Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 3, Cited by 0]

Bombay High Court

K. Talsania Construction vs Siddhi Apartments Chsl And 8 Ors on 7 February, 2019

Author: G.S.Kulkarni

Bench: G.S. Kulkarni

  pvr                                   1              arbp395-18.doc


               IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                      ORDINARY ORIGINAL CIVIL JURISDICTION

                       ARBITRATION PETITION NO.395 OF 2018

 K.Talsania Construction.                             ... Petitioner
             Vs.
 1.Siddhi Apartments Co-op.Housing Society Ltd. & Ors....Respondents

                                  -----
 Mr.Simil Purohit with Vishal Kanade, Ketki Prajapati, Maulik Vora I/b.
 M/s.Pramod Kumar & Co., for the Petitioner.

 Mr.Rohan Cama with Harshi Panchal I/b. Divya Singhavi, for Respondent
 No.1.

 Mr.Sharan Jagtiani with Mutahhar Khan I/b. Devendra M.Shinde, for
 Respondent No.2.

 Dr.Birendra Saraf with Mehul Shah I/b. Yatin S.Khochare, for Respondent
 Nos.5 and 6.

 Mr.Ashwin Shete I/b. Jaykar & Partners, for Respondent nos.7 to 9.

                                      -----
                               CORAM : G.S. KULKARNI, J.

                               DATE:     7 February,2019
                                        ---
 PC:-

 1.       This is a petition under Section 9 of the Arbitration and Conciliation

 Act,1996 (for short 'the Act') wherein the petitioner who is a developer is

 seeking interim reliefs pending the arbitral proceedings. The petitioner has

 prayed for the following reliefs:-




::: Uploaded on - 08/02/2019                   ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                          2               arbp395-18.doc

                   "(a)    that pending the commencement and culmination of the
                   arbitral proceedings between the Petitioner and Respondent no.1,
                   this Hon'ble Court be pleased to appoint the Court Receiver, High
                   Court, Bombay or any other fit and proper person as Receiver of
                   the property described in Exhibit 'A' hereto with all powers under
                   Order XL Rule 1 of the Code of Civil Procedure including power to
                   take physical possession of the subject Premises described in the
                   Exhibit 'B' hereto from Respondent Nos.2 to 9, their family
                   members and/or any person found in possession thereof, with the
                   help of police assistance, if necessary, including the breaking open
                   of lock and to hand over the same to the Petitioner for demolition
                   and re-development of the Property in accordance with the said
                   Agreement being Exhibit 'I' hereto;

                   (b)     that pending the commencement and culmination of the
                   arbitral proceedings between the Petitioner and Respondent No.1,
                   this Hon'ble Court be pleased to grant an order and injunction
                   restraining the Respondents No.2 to 9, their family members,
                   servants, agents and any person claiming by, through and/or under
                   them or any one or more of them from in any manner selling,
                   transferring, alienating, dealing with, disposing off and/or creating
                   third party rights and/or encumbrances in respect of the subject
                   premises described in Exhibit'B' hereto or any part thereof and/or
                   parting with possession thereof and/or obstructing, interfering with
                   and/or creating hurdles in re-development of the property
                   described in Exhibit 'A' hereto by the Petitioner under said
                   Agreement (being Exhibit 'I' hereto), in any manner whatsoever."



 2.       In brief the facts are:

          Respondent no.1 - Co-operative society (for short 'the society') is

 the owner of the land bearing final plot No.69/B/3 admeasuring about

 1738 sq.meters of Village Valnai, Taluka Borivali. Part of the land

 belonging to the Society (508 sq.meters) was occupied by slum and the

 balance land (1230 sq.meters) was in possession of the society having the

 building consisting of flats occupied by 34 members. Respondent no.1-




::: Uploaded on - 08/02/2019                           ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                        3                 arbp395-18.doc


 society was desirous of a redevelopment of its building in the form of a

 composite redevelopment which would include redevelopment of the area

 occupied by the slum dwellers and the area in the occupation of the

 society. The society had accordingly taken steps to invite bids from the

 developers.



 3.       It is not in dispute that in that the society followed a open-tender

 process by appointing a Project Management Consultant (PMC). Initially

 a tender process was initiated by a PMC namely Namarch Consultants

 who had issued the tender notice dated 3 August 2014 (page 149A). In

 the said tender document as prepared by the said PMC as regards the

 status of the plot the following statements were made:-

          "(A) Plot Details

          01)      Status of the Plot   : Conveyance is on the name of the society."




 4.       There was another clause in the said tender document as published

 under the said tender notice being clause (H) pertaining to 'cost of

 conveyance to be considered', which read as under:-

          "H) COST OF CONVEYANCE CONSIDERED:
          "Developer has to give lump sum cost he
          Considers would incur to obtain conveyance
          (Lump sum)"




::: Uploaded on - 08/02/2019                           ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                        4               arbp395-18.doc




 There were bids received under this tender notice. The petitioner had

 submitted its bid. However, for certain reasons this tender could not be

 finalised and was not granted to any of the bidders.



 5.       The society thereafter appointed Rex Con Cor as a new PMC, who

 again prepared a tender document. A fresh tender notice came to be

 published on 10 June 2015               (page 264A) as published in the local

 newspapers Maharashtra Times, Times of India and Mumbai Samachar

 which was approved by Special General Body meeting of the society held

 on 7 June 2015. The minutes of the meeting indicate that a resolution to

 the following effect was proposed by respondent no.2- Bhimsen K.Khatri.

 The relevant portion of the resolution reads thus:

          "Resolution:A tender notice for inviting the bidders for the demolition and
          the redevelopment of the society property/bldg of Siddhi Apartment CHS
          Ltd. Be published in the local two newspapers i.e. Times of India,
          Maharashtra Times and Mumbai Samachar on 10 th June 2015, pre bid
          meeting on 26 at PMC office, with tender submission date as on
          28.06.2015 between 12.00 noon to 5.00 p.m. and opening of the tenders
          submitted by the bidders on the very same day @ 7 p.m. at the society
          office."




 6.       In the tender document as prepared for this new tender, an

 inadvertent mistake had taken place to the effect that the society was yet




::: Uploaded on - 08/02/2019                         ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                         5               arbp395-18.doc


 to get the conveyance of the property executed in favour of the society.

 However, at the same time, there were following disclosures under the

 title "Highlights of the Project":-

                                "HIGHLIGHTS OF THE PROJECT
          1. Calm and serene location within Mumbai-Centrally located.
          2. Good residential area.
          3. Highway, Airport, market, school hospital, etc. all nearby
          4. Consent of all members of Redevelopment.
          5. Facing/Touching 30' ft. wide DP Road.
          6. Decent/peace loving/class society/members.
          7. Ownership Plot/FSI RIGHTS OF LAND WITH SOCIETY.
                                                (emphasis supplied)



 7.       In the said tender document under another heading titled as

 "Liabilities of the Project", the following was provided:-

          ".. .. ..
          4. Conveyance cost needs to be adjusted approx. 50 lacs, which includes cost
          of purchase of 133 sq.mtr plot from original owner, stamp duty and
          registration of documents and mutation/update of all property documents as
          per standard norms."                         (emphasis supplied)




 8.       In response to this tender, two bids were received, one was of the

 petitioner and the other was of one Shivshakti Construction. There was a

 special general body meeting of the society held on 28 June 2015 to

 transact the business; "to accept the tender documents alongwith the

 relevant documents and EMD envelopments for the redevelopment of the

 society building/property".          In the minutes of the meeting of the said




::: Uploaded on - 08/02/2019                          ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                         6                arbp395-18.doc


 Special General Meeting, in regard to the say of respondent no.2-

 Mr.Bhimsen Khatri the following was recorded :-

          "... Shri.Desai on verification with the other committee members revealed to
          the meeting that the conveyance process is in final stage and society
          redevelopment process will not be hampered. He further informed that the
          cost for the conveyance has to be borne by the prospective developer since the
          society cannot afford for the same at this stage. Dr.Khatri categorically
          clarified that he wanted to go with the common decision but it should be
          most benefiting to the society and further requested the chair to postpone the
          date of SGBM scheduled for the selection of the developer since he would not
          be in India till 26th July,2015."
                                                             (emphasis supplied)


 9.       Thereafter a special general body meeting was held on 14 August

 2015. Discussion took place in the meeting to finalize the tender. The

 minutes of the meeting recorded thus:-

          "But the PMC representative Shri.Sinha informed the meeting that from
          PMC REX CON COR Consultants office one tender form is issued to the
          potential bidder M/s.Aditya Developers who was accompanied by our
          respectable member Dr.Shri.Khatri. He stressed the efforts of Dr.Khatri for
          the benefit of all the society members being the only member who strived for
          additional opportunity to bidders. Shri.Sinha further informed that the
          visiting developer was advised to submit the duly filled tender form along
          with the FTGL tender terms set to society office within the given period of
          fifteen days from 28th July 2015 to 12th August 2015, as decided in the
          meeting on 28th July 2015. The member/developer both were guided by the
          PMC office about the timely submission.
          Hon.Secretary informed the SGBM that the society has not received any
          tender form after the previous meeting of 28 th July 2015.
          .........

          Then PMC Shri.Anup Gupta also explained how the society gave the
          opportunity to all who desired and proposed for bringing more
          bidders/developers in previous meeting.
          Again at this stage the general body unanimously approved the tender
          process and confirmed that the subject of searching any more further bidders
          be closed and mock voting be taken.
          Society members unanimously approved by majority vote that the search of




::: Uploaded on - 08/02/2019                           ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                         7                arbp395-18.doc

          more builders and higher financial offer to be closed.
          .. ... ...
          The Hon.Secy informed the chair that the society is in receipt of 2(two)
          verbal/mail votes and those required to be taken into account since the
          members are out of station. After collecting the entire mock voting forms
          PMC representative, as per instruction of the chairman went through the
          same and counted them by loudly reading for the knowledge of the members
          with the name of the developers and the votes casted. PMC Shri.Parinay
          Sinha counted the votes in front of general body. The Chairman with PMC
          help declared the name of the developer selected by the SGBM as "Total mock
          votes 29 casted and all in favour of M/s.K.Talsanisa Constructions." 27 votes
          in writing and 2 verbal. The chairman asked the members to submit written
          vote against this verbal vote. Based on percentage of highest /all vote casted
          in favour of one developer, as such M/s.K.Talsania Constructions is selected
          by the mock voting for the final selection in presence of Registrar of co-op.
          Societies."
                                                                 (emphasis supplied)



 10.               Thus on a majority, voting as undertaken, the members of the

 society resolved to appoint the petitioner as the developer to undertake

 the redevelopment of the premises of the society. Thereafter again on 22

 October 2015 a Special General Body meeting was held for confirmation

 of the award of the tender to the petitioner. During this meeting, the

 authorised officer of the Deputy Registrar Mr.Rokade was present and the

 following decision was taken by majority:-

          "The authorized officer MR.S.B.Rokade again confirmed the quorum for this
          meeting. He also noted the presence of representative of competitive
          developers Shri.Kishore Talsania for M/s.K.Talsania and Shri.Praful Shah
          for M/s.Shakti Construction and the society's PMC M/s.Rex Con Cor
          Consultants Pvt.Ltd."




::: Uploaded on - 08/02/2019                           ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                    8              arbp395-18.doc


 11.               Accordingly the petitioner being awarded the re-development

 contract, a development agreement dated 30 May 2016 was entered

 between the society and the petitioner. The agreement was acted upon

 and it is the case of the petitioner that in pursuance of the said agreement,

 the petitioner has undertaken construction of the slums building to

 accommodate forty six slum dwellers.          After receipt of the occupation

 certificate, the eligible slum dwellers are already put into possession of

 their respective tenements. It is stated that thereafter the petitioner

 intended to commence the construction of the society's building as also

 commercial component as would be available in the said building of the

 petitioner. The case of the petitioner is that it has made substantial

 investment in undertaking the construction of the slum dwellers building

 and now as per the terms of the development agreement, is entitled to

 undertake further construction of the society's building. It is at this stage

 that the petitioner requested respondent no.2 to vacate flat nos.14 and 15,

 respondent nos.3 and 4 to vacate flat no.25 and respondent nos.5,6,7,8

 and 9 to vacate flat nos.31 and 72. However, on some reasons which are

 untenable and contrary to the development agreement entered by the

 petitioner with the society, these respondents have refused to vacate their

 respective tenements. As regards the other members of the society out of




::: Uploaded on - 08/02/2019                    ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                     9              arbp395-18.doc


 total 34 members, 28 members have already executed agreements for

 permanent alternate accommodation and are ready and willing to hand

 over the possession of the respective flats to the petitioner. Further about

 18 members have already vacated their respective premises. It is in these

 circumstances on refusal on the part of these respondents to vacate the

 respective tenements, the present petition has been filed seeking the

 reliefs as noted above.



 12.               Mr.Kanade, learned Counsel for the petitioner referring to the

 clauses in the development agreement would submit that in the above

 circumstances, respondent nos.2 to 9 cannot take a position that they

 would not vacate their respective flats and hand over the vacant

 possession to the society and delay the work of redevelopment. He

 submits that the petitioner has invested substantial amounts, the

 construction of the slum rehabilitation building is already completed, any

 further delay in starting the construction will cause a serious prejudice to

 the petitioner. Mr.Kanade would submit that the redevelopment project

 was a composite project of construction of the slum rehabilitation building

 as already completed and the society building. It is submitted that now

 after completion of first part of the project and when the petitioner




::: Uploaded on - 08/02/2019                     ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                    10               arbp395-18.doc


 intends to undertake the redevelopment of the existing building of the

 society, for which majority of the members have entered into agreements

 for permanent alternate accommodation, these respondents intend to stall

 the project to also causing a prejudice to the majority of the member of

 the society. It is submitted that respondent no.2- Bhimsen K.Khatri is not

 vacating flat nos.14 and 15 whereas respondent nos.3 and 4 are not

 vacating flat no.25 and respondent nos.5 to 9 are not vacating flat nos.31

 and 72. It is submitted that there are no justifiable reasons for them not

 to vacate the flats.          The Court's attention is drawn to the various

 averments as made in the petition on the basis of which the relief is

 sought.




 13.               Mr.Ashwin Shete, learned Counsel for respondent nos.7 to 9

 at the outset submits that his clients have no objection for redevelopment

 to be undertaken as also for vacating the premises. It is submitted that the

 disputes inter-se between respondent nos.5 to 9 are sub-judice and are

 subject matter of civil suit no. 3182 of 2015 filed before the City Civil

 Court at Bombay.



 14.               Dr.Saraf, learned Counsel for respondent nos.5 and 6 would




::: Uploaded on - 08/02/2019                    ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                       11                 arbp395-18.doc


 also not dispute that there are inter-se disputes between his clients and

 respondent nos.7 to 9. Dr.Saraf, learned Counsel for respondent nos.5

 and 6 on merits has opposed the reliefs as prayed in the petition.

 Dr.Saraf's principal contention is that the petitioner is acting in breach of

 clauses 3.1, 10.1 and 10.2 of the development agreement as entered with

 the society which provide for certain conditions, compliance of which is

 mandatory by the petitioner, before which the petitioner cannot called

 upon the respondents to vacate the premises. These conditions of the

 development agreement read thus:-

          "3.1 It is also agreed by and between the parties hereto that as per the
          representation, the TDR that is to be loaded on the said property, the
          premium for the fungible FSI availed on the sale area, and the
          development charges, if any [covering the premises allotted to the
          Members of the Society] shall be paid by the Developer on or before
          request being made by the developer to vacate respective tenements of
          the occupants of the society.

          ...... ....
          10.2 The developers shall initially get the specific principal approval of
          Municipal Commissioner for the plans for plot potential FSI; admissible
          TDR and the admissible compensatory fungible FSI. The developers
          agrees to get the plans and specification sanctioned for consumption of
          the basic FSI of 1.00 and further additional FSI of 0.50 by paying
          premium (within one TDR) and admissible compensatory fungible FSI for
          accommodating all the Members before getting the vacant possession of
          all Flats. The developer shall pay the payment of premium for the fungible
          F.S.I. The developer shall get the approval of admissible FSI i.e. said
          property potential together with TDR & compensatory fungible FSI
          loading of TDR which is covering the Members' existing premises initially
          and not for the entire property before demand for vacating flats.
                                                      (emphasis supplied)




::: Uploaded on - 08/02/2019                         ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                 12               arbp395-18.doc




 15.      The next contention of Dr.Saraf is that the scheme under the

 development agreement in question is undertaken by the petitioner as a

 slum scheme. It is contended that this is clear from the permission issued

 by Slum Rehabilitation Authority. It is submitted that the redevelopment

 of the premises of the society can never form part of the slum scheme as

 the society premises are required to be independent premises which

 according to Mr.Saraf is clear from clause 17(r) of the agreement which

 provides that the property shall not be developed as SRA property and a

 distinct demarcation will have to be earmarked for development of SRA

 portion and development of the society's building and that the developer

 shall not to describe or introduce the words 'SRA' in the name of the

 society, however, both the buildings will be distinct and separate and shall

 not have common compound.          It is submitted that the development in

 question is being undertaken by the petitioner contrary to these clauses of

 the agreement.



 16.      Mr.Jagtiani, learned Counsel for respondent no.2 has also opposed

 this petition on the ground that in fact, the tender process undertaken by

 the petitioner itself is vitiated by fraud inasmuch as the tender document




::: Uploaded on - 08/02/2019                 ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                        13                 arbp395-18.doc


 itself mislead the bidding parties on the issue of conveyance. Mr.Jagtiani

 would submit that the tender document as earlier issued by the Project

 Management Consultant namely Namarach Consultants, there was a

 discrepancy as made in the tender document in regard to the conveyance,

 as noted in the foregoing paragraphs. It is submitted that in the second

 round in the tender document issued at the behest of new PMC Rex Con

 Cor, again in regard to the conveyance, there was a misrepresentation, as

 noted above, which is a fraud played by the society on its members in

 pursuing the said tender process by the PMC - Rex Con Cor.                                It is

 therefore submitted that          the development agreement ought not to be

 acted upon and/or given effect to. It is submitted that respondent no.2

 has already initiated the proceedings in a revision before the co-operative

 authorities, whereby the meeting as held by the society to proceed with

 the development, has been questioned in the said proceedings. In support

 of his submission, Mr.Jagtiani has placed reliance on the following

 observations of the Division Bench of this Court in the decision in "Girish

 Mulchand Mehta & Anr. Vs. Mehesh S.Mehta & Anr.1:

          " 20. It was also aruged that the property was in good condition and
          there was no need to redevelop the existing building. In the first place, as
          noted earlier, the decision of the General Body of the Society to redevelop
          the suit property has not been challenged at all. Besides, no provision in
          the Co-operative Societies Act or the rules or any other legal provision has

 1   2010(2) Mh.L.J. 657




::: Uploaded on - 08/02/2019                          ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                        14                arbp395-18.doc

          been brought to our notice which would curtail the right of the society in
          redevelop the property when the General Body of the Society intends to
          do so. Essentially, that is the commercial wisdom of the General Body of
          the Society. It is not open to the Court to sit over the said wisdom of the
          General Body as an Appellate Authority. Merely because some members in
          minority disapprove of the decision, that cannot be the basis to negate the
          decision of the General Body, unless it is shown that the decision was the
          product of fraud or misrepresentation or was opposed to some statutory
          prohibition. That is not the grievance made before us... .. ."
                                                       (emphasis supplied)


 17.      On the other hand Mr.Cama learned Counsel for the respondent-

 society has opposed the submissions as made by Dr.Saraf, learned Counsel

 for respondent nos.5 and 6                and Mr.Jagtiani, learned Counsel for

 respondent no.2. Mr.Cama at the outset would submit that the society as

 a body is wholeheartedly supporting the petitioner. It is submitted that 28

 members have already entered into an agreement for permanent alternate

 accommodation as also the majority of them have vacated the premises. It

 is submitted that the contesting respondents are creating unnecessary

 hurdles in the redevelopment of the premises of the society which is

 causing irreparable prejudice and injury to the other members of the

 society. Mr.Cama would submit that the contention as urged by Dr.Saraf

 referring to clause 3.1 and 10.2 of the development agreement to contend

 that such a compliance is not made by the developer, is totally

 misconceived. It is submitted that these respondents have completely

 misread the said clauses of the agreement to allege non compliance of the




::: Uploaded on - 08/02/2019                         ::: Downloaded on - 09/02/2019 00:57:33 :::
   pvr                                15                 arbp395-18.doc


 petitioner. It is submitted that the petitioner is making compliance of all

 the clauses of the agreement including the said clauses as referred by

 Dr.Saraf and would submit that these respondents are misreading the said

 clauses. As regards Dr.Saraf's contention that the development of the

 society's building cannot form development under the slums scheme,

 Mr.Cama referring to the various clauses of the development agreement

 would contend that Dr.Saraf's submission is misconceived and contrary to

 the development agreement.



 18.      Mr.Cama in response to the submissions of Mr.Jagtiani would

 submit that at all the relevant time respondent no.2 Mr.Khatri was part

 and parcel of the decision making process and was making an attempt to

 avoid awarding of the contract of redevelopment to the petitioner. My

 attention is drawn to the several documents on record to make good his

 submission that at every stage of the decision making process, the

 respondent no.2 was involved.            Mr.Cama would submit that the

 submissions as made by Mr.Jagtiani are in the teeth of the ratio laid down

 by the Division Bench in its decision in Girish Mulchand Mehta (supra),

 where the Division Bench taking a review of the law, has categorically

 observed that minuscule minority of the members in a society cannot




::: Uploaded on - 08/02/2019                  ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                 16                arbp395-18.doc


 override the majority opinion of the members, merely on the ground that

 certain terms and conditions of the development agreement are not

 acceptable to these members. Mr.Cama further submits that at all material

 times it was to the knowledge of respondent no.2 that the conveyance is

 already obtained as it was also clear from the first tender document which

 was prepared by PMC Namarch Consultants, and the clause in regard to

 payment was only in the nature of recompense clause, wherein it was

 accepted that the developer who would be appointed would compensate

 the conveyance cost incurred by the society. It is submitted that both the

 petitioner and the other bidders who responded to the tender published by

 the PMC Rex Con Cor also were aware that the conveyance was already

 obtained and there was no dispute in this regard. Mr.Cama would thus

 submit that the contention of Mr.Jagtiani that a fraud is played by the

 society on its members, is patently incorrect and in fact false to the

 knowledge of respondent no.2.



 19.      Mr.Kanade, learned Counsel for the petitioner also supports the

 arguments as made on behalf of Mr.Cama to submit that at all material

 times the bidding parties were aware that the conveyance was already

 obtained by the society and it is on that basis the petitioner participated in




::: Uploaded on - 08/02/2019                  ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                 17                arbp395-18.doc


 the tender in question and agreed to re-compensate the society in that

 regard.



 20.      Having heard the learned Counsel for the parties and having

 perused the record, I am not persuaded to accept the submissions as urged

 on behalf of the respondents. Firstly dealing with the submissions of

 Dr.Saraf, in my clear opinion, the provisions of clauses 3.1 and 10.2 of the

 agreement, of which Dr.Saraf would urge, that there is breach on the part

 of the petitioner, cannot be accepted. This for the reason that, there is

 complete misreading of these clauses in making this argument. On a

 plain reading of clause 3.1 it is clear that in respect of the TDR which is to

 be loaded on the property and for the fungible FSI which is to be availed

 on the sale area, the premium and the development charges, if any which

 would cover the premises allotted to the members of the society, are

 required to be paid by the developer on or before the request is made by

 the developer to vacate the tenements of the occupants of the society.

 Further clause 10.2 provides that the developer is required to make

 payment of premium for fungible FSI and that the developer will obtain

 approval of admissible FSI, that is the said property potential, together

 with TDR and compensatory fungible FSI, loading of TDR which would be




::: Uploaded on - 08/02/2019                  ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                       18                 arbp395-18.doc


 covering the members' existing premises, "initially" and not for the entire

 property before the demand for vacating flats.


 21.      A cumulative reading of the clauses 3.1 and 10.2, in my opinion,

 does not indicate that the developer would be required to make payment

 of the entire amount of the charges/premium in regard to the full TDR

 and compensatory fungible FSI and it would be sufficient that the charges

 in regard to construction of the premises covering tenements of the

 members of the society are initially paid as clearly agreed between the

 society and the petitioner. This is significantly clear from the following

 recital as contained in clause 10.2:-

          10.2 The developers shall initially get the specific principal approval of
          Municipal Commissioner for the plans for plot potential FSI; admissible
          TDR and the admissible compensatory fungible FSI. The developers
          agrees to get the plans and specification sanctioned for consumption of
          the basic FSI of 1.00 and further additional FSI of 0.50 by paying
          premium (within one TDR) and admissible compensatory fungible FSI for
          accommodating all the Members before getting the vacant possession of
          all Flats. The developer shall pay the payment of premium for the fungible
          F.S.I. The developer shall get the approval of admissible FSI i.e. said
          property potential together with TDR & compensatory fungible FSI
          loading of TDR which is covering the Members' existing premises initially
          and not for the entire property before demand for vacating flats.
                                                               (emphasis added)


 22.      However, to clarify this position, this Court had directed the

 respondents to file an affidavit so as to ascertain whether clauses 3.1 and

 10.2 as they stand are being complied by the petitioner and that the




::: Uploaded on - 08/02/2019                         ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                          19                 arbp395-18.doc


 members of the society in no manner are prejudiced even in regard to the

 payment in regard to the construction of the society premises/building. An

 affidavit dated 31 January 2019 is filed by Jayur Kishore Shah -partner of

 the petitioner to the following effect:-

                   "1.     I say that as on date the Concerned Development Authority
                   has permitted and sanctioned the development potentiality of
                   1230 sq.mtrs. As "Base Land FSI", the Petitioner has got generated
                   from the Concerned Development Authority/SRA and loaded the
                   development potentiality of 885.50 sq.mtrs. The Petitioner has
                   also been granted the Fungible FSI of 562 sq.mtrs and premium
                   FSI of 174 sq.mtrs. Aggregating in all 2851.50 sq.mtrs. The
                   Petitioner have paid an amount of Rs.71,25,000/- (Rupees
                   Seventy one lakh Twenty Five thousand only) as and by way of
                   premium to the Concerned Authority towards procuring the
                   premium FSI of 174 sq.mtrs. The constructed area in the form of
                   residential premises to be provided to the Society for its members
                   is 2,367.64 sq.mtrs (built up area). IN view of the above, I say that
                   the Clause no.3.1 read with Clause no.102 of the Development
                   Agreement dated 30th May 2016 have been fully complied with
                   and therefore the time for the Members of Respondent No.1
                   Society to vacate their respective premises, has arisen.
                   2.      I say that I.O.D. has also been granted in respect of the
                   Building wherein the Members of the Respondent No.1 society will
                   be accommodated. I further say that the FSI presently allowed
                   sufficiently covers the Members' premises and also makes available
                   to the Petitioner an area of 485.12 sq.mtrs for Free sale which
                   includes security flats."



 23.      It is thus clear that there is no substance in the contention as urged

 by Dr.Saraf that there is violation of clauses 3.1 and 10.2 to the prejudice

 of the members of the society. It is significant to note that the arguments

 of Dr.Saraf are in no manner whatsoever are supported by the society

 which would represent the majority members of the society. This




::: Uploaded on - 08/02/2019                            ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                20               arbp395-18.doc


 compounds the fact that if the majority members themselves are satisfied

 with the clear purport and implication of these clauses of the agreement

 and the majority of members do not find any compliance and a prejudice,

 it would be too far-fetched for Dr.Saraf, learned Counsel for respondent

 nos.5 and 6 to assert such interpretation of clause 3.1 and 10.2 of the

 development agreement only because respondent no.2 so believes.

 Moreover, Dr.Saraf's clients have no justifiable answer to the affidavit as

 filed by Mr.Jayur Kishor Shah on behalf of the petitioner, as directed by

 the Court.



 24.      As regards the the next contention of Dr.Saraf that the entire

 development has been undertaken as a slum project and which is contrary

 to the terms and conditions of the agreement, also cannot be accepted. It

 is clear from the record and the development agreement, that the

 development in question is for a composite development. Admittedly the

 area admeasuring 508 sq.meters was covered by slum and titled as 'slum

 area' in clause 1A of the development agreement. An area of 1230

 sq.meters was the area defined as the society's area. There are clear

 clauses in the agreement which obligates the petitioner to put boundary

 wall and keep the areas demarcated. In my opinion, this argument of




::: Uploaded on - 08/02/2019                ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                  21               arbp395-18.doc


 Dr.Saraf is thus an absolute exaggeration and presumptuous. This apart,

 this argument of Dr.Saraf, also cannot be accepted at such a belated stage

 of the project. Further the argument is also contrary to the very terms of

 the development agreement which takes within its fold a composite

 development of the slum area and the society area. It can also be clearly

 seen from the record that it is not the case that Dr.Saraf's client was not

 aware in regard to the nature of development and that the development is

 composite development of slum and society area. Dr.Saraf 's client was

 also aware that it would be impossible to construct the slum rehabilitation

 building without the benefits of redevelopment coming to the share of the

 developer in undertaking the construction of free sale area                    and in

 constructing society's premises. Thus, considering the documents on

 record      in my clear opinion, the contentions as urged by Dr.Saraf on

 behalf of respondent nos.5 and 6 are wholly misconceived and deserve to

 be rejected.



 25.      It appears that respondent nos.5 and 6 intends to create hurdles in

 the smooth redevelopment of the society's building and more particularly

 when he was completely aware about the entire sequence of the events

 which had led the petitioner to undertake this project and that too after




::: Uploaded on - 08/02/2019                  ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                 22               arbp395-18.doc


 the petitioner completing half the project, that is completion of

 rehabilitation building.



 26.      As regards the contention of Mr.Jagtiani, learned Counsel for

 respondent no.2 that there is fraud which is played by the society on its

 members by entering into the development agreement, also cannot be

 accepted. The argument is totally untenable. This firstly for the reason

 that respondent no.2 being a member of the society has never assailed the

 development agreement before the competent Court in the manner known

 to law. Further the revision proceedings as initiated by respondent no.2

 before the co-operative authority would also not assist Mr.Jagtiani's client,

 as those proceedings are not the proceedings where respondent no.2

 would succeed in getting a declaration that the development agreement

 itself is vitiated by fraud.    In my clear opinion, the argument of

 Mr.Jagtiani's client is clearly an afterthought. It is too late in time for

 respondent no.2 to contend that the agreement itself is vitiated by fraud.

 This more particularly when respondent no.2 has participated in various

 meetings which not only pertaining to appointment of the project

 management consultant but also inviting bids by publication of tender.

 The record also indicates that respondent no.2 was clearly aware that the




::: Uploaded on - 08/02/2019                 ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                          23                arbp395-18.doc


 conveyance of the society has been obtained. It is further surprising as to

 how this argument can be advanced by respondent no.2 when the record

 of special general body meeting clearly indicates that respondent no.2 had

 agreed that he would go with the majority vote and also accepted

 awarding of tender for redevelopment to the petitioner. It is also quite

 clear that the stand as taken by respondent no.2 is not bonafide.                              It

 appears that the entire arguments of respondent no.2 as urged by

 Mr.Jagtiani are arguments in desperation and that respondent no.2 has no

 bonafide reasons in opposing the redevelopment and in not co-operating

 in vacating of the premises. In this context Mr.Cama would be right in his

 contention referring to the decision of the Division Bench in "Girish

 Mulchand Mehta" (supra), to contend that minuscule members cannot

 withhold the greater benefits of the majority members of the society. The

 division Bench in the said decision considering the law on the issue as

 made the following observations:-

                   "16. In the present case, it is not in dispute that the General
                   Body of the Society which is supreme, has taken a conscious
                   decision to redevelop the suit building. The General Body of the
                   society has also resolved to appoint the respondent no.1 as the
                   Developer. Those decisions have not been challenged at all. The
                   appellants who were members of the Society at the relevant time,
                   are bound by the said decisions. The appellants in the dispute filed
                   before the Co-operative Court have only challenged the Resolution
                   dated 27-4-2008, which challenge would merely revolve around
                   the terms and conditions of the Development Agreement. As a
                   matter of fact, the General Body of the Society has approved the




::: Uploaded on - 08/02/2019                           ::: Downloaded on - 09/02/2019 00:57:34 :::
   pvr                                        24                 arbp395-18.doc

                   terms and conditions of the Development Agreement by
                   overwhelming majority. Merely because the terms and conditions
                   of the Development Agreement are not acceptable to the
                   appellants, who are in minuscule minority (only two out of twelve
                   members), cannot be the basis not to abide by the decision of the
                   overwhelming majority of the General Body of the Society. ...
                                                                (emphasis supplied)




 27.      In the aforesaid circumstances, I am of the clear opinion that the

 petitioner has made out a prima facie case for grant of interim reliefs

 pending the arbitral proceedings. The balance of convenience is

 overwhelmingly in favour of the majority members of the society for

 whose benefit the petitioner would undertake the development. If the

 relief as prayed for is not granted, certainly the petitioner and the

 members of the society will suffer a serious prejudice. I have no hesitation

 but to grant interim reliefs to the petitioner. Accordingly, the following

 order:-

                                           ORDER

(i) Respondent nos.2 to 9 are directed to vacate their respective flats and hand over the possession of their flats to the society within a period of four weeks from today.

(ii) Learned counsel for the respondent nos.7 to 9 on instructions, states that his clients shall hand over the possession of flat no.72 to the ::: Uploaded on - 08/02/2019 ::: Downloaded on - 09/02/2019 00:57:34 ::: pvr 25 arbp395-18.doc society within a period of four weeks from today. Statement is accepted.

(iii) On failure of respondent nos.2 to 6 who are occupying flat nos.14 and 15 and flat nos.25 and 31 respectively, to hand over the possession of the respective flats to the society, as directed in para 1 above, the Court Receiver, High Court, Bombay shall stand appointed as a receiver of the said flats with all powers under Order 40 Rule 1 of the Code of Civil Procedure, 1908 to take physical possession of the said flats and to hand over these flats to the society.

(iv) On completion of the re-development, the petitioner/society shall hand over the permanent alternate premises to the Court Receiver to be handed over to the parties, from whom the possession was taken over. In respect of flats voluntarily surrendered and vacated, the permanent alternate premises be handed over to those persons from whom the premises were taken over.

(v) The petitioner and the society are permitted to enter into an agreement for permanent alternate accommodation with the respondent no.2 to 9 and as and when these respondents come forward to execute the ::: Uploaded on - 08/02/2019 ::: Downloaded on - 09/02/2019 00:57:34 ::: pvr 26 arbp395-18.doc said agreements.

(vi) In view of the dispute between inter se between respondent nos.5 to 9, it would be open to these respondents to nominate any person with whom such an agreement for permanent alternate accommodation is to be entered into qua flat nos. 31 and 72, with which these respondents are concerned. Such an arrangement be informed to the society as also to the petitioner, within a period of two weeks from today. This arrangement shall be subject to the outcome of the proceedings of Suit No.3182 of 2015 and counter claim no.2 of 2018 which are pending before the City Civil Court, Dindoshi at Mumbai.

(vii) The petitioner shall pay the costs/charges of the Court Receiver.

(viii) The parties shall take steps to initiate the arbitral process within a period of 90 days from today.

(ix) It is clarified that respondent nos.5 to 9 shall keep indemnified the petitioner and the society in case any third party makes a claim against them in the inter se disputes between these respondents. ::: Uploaded on - 08/02/2019 ::: Downloaded on - 09/02/2019 00:57:34 :::

   pvr                                   27                arbp395-18.doc




 (x)      It is further clarified that in passing the above order, this Court has

not adjudicated in regard to any rights inter se between respondent nos.5 to 9 nor in any manner has touched and/or reflected on the individual rights of these respondents.

(xi) Mr.Kanade learned counsel for the petitioner states that the rent for the transit accommodation shall be paid to the person from whom possession of the respective flats would be taken by the society. Statement is accepted.

(xii) Petition is accordingly disposed of in the above terms. No order as to costs.

(G.S.Kulkarni, J.) ::: Uploaded on - 08/02/2019 ::: Downloaded on - 09/02/2019 00:57:34 :::