Section 4(3)(i) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
(i)where the transmission line or substation is dedicated for evacuation of power from a particular generating station, the generating company and transmission licensee shall endeavour to commission the generating station and the transmission system simultaneously as far as practicable and shall ensure the same through appropriate Implementation Agreement in accordance with Regulation 12(2) of these Regulations :