State of Maharashtra - Subsection

Section 9(9) in Maharashtra Electricity Regulatory Commission (Transmission Open Access) Regulations, 2005

9.2Notwithstanding the provisions contained in Regulation 9.1, a Transmission System User may surrender the whole or any part of his transmission capacity rights to the Transmission Licensee:Provided that such surrender of capacity shall be on such terms and conditions as may be mutually agreed upon between the Transmission System User and the Transmission Licensee:Provided further that if any dispute arises with reference to the terms and conditions of such surrender or where the Transmission System User and the Transmission Licensee cannot agree on the terms and conditions of such surrender, it shall be referred to the Commission for decision.