Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 2, Cited by 1]

Jammu & Kashmir High Court

M/S K.K.Enterprises vs Uoi.Th.Ministry Of Defence And Ors. on 7 March, 2014

        HIGH COURT OF JAMMU AND KASHMIR
                              AT JAMMU

A.A. No.24/2012


                                      Date of order: 07.03.2014
M/S K.K.Enterprises             v.            Union of India and ors.
Coram:
        Hon'ble Mr. Justice M. M. Kumar, Chief Justice

Appearing counsel:
For the petitioner (s)   :     Mr.Anil Mahajan, Advocate.
For the respondent(s)    :     Mr. R.P.Jamwal, CGSC.


 i)   Whether to be reported
      Press, Journal/Media          :           Yes.
 ii)  Whether to be reported in
      Digest/Journal                :           Yes
__________________________________________________________________


1.      This order shall dispose of three* arbitration applications

filed by the same petitioner against the same respondents.

However, the cause of action in each one of them emerges

from different contract agreements which necessitated filing of

three separate petitions under Section 11 of the Jammu &

Kashmir Arbitration and Conciliation Act, 1997.

2.      Few undisputed facts taken from A.A. No.24/2012 may

first be noticed.

2.1. The petitioner is a duly approved contractor with Military

Engineering Service, Ministry of Defence Government of India

and is engaged in executing works of civil nature. The petitioner

was a successful bidder and on 10.10.2007 a contract was

allotted to it for a sum of Rs.8,92,405.57 which was for 'special

repairs to building No.P-11 & T-22 , Bikaner line at Domana'
                                2




(AnnexureP-1). Accordingly contract agreement was executed

between    respondents-Union       of   India   through   Garrison

Engineer, Jammu-respondent No.3 and the petitioner firm. The

general conditions of contract namely 'IAFW 2249' constituted

part and parcel of the contract agreement (Annexure P-2). The

initial date for completion of work fixed in the contract

agreement was 13.07.2008 and the same was later extended

upto 25.11.2008.

2.2. The petitioner claimed that as per the contract agreement

intimation was sent about completion of work through various

letters. It has been confirmed by the officers of the department

that the work was completed by the petitioner on 07.10.2008.

The completion certificate was issued by the department on

29.11.2008. These letters have been placed on record

(Annexure P-3 to P-5). As per the contract agreement, Chief

Engineer is the designated authority to appoint the arbitrator.

The petitioner submitted final bill claiming full payment but the

same became subject matter of disptue. A copy of letter dated

13.07.2012 was sent to respondent No.3 claiming that the work

was completed on 25.11.2008 and the bill has been paid on

18.08.2009. It has been brought to my notice during the course

of arguments that the final bill submitted by the petitioner did

not find complete approval of the respondents. A perusal of the

documents with the final bill shows that there are a number of
                                 3




items     which   have   been    scored    off   and   there   are

cuttings/omissions. Even the signature/counter signatures of

the contractor have been deleted. The aforesaid documents

have been placed on record and relied upon by the

respondents themselves. Signatures which have been encircled

at pages 15 and 18 clearly show that the signatures have been

cancelled by crossing the same. It is thus clear that final bill

submitted by the petitioner has not been fully honoured by the

respondents.

3.      I have heard learned counsel for the parties and have

perused the record with their able assistance.

4.      Mr. Mahajan, learned counsel for the petitioner has

argued that in terms of Clause 70 of the general conditions of

the contract namely IAFW 2249 all disputes between the

parties to the contract are required to be referred to the

arbitration of a engineer officer after written notice by either of

the party to the contract. In the face of the arbitration clause

which stands incorporated in the contract agreement and live

dispute between the parties it has been submitted that the

prayer made by the petitioner deserves to be accepted.

5.      On the contrary, Mr. Jamwal learned counsel for the

respondents has vehemently argued that Clause 65 as

reproduced in Annexure R-5 of the objections creates a

complete bar for referring the dispute between the parties to the
                                   4




contract once the final bill has been submitted by the

contractor. According to Mr. Jamwal, the submission of the final

bill by the contractor itself results into operation of Clause 65,

which provides that no further claim could be made by the

contractor after submission of the final bill. According to the

learned counsel, any other claim is deemed to have been

waived and it would be extinguished.

6.   Having heard learned counsel for the parties and

perusing the record I am of the considered view that two basic

conditions for making reference to arbitrator stand satisfied in

the present case. There is Clause 70 of the general conditions

of contract in the form of IAFW 2249 which provide for

arbitration in case of dispute between the parties. The aforesaid

Clause 70 stands incorporated in the contract agreement

executed between the parties as is evident from the copy of the

original contract agreement which has been placed on record

with CMA No.5/2013 filed in A.A. No.24/2012. The aforesaid

Clause 5(b) is set out below in extenso:-

            "5.    General conditions of contract, IAFW-2249 (1989
           print) together with amendment No.1 to 15 and errata 1 to
           20.
            EEEEEEEEEEEE..
            EEEEEEEEEEEE..
            (a)EEEEEEEEEEE..
            (b)    To execute all the works referred to in the said
           documents upon the terms and conditions contained or
           referred to three-in and as detailed in the General Summary
           on the subsequent page and to carry out each deviation as
           may be order vide condition 7 of IAFW-2249, (upto a
           maximum of 20 percent) and further agreed to refer all
           disputes as required by condition 70 to the sole arbitrator of
           an serving officer having degree in Engineering of equivalent
                                       5




              or having passed final/direct final examination of Sub
              Division II of Institution of surveyors (India) recognized by the
              Govt. of India be appointed by Chief Engineer (or Officiating
              Chief Engineer) Pathankot Zone Pathankot whose decision
              shall be final conclusive and binding.
              To be deleted where inapplicable."


7.       A perusal of the aforesaid provision shows that the parties

have agreed to refer all disputes as per the requirement of

condition 70 to the sole arbitration of a serving officer having

degree in engineering or equivalent or having passed final

examination of Sub Division II of Institution of surveyors (India)

recognized by the Govt. of India. The arbitrator is to be

appointed by the Chief Engineer or Officiating Chief Engineer,

Pathankot Zone Pathankot whose decision is to be binding and

final.

         The oft quoted clause 70 may also be set out below in

extenso, which reads thus:-

              "70. Arbitration.--- All disputes, between the parties to the
              Contract (other than those for which the decision of the
              C.W.E. or any other person is by the Contract expressed to
              be final and binding) shall, after written notice by either party
              to the Contract to the either of them, be referred to the sole
              arbitration of an Engineer Officer to be appointed by the
              authority mentioned in the tender documents.
              Unless both parties agree in writing such reference shall not
              take place until after the completion or alleged completion of
              the Works or termination or determination of the Contract
              under Condition Nos. 55, 56 and 57 hereof.
              Provided that in the event of abandonment of the Words or
              cancellation of the Contract under Condition Nos.52, 53 or 54
              hereof, such reference shall not take place until alternative
              arrangements have been finalized by the Government to get
              the Works completed by or through any other Contractor or
              Contractors or Agency or Agencies.
              Provided always that commencement or continuance of any
              arbitration proceeding hereunder or otherwise shall not in
              any manner militate against the Government's right of
              recovery from the contractor as provided in Condition 67
              hereof.
                                      6




             If the Arbitrator so appointed resigns his appointment or
            vacates his office or is unable or unwilling to act due to any
            reason whatsoever, the authority appointing him may appoint
            a new Arbitrator to act in his place.
            The Arbitrator shall be deemed to have entered on the
            reference on the date he issues notice to both the parties,
            asking them to submit to him their statement of the case and
            pleadings in defence.
            The Arbitrator may proceed with the arbitration, exparte, if
            either party, inspite of a notice from the Arbitrator fails to take
            part in the proceedings.
            The arbitrator may, from time to time with the consent of the
            parties, enlarge, the time upto but not exceeding one year
            from the date of his entering on the reference, for making
            and publishing the award.
            The Arbitrator shall give his award within a period of six
            months from the date of his entering on the reference or
            within the extended time as the case may be on all matters
            referred to him and shall indicate his findings, along with
            sums awarded, separately on each individual item of dispute.
            The venue of Arbitration shall be such place or places as
            may be fixed by the Arbitrator in his sole discretion.
             The Award of the Arbitrator shall be final and binding on both
            parties to the Contract."

8.      A perusal of Clause 70 would show that all disputes

between the parties to the contract are to be referred to the sole

arbitration of a engineer officer to be appointed by the authority

mentioned in the tender document. It also cover certain other

situations which are not attracted to the facts of the present

case.

9.      It has been claimed that the work was satisfactorily

completed by the petitioner on 25.11.2008. Such a claim is

evident from the perusal of letter dated 29.11.2008 sent under

registered post to the petitioner by respondent No.3 (Annexure

P-4). The petitioner has also complied with the conditions laid

down in Clause 70 of IAFW 2249 by sending a notice for

appointment of arbitrator on 13.07.2012 (Annexure P-6).
                                  7




However, arbitrator has not been appointed within the period of

30 days resulting in filing of the instant petition on 18.09.2012.

The respondents have failed to appoint the arbitrator till today.

Therefore, an independent arbitrator is to be appointed by this

Court as has been laid down by Hon'ble the Supreme Court of

India in Datar Switchgears Limited v. Tata Finance Ltd. and anr.

(2000) 8 SCC 151, of Punj Llyod Ltd. v. Petronet MHB Ltd. (2006) 2

SCC 638, Indian Oil Corporation Limited v. Raja Transport (P) Ltd.,

(2009) 8 SCC 520 and Deep Trading Corporation v. Indian Oil

Corporation and others, (2013) 4 SCC 35.

10.   It is well settled that once there is a live dispute between

the parties and arbitration Clause exists between them then the

dispute is required to be referred to the arbitrator. In that regard

reliance may be placed on the observations of the Supreme

Court made in the cases of SBP & Co. v. Patel Engineering Ltd.

(2005) 8 SCC 618, National Insurance Co. Ltd. v. Boghara Polyfab (P)

Ltd., (2009) 1 SCC 267 and Omnia Technologies (P) Ltd. v. WMA Van

Loosbroek, (2011) 3 SCC 682.


11.   The argument of Mr. Jamwal that Clause 65 creates bar

on the rights of the petitioner to seek reference after submission

of final bill has failed to impress me because Clause 65

contemplates that the contractor would be entitled to be paid

the final sum. In the present case the final bill submitted by the

contractor has been objected to by the respondents on many

counts and even the signatures on the final bill have been
                                  8




canceled by putting a line going over the signatures as is

evident from the perusal of Annexure R-4 at pages 15 and 18. It

is doubtful whether it could be claimed that there was a final bill

and secondly whether in the facts and circumstances of the

case said Clause 65 could be invoked. Admittedly the

petitioner-contractor has not been paid the whole amount

claimed in the final bill which as per Clause 65 he was entitled

to be paid. The judgment of Hon'ble the Supreme Court

rendered in the case of Union of India v. M/s Onkar Nath Bhalla and

Sons, (2009) 7 SCC 350 would also not be attracted to the facts of

the present case because in para 10 of the judgment their

Lordships of Hon'ble the Supreme Court have noticed that

there was no protest raised by the contractor with regard to the

payment made on the basis of the final bill nor any reservation

was reflected. It was in the aforesaid facts and circumstances

that rights of the contractor were deemed to have been waived

and there was no question of any pending dispute referable to

the arbitrator. In the present case the facts are entirely different.

The final bill infact has not been honoured by the respondents

and moreover signatures on the final bill have been cancelled

after crossing the same by putting a line across the signatures

by the contractor himself. Thus the judgment in the case of M/S

Onkar Nath Bhalla (supra) has no application to the case of the

petitioner.
                                    9




12.      As a sequel to the above discussion, the prayer made by

the petitioner in all the three petitions is accepted. The

additional Chief Engineer in the office of Chief Engineer

Northern Command C/o 56 A.P.O. is appointed as arbitrator,

who shall enter the reference and proceed in accordance with

law. An intimation in that regard be sent to the Additional Chief

Engineer in the office of Chief Engineer Northern Command

C/o 56 A.P.O. under registered a/d cover along with copy of this

order. The petitioner shall be entitled to raise all claims before

the arbitrator which shall be decided in accordance with law.

 13. All the three petitions stand disposed of.



                                                  (M. M. Kumar)
                                                  Chief Justice
Jammu,
07.03.2014
Vinod.



*

S.No. Case No. Title

1. A.A.No.24/2012, CMA M/S K.K.Enterprises v. Union of No.5/2014 India and ors.

2. A.A.No.25/2012, CMA M/S K.K.Enterprises v. Union of No.3/2014 India and ors.

3. A.A.No.26/2012, CMA M/S K.K.Enterprises v. Union of No.4/2014 India and ors.





                                                  (M. M. Kumar)
Jammu                                              Chief Justice
07.03.2014.