Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 7, Cited by 0]

Karnataka High Court

M/S. Rays Power Infra Limited vs The State Of Karnataka on 9 September, 2025

Author: R Devdas

Bench: R Devdas

                                -1-


      THE HIGH COURT OF KARNATAKA AT BENGALURU

       DATED THIS THE 9TH DAY OF SEPTEMBER, 2025

                             BEFORE

             THE HON'BLE MR. JUSTICE R. DEVDAS

        WRIT PETITION NO.35002 OF 2024 (GM-RES)
                         C/W
        WRIT PETITION NO.21533 OF 2024 (GM-RES)


   IN WP 35002/2024

   BETWEEN

1. M/S. RAYS POWER INFRA LIMITED
   A COMPANY INCORPORATED UNDER
   THE PROVISION OF THE COMPANIES ACT 2013
   HAVING ITS REGISTERED OFFICE AT
   1ST, 21 EVERSHINE MALL, NORTH METER CABIN 1
   MALAD WEST MUMBAI 400064
   REP BY ITS AUTHORIZED SIGNATORY
   MR SANNA THIPPESWAMY
   LEGAL MANAGER.

2. RAYSALFA POWER PRIVATE LIMITED
  A COMPANY INCORPORATED UNDER
  THE PROVISION OF THE COMPANIES ACT 2013
  HAVING ITS REGISTERED OFFICE AT
  605, 6TH FLOOR, MANJUSHA BUILDING,
  57 NEHRU PLACE DELHI, SOUTH DELHI-110019
  REP BY ITS AUTHORIZED SIGNATORY
  MR SANNA THIPPESWAMY

3. DADUR SOLAR POWER PRIVATE LIMITED
   A COMPANY INCORPORATED UNDER
   THE PROVISION OF THE COMPANIES ACT 2013
   HAVING ITS REGISTERED OFFICE AT
   D-43, JANPATH, SHYAM NAGAR, JAIPUR-302019
   REP BY ITS AUTHORIZED SIGNATORY
   MR SANNA THIPPESWAMY

4. NILAJ SOLAR POWER PRIVATE LIMITED
   A COMPANY INCORPORATED UNDER
                                   -2-

     THE PROVISION OF THE COMPANIES ACT 2013
     HAVING ITS REGISTERED OFFICE AT
     P.NO.65, SARDAR PATEL MARG, C-SCHEME
     ASHOK NAGAR, JAIPUR-302001
     REP BY ITS AUTHORIZED SIGNATORY

5. ANNIGERI SOLAR POWER PRIVATE LIMITED
   A COMPANY INCORPORATED UNDER
   THE PROVISION OF THE COMPANIES ACT 2013
   HAVING ITS REGISTERED OFFICE AT
   SARDAR PATEL MARG, C-SCHEME
   ASHOK NAGAR, JAIPUR-302001
   REP BY ITS AUTHORIZED SIGNATORY

6. SIRA SOLAR POWER PRIVATE LIMITED
   A COMPANY INCORPORATED UNDER
   THE PROVISION OF THE COMPANIES ACT 2013
   HAVING ITS REGISTERED OFFICE AT
   65, SARDAR PATEL MARG, C-SCHEME
   ASHOK NAGAR, JAIPUR-302001
   REP BY ITS AUTHORIZED SIGNATORY
                                                      ...PETITIONERS
     (BY SRI. GURUDAS S KANNUR., SR. COUNSEL FOR
         SRI. SHIVA KUMAR.C., ADVOCATE)

     AND

1.    THE STATE OF KARNATAKA
      DEPARTMENT OF ENERGY
      VIKASA SOUDHA, DR B R AMBEDKAR VEEDHI
      BANGALORE 560001
      REP BY THE ADDITIONAL CHIEF SECRETARY
      TO THE GOVERNMENT.

2.    KARNATAKA RENEWABLE ENERGY
      DEVELOPMENT LTD
      GOVERNMENT OF KARNATAKA UNDERTAKING
      NO.6/13/1 10TH BLOCK 2ND STAGE
      NAGARABHAVI, BANGALORE 560072
      REP BY ITS MANAGING DIRECTOR.

3.    CENTRAL TRANSMISSION UTILITY OF INDIA LIMITED
      HAVING ITS REGISTERED OFFICE
      AT PLOT NO.2 SECTOR 29
      NEAR IFFCO CHOWK METRO STATION
      GURAGON 122 001
      REP BY ITS MANAGING DIRECTOR.
                                      -3-



4.     UNION OF INDIA
       REP BY ITS SECRETARY
       MINISTRY OF NEW AND RENEWABLE ENERGY
       BLOCK 14 CGO COMPLEX
       LODHI ROAD NEW DELHI 110 003.

5.     ACME SOLAR HOLDINGS LTD.,
       NO.152, SECTOR 44, GURGAON,
       HARYANA-122002

6.     AMPIN ENERGY UTILITY PRIVATE LTD.,

7.     AMPIN ENERGY C & I FOURTEEN PVT. LTD.,

8.     AMPIN ENERGY C & I TWENTYEIGHT PVT. LTD.,

9.     AMPIN ENERGY C & I TWENTYNINE PVT. LTD.,

       ALL HAVING OFFICE AT 'ORBIS', 2ND CROSS
       RESIDENCY ROAD, BENGALURU-560025.

10.    ESSAR RENEWABLES LIMITED
       ESSAR HOUSE, 11 K.K.MARG,
       MAHALAKSHMI, HAJI ALI, MUMBAI-400034.
                                                    ......RESPONDENTS

      (BY SRI.REBUEN JACOB, AAG FOR SRI. MOHAMMAD JAFFAR SHAH,
      AGA FOR R1
      SRI. PIYUSH KUMAR JAIN D., ADVOCATE FOR R2
      SRI. S.S.NAGANAD., SR. COUNSEL FOR SMT.SUMANA NAGANAD.,
      ADVOCATE FOR R3
      SRI. K. ARAVIND KAMATH., ASG A/W SMT. SADHANA S DESAI.,
      ADVOCATE FOR R4
      SRI. K.G. RAGHAVAN., SR. COUNSEL FOR SRI. ARYAMAN GHULATI,
      PRITHU CHAWLA & SMT. RASHMI VAISH., ADVOCATES FOR R5
      SRI. UDAYA HOLLA, SR. COUNSEL A/W SRI. ROHAN SACHDEVA &
      SRI. SUDHEESH S KESARKAR., ADVOCATES FOR R6 TO R9
      SRI. DEEP RAO PALEPU A/W SRI. SUDHEESH S KESARKAR.,
      ADVOCATES FOR R10)

           THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF
      THE CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT, OR
      DIRECTION MORE IN THE NATURE OF WRIT OF MANDAMAUS TO
      DIRECT THE R1 &/OR R2 FORTHWITH GRANT GNA AUTHORIZATION
      FOR RE PARK IN TERMS OF REGULATION 5.8(vii)(A) OF GNA
      REGULATIONS, 2002 (AS AMMENDED) WITHOUT INSISITNG GO AS
                              -4-

PRESCRIBED FORMAT TO THE PETITIONERS WITHIN A FIXED TIME
PERIODS OF TWO WEEKS AND ETC.


IN WP 21533 OF 2024
BETWEEN

M/S. RAYS POWER INFRA LIMITED
A COMPANY INCORPORATED UNDER
THE PROVISION OF THE COMPANIES ACT, 2013
HAVING ITS REGISTERED OFFICE AT
1ST, 21 EVERSHINE MALL,
NORTH METER CABIN 1
MALAD WEST MUMBAI 400064
REP BY ITS AUTHORIZED SIGNATORY
MR SANNA THIPPESWAMY
                                              ...PETITIONERS
(BY SRI. GURUDAS S KANNUR., SR. COUNSEL FOR
    SRI. SHIVA KUMAR.C., ADVOCATE)

AND

1 . THE STATE OF KARNATAKA
    DEPARTMENT OF ENERGY
    VIKASA SOUDHA, DR B R AMBEDKAR VEEDHI
    BANGALORE 560001
    REP BY THE ADDITIONAL CHIEF SECRETARY
    TO THE GOVERNMENT.

2 . KARNATAKA RENEWABLE ENERGY
    DEVELOPMENT LTD
    GOVERNMENT OF KARNATAKA UNDERTAKING
    NO.6/13/1 10TH BLOCK 2ND STAGE
    NAGARABHAVI, BANGALORE 560072
    REP BY ITS MANAGING DIRECTOR.

3 . CENTRAL TRANSMISSION UTILITY
    OF INDIA LIMITED
    HAVING ITS REGISTERED OFFICE
    AT PLOT NO.2 SECTOR 29
    NEAR IFFCO CHOWK METRO STATION
    GURGAON 122 001
    REP BY ITS MANAGING DIRECTOR.

4 . UNION OF INDIA
    REP BY ITS SECRETARY
    MINISTRY OF NEW AND RENEWABLE ENERGY
                                -5-


     BLOCK 14 CGO COMPLEX
     LODHI ROAD NEW DELHI 110 003

5 . CENTRAL ELECRICITY REGULATORY COMMISSION
    6TH 7TH & 8TH FLOORS,
    TOWER B, WORLD TRADE CENTRE
    NAUROJI NAGAR, NEW DELHI-110029.

6.   ACME SOLAR HOLDINGS LTD.,
     NO.152, SECTOR 44, GURGAON,
     HARYANA-122002

7.   AMPIN ENERGY UTILITY PRIVATE LTD.,

8.   AMPIN ENERGY C & I FOURTEEN PVT. LTD.,

9.   AMPIN ENERGY C & I TWENTYEIGHT PVT. LTD.,

10. AMPIN ENERGY C & I TWENTYNINE PVT. LTD.,

     ALL HAVING OFFICE AT 'ORBIS', 2ND CROSS
     RESIDENCY ROAD, BENGALURU-560025.

11. ESSAR RENEWABLES LIMITED
    ESSAR HOUSE, 11 K.K.MARG,
    MAHALAKSHMI, HAJI ALI, MUMBAI-400034.
                                                 ......RESPONDENTS

(BY SRI.REBUEN JACOB, AAG FOR SRI. MOHAMMAD JAFFAR SHAH,
 AGA FOR R1
SRI. PIYUSH KUMAR JAIN D., ADVOCATE FOR R2
SRI. S.S.NAGANAD., SR. COUNSEL FOR SMT.SUMANA NAGANAD.,
ADVOCATE FOR R3
SRI. K. ARAVIND KAMATH., ASG A/W SMT. SADHANA S DESAI.,
ADVOCATE FOR R4 & R5
SRI. K.G. RAGHAVAN., SR. COUNSEL FOR
SRI. ARYAMAN GHULATI, PRITHU CHAWLA & SMT. RASHMI
VAISH., ADVOCATES FOR R6
SRI. UDAYA HOLLA, SR. COUNSEL A/W SRI. ROHAN
SACHDEVA & SRI. SUDHEESH S KESARKAR., ADVOCATES R7
TO R10
SRI. DEEP RAO PALEPU A/W SRI. SUDHEESH S KESARKAR.,
ADVOCATES FOR R11)

     THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF
THE CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT, OR
                                -6-

DIRECTION MORE IN THE NATURE OF WRIT OF MANDAMAUS TO HOLD
AND DECLARE THAT THE R1 &/OR R2 HAS/HAVE AN INHERINT POWER
TO ISSUE GNA AUTHORIZATION AS REQUIRED UNDER REGULATION
5.8(vii)(A) OF GNA REGULATIONS, 2002 (AS AMMENDED) AND ETC.

    THESE WRIT PETITIONS HAVING BEEN HEARD AND RESERVED ON
13.08.2025 AND COMING ON FOR PRONOUNCEMENT OF ORDERS,
THIS DAY, THIS COURT MADE THE FOLLOWING:

CORAM: HON'BLE MR JUSTICE R DEVDAS


                         CAV ORDER

          (PER: HON'BLE MR JUSTICE R DEVDAS)

     The grievances of the petitioners in both these writ

petitions being common and the respondents against whom

directions are sought at the hands of the petitioners also

being common, therefore, these two writ petitions were

clubbed, heard together and are being disposed of by this

common order.


     2.   Petitioner   No.1   through   its   subsidiaries/Special

Purpose Vehicles applied to the third respondent-Central

Transmission Utility of India Limited (hereinafter referred to

as 'CTUIL' for short) for connectivity, for establishing solar

power parks, responding to the notification published by the

CTUIL in its website, during the month of August 2024. Two

sets of applications were filed in the name of three
                                    -7-


subsidiaries   of   the   petitioners,        seeking   connectivity       at

Tumkur-II Sub-station for 300 MW and 290 MW respectively

while also seeking connectivity at Ballari sub-station for 300

MW.     Problems    arose    for     the      petitioners     in     seeking

authorization at the hands of the Government of Karnataka

which is a requirement in terms of regulation 5.8 (vii) (a) of

the General Network Access Regulations, 2022 (for short

'GNA    Regulations')     notified       by   the   Central        Electricity

Regulatory Commission (for short 'CERC').


       3. The grievance of the petitioners, in a nutshell, is that

the prescription of securing an authorization at the hands of

the State Government applies only in case of applicants for

establishment of Renewable Power Park or Renewable Power

Park Developers and not in respect of applicants for grant of

connectivity (applicants for connectivity or for enhancement

of quantum of connectivity; generating stations including

Renewable Energy Generating Stations (REGS), with or

without Energy Storage System (ESS); captive generating

plants; standalone ESS etc).         In other words, two categories

are made, segregating the renewable power park developers
                               -8-


from all other categories.    The mandatory requirement of

securing authorization from the competent Government

applies only in respect of Renewable Power Park Developers.

Secondly, there is only one queue for both categories and

seniority is based on the seniority of filing application.

Thirdly, the other applicants can by-pass the Renewable

Power Park Developers in seniority since the power park

developers are yet to obtain an authorization at the hands of

the competent Government.           Fourthly, no guidelines are

prescribed to the competent Government under the GNA

Regulations for consideration and grant of authorization. The

State Government is insisting on the petitioners to apply for

a   Government     Order   (for     short   'GO')   for   grant   of

authorization.   Although the petitioners have applied to the

State Government for grant of authorization, the process of

issuance of GO is tedious and the petitioners are forced to

pay enormous charges for grant of GO.               The issue has

become more complicated since petitions have been filed by

the Association of Energy Developers in a separate writ

petition and interim orders have been passed by this Court in

the matter of collection of fee for grant of GO. Fifthly, since
                              -9-


the connectivity is limited in capacity, by the time the

petitioners secure authorization at the hands of the State

Government, the applicants in all other categories will be

granted connectivity and the petitioners will be left high and

dry.


       4. Having regard to such grievance vented out by the

petitioners, interim orders were passed by this Court on

16.01.2025 directing the third respondent-CTUIL to reserve

600 MW in Ballari and 890 MW in Tumkuru-II Grid sub-

stations for allotment to the petitioners, while granting

liberty to the third respondent to grant connectivity to other

applicants barring the portion reserved for the petitioners,

until further orders.


       5. Learned Senior Counsel Sri G.S.Kannur appearing for

the petitioners contended that the word 'authorisation' which

is mandated in the impugned Regulations is not defined.

There are no    guidelines stipulated in the GNA Regulations

guiding the State Government in the matter of grant of

authorization. On the other hand, the State Government, on

the recommendation of the Nodal Agency KREDL, and in
                                       -10-


terms    of   the    renewable         energy           policy   of    the   State

Government, is insisting that the petitioners should apply for

grant of GO.      It is submitted that it is not disputed at the

hands of the respondents, more particularly, KREDL and the

State Government that all the other applicants who have

been granted connectivity or would be granted connectivity

in the future will have to approach the State Government for

grant of GO.        However, in respect of the renewable power

park    developers,      a    distinction         is    sought    to   be    made

mandating them for securing authorization at the hands of

the State Government even prior to the connectivity being

granted by the CTUIL.                 It is submitted that although

applications were filed by the petitioners well in time and

they    stand    high    in     the    seniority          list   of    applicants,

nevertheless, since the petitioners are not able to secure

authorization at the hands of the State Government, the

applicants below the petitioners in the seniority are permitted

to by-pass the petitioners and connectivity is being given to

them.     It is pointed out that having regard to the existing

renewable       energy       potential,      at        present   the    evacuate

substantial capacity through the ISTS at Tumakuru-II sub-
                             -11-


station is 1.5 GW and at Ballari also it is 1.5 GW. Therefore,

if the other applicants who are below the petitioners in

seniority are permitted to by-pass the petitioners in the line

of seniority and connectivity is awarded to such applicants,

the petitioners will be left without any capacity for grant of

connectivity.


     6. Faced with such difficult situations, the petitioners

are before this Court seeking appropriate directions either to

the CTUIL to process the applications filed by the petitioners

without insisting on authorization or a direction to the State

Government to issue authorization without insisting on GO.

Learned Senior Counsel would submit that it has been more

than three months after applications are filed by the

petitioners seeking authorization at the hands of the State

Government.     The State Government, through KREDL is

holding up the applications on one pretext or the other. In

one case, it is informed to the petitioners that some other

applicants have applied for the same coordinates (place of

establishment of the wind turbines), although such applicants

are found not eligible to seek GO. Objections are also raised
                                 -12-


that the requisite fee is not paid, although the State

Government is aware that this Court has passed interim

orders directing the State Government not to collect the fee

prescribed, which is under challenge.            In another case,

although the fee is paid, some other objection is raised and

the application is not being processed.              Learned Senior

Counsel pointed out that although the learned Additional

Advocate General had made a statement before this Court

that the said application where fee has been paid by the

petitioners   will   be   processed    within    a   specified   time,

nevertheless till date the said application has not been

processed.


     7. Sri.K.Aravind Kamath, learned Additional Solicitor

General of India, appearing for the respondent-Union of India

and the CERC submitted that the requirement of the

renewable power park developers to secure authorization at

the hands of the competent Government stems from the fact

that the Power park developer is not a generating company

as defined in Section 2(30) of The Electricity Act. It is only a

generating    company      or   a   generating   station   which    is
                                   -13-


empowered to seek a dedicated transmission line.                       That is

the reason why the other applicants who seek connectivity at

the hands of the CTUIL need not obtain authorization at the

hands   of   the     competent        Government.          Learned         ASG

submitted that in terms of the second proviso to Section 9 of

the Electricity Act, no licence is required for a generating

company.     However, in the year 2015 the Government of

India   came    up    with   a   Policy      in   order    to    encourage

development of renewable energy and for the first time

provision was made for 'Park Generators' to apply for

connectivity and establish generating parks where other

generating companies could establish their units. However,

having regard to the statutory provisions, the distinction is

made between the generating companies and a renewable

power park developer.        The learned ASG would therefore

submit that the contention of the petitioners that power park

developers     are    discriminated       against     by       insisting    on

procuring    authorization       at    the    hands       of     the    State

Government while the same is not made applicable to the

other generating companies, cannot be accepted.                     There is

an intelligible differentia and therefore, the extant GNA
                                  -14-


Regulations or more particularly Regulation No.5.8 (vii)

cannot be held as unconstitutional.


      8. Learned Additional Advocate General Sri Reuben

Jacob appearing for the respondent-State and respondent

No.2-KREDL submitted that in terms of the Karnataka

Renewable Energy Policy 2022-2027 which came into force

on 06.05.2022, a project proponent including Park Developer

who   require   authorization     at    the   hands   of   the   State

Government      for   projects    connected     to    CTU    (Central

Transmission Utility) are required to file application.           The

Policy also requires the applicant to secure a Government

Order and therefore the petitioners are required to obtain a

Government Order.        The learned AAG has adopted the

submissions made by the learned ASG, while pointing out to

the provisions contained in the GNA Regulations, that a

distinction is made insofar as generators are concerned when

compared to a Park Developer which is not a generator.


      9. Learned Senior Counsel Sri S.S.Naganand, appearing

for the CTUIL adopted the arguments of the learned ASG,

insofar as the requirements in terms of GNA Regulations are
                                      -15-


concerned.        Learned Senior Counsel also pointed out to

I.A.No.1/2024 filed at the hands of the CTUIL and submitted

that the CTUIL has considered and rejected the applications

filed by the petitioners and therefore the writ petition has

been rendered infructuous. It is submitted that by order

dated 08.08.2024, this Court had directed CTUIL to consider

the application filed by the petitioner for grant of GNA

connectivity      on   a    seniority    basis    without   insisting   on

authorization. The petitioners had also written to the CTUIL

seeking consideration of the applications in terms of the

directions issued by this Court.            Accordingly, orders were

passed by CTUIL on 30.08.2024 and 02.09.2024 rejecting

the applications.          The learned Senior Counsel, therefore

submitted that as on date, the applications filed by the

petitioners are not available for consideration.


     10.     In    this    regard,      learned   Senior    Counsel     Sri

G.S.Kannur appearing for the petitioners drew the attention

of this Court to the last paragraphs of the communications

dated 30.08.2024 and 02.09.2024, where it is stated that the

rejection of the application of the petitioners shall be subject
                                -16-


to the directions that may be issued by this court. Therefore,

it is submitted that CTUIL is aware of the fact that such

orders being passed contrary to the directions issued by this

Court cannot be sustained and therefore leave of this court is

sought by CTUIL that such orders will be subject to the final

outcome of these writ petitions.


      11.     Learned    Senior   Counsels     Sri.K.G.Raghavan,

Sri.Udaya Holla along with learned Counsels Sri.Deep Rao

Palepu appearing for the impleading applicants have all

expressed concerns on behalf of the impleading applicants

who are the competing applicants seeking connectivity at the

hands of CTUIL. It is contended that by virtue of the interim

orders passed by this Court directing reservation of 900 MW

in favour of the petitioners, the petitioners are benefited

although they do not comply with the requirements as per

the GNA Regulations. It is contended that some of the

impleading applicants who are above the petitioners in

seniority of application, have been deprived of their rights in

obtaining connectivity at the hands of CTUIL. Although some

of   the    impleading   applicants   were   initially   below   the
                                   -17-


petitioners    in   seniority,    nevertheless   they   have    been

deprived of a right to be considered, as a result of the

interim orders passed by this Court. It is contended that in

terms of the GNA Regulations, if the petitioners did not

comply with the requirements, they could be ignored while

the next in line is eligible for consideration. However, since

interim orders have been passed by this Court reserving 900

MW in favour of the petitioners, the next in line is deprived of

an opportunity of consideration.         It is also a fact that the

seniority which would be lost by the petitioners, have been

protected at the hands of this Court.              It is therefore

submitted that at any rate the seniority of the impleading

applicants need to be protected and restored at the hands of

this Court.

     12.      Heard    learned     Senior     Counsel   Sri.Gurudas

S.Kannur, appearing for the petitioners, Sri.Rebuen Jacob,

Additional Advocate General for respondent No.1-State and

respondent      No.2      -      Karnataka     Renewable       Energy

Development Ltd., Sri.S.S.Naganad, learned Senior Counsel

appearing for respondent No.3,              Sri.K. Aravind Kamath,
                                   -18-


Additional Solicitor General of India,               Sri.K.G. Raghavan,

Sri.Udaya Holla, learned Senior Counsels, and Sri.Deep Rao

Palepu    along   with   Sri.    Sudheesh        S   Kesarkar,   learned

Counsels for impleading applicants and perused the material

on records.


       13. The primary contention of the petitioners is that

since two categories are made viz., the Park Developers on

the one hand and all the others on the other hand, but since

one single queue of applicants is provided for, the Park

Developers are put at a disadvantage. It is their contention

that since authorization is required to be obtained by Park

Developers, at the hands of the Government, the time

required by the Park Developers to obtain authorization

should have been kept in mind. On facts, it was submitted

that     the   petitioners      have     filed   application     seeking

authorization, more than three months ago and authorization

is yet to be issued.     It is the contention of the petitioners

that since proper guidelines are not prescribed under the

GNA Regulations to the competent Government in the matter

of grant of authorization, the State Government is acting
                                 -19-


arbitrarily, while forcing the petitioners to obtain Government

Order.   Although       the   petitioners   have     made     further

application   to   secure     Government    Order,    there    again

payment of fee has become an issue.                In another writ

petition pending consideration before this Court, interim

orders are passed restricting the State Government from

seeking payment of fee, till the disposal of the writ petition.

When these difficulties faced by the petitioners are brought

to the notice of the CTUIL, the CTUIL has not taken any

initiative to redress the grievance of the petitioners.


     14. During the course of these proceedings, the

petitioners sought leave of this Court to approach the Central

Electricity Regulatory Commission to relax the requirement of

obtaining an authorization from the State Government,

having regard to Regulation No.41 of the Central Electricity

Regulatory Commission (Connectivity and General Network

Access to the Interstate Transmission System) Regulations,

2022.    Accordingly,    by order dated 17.03.2025 this Court

granted permission to the petitioners to approach the

Commission while also directing the Commission to consider
                                    -20-


the representation that would be given by the petitioners for

relaxation and to take a decision to put an end to the

litigation. However, it appears that the Central Commission

rejected the representation given by the petitioners.


     15.    It is noticeable that the Hon'ble Apex Court, in

the case of Reliance Energy Limited and Another /vs./

Maharashtra State Road Development Corporation Ltd.

and Others (2007) 8 SCC 1, has held that the standards

applied by Courts in judicial review must be justified by

constitutional principles which govern the proper exercise of

public power in a democracy. It was held that Articles 21 and

14 are the heart of the chapter on fundamental rights. They

cover various aspects of life. "Level playing field" was held

to be an important concept while construing Article 19(1)(g)

of the Constitution. It was further held in paragraphs-36 and

38 which read as hereunder:


           "36. We find merit in this civil appeal. Standards
     applied by courts in judicial review must be justified by
     constitutional   principles     which      govern   the     proper
     exercise of public power in a democracy. Article 14 of
     the   Constitution   embodies        the   principle   of   "non-
                            -21-


discrimination". However, it is not a free-standing
provision. It has to be read in conjunction with rights
conferred by other articles like Article 21 of the
Constitution. The said Article 21 refers to "right to life".
It includes "opportunity".      In our view, as held in the
latest judgment of the Constitution Bench of nine
Judges in I.R. Coelho.v.State of T.N. [(2007) 2 SCC 1],
Articles   21/14   are   the    heart   of   the   chapter   on
fundamental rights. They cover various aspects of life.
"Level playing field" is an important concept while
construing Article 19(1)(g) of the Constitution. It is this
doctrine which is invoked by REL/HDEC in the present
case. When Article 19(1)(g) confers fundamental right
to carry on business to a company, it is entitled to
invoke the said doctrine of "level playing field". We may
clarify that this doctrine is, however, subject to public
interest. In the world of globalisation, competition is an
important factor to be kept in mind. The doctrine of
"level playing field" is an important doctrine which is
embodied in Article 19(1)(g) of the Constitution. This is
because the said doctrine provides space within which
equally placed competitors are allowed to bid so as to
subserve the larger public interest. "Globalisation", in
essence, is liberalisation of trade. Today India has
dismantled    licence    raj.     The    economic     reforms
introduced after 1992 have brought in the concept of
"globalisation". Decisions or acts which result in unequal
and discriminatory treatment, would violate the doctrine
of "level playing field" embodied in Article 19(1)(g).
                                -22-


     Time has come, therefore, to say that Article 14 which
     refers to the principle of "equality" should not be read
     as a stand alone item but it should be read in
     conjunction with Article 21 which embodies several
     aspects of life. There is one more aspect which needs to
     be mentioned in the matter of implementation of the
     aforestated doctrine of "level playing field". According to
     Lord Goldsmith, commitment to the "rule of law" is the
     heart of parliamentary democracy. One of the important
     elements of the "rule of law" is legal certainty. Article
     14 applies to government policies and if the policy or
     act of the Government, even in contractual matters,
     fails to satisfy the test of "reasonableness", then such
     an act or decision would be unconstitutional.

             38. When tenders are invited, the terms and
     conditions must indicate with legal certainty, norms and
     benchmarks. This "legal certainty" is an important
     aspect of the rule of law. If there is vagueness or
     subjectivity in the said norms it may result in unequal
     and discriminatory treatment. It may violate doctrine of
     "level playing field".

                                            (Emphasis supplied)

     16.     Applying the tests as expounded by the Hon'ble

Apex Court, this Court finds, in the present context, that the

grievances    of   the   petitioners   is    well   founded.       The

respondents, more particularly the CTUIL and the CERC are
                                      -23-


aware of the difficulties faced by the petitioners in the matter

of   obtaining    authorization       at    the    hands    of    the    State

Government.             The     CERC        declined   to    entertain       a

representation given by the petitioners to redress their

grievance. This Court is therefore of the considered opinion

that there is substance in the contentions of the petitioners

that they have been discriminated against by virtue of a

stipulation in the GNA Regulations requiring a Park Developer

to obtain authorization at the hands of the Government. The

problem    for    the   petitioners/Park          Developers      is    further

complicated at the hands of the State Government in

insisting that the petitioners have to apply and obtain a

Government Order, although there is no such requirement

under the GNA Regulations. There can be no doubt that the

respondent authorities have failed to create a Level Playing

Field for the petitioners.


      17. This Court is also of the considered opinion that it

is bounden duty of the CERC which formulated the GNA

Regulations      and    which   is    also    empowered          to    remove

difficulties faced by the petitioners, to have considered
                                  -24-


issuing directions relaxing the requirement and the CERC has

failed in its duties.


      18.   This Court is also of the considered opinion that

the apprehensions of the impleading applicants is unfounded.

The petitioners are not before this Court to seek out of turn

consideration     of    their   applications.        The    petitioners

grievances are genuine in as much as, the GNA Regulations

do    not   prescribe     any    guidelines     to    the   competent

Government for grant of authorization; no time frame is fixed

to enable the competent Government to consider and grant

authorization; as a consequence, though the petitioners have

filed the application before the CTUIL, their application is not

considered by CTUIL on the ground that the petitioners have

not   secured    authorization    at    the   hands    of   the   State

Government. The other applicants who are in the queue are

allowed to by-pass the petitioners on the ground that the

petitioners are not qualified.      This Court is therefore of the

considered opinion that the respondent authorities have

failed to create a level playing field for the applicants. The

respondent authorities have failed to notice this anomalous
                                 -25-


fcsituation    where,   by   the    time    the   petitioners    secure

authorization at the hands of the State Government, the

connectivity gets exhausted and the petitioners will be left

high and dry. The least that was required from the

respondent authorities and the GNA Regulations was to

provide separate queues for Renewable Power Developers

and Renewable Power 'Park Developers'.


     19.      For the reasons stated above, this Court proceeds

to pass the following;


                                    ORDER

(i) The writ petitions are partly allowed.

(ii) The interim directions issued by this Court on 16.01.2025 reserving 890 MW in Tumkur-II sub-station and 600 MW in Bellary sub-station of connectivity for consideration of the applications filed by the petitioners, shall stand extended till authorization is granted by the respondent State Government, in favour of the petitioners.

(iii) Liberty is also reserved to the respondent authorities (CERC and CTUIL) to reconsider the applications of the petitioners and grant -26- in-principle approval/ connectivity to the petitioners subject to they obtaining authorization at the hands of the State Government.

(iv) I.A.No.1/2024 filed by the CTUIL stands rejected, consequently setting aside the orders dated 30.08.2024 and 02.09.2024 passed by CTUIL, while restoring the applications of the petitioners for re-consideration.

(v) The impleading applications are formally allowed. The learned counsel for the petitioners shall carryout the amendment in the cause title.

Ordered accordingly.

Pending I.As. if any, stand disposed of.

Sd/-

(R DEVDAS) JUDGE JT/KLY CT: JL