Section 22(3) in The Cost Accounting Records (Petroleum Industry) Rules, 2002

(3)In the case of new major projects for product or activity referred to under rule 2, proper records shall be maintained indicating the funds raised from different sources, their utilisation, stage-wise cost incurred and progress of the project as per the project report. Cost and time over run shall also be analysed with reference to the cost of services or activity and profitability of the company.