Union of India - Section

Section 7 in The Forest (Conservation) Rules, 2003

7. Processing of proposals received by the Central Government.

(1)
(a)The Regional Office, after having received the proposal referred in clause (a) and clause (c) of sub-rule (4) of rule 6 shall determine the completeness of proposal within five working days.
(b)If the Regional Office finds that the proposal is incomplete, it shall return it within the period of five working days as specified under clause (a), to the State Government or the Union territory Administration, as the case may be, and this time period and the time taken by the State Government to re-submit the proposal shall not be counted for any future reference.
(2)[ (a) The Regional Office shall after examination of the proposal involving forest land up to five hectares other than the proposal related to mining, encroachments, and hydel projects, which are complete in all respect, and after such further enquiry as it may consider necessary, grant in-principle approval subject to fulfillment of stipulated conditions, or reject the same within twenty five days of its receipt from the State Government or the Union Territory Administration, as the case may be, and communicate the same to the concerned State Government or the Union Territory Administration, as the case may be, within next five days.
(b)[ In case a proposal involves forest land more than one hundred hectares or renewal of lease, Regional Office shall within forty-five days of the receipt of the proposal complete in all respects from the State Government or the Union territory Administration, as the case may be, inspect the forest land proposed to be diverted and prepare a site inspection report:
Provided that in case of the proposals seeking approval under the Act for prospecting of minerals in forest land, prior site inspection by the Regional Office shall be required only if the area of forest land required for construction of roads, paths, drilling of bore holes and all such non-forest purpose is more than one hundred hectares.] [Substituted by Notification No. G.S.R. 713(E), dated 10.10.2014 (w.e.f. 10.1.2003).]
(c)Regional Office shall refer all proposals involving forest land above five hectares and up to forty hectares; proposals related to mining, encroachments, and hydel projects involving forest land up to five hectares; and all proposals related to linear projects which are complete in all respects, including site inspection report, wherever required, to the Regional Empowered Committee within ten days of the receipt of the proposal from the State Government or the Union Territory Administration, as the case may be:
Provided that proposals referred to in clause (b) above, shall be referred to the Regional Empowered Committee within five days of the receipt of the site inspection report.
(d)The Regional Empowered Committee shall within a period of thirty days examine the proposals referred to it under clause (c) above and after such further enquiry as it may consider necessary, grant in-principle approval to the proposals other than proposals related to mining, encroachment and hydel projects subject to fulfilment of stipulated conditions, or reject the same and the Regional Office shall communicate the decision of the Regional Empowered Committee to the concerned State Government or the Union Territory Administration, as the case may be, within next five working days.
(e)The Regional Empowered Committee shall within a period of thirty days examine the proposals related to mining, encroachments, and hydel project involving diversion of forest land up to forty hectares and tender its advice:
Provided that the Regional Empowered Committee may suggest such conditions or restrictions if any, required to be imposed on the use of any forest land for non-forest purpose, which in its opinion would minimise adverse environmental impact.
(f)The Regional Office shall within a period of five days of the receipt of the advice of the Regional Empowered Committee on proposals referred to in clause (e) above, forward such proposal along with advice of the Regional Empowered Committee to the Secretary, Ministry of Environment, Forests and Climate Change for obtaining the decision of the Central Government:
Provided that time taken in transit of a proposal from Regional Office to the Ministry of Environment, Forests and Climate Change shall not be more than five days.
(g)The Central Government shall, after considering the advice of the Regional Empowered Committee and after further enquiry as it may consider necessary, grant in-principle approval subject to fulfillment of stipulated conditions, or reject the same within thirty days of its receipt from the Regional Office and communicate the same to the concerned State Government or the Union Territory Administration, as the case may be, within next five working days.]
(3)
(a)All proposals involving clearing of trees in forest land or portion thereof for the purpose of using it for re-afforestation shall be finally disposed of by the Regional Office within a period of sixty days of receipt of the proposals from the State Government or the Union territory Administration, as the case may be.
(b)While examining the proposal, the Regional Office shall ensure that the final decision is in conformity with the National Forest Policy, Working Plan guidelines and other relevant rules and guidelines issued by the Central Government from time to time.
(c)The Regional Office shall however seek prior clearance of the Ministry of Environment and Forests whenever the proposal involves clear-felling of forest land having crown density above forty per cent irrespective of the area involved, or clear-felling of forest area of size more than twenty hectares in the plains and ten hectares in the hilly region, irrespective of density.
(4)
(a)The Ministry of Environment and Forests, after having received the proposal referred to in clause (b) of sub-rule (4) of rule 6 shall determine the completeness of the proposal within ten days.
(b)If the Ministry of Environment and Forests finds that the proposal is incomplete, it shall return it within the period of ten days as specified under clause (a), to the State Government or the Union territory Administration, as the case may be, and this time period and the time taken by the State Government to resubmit the proposal shall not be counted for any future reference.
(c)[ in case the proposal involves forest land more than one hundred hectares or renewal of lease, the Ministry of Environment, Forests and Climate Change shall within ten days of the receipt of a proposal complete in all respects, request the concerned Regional Office to inspect the forest land proposed to be diverted and submit a report to the Ministry of Environment, Forests and Climate Change within a period of forty-five days: [Substituted by Notification No. G.S.R. 200 (E), dated 6.3.2017 (w.e.f. 10.1.2003).]
Provided that in case of the proposals seeking approval under the Act for prospecting of minerals in forest land, prior site inspection by the Regional Office shall be required only if the area of forest land actually required for construction of roads, paths, drilling of bore holes and all such non-forest purpose is more than one hundred hectares:Provided further that the total time taken in communication of the request for site inspection from the Ministry of Environment, Forests and Climate Change to Regional Office and communication of the site inspection report from the Regional Office to the Ministry of Environment, Forests and Climate Change shall not be more than ten days, over and above the time taken in undertaking site inspection by the Regional Office.] [Inserted by Notification No. G.S.R. 200(E), dated 6.3.2017 (w.e.f. 10.1.2003).]
(d)The Central Government shall refer every proposal, which is complete in all respects, received by it under clause (b) of sub-rule (4) of rule 6 including site inspection reports, wherever required, to the Committee for its advice and the Committee shall give its advice within thirty days from the date of receipt of the said proposal.
(e)The Committee shall have due regard to all or any of the following matters while tendering its advice on the proposals referred to it under clause (d), namely:-
(i)whether the forests land proposed to be used for non-forest purpose forms part of a nature reserve, national park, wildlife sanctuary, biosphere reserve or forms part of the habitat of any endangered or threatened species of flora and fauna or of an area lying severely eroded catchment;
(ii)whether the use of any forest land is for agricultural purposes or for the rehabilitation of persons displaced from their residences by reason of any river valley or hydro-electric project;
(iii)whether the State Government or the Union territory Administration, as the case may be, has certified that it has considered all other alternatives and that no other alternatives in the circumstances are feasible and that the required area is the minimum needed for the purpose;
(iv)whether the State Government or the Union territory Administration, as the case may be, undertakes to provide at its cost for the acquisition of land of an equivalent area and afforestation thereof;
(v)whether the per unit requirement of forest land is significantly higher than the national average for similar projects; and
(vi)whether the State Government or the Union territory Administration, as the case may be, before making their recommendation has considered all issues having direct and indirect impact of the diversion of forest land on forest, wildlife and environment.
(f)While tendering advice, the Committee may also suggest any condition or restriction on the use of any forest land for any non-forest purpose, which in its opinion would minimise adverse environmental impact.
(g)The Central Government shall, after considering the advice of the Committee under clause (e) and clause (f) and after such further enquiry as it may consider necessary, grant in-principle approval subject to fulfillment of stipulated conditions, or reject the same within thirty days of the receipt of advice from the Committee and communicate the same to the concerned State Government or the Union territory Administration, as the case may be, within next five working days.