 13
             works, as the case may be, or prescribed nature of
            magnitude executed on independent contract basis
            or as a builder during the last five years. The
            works should have been executed in the same
            name and style in which the enlistment is sought.
            Enlistment of an individual in corresponding
            category may also be done based on his technical
            qualification in lieu of experience of completion of
            works in last 5 years if provision exists in Table 1
            of the Rules but other eligibility criteria remaining
            the same."


9.     On a plain reading of the aforesaid Rule, it is quite clear that the

experience of the requisite number of works is a condition precedent.

Thus, the only clause attracted to the field of empanelment is clause

11.1. Learned senior counsel has drawn our attention to certain aspects

which relate to the facts which he has obtained by way of information

under the RTI Act, 2005. Mr. Sharma, learned senior counsel has

drawn our attention to paragraph 49 of Annexure A-5 of the paper

book, specially, questions 3.1 and 3.2, which read as follow:-

               "3.1 Whether M/s Vishal Nirmati registered
            enlisted under category-I fulfills conditions as
            mentioned at S.No.2.
               3.2 Whether the firm submitted the details of
            executed works, having been executed in the same
            name and style in which the enlistment was sought
            i.e. M/s Vishal Nirmal Pvt. Ltd."


10.    Thereafter, learned senior counsel has drawn our attention to

Annexure A-7, which is the reply, given by the competent authority



LPA No.509/2011                                              Page 6 of 13
 under the RTI Act. Reply given to questions 3.1 and 3.2 reads as

under:-

               "M/s Vishal Nirmiti has been enlisted in class-I.
            As per documents of the said firm, it was revealed
            that three firms were amalgamated with M/s
            Vishal Nirmiti Pvt. Ltd. by the order of Hon‟ble
            High Court, Bombay dated 23-11-2007 and the
            work experience of one of the amalgamated firm
            i.e. M/s Permanent Prestress Pvt. Ltd. has been
            considered by the Sub-Committee as well as
            Enlistment Committee and the same was approved
            by the competent authority (Copy enclosed). Now
            as per CPWD/DJB norms, the enlistment case of
            the above firms has been moved for review of the
            competent authority."


11.    Be it noted, thereafter an appeal was preferred and the

competent authority had passed the following order:-

            "The above case was taken up for hearing today
            i.e. on 17.5.2010. Appellant was present. From
            Deptt. Side Sh. Harish Chander EO to CE(Dr.)
            Proj-I was present. After carefully going through
            the RTI application and the reply furnished by the
            deptt. and hearing both sides, I direct that specific
            reply in respect of Q No.3.1, 3.2 and 3.3(i) of
            original RTI application may be provided to the
            appellant within a week‟s time."


12.    After the appellate authority passed the order, the DJB

proceeded to inform the petitioner in the form of reply as follows:-

               "No. Further, the case was reviewed by the
            competent authority after receipt of letter from
            DJB Contractors Welfare Association (Regd.)
            (copy attached)."


LPA No.509/2011                                              Page 7 of 13
 13.    Learned senior counsel has also invited our attention to the

meeting of DJB held on 23rd August, 2010. For the sake of

completeness, we think it appropriate to reproduce the same.

                   "In the last Board meeting held on
            12.08.2010, one of the Members raised the issue
            of registration of M/s Vishal Nimriti Pvt. Ltd. as
            Class-I contractor. The issue arose in respect of a
            preamble for the award of work of Shifting of
            water mains falling in the alignment of proposed
            Master Plan Road from Narela flyover to Western
            Jamuna Canal (WJC) to the firm. Though the
            Board finally agreed to award the work, yet it was
            decided that the work order should only be issued
            after completing the review of the enlistment of
            the firm by the Enlistment Committee.
            Accordingly, it would be prudent that the firm is
            not considered for further participation in the
            tenders till a final decision is taken in respect of
            the enlistment of the firm as Class-I contractor."


14.    Thereafter, vide Annexure A-11 dated 12th October, 2010, the

following order came to be passed:-

                   " It is in continuation to communication
            from Member (WS) issued vide No.F-
            53/DJB/M(WS)/2010-2304             dated     23.8.10
            directing that M/s Vishal Nirmiti Pvt. Ltd. be not
            considered for participation in the tenders till a
            final decision is taken in respect of enlistment of
            the firm as Class-I contractor.
               On review of the matter by the Enlistment
            Committee and as approved by the competent
            authority, since the initial enlistment of the firm;
            namely, M/s Vishal Nirmriti Pvt. Ltd. as Class I
            contractor has been found in order, the
            communication as referred to above is withdrawn.
               This is being issued with the approval of
            competent authority."

LPA No.509/2011                                             Page 8 of 13
 15.    Learned senior counsel would contend that the application of the

fifth respondent has been treated to be an order by the reviewing

authority, but no reasons have been given. There is no adjudication of a

lis or adjudication of disputes between two parties, but this was a case

for determining the eligibility criteria for empanelment. It does not

necessarily grant or award contract. That apart, it clearly states that

enlistment committee has reviewed the matter and has been approved

by the competent authority. In certain cases ascribing of reasons may

be the necessity, but if the reasons are perceptible from the factual

matrix that is available to the Court on that score, the order is not to be axed.

We are inclined to think as we find, when the new entity came into existence

and the company namely, M/s Permanent Prestress Pvt. Ltd. had the

requisite experience which has not been disputed either in facts or law, the

same can be taken into consideration. In this connection, we may refer with

profit to paragraph 39 of New Horizons (supra), which reads as follows:-

               "39. On behalf of the respondents reliance has
            been placed on the decision of the Delhi High
            Court in Paharpur Cooling Towers Ltd., v.
            Banbaigon Refinery and Petrochemicals Ltd.
            wherein it has been held that the expression
            "tenderer should possess such experience" would
            mean the experience of the tenderer itself and not
            that of its collaborator. It has been pointed out that
            SLP (C) No. 1484 of 1994 filed against the said
            judgment has been dismissed by this Court by
            order dated 28-1-1994. It has been urged that on
            the same logic the experience of a shareholder
            would not be included within the expression
            "experience of the tenderer". We fail to appreciate
            the relevance of this judgment. There can be no


LPA No.509/2011                                                  Page 9 of 13
             comparison between a collaborator who has no
            stake in the business of the company and a
            constituent of a company, such as NHL,
            constituted as a joint venture, wherein the
            constituents in the joint venture have a substantial
            stake in the success of the venture."


16.    On a perusal of the aforesaid paragraph, it is clear as day that

what is required is the stake of the joint venture company. In the said

case, the Apex Court was dealing with the concept of joint ventures

and in the present case when there is amalgamation of the two entities

which have merged with each other and become one, we are disposed

to think that the entire conception as enshrined and engrafted under

Sections 391 and 392 of the Companies Act come into play. It cannot

be said that both the companies should have experience. It cannot be

said that M/s Permanent Prestress Pvt. Ltd. has no stakes. In fact the

stakes have been unified into one and that is also stated in paragraph 23

of the decision in the case of New Horizon (supra).The said paragraph

reads as follows:-

               "23. Even if it be assumed that the requirement
            regarding experience as set out in the
            advertisement dated 22-4-1993 inviting tenders is
            a condition about eligibility for consideration of
            the tender, though we find no basis for the same,
            the said requirement regarding experience cannot
            be construed to mean that the said experience
            should be of the tenderer in his name only. It is
            possible to visualise a situation where a person
            having past experience has entered into a
            partnership and the tender has been submitted in
            the name of the partnership firm which may not
            have any past experience in its own name. That
            does not mean that the earlier experience of one of

LPA No.509/2011                                             Page 10 of 13
             the partners of the firm cannot be taken into
            consideration. Similarly, a company incorporated
            under the Companies Act having past experience
            may undergo reorganisation as a result of merger
            or amalgamation with another company which
            may have no such past experience and the tender
            is submitted in the name of the reorganised
            company. It could not be the purport of the
            requirement about experience that the experience
            of the company which has merged into the
            reorganised company cannot be taken into
            consideration because the tender has not been
            submitted in its name and has been submitted in
            the name of the reorganised company which does
            not have experience in its name. Conversely there
            may be a split in a company and persons looking
            after a particular field of the business of the
            company form a new company after leaving it.
            The new company, though having persons with
            experience in the field, has no experience in its
            name while the original company having
            experience in its name lacks persons with
            experience. The requirement regarding experience
            does not mean that the offer of the original
            company must be considered because it has
            experience in its name though it does not have
            experienced persons with it and ignore the offer of
            the new company because it does not have
            experience in its name though it has persons
            having experience in the field. While considering
            the requirement regarding experience it has to be
            borne in mind that the said requirement is
            contained in a document inviting offers for a
            commercial transaction. The terms and conditions
            of such a document have to be construed from the
            standpoint of a prudent businessman. When a
            businessman enters into a contract whereunder
            some work is to be performed he seeks to assure
            himself about the credentials of the person who is
            to be entrusted with the performance of the work.
            Such credentials are to be examined from a
            commercial point of view which means that if the
            contract is to be entered with a company he will
            look into the background of the company and the
            persons who are in control of the same and their
            capacity to execute the work. He would go not by
            the name of the company but by the persons
            behind the company. While keeping in view the
            past experience he would also take note of the
            present state of affairs and the equipment and
            resources at the disposal of the company. The

LPA No.509/2011                                            Page 11 of 13
              same has to be the approach of the authorities
             while considering a tender received in response to
             the advertisement issued on 22-4-1993. This
             would require that first the terms of the offer must
             be examined and if they are found satisfactory the
             next step would be to consider the credentials of
             the tenderer and his ability to perform the work to
             be entrusted. For judging the credentials past
             experience will have to be considered along with
             the present state of equipment and resources
             available with the tenderer. Past experience may
             not be of much help if the machinery and
             equipment is outdated. Conversely lack of
             experience may be made good by improved
             technology      and    better    equipment.      The
             advertisement dated 22-4-1993 when read with the
             notice for inviting tenders dated 26-4-1993 does
             not preclude adoption of this course of action. If
             the Tender Evaluation Committee had adopted this
             approach and had examined the tender of NHL in
             this perspective it would have found that NHL,
             being a joint venture, has access to the benefit of
             the resources and strength of its parent/owning
             companies as well as to the experience in database
             management, sales and publishing of its parent
             group companies because after reorganisation of
             the Company in 1992 60% of the share capital of
             NHL is owned by Indian group of companies
             namely, TPI, LMI, WML, etc. and Mr Aroon
             Purie and 40% of the share capital is owned by
             IIPL a wholly-owned subsidiary of Singapore
             Telecom which was established in 1967 and is
             having long experience in publishing the
             Singapore telephone directory with yellow pages
             and other directories. Moreover in the tender it
             was specifically stated that IIPL will be providing
             its unique integrated directory management system
             along with the expertise of its managers and that
             the managers will be actively involved in the
             project both out of Singapore and resident in
             India."


17.    In view of the aforesaid, we are of the considered opinion that

eligibility criteria as enumerated under Rule 11.1 of the Rules stands

satisfied.


LPA No.509/2011                                              Page 12 of 13
 18.    We will be failing in our duty, if we do not take note of the

submission of Mr. Sharma that the learned single Judge should not

have referred to the Competition Act and certain historical statements

made by great protagonists in the field of Economics and Industry with

regard to competition and that has influenced the order.         In our

considered opinion, such references in the present case do not vitiate

the order. It is the economic philosophy which has been brought into

the legal philosophy as the single Judge had felt that the petitioner

though claims to be an association of 160 members is scared of

including any other member and possibly wants to shy away to

compete with the fifth respondent. The purpose of reference to this

statement has to be understood in this way and not in the manner Mr.

Sharma has appreciated. Hence, said submission of Mr. Sharma leaves

us totally unimpressed.

19.    In view of the aforesaid, we do not perceive any reason to issue

notice on the question of condonation of delay and accordingly the

application for condonation of delay stands rejected and as a natural

corollary, the appeal stands dismissed in limine.


                                             CHIEF JUSTICE


                                             SANJIV KHANNA, J.

MAY 30, 2011 NA LPA No.509/2011 Page 13 of 13