Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Entire Act]

Union of India - Section

Section 151 in The Coal Mines Regulations, 2017

151. Intentional flooding.

(1)When the owner, agent or manager intends or proposes, by introducing water from the surface or from any other part of the mine or from an adjacent mine, to flood any part of the workings of his mine, he shall give, in writing, not less than fourteen days notice of such intention or proposal to the Chief Inspector and the Regional Inspector and to the management of all adjoining mines and of such other mines as might be affected by such flooding:Provided that the Regional Inspector may, by an order in writing and subject to such conditions as he may specify therein, permit such operations to be commenced on any day prior to the expiry of the said notice period of fourteen days:Provided further that the Regional Inspector may, by an order in writing, either prohibit any such operation or require that such operation shall not be commenced until such precautions as he may specify therein, have been taken to his satisfaction.
(2)If the operations in respect of which notice is given under sub-regulation (1) are not commenced within sixty days from the expiry of the said notice period of fourteen days, the notice shall be deemed to have lapsed and the provision of the sub-regulation (1) shall apply as if no such notice had been given.