Section 13 in Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations, 2017

13. A Generating Station already connected to the Distribution System or to whom Connectivity is already granted under an existing arrangement shall not be required to apply for Connectivity for the same capacity. However, in case of augmentation of capacity of the Generating Station, a fresh application for modification to the Connectivity provisions shall be required in accordance with the provisions of these Regulations.